- CN211974238U CN211974238U CN202020502936.5U CN202020502936U CN211974238U CN 211974238 U CN211974238 U CN 211974238U CN 202020502936 U CN202020502936 U CN 202020502936U CN 211974238 U CN211974238 U CN 211974238U
- Authority
- CN
- China
- Prior art keywords
- steel
- fixing
- half frame
- platform
- platform body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model relates to a special construction platform of steel construction relates to construction equipment's technical field, including platform body and the steel sheet of setting in the platform body, the platform body is pegged graft relatively by two half frames and is formed, steel sheet and half frame sliding connection, and the steel sheet slides in to half frame inside from the terminal surface of half frame. The utility model discloses have easy to assemble, the effect of dismantling.
Description
Technical Field
The utility model belongs to the technical field of the technique of architectural equipment and specifically relates to a special construction platform of steel construction is related to.
Background
In the current construction process of constructional engineering, a steel structure platform also becomes a working platform, adopts a fully assembled structure, is flexible in design and widely applied to modern warehouses, and generally consists of section steel, plates and the like; because the H-shaped steel is used as the upright post and the main beam, the plate paved on the surface can be made of different materials according to the bearing requirements of the platform, and steel plates, square timbers and the like can be used; the links between the various components are secured using welds, screws, or nails.
The utility model discloses a have the china utility model patent of grant bulletin number CN208815870U at present and disclose a special construction platform of steel construction, including platform body, steel structure support and steel sheet, the equal fixed mounting in platform body bottom both sides has steel structure support, and the welding of steel structure support surface both ends has the dead lever, and platform body both sides run through there is the through-hole, and the dead lever penetrates in the through-hole. The platform body is fixedly connected with the steel plate through steel rods in an inserting mode. When the steel pipe is installed, the steel plate and the platform body are inserted into the steel pipe, so that the platform body penetrates through the fixing rods of the steel structure supports, and the steel structure supports on the two sides are connected through the supporting rods. The installation and the disassembly are convenient, and the time is saved for the construction.
The above prior art solutions have the following drawbacks: when dismantling construction platform, need follow the roll-off with the steel pipe on the platform body, and the steel pipe is more, is difficult to accomodate the arrangement.
SUMMERY OF THE UTILITY MODEL
Not enough to prior art exists, the utility model aims at providing a special construction platform of steel construction has easy to assemble, the effect of dismantling.
The above utility model discloses an above-mentioned utility model purpose can realize through following technical scheme:
the utility model provides a special construction platform of steel construction, includes the platform body and sets up at this internal steel sheet of platform, the platform body is pegged graft relatively by two half frames and is formed, steel sheet and half frame sliding connection, and the steel sheet slides in to half frame inside from the terminal surface of half frame.
Through adopting above-mentioned technical scheme, when installation construction platform, slide in the terminal surface with the steel sheet from half frame, when the steel sheet slided half frame inside, impel two half frames relatively, and the plug is fixed together. Consequently when the equipment or dismantle the platform body, simple swift when accomodating the arrangement, two half frames and several steel sheet arrangement are simple, and area is little.
The present invention may be further configured in a preferred embodiment as: the end face of one end of the half frame is provided with two convex first inserting blocks, a concave first inserting groove is formed between the two first inserting blocks, the end face of one end of the other half frame is provided with two concave second inserting grooves, a second inserting block is arranged between the two second inserting grooves, the first inserting blocks are inserted into the second inserting grooves, and the second inserting blocks are inserted into the first inserting grooves.
By adopting the technical scheme, when the two half frames are oppositely plugged together, the two first plugging blocks are plugged into the second plugging grooves, and meanwhile, the second plugging blocks are plugged into the first plugging grooves, so that the first plugging blocks and the second plugging blocks are alternately plugged together, and the two half frames are more stable and stable when being plugged together.
The present invention may be further configured in a preferred embodiment as: and a first inserting block and a first inserting groove, and a second inserting block and a second inserting groove are respectively arranged at two ends of the half frame.
Through adopting above-mentioned technical scheme, when two half frames are pegged graft together, different grafting structure sets up at the both ends of half frame, consequently two half frame concatenations are in the same place, make the platform body more firm.
The present invention may be further configured in a preferred embodiment as: the inner wall of the half frame is provided with an inward concave sliding groove, a group of convex sliding blocks are arranged on the opposite surfaces of the steel plates, and the sliding blocks slide in the sliding grooves.
Through adopting above-mentioned technical scheme, when the installation or when dismantling the platform body, make the slider aim at the spout and slide in the spout, consequently the steel sheet can slide in or the roll-off semi-frame along the spout, convenient operation to the steel sheet is fixed stable.
The present invention may be further configured in a preferred embodiment as: the sliding groove at the end part of the half frame is provided with an inclined notch.
Through adopting above-mentioned technical scheme, the breach makes spout tip widen, therefore the slider slides in the spout more easily, strengthens the convenience of installation.
The present invention may be further configured in a preferred embodiment as: be close to there is convex fixed block or sunken fixed slot on the steel sheet one side lateral wall at platform body both ends, a set of opposite lateral wall of steel sheet that is located the platform body middle part is provided with fixed block and fixed slot respectively, and the fixed block is pegged graft with the fixed slot.
Through adopting above-mentioned technical scheme, after the steel sheet all slided into on the half frame, two adjacent steel sheets all peg graft together, make the steel sheet link up inseparabler, even construction platform is more firm.
The present invention may be further configured in a preferred embodiment as: and a fixing part is arranged at the joint of the half frames.
Through adopting above-mentioned technical scheme, after two half frame splices, fixed to steel structural support on, consequently two half frame's position is locked, and the mounting is firm in order to further make the platform body, reduces steel structural support's the influence of rocking the steadiness receipts of platform body.
The present invention may be further configured in a preferred embodiment as: the mounting includes the fixed plate of horizontal at two half frame grafting gap bottoms, and the one end of fixed plate is detained through first fixed and is rotated and connect on a half frame, and the other end of fixed plate is fixed on another half frame through the fixed knot of second.
By adopting the technical scheme, when the platform body is disassembled, the second fixing fastener is screwed off, the fixing plate is rotated, the fixing plate rotates by taking the axis of the rod body of the first fixing fastener as an axis, and the two half frames can be opened when being far away from the lower part of the platform body; when the installation, can with the second fixed knot screw on the platform body.
To sum up, the utility model discloses a following at least one useful technological effect:
1. when the steel plate slides into the half frames, the two half frames are pushed oppositely and are inserted and fixed together. Therefore, when the platform body is assembled or disassembled, the assembly is simple and quick, when the platform body is stored and arranged, the arrangement of the two half frames and the plurality of steel plates is simple, and the occupied area is small;
2. the first inserting block and the second inserting block are inserted together in a crossed manner, so that the two half frames are more stable and stable when being inserted together;
3. the mounting is in order to further make the platform body firm, reduces steel structure support's the influence of rocking the steadiness receipts of platform body.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic structural view of the steel structural support of the present invention;
fig. 3 is a schematic structural diagram of the platform body of the present invention;
a partially enlarged schematic view of portion a in fig. 4;
FIG. 5 is a schematic structural view of a first insertion groove of the present invention;
fig. 6 is a schematic structural view of the fixing member of the present invention;
fig. 7 is a schematic structural diagram of the middle steel plate of the present invention.
In the figure, 1, a platform body; 11. a through hole; 12. a half frame; 13. a first plug-in block; 14. a first insertion groove; 15. a second insertion groove; 16. a second insertion block; 17. a chute; 18. a notch; 2. a steel structure bracket; 21. a connecting rod; 22. looping; 3. a support platform; 31. fixing the rod; 4. a steel plate; 41. a slider; 42. fixing grooves; 43. a fixed block; 5. a support bar; 51. a trench; 6. a fixing member; 61. a fixing plate; 62. a fixing buckle; 621. a first fixing buckle; 622. and a second fixing buckle.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Referring to fig. 1, for the utility model discloses a special construction platform of steel construction, including platform body 1, steel structure support 2 and steel sheet 4, platform body 1 is gone into in the grafting of steel sheet 4, and steel structure support 2 supports in the bottom of platform body 1.
Referring to fig. 2, the platform body 1 is a rectangular frame, the steel structure supports 2 are arranged at four corners of the bottom of the rectangular frame, the steel structure supports 2 are formed by welding I-shaped steel, the supporting platform 3 is welded at one side of each steel structure support 2, and the fixing rods 31 are arranged on the top surfaces of the supporting platforms 3. Through holes 11 are formed in two sides of the platform body 1, the platform body 1 is erected on the supporting platform 3, and the fixing rod 31 penetrates through the through holes 11. And the two steel structure brackets 2 on one side are fixed by welding through connecting rods 21. Be fixed with the latch closure 22 on steel structure support 2's lateral wall, support between two steel structure support 2 and have bracing piece 5, there is slot 51 at the both ends of bracing piece 5, supports behind platform body 1 below when steel structure support 2, hangs slot 51 on latch closure 22, the steel structure support 2 of both sides is fixed promptly.
Referring to fig. 3 and 4, the platform body 1 is formed by oppositely inserting two half frames 12, wherein one side end surface of one half frame 12 is provided with two convex first inserting blocks 13, a first inserting groove 14 (refer to fig. 5) which is concave inside the half frame 12 is arranged between the two first inserting blocks 13, one side end surface of the other half frame 12 is provided with two second inserting grooves 15 which are concave inside, a convex second inserting block 16 is arranged between the two second inserting grooves 15, after the two half frames 12 are oppositely combined, the first inserting blocks 13 are inserted into the second inserting grooves 15, and meanwhile, the second inserting blocks 16 are inserted into the first inserting grooves 14.
At the both ends of a half frame 12, one end sets up first inserted block 13 and first inserting groove 14, and the other end has second inserted block 16 and second inserting groove 15, and different grafting structures set up the both ends at half frame 12, therefore two half frames 12 splice together, make platform body 1 more firm.
Referring to fig. 6, a fixing member 6 is provided on the bottom surface where the half frames 12 meet, and the fixing member 6 includes a rectangular fixing plate 61, and the fixing plate 61 is fixed at the joint of the two half frames 12. There are two round holes on the fixed plate 61, all have fixed knot 62 in the round hole, and two fixed knots 62 are fixed respectively on two half frame 12 bottom surface lateral walls, are first fixed knot 621 and the fixed knot 622 of second respectively. When the platform body 1 is disassembled, the second fixing fastener 622 is screwed off, and the fixing plate 61 is rotated, so that the fixing plate 61 rotates around the axis of the rod body of the first fixing fastener 621, and the two half frames 12 are far away from the lower part of the platform body 1, and can be opened (refer to fig. 7); when the platform is installed, the two second fixing buckles 622 are screwed on the platform body 1.
Referring to fig. 3 and 4, the inner walls of the two sides where the insertion end of the platform body 1 is located are provided with recessed sliding grooves 17, the side walls of the two sides of the steel plate 4 are provided with protruding sliding blocks 41, the sliding blocks 41 slide in the sliding grooves 17, during installation, the steel plate 4 slides into the half frame 12 from the end surface of the half frame 12, and then the two half frames 12 are inserted together.
The slide groove 17 at the end face of the half frame 12 has an inclined notch 18, and the end of the slide groove 17 is widened, so that the slide block 41 slides more easily into the slide groove 17.
Referring to fig. 7, two adjacent steel plates 4 are fixed to each other by inserting the fixing groove 42 and the fixing block 43. One of the steel plates 4 has a protruding fixing block 43 on the side wall, and the adjacent steel plate 4 has a fixing groove 42 on the side wall. Only one side wall of the steel plate 4 close to the two ends of the platform body 1 is provided with a fixing block 43 or a fixing groove 42, and the opposite side walls of the steel plate 4 positioned in the center of the platform body 1 are respectively provided with the fixing groove 42 and the fixing block 43. When steel sheet 4 slided in spout 17, correspond the grafting with fixed slot 42 and fixed block 43 on each steel sheet 4, make the steel sheet 4 in the platform body 1 link up mutually, steel sheet 4 surface and platform body 1 surface parallel and level, platform body 1 surface is got up by stable stay.
The implementation principle of the embodiment is as follows: the steel plate 4 is slid into the half frame 12 from the end face of the half frame 12, and the slider 41 is slid in the slide groove 17. The steel plate 4 with the fixing block 43 or the fixing groove 42 on one side is slid into the half frames 12, the rest of the steel plate 4 is slid into the two half frames 12, the two half frames 12 are pushed towards each other simultaneously, the fixing groove 42 is inserted into the fixing block 43, the first inserting block 13 is inserted into the second inserting groove 15, and the second inserting block 16 is inserted into the first inserting groove 14.
The fixing plate 61 is rotated so that the fixing plate 61 is positioned below the joining edge of the two half frames 12, and the fixing buckle 62 is tightened.
The platform body 1 is erected on the supporting platform 3, the fixing rod 31 penetrates through the through hole 11, and the grooves 51 of the two supporting rods 5 are hung on the ring buckle 22.
The embodiment of this specific implementation mode is the preferred embodiment of the present invention, not limit according to this the utility model discloses a protection scope, so: all equivalent changes made according to the structure, shape and principle of the utility model are covered within the protection scope of the utility model.
Claims (8)
1. The utility model provides a special construction platform of steel construction, includes platform body (1) and sets up steel sheet (4) in platform body (1), its characterized in that: the platform body (1) is formed by oppositely inserting two half frames (12), the steel plate (4) is in sliding connection with the half frames (12), and the steel plate (4) slides in from the end face of the half frame (12) to the inside of the half frame (12).
2. The special construction platform for steel structures of claim 1, wherein: the end face of one end of the half frame (12) is provided with two convex first inserting blocks (13), a concave first inserting groove (14) is formed between the two first inserting blocks (13), the end face of one end of the other half frame (12) is provided with two concave second inserting grooves (15), a second inserting block (16) is arranged between the two second inserting grooves (15), the first inserting blocks (13) are inserted into the second inserting grooves (15), and the second inserting blocks (16) are inserted into the first inserting grooves (14).
3. The special construction platform for steel structures of claim 2, wherein: and a first inserting block (13), a first inserting groove (14), a second inserting block (16) and a second inserting groove (15) are respectively arranged at two ends of the half frame (12).
4. The special construction platform for steel structures of claim 1, wherein: the inner wall of the half frame (12) is provided with an inward concave sliding groove (17), a group of opposite steel plates (4) are provided with convex sliding blocks (41), and the sliding blocks (41) slide in the sliding groove (17).
5. The special construction platform of steel construction of claim 4, characterized in that: the sliding groove (17) at the end of the half frame (12) is provided with an inclined notch (18).
6. The special construction platform for steel structures of claim 1, wherein: the side wall of one side of the steel plate (4) close to the two ends of the platform body (1) is provided with a convex fixing block (43) or a concave fixing groove (42), the side wall of a group of opposite sides of the steel plate (4) located in the middle of the platform body (1) is provided with the fixing block (43) and the fixing groove (42) respectively, and the fixing block (43) is spliced with the fixing groove (42).
7. The special construction platform for steel structures of claim 1, wherein: the joint of the half frames (12) is provided with a fixing piece (6).
8. The special construction platform of steel construction of claim 7, characterized in that: the fixing piece (6) comprises a fixing plate (61) transversely arranged at the bottom of the insertion gap of the two half frames (12), one end of the fixing plate (61) is rotatably connected onto one half frame (12) through a first fixing buckle (621), and the other end of the fixing plate (61) is fixed onto the other half frame (12) through a second fixing buckle (622).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020502936.5U CN211974238U (en) | 2020-04-08 | 2020-04-08 | Construction platform special for steel structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020502936.5U CN211974238U (en) | 2020-04-08 | 2020-04-08 | Construction platform special for steel structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211974238U true CN211974238U (en) | 2020-11-20 |
Family
ID=73383600
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020502936.5U Expired - Fee Related CN211974238U (en) | 2020-04-08 | 2020-04-08 | Construction platform special for steel structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211974238U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112575903A (en) * | 2020-12-12 | 2021-03-30 | 深圳新艺华建筑装饰工程有限公司 | Ultrahigh special-shaped frame steel structure and construction method thereof |
CN114215323A (en) * | 2021-12-27 | 2022-03-22 | 广州地铁设计研究院股份有限公司 | Civil engineering and mechanical-electrical integration assembly type maintenance platform and construction method thereof |
-
2020
- 2020-04-08 CN CN202020502936.5U patent/CN211974238U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112575903A (en) * | 2020-12-12 | 2021-03-30 | 深圳新艺华建筑装饰工程有限公司 | Ultrahigh special-shaped frame steel structure and construction method thereof |
CN114215323A (en) * | 2021-12-27 | 2022-03-22 | 广州地铁设计研究院股份有限公司 | Civil engineering and mechanical-electrical integration assembly type maintenance platform and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN211974238U (en) | Construction platform special for steel structure | |
CN110042928B (en) | Modularized spliced house and construction method thereof | |
CN111088872B (en) | Steel structure supporting beam convenient to transport | |
CN113585293A (en) | Ecological environmental protection pin-connected panel municipal administration side slope reinforced structure | |
CN211229127U (en) | Building wood steel structure | |
CN210482573U (en) | Assembled steel structure node | |
CN215802266U (en) | Direct-insertion type bolt-free connecting joint of closed cavity column and steel beam | |
CN115450350A (en) | Flexibly connected inner partition wall structure and mounting method thereof | |
CN215166620U (en) | High-strength steel structure node | |
CN209817127U (en) | Clip type node connection structure | |
CN111827663A (en) | Wall form strutting arrangement | |
CN221236205U (en) | Assembled connecting piece for steel structure building | |
CN111958184A (en) | Assembled aluminum alloy door and window and production process thereof | |
CN221030702U (en) | Node connection structure of steel joist | |
CN220928772U (en) | Temporary support of butt-clamping embedded part | |
CN213773968U (en) | Environment-friendly assembled finger joint board log cabin wall body | |
CN218029294U (en) | Steel construction communication computer lab that can build fast | |
CN220954542U (en) | Can dismantle scalable elevator shaft operation platform structure | |
CN220100177U (en) | Steel beam and core tube inner steel rib column connecting node | |
CN219118713U (en) | Side column lantern frame assembly type cantilever supporting platform for storage | |
CN217811770U (en) | Assembly type pouring type disassembly-free formwork structure body | |
CN219451411U (en) | Frame device is chosen in construction | |
CN214329282U (en) | Assembled truss | |
CN211665938U (en) | Pin-connected panel building structure | |
CN214330065U (en) | Structure convenient to detach's interim frame is built in room |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20201120 |