CN211974017U - Prefabricated bathroom floor - Google Patents
Prefabricated bathroom floor Download PDFInfo
- Publication number
- CN211974017U CN211974017U CN202020304738.8U CN202020304738U CN211974017U CN 211974017 U CN211974017 U CN 211974017U CN 202020304738 U CN202020304738 U CN 202020304738U CN 211974017 U CN211974017 U CN 211974017U
- Authority
- CN
- China
- Prior art keywords
- layer
- fence
- waterproof
- stainless steel
- rail
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Residential Or Office Buildings (AREA)
Abstract
A prefabricated toilet floor slab comprises a concrete layer, wherein the peripheral edge of the concrete layer vertically extends upwards to form a circle of first fence, a stainless steel layer is arranged at the bottom of the concrete layer and used for being welded and installed with a floor steel beam discontinuously, the peripheral edge of the stainless steel layer vertically extends upwards to form a circle of second fence, the second fence surrounds the first fence, and four symmetrically arranged hanging rings are welded on the second fence; the top of concrete layer is equipped with the waterproof layer, the top of waterproof layer is equipped with decorative cover layer. The utility model discloses a waterproof layer and stainless steel layer carry out dual waterproof for waterproof performance is good, and first rail and second rail can prevent that water from oozing from the side moreover, and the waterproof of this prefabricated bathroom floor simultaneously, decoration are by mill integrated into one piece, and direct welding installation after the fortune is to the building site reduces the field operation time, and in addition, the no wet operation is identical with the theory of assembled steel structure building.
Description
Technical Field
The utility model relates to an assembly type building structure technical field, in particular to prefabricated bathroom floor.
Background
At present, when a common method for adopting a composite floor slab in engineering is used in a toilet, because a cast-in-place layer between the floor slab and peripheral beams and a composite slab floor slab is thin, a vertical construction joint exists in a prefabricated part of a composite component, if the cast-in-place layer cracks, the concrete self-waterproofness fails, and the quality problems of cracking, even water leakage and the like are easily caused. The water leakage of the toilet easily causes the problems of household complaints, project repair and the like, and causes certain economic loss. In addition, the defects are not easy to repair in the later period, and inconvenience is brought to later-period use and maintenance.
SUMMERY OF THE UTILITY MODEL
Based on this, the utility model aims at providing a prefabricated bathroom floor that waterproof performance is good.
A prefabricated toilet floor slab comprises a concrete layer, wherein the peripheral edge of the concrete layer vertically extends upwards to form a circle of first fence, a stainless steel layer is arranged at the bottom of the concrete layer and used for being welded and installed with a floor steel beam discontinuously, the peripheral edge of the stainless steel layer vertically extends upwards to form a circle of second fence, the second fence surrounds the first fence, and four symmetrically arranged hanging rings are welded on the second fence;
the top of concrete layer is equipped with the waterproof layer, the top of waterproof layer is equipped with decorative cover layer.
Compared with the prior art, the utility model discloses a waterproof layer and stainless steel layer carry out dual waterproof for waterproof performance is good, and first rail and second rail can prevent that water from oozing from the side, and this prefabricated bathroom floor's is waterproof simultaneously, decorate by mill integrated into one piece, and direct welding installation after fortune to the building site reduces the on-the-spot operation time, and in addition, the no wet operation is identical with the theory of assembled steel construction building.
Further, the inside reinforcing bar net that arranges of concrete layer, the reinforcing bar net includes horizontal reinforcing bar and the longitudinal reinforcement of many parallel equidistance settings, the both ends of horizontal reinforcing bar and longitudinal reinforcement upwards extend perpendicularly respectively to in the first rail.
Further, the stainless steel layer is made of 304 stainless steel and has a thickness of 1.2 mm.
Further, the height of the second rail is 150mm, and the sum of the thicknesses of the second rail and the first rail is 50 mm.
Further, a top of the decorative covering does not protrude above a top of the second rail.
Further, the thickness of concrete layer is 80mm, the sum of the thickness of decorative cover and waterproof layer is 50 mm.
Furthermore, a reserved water pipe hole is formed in the concrete layer and penetrates through the stainless steel layer, the waterproof layer and the decorative surface layer.
Drawings
Fig. 1 is a schematic top view of a prefabricated toilet floor in an embodiment of the present invention;
fig. 2 is a schematic cross-sectional view of the prefabricated toilet floor of fig. 1, taken along the line a-a.
Description of the main element symbols:
|
10 | |
101 |
Reserved |
102 | |
11 |
|
111 | |
112 |
Water- |
12 | |
13 |
Reinforcing |
14 |
The following detailed description of the invention will be further described in conjunction with the above-identified drawings.
Detailed Description
In order to facilitate understanding of the present invention, the present invention will be described more fully hereinafter with reference to the accompanying drawings. Several embodiments of the invention are given in the accompanying drawings. The invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete.
It will be understood that when an element is referred to as being "secured to" another element, it can be directly on the other element or intervening elements may also be present. When an element is referred to as being "connected" to another element, it can be directly connected to the other element or intervening elements may also be present. The terms "vertical," "horizontal," "left," "right," and the like as used herein are for illustrative purposes only.
Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs. The terminology used in the description of the invention herein is for the purpose of describing particular embodiments only and is not intended to be limiting of the invention. As used herein, the term "and/or" includes any and all combinations of one or more of the associated listed items.
Referring to fig. 1 to 2, an embodiment of the present invention provides a prefabricated toilet floor, including a concrete layer 10, a circle of first rail 101 is formed by upward and vertical extending of a peripheral edge of the concrete layer 10, a stainless steel layer 11 is disposed at a bottom of the concrete layer 10, the stainless steel layer 11 is used for performing discontinuous welding installation with a floor steel beam, a circle of second rail 111 is formed by upward and vertical extending of a peripheral edge of the stainless steel layer 11, the second rail 111 surrounds the first rail 101, and four symmetrically disposed hanging rings 112 are welded on the second rail 111;
the top of concrete layer 10 is equipped with waterproof layer 12, the top of waterproof layer 12 is equipped with decorative cover 13.
It should be noted that, in this embodiment, the waterproof layer 12 and the decorative surface layer 13 are processed in a factory, which may not be limited by a field space and is convenient for operation, and may reduce a field operation time, thereby improving a working efficiency. The four hanging rings 112 are used for conveniently hoisting the prefabricated toilet floor slab during installation. In addition, the waterproof layer 12 and the stainless steel layer 11 can achieve a double waterproof effect, so that the waterproof performance is good, and the first rail 101 and the second rail 111 can prevent water from leaking out from the sides.
Referring to fig. 1, a reinforcing mesh 14 is disposed inside the concrete layer 10, the reinforcing mesh 14 includes a plurality of parallel transverse reinforcing bars and longitudinal reinforcing bars disposed at equal intervals, and both ends of the transverse reinforcing bars and the longitudinal reinforcing bars respectively extend upwards and vertically into the first fence 101, so as to increase the strength of the concrete layer 10 and the first fence 101.
In a preferred embodiment of the present invention, the stainless steel layer 11 is made of 304 stainless steel, and has a thickness of 1.2mm, which not only can achieve the waterproof effect, but also can prevent the prefabricated toilet floor slab from being too heavy.
In another preferred embodiment of the present invention, in order to achieve a good side waterproof effect and facilitate installation, the height of the second rail 111 is 150mm, and the sum of the thicknesses of the second rail 111 and the first rail 101 is 50 mm.
Referring to fig. 2, the top of the decorative surface layer 13 does not protrude from the top of the second rail 111, so as to prevent water from leaking out from the side.
Specifically, in this embodiment, in order to facilitate standardized production, the thickness of the concrete layer 10 is 80mm, and the sum of the thicknesses of the decorative surface layer 13 and the waterproof layer 12 is 50 mm.
Referring to fig. 1, a reserved water pipe hole 102 is formed in the concrete layer 10, and the reserved water pipe hole 102 penetrates through the stainless steel layer 11, the waterproof layer 12 and the decorative surface layer 13.
It should be noted that, in the present invention, the concrete embodiment of the prefabricated toilet floor slab is as follows:
firstly, arranging a steel edge die on a steel die table according to the design drawing requirement of a toilet;
secondly, bending the stainless steel according to the design drawing requirement of the toilet to form a stainless steel layer 11 containing a second rail 111, welding four lifting rings 112 on the side edge of the second rail 111, and drilling holes in the stainless steel layer 11 to form reserved holes;
thirdly, binding reinforcing mesh 14, and placing related water pipes at the reserved holes to reserve holes;
fourthly, pouring concrete to form a concrete layer 10;
fifthly, after the concrete meets the requirement, performing waterproof treatment on the top of the concrete layer 10 to form a waterproof layer 12, and then paving a decorative surface layer 13 on the top of the waterproof layer 12;
sixthly, after the requirement is met, the prefabricated toilet floor slab and the floor steel beam are lifted by the crane through the lifting ring 112 to be positioned, the stainless steel layer 11 and the floor steel beam are welded and installed discontinuously, and the whole site is free of wet operation and is identical to the idea of the fabricated steel structure building.
To sum up, the utility model discloses a waterproof layer 12 and stainless steel layer 11 carry out dual waterproof for waterproof performance is good, and first rail 101 and second rail 111 can prevent that water from oozing from the side moreover, and the waterproof of this prefabricated bathroom floor simultaneously, decorate by mill integrated into one piece, transport to the site back direct weld installation, reduce the on-the-spot operation time, and in addition, the no wet operation is identical with the theory of assembled steel construction building.
The above-mentioned embodiments only represent some embodiments of the present invention, and the description thereof is specific and detailed, but not to be construed as limiting the scope of the present invention. It should be noted that, for those skilled in the art, without departing from the spirit of the present invention, several variations and modifications can be made, which are within the scope of the present invention. Therefore, the protection scope of the present invention should be subject to the appended claims.
Claims (7)
1. The utility model provides a prefabricated bathroom floor, includes concrete layer, its characterized in that: the periphery of the concrete layer extends upwards vertically to form a circle of first fence, a stainless steel layer is arranged at the bottom of the concrete layer and used for being welded and installed with a floor steel beam discontinuously, the periphery of the stainless steel layer extends upwards vertically to form a circle of second fence, the second fence surrounds the first fence, and four symmetrically arranged hanging rings are welded on the second fence;
the top of concrete layer is equipped with the waterproof layer, the top of waterproof layer is equipped with decorative cover layer.
2. The prefabricated toilet floor according to claim 1, wherein a reinforcing mesh is arranged inside the concrete layer, the reinforcing mesh comprises a plurality of parallel and equidistantly arranged transverse reinforcing bars and longitudinal reinforcing bars, and both ends of the transverse reinforcing bars and the longitudinal reinforcing bars respectively vertically extend upwards into the first fence.
3. The prefabricated toilet floor of claim 1, wherein said stainless steel layer is made of 304 stainless steel and has a thickness of 1.2 mm.
4. The prefabricated toilet floor of claim 1, wherein the second rail has a height of 150mm and the sum of the thicknesses of the second rail and the first rail is 50 mm.
5. The prefabricated lavatory floor of claim 1, wherein a top of the finishing layer does not protrude above a top of the second rail.
6. The prefabricated lavatory floor of claim 5, wherein the concrete layer has a thickness of 80mm and the sum of the thicknesses of the finishing coat and the waterproof layer is 50 mm.
7. The prefabricated toilet floor according to claim 1, wherein a reserved water pipe hole is formed in the concrete layer, and the reserved water pipe hole penetrates through the stainless steel layer, the waterproof layer and the decorative surface layer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020304738.8U CN211974017U (en) | 2020-03-12 | 2020-03-12 | Prefabricated bathroom floor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020304738.8U CN211974017U (en) | 2020-03-12 | 2020-03-12 | Prefabricated bathroom floor |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211974017U true CN211974017U (en) | 2020-11-20 |
Family
ID=73395043
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020304738.8U Active CN211974017U (en) | 2020-03-12 | 2020-03-12 | Prefabricated bathroom floor |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211974017U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113356643A (en) * | 2021-06-02 | 2021-09-07 | 蔡庸刚 | Prefabricated bathroom of integration |
-
2020
- 2020-03-12 CN CN202020304738.8U patent/CN211974017U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113356643A (en) * | 2021-06-02 | 2021-09-07 | 蔡庸刚 | Prefabricated bathroom of integration |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AU2018267563B2 (en) | Modular integrated building and construction method thereof | |
CN106121107B (en) | Assemble type concrete slab and its plate dry type connection method | |
CN102979304B (en) | Construction method of double shear wall formworks at deformation joint of high-rise building | |
CN211396208U (en) | Green type coincide floor's mosaic structure | |
CN206859479U (en) | A kind of steel bar girder laminated floor slab | |
CN210152069U (en) | Assembled high-rise steel structure residential system | |
CN211974017U (en) | Prefabricated bathroom floor | |
CN110815511A (en) | Integral toilet box mold and manufacturing and mounting method thereof | |
CN104264897B (en) | Alternate tooth must superimposed beam and plate | |
CN105275145A (en) | Assembly type multifunctional composite wallboard | |
CN106320601B (en) | Assembly concrete is whole without heat bridge board wall and its vertical connection method | |
CN107700840A (en) | Formwork structure | |
CN205224391U (en) | Multi -functional composite wall panel of assembled | |
CN201649291U (en) | Box house | |
CN114809512A (en) | Oversized prefabricated bare concrete hanging plate and manufacturing and mounting process | |
CN103541478B (en) | Lattice superposed beam and plate and construction method thereof | |
CN207633655U (en) | Outer gutter formwork structure | |
CN206189916U (en) | Bathroom room | |
CN103541479A (en) | Latticed two-way laminated slab | |
CN206189908U (en) | Bathroom room | |
CN201778774U (en) | Movable pedestal of oil pumping unit | |
CN106223532B (en) | Assembly concrete is whole without heat bridge wallboard | |
CN217128668U (en) | Integrated prefabricated floor in kitchen bathroom | |
CN205840314U (en) | A kind of assembled inner-outer wall composite shuttering mortar leakage prevention device | |
CN207160359U (en) | Prestressed concrete bidirectional laminated slab |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |