CN211973775U - Drainage ditch pouring template fixing device - Google Patents

Drainage ditch pouring template fixing device Download PDF

Info

Publication number
CN211973775U
CN211973775U CN202020156036.XU CN202020156036U CN211973775U CN 211973775 U CN211973775 U CN 211973775U CN 202020156036 U CN202020156036 U CN 202020156036U CN 211973775 U CN211973775 U CN 211973775U
Authority
CN
China
Prior art keywords
fixing
template
fixed
supporting arm
drainage ditch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020156036.XU
Other languages
Chinese (zh)
Inventor
陈强
张敏健
廖朝晖
郭智磊
陈云
刘林华
孙步红
许庆辉
陈琳
吴锦堂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 16 Co Ltd
PowerChina Airport Construction Co Ltd
Original Assignee
Sinohydro Bureau 16 Co Ltd
PowerChina Airport Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 16 Co Ltd, PowerChina Airport Construction Co Ltd filed Critical Sinohydro Bureau 16 Co Ltd
Priority to CN202020156036.XU priority Critical patent/CN211973775U/en
Application granted granted Critical
Publication of CN211973775U publication Critical patent/CN211973775U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

A fixing device for a pouring formwork of a drainage ditch is characterized in that a clamping frame consisting of 4 vertical fixing supporting arms is fixed below a cross arm, the distance between a first fixing supporting arm and an adjacent second fixing supporting arm is equal to the sum of the width of the wall of the drainage ditch and the thickness of formworks on two sides, and the distance between a third fixing supporting arm and an adjacent fourth fixing supporting arm is equal to the sum of the width of the other wall of the drainage ditch and the thickness of the formworks on two sides. The utility model can be recycled, the template can be ensured not to translate through the plane side of every two fixed supporting arms clinging to the template, the template positioning is ensured to the maximum extent, secondary fixing is not needed, and the installation precision is improved; simultaneously, when demolising the template, need not the instrument and sled and remove, as long as up lift the fixed bolster, can remove the fixed to the template, easy operation has guaranteed the integrality of ditch wall, sled when also having avoided demolising the mould and removed the iron nail and lead to the damaged defect of concrete, improved the efficiency of artifical demolising greatly.

Description

Drainage ditch pouring template fixing device
Technical Field
The utility model belongs to template fixing device is pour in escape canal.
Background
The concrete drainage ditch of the traditional central separation zone is U-shaped, after a bottom plate is poured, ditch walls on two sides are poured simultaneously, four ditch wall templates are fixed, generally, battens stretch across and are erected above the templates and fixed by iron nails, and two sides of the battens are connected to concrete bottom reinforcing steel bars to be poured by iron wires to be fixed. By adopting a traditional method, in order to strengthen the supporting force of the template, an iron nail with the diameter of more than 5mm is generally used, the fixed battens of the template are difficult to assemble and disassemble, are easy to damage, and have low recycling coefficient. Because the escape canal when carrying out concrete placement, the bearing capacity of stuff support is not enough, leads to the template below can strut because of the power of empting of concrete, and leads to the template skew, when demolising the template simultaneously, need remove the iron nail with the help of the instrument sled, leads to concrete surface and edges and corners that pour to be impaired because of the form removal easily like this.
Disclosure of Invention
The utility model aims to overcome the damaged defect that current central authorities 'separate zone concrete escape canal leads to because of the form removal in the construction process of production, provide an easy operation, quick, can improve the efficiency of construction, guarantee construction precision's escape canal and pour template fixing device.
The utility model discloses the technical scheme who adopts is a template fixing device is pour in escape canal, and its main points lie in, the tight frame of clamp that comprises the fixed 4 vertically fixed supporting arms in a horizontal arm below in it, and the interval between first fixed supporting arm and the adjacent fixed supporting arm of second equals escape canal wall width and both sides template thickness sum, and the interval between third fixed supporting arm and the adjacent fixed supporting arm of fourth equals another ditch wall width of escape canal and both sides template thickness sum.
The cross arm and the supporting arm are made of angle steel. The clamping frames can be formed by welding or fixing parts.
The clamping device is also provided with a longitudinal fixing rod which is fixed between the two clamping frames. Make the clamping frame all have the reinforcing action to whole template through the longitudinal fixing pole between two clamping frames, can prevent effectively that the template below from not being strutted when empting the concrete, guarantee construction quality.
There are 4 longitudinal fixing rods fixed to the bottom of the fixing support arms. Because the bottom end of the fixed supporting arm is stressed by large concrete pressure, the longitudinal fixing rod is fixed at the lower end of the fixed supporting arm, and the effect is optimal.
There are 8 longitudinal fixing rods fixed to the bottom and upper ends of the fixing support arms.
The utility model can be recycled, the template can be ensured not to translate through the plane side of every two fixed supporting arms clinging to the template, the template positioning is ensured to the maximum extent, secondary fixing is not needed, and the installation precision is improved; simultaneously, when demolising the template, need not the instrument and prize and remove, as long as up lift the fixed bolster, can remove the fixed to the template, easy operation has guaranteed the integrality of ditch wall, sled iron nail when also having avoided demolising leads to the damaged defect of concrete, improved the efficiency of artifical demolising greatly, make the clamping frame all have the additional work to whole template through the longitudinal fixing pole between two clamping frames simultaneously, can prevent effectively that the template below from not being strutted when empting the concrete, guarantee construction quality.
Drawings
FIG. 1 is a schematic structural diagram of embodiment 1 of the present invention
FIG. 2 is a side view of FIG. 1
FIG. 3 is a schematic structural diagram of embodiment 2 of the present invention
FIG. 4 is a schematic structural view of an A-shaped longitudinal fixing rod
FIG. 5 is a schematic view of a B-shaped longitudinal fixing rod
Wherein: 1 fixed support arm 11 first fixed support arm 12 second fixed support arm 13 third fixed support arm 14 fourth fixed support arm 2 crossbar 31A type longitudinal fixed rod 32B type longitudinal fixed rod.
Detailed description of the preferred embodiments
The present invention will now be described in detail with reference to the drawings, which illustrate examples that will enable those skilled in the art to more fully understand the invention, but which are not intended to limit the invention in any way
Example 1, as shown in fig. 1 and 2, a gutter-casting formwork fixing apparatus is provided in which a clamp frame consisting of 4 vertical fixing support arms 1 is fixed below a cross arm 2, the distance between a first fixing support arm 11 and an adjacent second fixing support arm 12 is equal to the sum of the width of a gutter wall and the thickness of formwork on both sides, and the distance between a third fixing support arm 13 and an adjacent fourth fixing support arm 14 is equal to the sum of the width of the other gutter wall of a gutter and the thickness of formwork on both sides. The cross arm and the supporting arm are made of angle steel. The clamping frames can be formed by welding or fixing parts. When the cast-in-place formwork is used, after the cast-in-place formwork is accurately positioned, the clamping frames are inserted into the outer side of the formwork at equal intervals, the fixed supporting arms face downwards, the cross arms are arranged upwards, so that the first fixed supporting arm 11 and the adjacent second fixed supporting arm 12 are tightly attached to one side of the trench wall formwork, and the third fixed supporting arm 13 and the adjacent fourth fixed supporting arm 14 are tightly attached to the other side of the trench wall formwork. When the concrete reaches a certain strength, the cross arm of the middle lattice is held to lift upwards when the formwork is removed.
Embodiment 2, as shown in fig. 3, is an improvement on the basis of embodiment 1, and adds a longitudinal fixing rod, which is fixed between two clamping frames, one surface of which is tightly attached to the formwork, and the adjacent clamping frames are placed in opposite or reverse directions, and because the fixing support arm is made of angle steel, the fixing modes between the longitudinal fixing rod and the fixing support arm are different, the longitudinal fixing rod is divided into two types, namely an a-type longitudinal fixing rod 31 and a B-type longitudinal fixing rod 32, as shown in fig. 4 and 5, wherein the a-type longitudinal fixing rod is a fixing surface which is formed by bending two ends of flat steel at right angles and forms an angle steel back plane with the fixing support arm. The B-shaped longitudinal fixing rod 32 is formed by bending two ends of flat steel into steps at right angles, the step height is not less than the thickness of the angle steel edge, the angle steel edge is thin, the processing difficulty is high, the step height can be properly increased, and the gasket is kept stable during fixed installation. The single clamping frame is continuously fixed into a whole through the longitudinal fixing rod, so that the clamping frame has a reinforcing effect on the whole formwork, the lower part of the formwork is effectively prevented from being propped open when the concrete is poured, and the construction quality is ensured. Generally, there are 4 longitudinal fixing rods fixed to the bottom end of the fixing support arm, and 8 longitudinal fixing rods fixed to the bottom end and the upper end of the fixing support arm, with the fixing mode being welding and alternate with fixing pieces. The rest of the composition which is not described is the same as that of example 1.

Claims (5)

1. A fixing device for a pouring formwork of a drainage ditch is characterized in that a clamping frame consisting of 4 vertical fixing supporting arms is fixed below a cross arm, the distance between a first fixing supporting arm and an adjacent second fixing supporting arm is equal to the sum of the width of the wall of the drainage ditch and the thickness of formworks on two sides, and the distance between a third fixing supporting arm and an adjacent fourth fixing supporting arm is equal to the sum of the width of the other wall of the drainage ditch and the thickness of the formworks on two sides.
2. The drain casting form fixture of claim 1, wherein the cross arms and the fixed support arms are formed from angle steel.
3. The drain casting form fixture of claim 1, further comprising a longitudinal retaining bar secured between the two clamping brackets.
4. The drain runner formwork mounting assembly of claim 3, wherein there are 4 longitudinal support rods secured to the bottom ends of the support arms.
5. A drain runner formwork mounting arrangement according to claim 3, wherein there are 8 longitudinal fixing rods secured to the lower and upper ends of the fixed support arms respectively.
CN202020156036.XU 2020-02-08 2020-02-08 Drainage ditch pouring template fixing device Active CN211973775U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020156036.XU CN211973775U (en) 2020-02-08 2020-02-08 Drainage ditch pouring template fixing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020156036.XU CN211973775U (en) 2020-02-08 2020-02-08 Drainage ditch pouring template fixing device

Publications (1)

Publication Number Publication Date
CN211973775U true CN211973775U (en) 2020-11-20

Family

ID=73372456

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020156036.XU Active CN211973775U (en) 2020-02-08 2020-02-08 Drainage ditch pouring template fixing device

Country Status (1)

Country Link
CN (1) CN211973775U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116695848A (en) * 2023-08-08 2023-09-05 山西三建集团建设工程有限公司 Construction method of cast-in-place concrete drain open trench

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116695848A (en) * 2023-08-08 2023-09-05 山西三建集团建设工程有限公司 Construction method of cast-in-place concrete drain open trench

Similar Documents

Publication Publication Date Title
CN211973775U (en) Drainage ditch pouring template fixing device
CN211973774U (en) Reinforced drainage ditch pouring template fixing device
CN114482691A (en) Assembled airport enclosure foundation template and using method thereof
CN214575658U (en) Post-cast strip template with cast-in-place concrete structure
CN209741897U (en) Quick-release supporting structure for foundation cup opening template
CN214194680U (en) Post-cast strip structure of underground garage
CN213418485U (en) Formwork supporting device for foundation preformed hole without formwork dismantling
CN210086255U (en) Secant pile guide wall template construction system
CN212053745U (en) Formwork support frame for post-cast strip construction
CN114016533A (en) Construction structure and construction method of large-section bearing platform deep cup foundation
CN208168349U (en) A kind of profile steel concrete column template reinforcing device
CN217168924U (en) Bridge sidewalk plate prefabricated formwork
CN106468101A (en) A kind of locating support for cast-in-place upper reversed beam side template
CN218643371U (en) A template that is used for side slope protection skeleton to stop water along concrete placement construction
CN217997986U (en) Mountain style of calligraphy template reinforcing apparatus
CN111058561A (en) Construction method for thin-wall square box rib-free accurate positioning hollow floor
CN217128944U (en) Toilet falling plate formwork supporting and positioning structure
CN218779935U (en) Steel form device is used in subsiding crack construction
CN219862911U (en) Anti-floating template of reentrant corner embedded rubber strip
CN214696840U (en) Template system for foundation pit construction
CN217106138U (en) Reinforcing structure for anti-bank template
CN213233067U (en) Rectangular side ditch wood pattern reinforcing apparatus
CN219666970U (en) Bridge cast steel template with protection support
CN216379660U (en) Advanced waterstop drainage tank and protective layer flanging device for bottom plate
CN219583141U (en) Mould for machine-made building block arch stacking

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant