CN211949165U - Hoop fixing device for ceiling conversion layer of top steel structure - Google Patents

Hoop fixing device for ceiling conversion layer of top steel structure Download PDF

Info

Publication number
CN211949165U
CN211949165U CN202020547382.0U CN202020547382U CN211949165U CN 211949165 U CN211949165 U CN 211949165U CN 202020547382 U CN202020547382 U CN 202020547382U CN 211949165 U CN211949165 U CN 211949165U
Authority
CN
China
Prior art keywords
cardboard
bottom plate
steelframe
steel
screw rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020547382.0U
Other languages
Chinese (zh)
Inventor
张留洋
蔡冲
彭真
李净
周萌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Construction Decoration Corp of China Construction Seventh Engineering Division Corp Ltd
Original Assignee
Construction Decoration Corp of China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Construction Decoration Corp of China Construction Seventh Engineering Division Corp Ltd filed Critical Construction Decoration Corp of China Construction Seventh Engineering Division Corp Ltd
Priority to CN202020547382.0U priority Critical patent/CN211949165U/en
Application granted granted Critical
Publication of CN211949165U publication Critical patent/CN211949165U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The application provides a top surface steel construction furred ceiling conversion layer staple bolt fixing device, left cardboard and right cardboard including the symmetry setting, left side cardboard and right cardboard articulate on the steelframe, the bottom welding of left side cardboard and right cardboard has the bottom plate, threaded connection has the screw rod on the bottom plate, the top butt of screw rod is in on the steelframe, the below welding of bottom plate has the square steel, the square steel below is used for connecting the furred ceiling device. Through articulating left cardboard and right cardboard symmetry in the both sides of steelframe, then at the bottom welding bottom plate of left cardboard and right cardboard, at the below welding square steel of bottom plate, threaded connection has the screw rod on the bottom plate, the top butt of screw rod is on the steelframe, connect the furred ceiling device on square steel, the device construction is simple, the reduction occupies original steelframe bearing load, simultaneously the firmness is high, satisfy and decorate the furred ceiling bearing requirement, the security performance is high.

Description

Hoop fixing device for ceiling conversion layer of top steel structure
Technical Field
The application relates to the technical field of building construction equipment, in particular to a hoop fixing device for a ceiling conversion layer of a top surface steel structure.
Background
In the construction engineering field, more and more building top surfaces adopt steel structure roofing, and when the furred ceiling construction was decorated to inside, the welding was comparatively difficult at top surface steel member, can destroy its structural stability even, and it is great to decorate the furred ceiling construction degree of difficulty. On the fixed top surface steel member of traditional staple bolt mode, it is big, with many materials to consume the labour, increases original steel construction bearing load, and fixed firmness is not high simultaneously, can't satisfy and decorate furred ceiling bearing requirement, and the security performance is not high.
SUMMERY OF THE UTILITY MODEL
For solving above-mentioned technical problem, this application provides a top surface steel construction furred ceiling conversion layer staple bolt fixing device, left cardboard and right cardboard including the symmetry setting, left side cardboard and right cardboard articulate on the steelframe, the bottom welding of left side cardboard and right cardboard has the bottom plate, threaded connection has the screw rod on the bottom plate, the top butt of screw rod is in on the steelframe, the below welding of bottom plate has the square steel, the square steel below is used for connecting the furred ceiling device.
Optionally, a rubber pad is arranged between the left clamping plate and the steel frame and between the right clamping plate and the steel frame.
Optionally, a rib plate is arranged between the bottom plate and the square steel.
Optionally, a gasket is arranged between the screw and the bottom plate.
Optionally, the left and right catch plates are both made of channel steel.
Use the technical scheme of this application, through articulating the both sides at the steelframe with left cardboard and right cardboard symmetry, then at the bottom welded bottom plate of left cardboard and right cardboard, below welding square steel at the bottom plate, threaded connection has the screw rod on the bottom plate, the top butt of screw rod is on the steelframe, connect the furred ceiling device on square steel, the device construction is simple, with just few, the welding point is few, reduce and occupy original steelframe bearing load, simultaneously the firmness is high, satisfy and decorate furred ceiling bearing requirement, the security performance is high.
Drawings
Fig. 1 is a schematic structural diagram of an embodiment of the present application.
Detailed Description
As shown in fig. 1, the application provides a top surface steel construction furred ceiling conversion layer staple bolt fixing device, left cardboard 1 and right cardboard 2 made by the channel-section steel that sets up including the symmetry, left cardboard 1 articulates on steelframe 7 with right cardboard 2, left cardboard 1 and right cardboard 2 all with be equipped with rubber pad 8 between the steelframe 7, the bottom welding of left cardboard 1 and right cardboard 2 has bottom plate 3, threaded connection has the screw rod 4 that plays the fixed action on the bottom plate 3, the top butt of screw rod 4 is on steelframe 7, be equipped with gasket 9 between screw rod 4 and the bottom plate 3, the welding of the below of bottom plate 3 has square steel 5, be equipped with reinforcing effect's gusset 6 between bottom plate 3 and the square steel 5, 5 below of square steel is used for connecting the furred ceiling device.
During the use, through with left cardboard and right cardboard symmetry articulate the both sides at the steelframe, then at the bottom welded bottom plate of left cardboard and right cardboard, pass the screw hole on the bottom plate with the screw rod to make the top butt of screw rod on the lower surface of steelframe, at the below welding square steel of bottom plate, connect the furred ceiling device on square steel.

Claims (5)

1. The utility model provides a top surface steel construction furred ceiling conversion layer staple bolt fixing device, its characterized in that, including left cardboard and the right cardboard that the symmetry set up, left cardboard and right cardboard articulate on the steelframe, the bottom welding of left cardboard and right cardboard has the bottom plate, threaded connection has the screw rod on the bottom plate, the top butt of screw rod is in on the steelframe, the welding of the below of bottom plate has the square steel, the square steel below is used for connecting the furred ceiling device.
2. The top steel structure ceiling conversion layer hoop fixing device as claimed in claim 1, wherein rubber pads are arranged between the left clamping plate and the steel frame and between the right clamping plate and the steel frame.
3. The anchor ear fixing device for the ceiling conversion layer of the steel structure with the top surface according to claim 1, wherein a rib plate is arranged between the bottom plate and the square steel.
4. The anchor ear fixing device for the ceiling conversion layer of the steel structure with the top surface as claimed in claim 1, wherein a gasket is arranged between the screw rod and the bottom plate.
5. The ceiling steel structure ceiling conversion layer hoop fixture as claimed in claim 1, wherein the left and right clamping plates are made of channel steel.
CN202020547382.0U 2020-04-14 2020-04-14 Hoop fixing device for ceiling conversion layer of top steel structure Active CN211949165U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020547382.0U CN211949165U (en) 2020-04-14 2020-04-14 Hoop fixing device for ceiling conversion layer of top steel structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020547382.0U CN211949165U (en) 2020-04-14 2020-04-14 Hoop fixing device for ceiling conversion layer of top steel structure

Publications (1)

Publication Number Publication Date
CN211949165U true CN211949165U (en) 2020-11-17

Family

ID=73164706

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020547382.0U Active CN211949165U (en) 2020-04-14 2020-04-14 Hoop fixing device for ceiling conversion layer of top steel structure

Country Status (1)

Country Link
CN (1) CN211949165U (en)

Similar Documents

Publication Publication Date Title
CN211974453U (en) Masonry brick wall steel plate belt reinforcing structure
CN215888960U (en) Steel structure beam
CN103437547B (en) A kind of aluminum alloy pattern plate
CN211949165U (en) Hoop fixing device for ceiling conversion layer of top steel structure
CN210944509U (en) Plate hoisting clamping part for building construction
CN210767411U (en) Water storage argil plate curtain wall beam column decoration structure
CN206337559U (en) A kind of prefabricated pile mechanical connecting structure
CN201714090U (en) Connection structure for aluminum alloy formwork components
CN211200726U (en) Connecting piece between square opening steel members
CN210104542U (en) Energy-consuming beam-falling-preventing device for controlling displacement of main beam
CN210767941U (en) Box steel column underpins node
CN206971801U (en) A kind of non-reinforced masonry building supporting reinforcing structure
CN208884809U (en) A kind of steel structures in construction works roof girder steel is connected and fixed structure
CN207776119U (en) A kind of connection structure of assembled wall
CN209114719U (en) Bolted honeycomb H profile steel beam
CN206562767U (en) Build beam forms shape-setting clamp
CN206681187U (en) The replaceable beam-type member of energy-consuming parts
CN220133173U (en) Semi-assembled steel-concrete combined shear wall
CN213683107U (en) Construction device for external wall internal corner waterproof structure
CN201144519Y (en) Rectangular assembly type wall big formwork
CN211804566U (en) Welding fixing device for steel structure production and processing
CN212176268U (en) Construction waste pressing brick convenient to use
CN220266977U (en) Novel rammed earth plate furred ceiling structure
CN215716074U (en) Concrete cantilever beam lengthening connecting joint without changing beam section size
CN211200905U (en) Concrete slab of high strength

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant