CN211899520U - Building outer wall construction structures - Google Patents

Building outer wall construction structures Download PDF

Info

Publication number
CN211899520U
CN211899520U CN202020065182.1U CN202020065182U CN211899520U CN 211899520 U CN211899520 U CN 211899520U CN 202020065182 U CN202020065182 U CN 202020065182U CN 211899520 U CN211899520 U CN 211899520U
Authority
CN
China
Prior art keywords
fixedly connected
guardrail
wall
workbench
top end
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020065182.1U
Other languages
Chinese (zh)
Inventor
颜军
李继填
曹伟明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Yijia Construction Engineering Co ltd
Original Assignee
Guangdong Yijia Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Yijia Construction Engineering Co ltd filed Critical Guangdong Yijia Construction Engineering Co ltd
Priority to CN202020065182.1U priority Critical patent/CN211899520U/en
Application granted granted Critical
Publication of CN211899520U publication Critical patent/CN211899520U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model belongs to the technical field of building engineering, in particular to a construction structure of an outer wall of a building, which comprises a device main body, an outer wall, a ground and an electric telescopic column, wherein the bottom end of the device main body is fixedly connected with the ground, the other side of the device main body is fixedly connected with the outer wall, the top end of the ground is movably connected with a universal wheel, the top end of the universal wheel is fixedly connected with a base, the middle of the top end of the base is movably connected with the electric telescopic column, the top end of the electric telescopic column is fixedly connected with a workbench, the workbench is arranged on the base, a guardrail is upwards drawn out to play a role in protecting workers, the safety factor of a working environment is improved, after the whitewashing work is finished, a limiting pin is drawn out from a limiting hole, the guardrail downwards moves under the action of the gravity of the guardrail and is inserted into a limiting, therefore, the whole volume of the device main body is greatly reduced, and the carrying of subsequent workers is facilitated.

Description

Building outer wall construction structures
Technical Field
The utility model belongs to the technical field of building engineering, specifically be a building outer wall construction structures.
Background
The outer wall of the building is used for enclosing the building, and has the functions and functions of bearing certain load, shielding wind and rain, preserving heat, insulating heat, preventing noise, preventing fire, and the like. The existing construction structure of the building outer wall has the defects of complex disassembly and assembly process and easy falling, and the problems need to be solved urgently.
The existing building outer wall construction structure can be inconvenient to carry, the condition of leaking materials, when the work is to the outer wall cement coating, cement often falls at the bottom corner of outer wall, forms protruding cement block, causes the cement clearance of corner to become difficult, and current work elevating platform is bulky, inconvenient to carry, therefore equipment is perfect inadequately, is difficult to satisfy modern society's demand.
Therefore, how to design a construction structure of the building outer wall becomes a problem which needs to be solved currently.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a building outer wall construction structures to propose inconvenient carrying in solving above-mentioned background art, leak the problem of material.
In order to achieve the above object, the utility model provides a following technical scheme: a construction structure of an external wall of a building comprises a device main body, an external wall, the ground and an electric telescopic column, wherein the ground is fixedly connected to the bottom end of the device main body, the external wall is fixedly connected to the other side of the device main body, a universal wheel is movably connected to the top end of the ground, a base is fixedly connected to the top end of the universal wheel, the electric telescopic column is movably connected to the middle of the top end of the base, a workbench is fixedly connected to the top end of the electric telescopic column, through holes are fixedly connected to the two ends of the workbench, a connecting block is fixedly connected to the other side of the workbench, a guardrail is movably connected to the inner wall of each through hole, a handrail is fixedly connected to the top end of the guardrail, a limiting block is movably connected to the bottom end of the guardrail, a bearing plate is embedded and connected to the, and two ends of the workbench are fixedly connected with limiting holes.
Preferably, two ends of the bottom of the base are movably connected with supporting legs.
Preferably, the periphery of the handrail is fixedly connected with a non-slip mat.
Preferably, the periphery of the bottom end of the guardrail is fixedly connected with a rubber layer.
Preferably, one of the bearing plates, the connecting groove, the flat plate and the connecting block form a material leakage prevention mechanism.
Preferably, the workbench is provided with one workbench, and the workbench, the electric telescopic column, the guardrail and the limiting block form a lifting mechanism together.
Compared with the prior art, the beneficial effects of the utility model are that:
1. this kind of building outer wall construction structure promotes the base and makes the flat board and the outer wall of accepting the board opposite side horizontal in the vertical direction to accept the board and dwindle zero with the gap between workstation and the outer wall, make and accept the board and can catch the cement that drops, avoided the cement to drop the corner in the outer wall bottom, reduced the work load of clearance, and accept the board and be connected with the workstation through the mode that the embedding is connected, the installation is dismantled conveniently.
2. This kind of building outer wall construction structure upwards takes the guardrail out, plays the effect of a protection to the workman, after accomplishing the work of painting, takes the spacer pin out from spacing hole, and the guardrail moves down, inserts the stopper in the middle of fixed, then adjusts electronic flexible post for the distance between workstation and the base is the shortest, makes the whole volume of device main part reduce greatly with this, has made things convenient for follow-up workman's carrying.
Drawings
FIG. 1 is a sectional view of the overall structure of the present invention;
FIG. 2 is a schematic view of the receiving plate of the present invention;
FIG. 3 is a schematic view of the guardrail and the workbench of the present invention;
fig. 4 is a schematic view of the position a of the present invention.
In the figure: 1. the device comprises a device main body, 2, an outer wall, 3, ground, 4, an electric telescopic column, 5, a workbench, 6, universal wheels, 7, supporting legs, 8, a limiting block, 9, a guardrail frame, 10, a via hole, 11, a handrail, 12, an anti-slip pad, 13, a connecting block, 14, a bearing plate, 15, a connecting groove, 16, a flat plate, 17, a limiting hole, 18, a rubber layer, 19 and a base.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, rather than all embodiments, and all other embodiments obtained by a person of ordinary skill in the art without creative work belong to the protection scope of the present invention based on the embodiments of the present invention.
In a first embodiment, please refer to fig. 1-4, the present invention provides a technical solution: a construction structure of an external wall of a building comprises a device main body 1, an external wall 2, a ground 3 and an electric telescopic column 4, wherein the ground 3 is fixedly connected to the bottom end of the device main body 1, the external wall 2 is fixedly connected to the other side of the device main body 1, a universal wheel 6 is movably connected to the top end of the ground 3, a base 19 is fixedly connected to the top end of the universal wheel 6, the electric telescopic column 4 is movably connected to the middle of the top end of the base 19, a workbench 5 is fixedly connected to the top end of the electric telescopic column 4, through holes 10 are fixedly connected to the two ends of the workbench 5, a connecting block 13 is fixedly connected to the other side of the workbench 5, a guardrail 9 is movably connected to the inner wall of each through hole 10, a handrail 11 is fixedly connected to the top end of the guardrail 9, a limiting block 8 is movably connected, the other side of the bearing plate 14 is fixedly connected with a flat plate 16, and two ends of the workbench 5 are fixedly connected with limit holes 17.
Preferably, the supporting legs 7 are movably connected to two ends of the bottom of the base 19, the base 19 generally needs to be stabilized on the ground after being moved to a proper position, in order to achieve the above situation, the four supporting legs 7 are rotated by one hundred eighty degrees, so that the four supporting legs 7 are in contact with the ground, and the distance between the universal wheel 6 and the ground is smaller than the distance between the four supporting legs 7 and the ground, so that the four supporting legs 7 can support the base 19, and the base 19 is prevented from rolling on the ground.
Preferably, the periphery of handrail 11 is fixedly connected with slipmat 12, and when the staff hand was taken on handrail 11, can cause the unstable condition of staff's standing because the hand skidded with handrail 11 usually, in order to avoid this condition, set up slipmat 12 in handrail 11's periphery, then the handle is put on slipmat 12 to the frictional resistance of handrail 11 with the staff hand has been increased, it is more stable when making the staff snatch handrail 11.
Preferably, the rubber layer 18 is fixedly connected to the periphery of the bottom end of the guardrail 9, when the guardrail 9 is fixed to the workbench 5, collision generally occurs, large friction is caused, in order to avoid the situation, the rubber layer 18 is arranged on the periphery of the bottom end of the guardrail 9, the guardrail 9 is prevented from being in direct contact with the workbench 5, the collision force between the guardrail 9 and the workbench 5 is reduced through the rubber layer 18, and the service life of the guardrail 9 and the workbench 5 is prolonged.
Preferably, one bearing plate 14, which forms a leakage-proof mechanism together with the connecting groove 15, the flat plate 16 and the connecting block 13, when the work is performed on the outer wall 2, cement often falls on the corner at the bottom end of the outer wall 2 to form a protruding cement block, so that the cement at the corner is difficult to clean, in order to avoid this situation, the bearing plate 14 is inserted into the connecting block 13 through the connecting groove, so that the bearing plate 14 is connected with the workbench 5 into a whole, then the base 19 is pushed to make the flat plate 16 at the other side of the bearing plate 14 horizontal to the outer wall 2 in the vertical direction, so that the gap between the workbench 5 and the outer wall 2 is reduced to zero by the bearing plate 14, the falling cement can be received by the bearing plate 14, the cement is prevented from falling on the corner at the bottom end of the outer wall 2, the cleaning workload is reduced, and the bearing plate 14 is connected with the workbench 5 in an embedding connection manner, the installation and the disassembly are convenient.
Preferably, one workbench 5 is provided, the workbench, the electric telescopic column 4, the guardrail 9 and the limiting block 8 form a lifting mechanism together, a height-adjustable workbench lifting platform is required when the outer wall 2 is painted, but the conventional workbench lifting platform is large in size and inconvenient to move, in order to avoid the situation, the workbench 5 is arranged on the base 19, a worker stands on the workbench 5 to pull out the guardrail 9 upwards, then the limiting pin penetrates through the bottom end of the guardrail 9 and the limiting hole 17 in the front of the workbench 5, so that the guardrail 9 is fixed on the periphery of the workbench 5, a protection effect is achieved for the worker, the safety factor of the working environment is improved, then the electric telescopic column 4 is opened, the workbench 5 is lifted to a proper height, the worker can conveniently paint the outer wall 2, after the painting work is finished, the limiting pin is pulled out from the limiting hole 17, because the effect of 9 gravity of guardrail, 9 downstream of guardrail insert the stopper 8 in the middle of fixed, then adjust electronic flexible post 4 for the distance between workstation 5 and the base 19 is the shortest, makes the whole volume of device main part 1 reduce greatly with this, has made things convenient for follow-up workman's carrying.
The working principle is as follows: firstly, the supporting feet 7 are installed, the supporting feet 7 are movably connected to two ends of the bottom of the base 19, the base 19 is required to be stabilized on the ground after being moved to a proper position, in order to achieve the situation, the four supporting feet 7 are rotated by one hundred eighty degrees, so that the four supporting feet 7 are in contact with the ground, the distance between the universal wheel 6 and the ground is smaller than that between the four supporting feet 7 and the ground, the four supporting feet 7 can support the base 19, and the base 19 is prevented from rolling on the ground;
then, the anti-slip mat 12 is installed, the anti-slip mat 12 is fixedly connected to the periphery of the handrail 11, when a worker puts a hand on the handrail 11, the situation that the worker is unstable in standing due to slipping of the hand and the handrail 11 is generally caused, in order to avoid the situation, the anti-slip mat 12 is arranged on the periphery of the handrail 11, and then the hand is placed on the anti-slip mat 12, so that the friction resistance between the handrail 11 and the hand of the worker is increased, and the worker can more stably grab the handrail 11;
then, the abrasion degree of the rubber layer 18 is checked, the rubber layer 18 is fixedly connected to the periphery of the bottom end of the guardrail 9, when the guardrail 9 is fixed with the workbench 5, collision usually occurs, and large friction is caused, in order to avoid the situation, the rubber layer 18 is arranged on the periphery of the bottom end of the guardrail 9, so that the guardrail 9 is prevented from being in direct contact with the workbench 5, the collision force between the guardrail 9 and the workbench 5 is reduced through the rubber layer 18, and the service lives of the guardrail 9 and the workbench 5 are prolonged;
next, the leakage-proof mechanism is installed, one receiving plate 14, the connecting groove 15, the flat plate 16 and the connecting block 13 form the leakage-proof mechanism, when the leakage-proof mechanism works on the outer wall 2, cement often falls on the corner at the bottom end of the outer wall 2 to form a protruding cement block, and therefore cement cleaning at the corner becomes difficult, in order to avoid the situation, the receiving plate 14 is inserted into the connecting block 13 through the connecting groove, so that the receiving plate 14 is connected with the workbench 5 into a whole, then the base 19 is pushed to enable the flat plate 16 at the other side of the receiving plate 14 to be horizontal with the outer wall 2 in the vertical direction, so that the receiving plate 14 reduces the gap between the workbench 5 and the outer wall 2 to zero, the receiving plate 14 can receive the falling cement, the cement is prevented from falling on the corner at the bottom end of the outer wall 2, the cleaning workload is reduced, and the receiving plate 14 is connected with the workbench 5 in an embedding connection mode, the installation and the disassembly are convenient;
finally, the guard bar 9 is put down to be convenient for a worker to carry, one working platform 5 is provided, the working platform 5, the electric telescopic column 4, the guard bar 9 and the limiting block 8 form a lifting mechanism together, the height-adjustable working lifting platform is needed when the outer wall 2 is painted, but the existing working lifting platform is large in size and inconvenient to move, in order to avoid the situation, the working platform 5 is arranged on the base 19, the worker stands on the working platform 5 to draw out the guard bar 9 upwards, then the limiting pin penetrates through the bottom end of the guard bar 9 and the limiting hole 17 in the front of the working platform 5, the guard bar 9 is fixed on the periphery of the working platform 5 to play a role in protecting workers, the safety coefficient of the working environment is improved, then the electric telescopic column 4 is opened to enable the working platform 5 to be lifted to a proper height, the worker can conveniently paint the outer wall 2, after the painting work is finished, take the spacer pin out from spacing hole 17, because the effect of guardrail 9 gravity, guardrail 9 moves down, inserts in the middle of the stopper 8 fixed, then adjusts electronic flexible post 4 for the distance between workstation 5 and the base 19 is the shortest, makes the whole volume of device main part 1 reduce greatly with this, has made things convenient for follow-up workman's carrying, and this is exactly this kind of building outer wall construction structure's theory of operation.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a building outer wall construction structures, includes device main part (1), outer wall (2), ground (3) and electronic flexible post (4), its characterized in that: the device comprises a device body (1), wherein the bottom end of the device body (1) is fixedly connected with a ground (3), the other side of the device body (1) is fixedly connected with an outer wall (2), the top end of the ground (3) is movably connected with a universal wheel (6), the top end of the universal wheel (6) is fixedly connected with a base (19), the middle of the top end of the base (19) is movably connected with an electric telescopic column (4), the top end of the electric telescopic column (4) is fixedly connected with a workbench (5), the two ends of the workbench (5) are fixedly connected with via holes (10), the other side of the workbench (5) is fixedly connected with a connecting block (13), the inner wall of each via hole (10) is movably connected with a guardrail (9), the top end of each guardrail (9) is fixedly connected with a handrail (11), the bottom end of each guardrail (9) is movably connected with a limiting block (8, one side of the bearing plate (14) is fixedly connected with a connecting groove (15).
2. The construction structure of an exterior wall of a building according to claim 1, wherein: the other side of the bearing plate (14) is fixedly connected with a flat plate (16), and two ends of the workbench (5) are fixedly connected with limiting holes (17).
3. The construction structure of an exterior wall of a building according to claim 1, wherein: the two ends of the bottom of the base (19) are movably connected with supporting legs (7).
4. The construction structure of an exterior wall of a building according to claim 1, wherein: the periphery of the handrail (11) is fixedly connected with an anti-skid pad (12).
5. The construction structure of an exterior wall of a building according to claim 1, wherein: the periphery of the bottom end of the guardrail (9) is fixedly connected with a rubber layer (18).
6. The construction structure of an exterior wall of a building according to claim 1, wherein: the material leakage prevention mechanism is composed of one bearing plate (14), a connecting groove (15), a flat plate (16) and a connecting block (13).
7. The construction structure of an exterior wall of a building according to claim 1, wherein: the working table (5) is provided with one lifting mechanism which is formed together with the electric telescopic column (4), the guardrail (9) and the limiting block (8).
CN202020065182.1U 2020-01-13 2020-01-13 Building outer wall construction structures Active CN211899520U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020065182.1U CN211899520U (en) 2020-01-13 2020-01-13 Building outer wall construction structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020065182.1U CN211899520U (en) 2020-01-13 2020-01-13 Building outer wall construction structures

Publications (1)

Publication Number Publication Date
CN211899520U true CN211899520U (en) 2020-11-10

Family

ID=73297867

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020065182.1U Active CN211899520U (en) 2020-01-13 2020-01-13 Building outer wall construction structures

Country Status (1)

Country Link
CN (1) CN211899520U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113431310A (en) * 2021-06-24 2021-09-24 刘巨星 Building outer wall construction structures

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113431310A (en) * 2021-06-24 2021-09-24 刘巨星 Building outer wall construction structures

Similar Documents

Publication Publication Date Title
CN204716124U (en) Portable removable level-sensing device inspection platform
CN211899520U (en) Building outer wall construction structures
CN202831589U (en) Movable type security operating platform
CN205933128U (en) Portable pneumatic type plug -in strip goes up and down to overhaul platform
CN205476387U (en) Scaffold
CN207003981U (en) A kind of movable altitude operation protective frame with safety supports
CN206607828U (en) A kind of safe construction platform
CN103696579A (en) Vertical material conveyor
CN114050500B (en) Power transmission line climbing tower manned chair along anti-falling track
CN206308987U (en) A kind of convenient Liftable and movable scaffold for building
CN210885190U (en) Integral type auxiliary device based on fire-fighting equipment installation usefulness
CN209837631U (en) Multistage assembled lattice frame building structure
CN217840832U (en) Fall protection device for building safety
CN218991476U (en) Vertical ladder with rest plate
CN203530857U (en) Operable lifting construction bearing platform
CN211035051U (en) Hoisting and transporting platform for indoor substation equipment
CN205976600U (en) Staircase structure for lift platform
CN205531275U (en) Automatic over -and -under type scaffold frame
CN207260642U (en) Working at height floor hanger
CN217840777U (en) Building engineering wall body equipment of building in room
CN216641337U (en) Scaffold work platform
CN213174706U (en) Scaffold for building engineering
CN220814839U (en) Building engineering building climbing frame
CN210564337U (en) Portable cat ladder of portable
CN205023638U (en) Protection device in gap between construction elevator well and floor

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant