CN211898808U - Reinforced concrete pipeline mounting structure - Google Patents
Reinforced concrete pipeline mounting structure Download PDFInfo
- Publication number
- CN211898808U CN211898808U CN202020079977.8U CN202020079977U CN211898808U CN 211898808 U CN211898808 U CN 211898808U CN 202020079977 U CN202020079977 U CN 202020079977U CN 211898808 U CN211898808 U CN 211898808U
- Authority
- CN
- China
- Prior art keywords
- clamp
- locating
- reinforced concrete
- plate
- rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000011150 reinforced concrete Substances 0.000 title claims abstract description 43
- 238000009434 installation Methods 0.000 claims abstract description 22
- 238000005728 strengthening Methods 0.000 claims description 4
- 239000004567 concrete Substances 0.000 abstract description 5
- 230000000694 effects Effects 0.000 abstract description 5
- 230000000087 stabilizing effect Effects 0.000 description 7
- 230000003014 reinforcing effect Effects 0.000 description 3
- 230000000712 assembly Effects 0.000 description 2
- 238000000429 assembly Methods 0.000 description 2
- 238000006073 displacement reaction Methods 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000001125 extrusion Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000002994 raw material Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Landscapes
- Supports For Pipes And Cables (AREA)
Abstract
The utility model relates to a reinforced concrete pipeline mounting structure belongs to reinforced concrete pipeline mounting's technical field, and it includes the locating plate, and the locating plate is placed in the pit bottom, is provided with a plurality of groups locating piece on the locating plate, and per two locating pieces symmetry sets up on the locating plate, is provided with the roll adjustment subassembly between every locating piece and the locating plate, and on adjacent locating plate homonymy locating piece, per two locating pieces are provided with clamping device, the utility model discloses have the effect that reaches the stable installation of different diameter concrete pipe.
Description
Technical Field
The utility model belongs to the technical field of the technique of reinforced concrete piping erection and specifically relates to a reinforced concrete piping erection structure is related to.
Background
At present, the reinforced concrete pipeline is widely applied to an infrastructure drainage system, and as a main product of traditional municipal drainage and water supply engineering, the reinforced concrete pipeline is widely accepted and applied, so that the reinforced concrete pipeline has absolute advantages and public praise. Firstly, the reinforced concrete pipeline has the advantages of higher compressive strength, simple production process, high processing efficiency, low manufacturing cost and the like. Secondly, the reinforced concrete pipeline has reasonable structural form, can be efficiently combined and connected together, and ensures the whole tightness. Finally, the reinforced concrete has wide raw materials, and after the reinforced concrete is prefabricated in batches and transported to a site for combination, the compression resistance and the seismic performance of the whole pipeline are ensured at a certain height, thereby providing guarantee for stable use.
The existing Chinese patent with reference to publication number CN207093920U discloses a reinforced concrete pipeline installation positioning stable structure, which comprises a cushion layer in a pipeline groove pit, wherein an embedded groove is arranged on the cushion layer, a plurality of stabilizing blocks are fixedly arranged on the embedded groove, every two stabilizing blocks are symmetrically arranged, concave arc-shaped grooves are arranged on the top surfaces of the stabilizing blocks, and a pipeline section is externally provided with a wall frame which is stably arranged on two adjacent cushion block concave arc-shaped grooves. Through the stable arrangement of a plurality of cushion blocks, the pipeline erected on the cushion blocks is stably placed, and the construction efficiency is improved.
The above prior art solutions have the following drawbacks: the stabilizing block is concrete, and the size of stabilizing the block after prefabricating out and the size of stabilizing the concave arc-shaped groove of block top surface are fixed size, and this device can not be applied to the installation of different specification concrete pipe promptly and lay, if want to adapt to different diameter piping erection, need prepare multiple stabilizing block that corresponds specification size, has increased concrete pipe erection cost, extravagant manpower and engineering installation time.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a reinforced concrete pipeline mounting structure reaches the effect that different diameter concrete pipeline stably installed.
The above utility model discloses an above-mentioned utility model purpose can realize through following technical scheme:
reinforced concrete pipeline mounting structure, including the locating plate, the locating plate is placed in the groove bottom of the well, is provided with a plurality of groups of locating pieces on the locating plate, and every two locating pieces symmetry sets up on the locating plate, is provided with the roll adjustment subassembly between every locating piece and the locating plate, and on adjacent locating plate homonymy locating piece, every two locating pieces were provided with clamping device.
Through adopting above-mentioned technical scheme, the locating plate is placed in the groove bottom of the well, provides supporting platform for the locating piece, and indirect increase locating piece bottom area makes the relative settlement degree of locating piece after the atress on every locating plate can not differ a lot. Every two parallel positioning blocks are fixed on a straight line by the clamping device, so that the two parallel positioning blocks are positioned on the straight line, and the axes of the installation pipelines cannot deviate. Every two locating pieces are symmetrically arranged on the locating plate to form a concave space, the reinforced concrete pipe is placed in the interior and is limited by the locating pieces, the fixed positions of the opposite locating pieces on the locating plate are enabled by adjusting the distance adjusting assembly, the distance between the opposite locating pieces is changed, and therefore the stable installation effect of the reinforced concrete pipe adapting to different diameters is achieved.
The utility model discloses further set up to: the locating piece includes diaphragm and riser, riser bottom surface and diaphragm top surface fixed connection, riser perpendicular to diaphragm, and the riser setting is in double-phase relative diaphragm furthest limit portion department, the roll adjustment subassembly includes first locating hole, and first locating hole is seted up on the diaphragm, runs through the diaphragm, has seted up a plurality of second locating holes on the locating plate, and the second locating hole is with the specification with first locating hole, and the second locating hole is along locating plate horizontal central axis evenly distributed, and first locating hole and second locating hole are the non-round hole, and first locating hole and second locating hole have inserted the bolt.
Through adopting above-mentioned technical scheme, through the positional relation of first locating hole and a plurality of second locating hole on the regulation diaphragm, change the distance between the relative riser to change the size of the concave type space that the relative riser formed, with this stable installation that adapts to different diameter reinforced concrete pipelines, first locating hole and second locating hole are the non-round hole, and the non-round hole setting is placed the diaphragm rotation on the locating plate.
The utility model discloses further set up to: all insert in establishing and be fixed with the strengthening rib on diaphragm, riser and the locating plate, the strengthening rib staggers first location and the setting of second locating hole.
By adopting the technical scheme, the installed pipeline is a reinforced concrete pipeline, the weight is large, and the transverse plate, the vertical plate and the positioning plate are provided with the reinforcing ribs, so that the pressure resistance of the transverse plate, the vertical plate and the positioning plate is enhanced.
The utility model discloses further set up to: be provided with the chamfer structure on the diaphragm, the chamfer structure is located the diaphragm top, keeps away from riser one side edge.
By adopting the technical scheme, after the distance between the two opposite positioning blocks is adjusted to adapt to the diameter of the reinforced concrete pipeline, the distance is generated between the two opposite transverse plates, when the reinforced concrete pipeline is erected in the space formed by the two opposite positioning blocks, the bottom of the pipeline and the top of the transverse plate are away from one side edge of the vertical plate to be in angular contact, the right-angled corners bear the weight of the reinforced concrete pipeline and are easy to collapse, the right-angled chamfers have certain radians, the pressure resistance of the bearing corners is enhanced, and the stability of the installation of the reinforced concrete pipeline is ensured.
The utility model discloses further set up to: the clamping device comprises a first clamp, a second clamp and a connecting rod, wherein one end of the connecting rod is fixedly connected with the first clamp, and the other end of the connecting rod is fixedly connected with the second clamp.
By adopting the technical scheme, the two parallel positioning blocks are clamped and fixed by the first clamp and the second clamp, and the connecting rod is in threaded connection between the first clamp and the second clamp, so that the two parallel positioning blocks are positioned on the same straight line, and the axis is on the same straight line when the reinforced concrete pipe is installed.
The utility model discloses further set up to: and the first clamp and the second clamp are in threaded connection with fastening components, the first clamp and the second clamp are both in U shapes, and the fastening components are positioned on the side walls of the first clamp and the second clamp, which are far away from the connecting rod.
Through adopting above-mentioned technical scheme, fastening components makes the locating piece that first anchor clamps and second anchor clamps held more firm, avoids the pipeline extrusion to produce the displacement phenomenon, ensures pipeline installation's stability.
The utility model discloses further set up to: the fastening assembly comprises a screw, a hand wheel and a push plate, screw threads penetrate through the side wall of the first clamp and the side wall of the second clamp far away from the connecting rod, one end of the screw inside the first clamp and the second clamp is in threaded connection with the push plate, and one end of the screw outside the first clamp and the second clamp is in fixed connection with the hand wheel.
Through adopting above-mentioned technical scheme, rotate the hand wheel, the hand wheel drives the screw rod and rotates, and the screw rod passes the anchor clamps lateral wall and drives the push pedal and take place the displacement in anchor clamps, and the push pedal does not have the size that the lateral wall of screw rod formed the locating piece with anchor clamps to this centre gripping that adapts to not equidimension locating piece increases the application range of equipment.
The utility model discloses further set up to: the connecting rod comprises an inner rod and an outer rod, a plurality of first bolt holes and second bolt holes of the same specification are formed in the inner rod and the outer rod respectively, one end of the inner rod is inserted into one end of the outer rod, the inner rod slides along the length direction of the outer rod in the outer rod, the other end of the inner rod is fixedly connected with a first clamp, the other end of the outer rod is fixedly connected with a second clamp, and the bolt penetrates through the first bolt holes and the second bolt holes.
Through adopting above-mentioned technical scheme, in the outer pole that interior pole inserted and inlayed, freely slided along outer pole direction in outer pole, through the position of first bolt hole and second bolt hole coincidence, the completion is to the change of connecting rod total length and form stable structure. The total length of the connecting rod is changed, namely the fastening component can adapt to the use of positioning blocks with different distances.
To sum up, the utility model discloses a beneficial technological effect does:
1. the distance between the two relative positioning blocks is adjusted, so that the utility model can be suitable for the stable installation of reinforced concrete pipelines with different diameters;
2. the distance adjusting assembly enables the two parallel positioning blocks to be located on the same straight line, the uniformity of pipeline positioning is guaranteed, the pipeline axes are located on the same straight line, and the phenomenon that adjacent pipeline sections cannot be butted upwards is avoided.
Drawings
FIG. 1 is a schematic view of the overall structure of a reinforced concrete pipe installation structure according to the present invention;
FIG. 2 is a view showing a state of use of the reinforced concrete pipe installation structure of the present invention;
FIG. 3 is a schematic view of the positioning block mounting structure of the reinforced concrete pipe mounting structure of the present invention;
fig. 4 is a schematic structural view of the clamping device of the reinforced concrete pipeline installation structure of the present invention.
In the figure, 1, a positioning plate; 2. positioning blocks; 21. a transverse plate; 211. a chamfering structure; 22. a vertical plate; 3. a distance adjusting component; 31. a first positioning hole; 32. a second positioning hole; 33. a bolt; 4. reinforcing ribs; 5. a clamping device; 51. a first clamp; 52. a second clamp; 53. a connecting rod; 531. an inner rod; 5311. a first bolt hole; 532. an outer rod; 5321. a second bolt hole; 54. a bolt; 6. a fastening assembly; 61. a screw; 62. a hand wheel; 63. a push plate.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Referring to fig. 1 and 2, do the utility model discloses a reinforced concrete pipeline mounting structure, including locating plate 1, locating plate 1 is the rectangular plate, and locating plate 1 places in the pit bottom. A plurality of positioning blocks 2 are fixedly arranged on the positioning plate 1, and at least two positioning blocks 2 are arranged and are oppositely arranged on the same plane of the positioning plate 1. The positioning block 2 comprises a transverse plate 21 and a vertical plate 22, the transverse plate 21 is horizontally placed on the positioning plate 1, the vertical plate 22 is vertically fixed on a top plate of the transverse plate 21, the vertical plate 22 is arranged at the position of the farthest distance from the edge of the two opposite transverse plates 21, the two opposite fixing blocks form a concave space, and a pipeline is erected in the concave space. The diaphragm 21 top corner department that is close to each other is provided with chamfer structure 211, when the reinforced concrete pipe frame was on two diaphragms 21, because gapped between two diaphragms 21, reinforced concrete pipe and diaphragm 21 top corner direct contact, if for the right angle, the easy damaged atress of right angle is weak, with right angle chamfer, has strengthened diaphragm 21's bearing nature. The transverse plate 21, the vertical plate 22 and the horizontal plate are internally provided with reinforcing ribs 4, so that the overall pressure resistance is increased.
Referring to fig. 3, the transverse plate 21 is provided with a first positioning hole 31, the positioning plate 1 is provided with a plurality of second positioning holes 32, the second positioning holes 32 are uniformly arranged along the central axis of the positioning plate 1 in the length direction, the first positioning hole 31 and the second positioning hole 32 have the same specification, and the first positioning hole 31 and the second positioning hole 32 are rectangular holes. The distance relation between the relative positioning blocks 2 is changed by adjusting the position relation of the transverse plate 21 on the positioning plate 1, so that the stable installation of reinforced concrete pipelines with different diameters is adapted, after the position relation is adjusted, the inserted pin 33 is inserted into the first positioning hole 31 and the second positioning hole 32, the fixing effect of the positioning blocks 2 and the positioning plate 1 is completed, and the inserted part of the inserted pin 33 is a long rectangular shape.
Referring to fig. 4, the clamping device 5 includes a first clamp 51, a second clamp 52, and a connecting rod 53, wherein the first clamp 51 and the second clamp 52 are concave, and the concave part is used for placing the clamped object. The link 53 includes an outer rod 532 and an inner rod 531, one end of the inner rod 531 is inserted into one end of the outer rod 532, and the inner rod 531 is freely slidable in the outer rod 532 in the direction of the outer rod 532. Seted up a plurality of first bolt holes 5311 on interior pole 531, seted up a plurality of second bolt holes 5321 on the outer pole 532, first bolt hole 5311 is the same with second bolt hole 5321 specification, and through adjusting interior pole 531 the inside gliding distance of outer pole 532, change the distance between first anchor clamps 51 and the second anchor clamps 52, thereby increase the utility model discloses an application range, interior pole 531 outer pole 532 after adjusting the position passes through bolt 54 fixedly. The fastening assemblies 6 are arranged on the first clamp 51 and the second clamp 52 in a threaded manner, the fastening assemblies 6 are arranged on one side wall, away from the connecting rod 53, of the first clamp 51 and the second clamp 52, each fastening assembly 6 comprises a screw rod 61, each screw rod 61 penetrates through the side wall, away from the connecting rod 53, of the first clamp 51 and the second clamp 52, one end, far away from the first clamp 51 and the second clamp 52, of each screw rod 61 is connected with a push plate 63 in a threaded manner, each push plate 63 is in a circular plate shape, and the other end of each screw rod 61 is fixedly connected with a hand wheel 62. When the object to be clamped placed in the first clamp 51 or the second clamp 52 is small, the hand wheel is rotated to adjust the position relation of the push plate 63 in the first clamp 51 or the second clamp 52, so that the push plate 63 is attached to one side of the clamped object, and the clamped object is firmly fastened.
The implementation principle of the embodiment is as follows: the positioning plate 1 is placed at the bottom of the excavated groove pit, the two positioning blocks 2 are fixedly arranged on the positioning plate 1, and the distance between the two opposite positioning blocks 2 is changed by adjusting the position relation of the first positioning hole 31 and the second positioning hole 32, so that the positioning blocks 2 can adapt to the size of the reinforced concrete pipeline. The positioning blocks 2 on the adjacent positioning plates 1 are fixedly provided with clamping devices 5, the first clamp 51 and the second clamp 52 respectively clamp the positioning blocks 2 on the same side on the two positioning plates 1, and if the distance is not enough, the distance between the adjacent positioning blocks 2 can be adapted by adjusting the relative distance relationship between the inner rod 531 and the outer rod 532. If the positioning block 2 is too small, the first clamp 51 or the second clamp 52 cannot clamp the positioning block, the position relation of the push plate 63 in the first clamp 51 or the second clamp 52 is adjusted by rotating the hand wheel, so that the push plate 63 tightly pushes the positioning block 2, and the positioning blocks 2 with different sizes are clamped. The adjacent positioning blocks 2 fixed by the clamping device 5 are on the same straight line, so that the central axis of the installation pipeline is always on the same straight line.
The embodiment of this specific implementation mode is the preferred embodiment of the present invention, not limit according to this the utility model discloses a protection scope, so: all equivalent changes made according to the structure, shape and principle of the utility model are covered within the protection scope of the utility model.
Claims (8)
1. Reinforced concrete pipeline mounting structure, including locating plate (1), locating plate (1) is placed in groove hole bottom, is provided with a plurality of groups locating piece (2) on locating plate (1), and per two locating piece (2) symmetry sets up its characterized in that on locating plate (1): a distance adjusting component (3) is arranged between each positioning block (2) and each positioning plate (1), the positioning blocks (2) on the same side of the adjacent positioning plates (1), and each two positioning blocks (2) are provided with clamping devices (5).
2. The reinforced concrete pipe installation structure according to claim 1, wherein: locating piece (2) are including diaphragm (21) and riser (22), riser (22) bottom surface and diaphragm (21) top surface fixed connection, riser (22) perpendicular to diaphragm (21), and riser (22) set up in double-phase relative diaphragm (21) farthest distance limit department, roll adjustment subassembly (3) are including first locating hole (31), and first locating hole (31) are seted up on diaphragm (21), run through diaphragm (21), have seted up a plurality of second locating holes (32) on locating plate (1), and second locating hole (32) and first locating hole (31) are with the specification, and locating plate (1) horizontal central axis evenly distributed is followed in second locating hole (32), and first locating hole (31) and second locating hole (32) are the non-round hole, and bolt (33) have been inserted in first locating hole (31) and second locating hole (32).
3. The reinforced concrete pipe installation structure according to claim 2, wherein: all insert in diaphragm (21), riser (22) and locating plate (1) and establish and be fixed with strengthening rib (4), first locating hole (31) and second locating hole (32) setting are staggered in strengthening rib (4).
4. A reinforced concrete pipe installation structure as recited in claim 3, wherein: be provided with chamfer structure (211) on diaphragm (21), chamfer structure (211) are located diaphragm (21) top, keep away from riser (22) one side edge.
5. The reinforced concrete pipe installation structure according to claim 1, wherein: the clamping device (5) comprises a first clamp (51), a second clamp (52) and a connecting rod (53), wherein one end of the connecting rod (53) is fixedly connected with the first clamp (51), and the other end of the connecting rod (53) is fixedly connected with the second clamp (52).
6. The reinforced concrete pipe installation structure according to claim 5, wherein: the clamping device is characterized in that fastening components (6) are connected to the first clamp (51) and the second clamp (52) in a threaded mode, the first clamp (51) and the second clamp (52) are both U-shaped, and the fastening components (6) are located on the side walls, far away from the connecting rod (53), of the first clamp (51) and the second clamp (52).
7. The reinforced concrete pipe installation structure according to claim 6, wherein: the fastening assembly (6) comprises a screw rod (61), a hand wheel (62) and a push plate (63), the screw rod (61) penetrates through the side wall of the first clamp (51) and the second clamp (52) far away from the connecting rod (53), one end of the screw rod (61) in the first clamp (51) and the second clamp (52) is in threaded connection with the push plate (63), and one end of the screw rod (61) in the first clamp (51) and the second clamp (52) is in external fixed connection with the hand wheel (62).
8. The reinforced concrete pipe installation structure according to claim 5, wherein: the connecting rod (53) comprises an inner rod (531) and an outer rod (532), a plurality of first bolt holes (5311) and second bolt holes (5321) of the same specification are respectively formed in the inner rod (531) and the outer rod (532), one end of the inner rod (531) is inserted into one end of the outer rod (532), the inner rod (531) slides in the outer rod (532) along the length direction of the outer rod (532), the other end of the inner rod (531) is fixedly connected with a first clamp (51), the other end of the outer rod (532) is fixedly connected with a second clamp (52), and a bolt (54) penetrates through the first bolt hole (5311) and the second bolt hole (5321).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020079977.8U CN211898808U (en) | 2020-01-14 | 2020-01-14 | Reinforced concrete pipeline mounting structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020079977.8U CN211898808U (en) | 2020-01-14 | 2020-01-14 | Reinforced concrete pipeline mounting structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211898808U true CN211898808U (en) | 2020-11-10 |
Family
ID=73297672
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020079977.8U Expired - Fee Related CN211898808U (en) | 2020-01-14 | 2020-01-14 | Reinforced concrete pipeline mounting structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211898808U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113048287A (en) * | 2021-04-01 | 2021-06-29 | 中交第二航务工程局有限公司 | Socket type reinforced concrete pipeline installation adjusting device and using method |
-
2020
- 2020-01-14 CN CN202020079977.8U patent/CN211898808U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113048287A (en) * | 2021-04-01 | 2021-06-29 | 中交第二航务工程局有限公司 | Socket type reinforced concrete pipeline installation adjusting device and using method |
CN113048287B (en) * | 2021-04-01 | 2022-07-12 | 中交第二航务工程局有限公司 | Socket type reinforced concrete pipeline installation adjusting device and using method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2018152956A1 (en) | Assembled-type round steel pipe casing fiber-reinforced concrete column connecting node and mounting method | |
CN211898808U (en) | Reinforced concrete pipeline mounting structure | |
CN107060150B (en) | Prefabricated assembled integral frame filling wall system and construction method thereof | |
CN114016383A (en) | Pipeline suspension protection device and construction method | |
CN113530001A (en) | Pier type shock insulation support and construction method thereof | |
CN204626966U (en) | A kind of deformation joint formwork erection device | |
CN105625466A (en) | Assembled prefabricated comprehensive pipe gallery | |
CN111088863A (en) | Pendant structure and precast concrete wallboard system | |
CN212405648U (en) | Curtain wall aluminum frame connecting piece | |
CN214738756U (en) | Steel construction building connecting device | |
CN206174139U (en) | Assembled steel structure node | |
CN213174794U (en) | Novel reserved hole formwork tool | |
CN212745303U (en) | Environment-friendly building water pipe | |
CN110593562B (en) | Steel frame shaping building template system | |
CN201106281Y (en) | Light-admitting and flexible system module plate and combined device | |
CN115234174A (en) | Geological exploration's that mine was used drilling rod device | |
CN210976098U (en) | Underground pipe gallery pre-buried support | |
CN205100443U (en) | Be used for overlength industry factory building siphon drainage system | |
CN111005744B (en) | Support beam structure of municipal shield tunnel | |
CN202611015U (en) | Junction self-locking type assembly wall body | |
CN211738236U (en) | Piping lane support with stable fixed knot constructs | |
CN108412191B (en) | Deformation joint double shear wall template assembling and disassembling device and method | |
CN215674094U (en) | Engineering pipeline connection structure is used in construction of building plumbing | |
CN220166979U (en) | Pipeline pouring fixing device | |
CN221372957U (en) | Reinforcing bar installation fixing device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20201110 |