CN211890751U - Tool rack for tunnel construction - Google Patents

Tool rack for tunnel construction Download PDF

Info

Publication number
CN211890751U
CN211890751U CN202020170899.2U CN202020170899U CN211890751U CN 211890751 U CN211890751 U CN 211890751U CN 202020170899 U CN202020170899 U CN 202020170899U CN 211890751 U CN211890751 U CN 211890751U
Authority
CN
China
Prior art keywords
fixedly connected
instrument
tool
tunnel construction
tray
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020170899.2U
Other languages
Chinese (zh)
Inventor
靳元方
刘静冬
杨立
杨顺模
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Engineering Co Ltd
Third Engineering Co Ltd of Highway Engineering Bureau of CCCC
Original Assignee
CCCC First Highway Engineering Co Ltd
Third Engineering Co Ltd of Highway Engineering Bureau of CCCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd, Third Engineering Co Ltd of Highway Engineering Bureau of CCCC filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN202020170899.2U priority Critical patent/CN211890751U/en
Application granted granted Critical
Publication of CN211890751U publication Critical patent/CN211890751U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model belongs to the technical field of tunnel construction, especially, be an instrument frame for tunnel construction, including the instrument bin, the inside wall fixedly connected with of instrument bin separates the baffle, separate the baffle and cut apart into the inside of instrument bin and store chamber and bin down, on store the interior diapire fixedly connected with hydraulic telescoping rod in chamber, hydraulic telescoping rod's last fixed surface is connected with the installation tray, the last fixed surface of installation tray is connected with the support column, the surface swing joint of support column has the bearing. The utility model discloses, through the setting of instrument tray, the eminence staff is when using, and the staff accessible removes the wheel and removes near the user with the device, starts hydraulic telescopic rod for the height that the instrument tray rose to the eminence staff and uses is provided with the bearing simultaneously, makes the instrument tray rotate, makes things convenient for the staff of eminence to take and puts the instrument, guarantees staff's work efficiency.

Description

Tool rack for tunnel construction
Technical Field
The utility model belongs to the technical field of the tunnel construction, concretely relates to tool holder for tunnel construction.
Background
A large number of various tools are required to be used in a tunnel construction site, the tools are mostly stored in order in a classified mode before being used, and a user takes the tools away according to the needs.
But at present the user places at will usually after using, and the instrument easily drops and injures the user by a crashing object, still need look for everywhere when scattering everywhere instrument uses once more in addition, wastes time and energy, and when the eminence needed the use instrument, the staff that needs the low department handed the instrument to the staff of eminence simultaneously, influences workman's work efficiency.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the problem of low work efficiency in the prior art and providing a tool rest for tunnel construction.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides an instrument frame for tunnel construction, includes the instrument bin, the inside wall fixedly connected with of instrument bin separates the baffle, separate the baffle and cut apart into the inside of instrument bin and store the chamber and bin down, the interior diapire fixedly connected with hydraulic telescoping rod who stores the chamber on, hydraulic telescoping rod's last fixed surface is connected with the installation tray, the last fixed surface of installation tray is connected with the support column, the surface swing joint of support column has the bearing, the fixed surface of bearing is connected with instrument tray.
Preferably, the tool storage box is provided with a sliding groove in the inner side wall, and a box cover is movably connected inside the sliding groove.
Preferably, the inner side wall of the lower storage box is fixedly connected with a vertical partition plate, and the inner side wall of the vertical partition plate is movably connected with a tool storage drawer through a sliding rail.
Preferably, the number of the bearings and the number of the tool trays are both two.
Preferably, the lower fixed surface of instrument bin is connected with the installation sleeve, the telescopic interior roof fixedly connected with coupling spring of installation, coupling spring's one end fixedly connected with connecting block, the inside wall fixedly connected with fixed axle of connecting block, the surface swing joint of fixed axle has the removal wheel.
Preferably, a pushing handle is fixedly connected to the outer surface of the tool storage box.
Compared with the prior art, the utility model provides a tool rest for tunnel construction possesses following beneficial effect:
1. the utility model discloses, through the setting of instrument tray, the eminence staff is when using, and the staff accessible removes the wheel and removes near the user with the device, starts hydraulic telescopic rod for the instrument tray rises to the height that the eminence staff used, simultaneously through the setting of bearing, makes the instrument tray rotate, makes things convenient for the staff of eminence to take and puts the instrument, guarantees staff's work efficiency.
2. The utility model discloses, through the setting that removes the wheel, at the construction site in tunnel, the many bumps in road surface are uneven, and the staff can play absorbing effect to the instrument bin when removing the device under the interact of installation sleeve, coupling spring and connecting block to guarantee the life of instrument.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention. In the drawings:
fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural view of a tool tray according to the present invention;
FIG. 3 is a schematic structural view of a cross section of the device of the present invention;
FIG. 4 is a schematic structural view of the movable wheel of the present invention;
in the figure: 1. a tool storage bin; 2. a baffle plate; 3. an upper storage chamber; 4. a lower storage tank; 5. a hydraulic telescopic rod; 6. installing a tray; 7. a support pillar; 8. a bearing; 9. a tool tray; 10. a chute; 11. a box cover; 12. a vertical partition plate; 13. a tool storage drawer; 14. installing a sleeve; 15. a connecting spring; 16. connecting blocks; 17. a fixed shaft; 18. a moving wheel; 19. And (6) pushing the hand.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example 1
Referring to fig. 1-4, a tool rack for tunnel construction comprises a tool storage box 1, wherein the inner side wall of the tool storage box 1 is fixedly connected with a baffle 2, the baffle 2 divides the interior of the tool storage box 1 into an upper storage cavity 3 and a lower storage box 4, the inner side wall of the lower storage box 4 is fixedly connected with a vertical partition plate 12, and the inner side wall of the vertical partition plate 12 is movably connected with a tool storage drawer 13 through a slide rail;
the inner bottom wall of the upper storage cavity 3 is fixedly connected with a hydraulic telescopic rod 5, the upper surface of the hydraulic telescopic rod 5 is fixedly connected with an installation tray 6, the upper surface of the installation tray 6 is fixedly connected with a support column 7, the outer surface of the support column 7 is movably connected with a bearing 8, the outer surface of the bearing 8 is fixedly connected with a tool tray 9, and the number of the bearing 8 and the number of the tool tray 9 are two;
when a worker at a high place uses the device, the worker can move the device to the position near a user through the moving wheel 18, the hydraulic telescopic rod 5 is started, the tool tray 9 is made to ascend to the height used by the worker at the high place, and meanwhile, the tool tray 9 can rotate through the arrangement of the bearing 8, so that the worker at the high place can conveniently take and place tools, and the working efficiency of the worker is guaranteed;
the inner side wall of the tool storage box 1 is provided with a sliding chute 10, and a box cover 11 is movably connected inside the sliding chute 10;
the lower surface of the tool storage box 1 is fixedly connected with a mounting sleeve 14, the inner top wall of the mounting sleeve 14 is fixedly connected with a connecting spring 15, one end of the connecting spring 15 is fixedly connected with a connecting block 16, the inner side wall of the connecting block 16 is fixedly connected with a fixed shaft 17, and the outer surface of the fixed shaft 17 is movably connected with a movable wheel 18;
on the construction site of the tunnel, the road surface is uneven, and when a worker moves the device, under the interaction of the installation sleeve 14, the connecting spring 15 and the connecting block 16, the shock absorption effect can be realized on the tool storage box 1, so that the service life of the tool is ensured;
a push handle 19 is fixedly connected to the outer surface of the tool storage box 1;
the utility model discloses a theory of operation and use flow: on the construction site of the tunnel, the road surface is uneven, and when a worker moves the device, under the interaction of the installation sleeve 14, the connecting spring 15 and the connecting block 16, the shock absorption effect can be realized on the tool storage box 1, so that the service life of the tool is ensured;
when a worker at a high place uses the device, the worker can move the device to the position near a user through the moving wheel 18, the hydraulic telescopic rod 5 is started, the tool tray 9 is made to ascend to the height used by the worker at the high place, and meanwhile, the tool tray 9 can rotate through the arrangement of the bearing 8, so that the worker at the high place can conveniently take and place tools, and the working efficiency of the worker is guaranteed;
finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. The utility model provides a tool rack for tunnel construction, includes instrument bin (1), its characterized in that, the inside wall fixedly connected with of instrument bin (1) separates baffle (2), separate baffle (2) and split into interior storage chamber (3) and lower bin (4) with instrument bin (1), go up inner diapire fixedly connected with hydraulic telescoping rod (5) of storage chamber (3), the last fixed surface of hydraulic telescoping rod (5) is connected with installation tray (6), the last fixed surface of installation tray (6) is connected with support column (7), the surface swing joint of support column (7) has bearing (8), the fixed surface of bearing (8) is connected with instrument tray (9).
2. The tool rack for tunnel construction according to claim 1, wherein a sliding groove (10) is formed in the inner side wall of the tool storage box (1), and a box cover (11) is movably connected to the inside of the sliding groove (10).
3. The tool rack for tunnel construction according to claim 1, wherein a vertical partition plate (12) is fixedly connected to the inner side wall of the lower storage box (4), and a tool storage drawer (13) is movably connected to the inner side wall of the vertical partition plate (12) through a slide rail.
4. A tool holder for tunnel construction according to claim 1, characterized in that the number of bearings (8) and tool trays (9) is two.
5. The tool rack for tunnel construction according to claim 1, wherein a mounting sleeve (14) is fixedly connected to the lower surface of the tool storage box (1), a connecting spring (15) is fixedly connected to the inner top wall of the mounting sleeve (14), a connecting block (16) is fixedly connected to one end of the connecting spring (15), a fixed shaft (17) is fixedly connected to the inner side wall of the connecting block (16), and a moving wheel (18) is movably connected to the outer surface of the fixed shaft (17).
6. The tool holder for tunnel construction according to claim 1, wherein a push handle (19) is fixedly connected to an outer surface of the tool storage case (1).
CN202020170899.2U 2020-02-14 2020-02-14 Tool rack for tunnel construction Expired - Fee Related CN211890751U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020170899.2U CN211890751U (en) 2020-02-14 2020-02-14 Tool rack for tunnel construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020170899.2U CN211890751U (en) 2020-02-14 2020-02-14 Tool rack for tunnel construction

Publications (1)

Publication Number Publication Date
CN211890751U true CN211890751U (en) 2020-11-10

Family

ID=73291409

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020170899.2U Expired - Fee Related CN211890751U (en) 2020-02-14 2020-02-14 Tool rack for tunnel construction

Country Status (1)

Country Link
CN (1) CN211890751U (en)

Similar Documents

Publication Publication Date Title
CN203650108U (en) Self-dumping type swarf collection cart
CN211890751U (en) Tool rack for tunnel construction
CN209080538U (en) A kind of environment measuring packaged type sample storage rack
CN209956014U (en) Multifunctional dust removal device
CN213411940U (en) Multifunctional decoration tool box
CN216546246U (en) Movable support for linear scale
CN210361185U (en) Workstation for machining
CN214284026U (en) Multifunctional furniture is made and is placed cabinet with instrument
CN212096244U (en) Strutting arrangement is used in maintenance of aviation spare part
CN210976699U (en) Building engineering protective bracket
CN112603043A (en) Renewable resource acceptance management system
CN220128765U (en) Maintenance tool box for rail transit
CN215872224U (en) Experimental apparatus data acquisition device
CN214980943U (en) Water conservancy construction maintenance equipment
CN216030639U (en) Special-shaped movable workbench cabinet
CN221023712U (en) Multifunctional emergency vehicle
CN213352437U (en) Open-air portable topography mapping instrument platform
CN211310734U (en) Welding platform for hydraulic oil cylinder auxiliary beam of refitted vehicle
CN210794482U (en) Road construction is with clear device of transporting of rubbish
CN212919328U (en) Case is deposited with portable instrument that has classification function to electromechanical engineering
CN221168586U (en) Machinery stereo garage routine maintenance device
CN214265463U (en) Multifunctional automobile part machining table
CN216128796U (en) Dustbin for municipal administration
CN211614430U (en) Drilling equipment is used in container processing
CN211364133U (en) Hand-push type easel for field sketching

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201110