CN211873771U - Scaffold device for tunnel construction - Google Patents

Scaffold device for tunnel construction Download PDF

Info

Publication number
CN211873771U
CN211873771U CN202020372412.9U CN202020372412U CN211873771U CN 211873771 U CN211873771 U CN 211873771U CN 202020372412 U CN202020372412 U CN 202020372412U CN 211873771 U CN211873771 U CN 211873771U
Authority
CN
China
Prior art keywords
mounting
frame
fixed
support frame
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020372412.9U
Other languages
Chinese (zh)
Inventor
梁雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020372412.9U priority Critical patent/CN211873771U/en
Application granted granted Critical
Publication of CN211873771U publication Critical patent/CN211873771U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a scaffold device for tunnel construction, including mounting bracket, support frame and base, the left and right sides of support frame all is provided with the mounting bracket, the downside of mounting bracket and support frame all is fixed with the base, all is provided with the installing frame between mounting bracket and the support frame, the inboard of installing frame is fixed with places the board, and the corresponding support frame one end of installing frame all is fixed with first installation piece, the one end of the corresponding mounting bracket of installing frame all is fixed with second installation piece, the mounting groove has all been seted up to the position department of the corresponding second installation piece in one side of mounting bracket, the regulation mouth has been seted up at the middle part of support frame, the front and back end of first installation piece all is fixed with the regulation pole, the position department of the corresponding regulation pole of end all has seted up the adjustment tank. The utility model discloses a set up installing frame, adjustment tank, regulation pole, first installation piece and regulation mouth, solved not possess the problem of the folding function of being convenient for among the scaffold device for tunnel construction.

Description

Scaffold device for tunnel construction
Technical Field
The utility model relates to a tunnel construction technical field specifically is a scaffold device for tunnel construction.
Background
Tunnels are engineering structures buried in the ground and are a form of human use of underground space. The tunnel can be divided into traffic tunnel, hydraulic tunnel, municipal tunnel, mine tunnel, and the tunnel is when being under construction, and constructor can often use scaffold device, and at present, do not possess the function of being convenient for folding etc. not enough among the scaffold device for the current tunnel construction, consequently is necessary to improve prior art to solve above-mentioned problem.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
An object of the utility model is to provide a scaffold device for tunnel construction to solve the problem that proposes among the above-mentioned background art.
(II) technical scheme
In order to achieve the above object, the utility model provides a following technical scheme: a scaffold device for tunnel construction comprises a mounting frame, a support frame and a base, wherein the left side and the right side of the support frame are respectively provided with the mounting frame, the base is fixed at the lower sides of the mounting frame and the support frame, a mounting frame is arranged between the mounting frame and the support frame, a placing plate is fixed at the inner side of the mounting frame, a first mounting block is fixed at one end of the mounting frame corresponding to the support frame, a second mounting block is fixed at one end of the mounting frame corresponding to the mounting frame, a mounting groove is formed at the position of one side of the mounting frame corresponding to the second mounting block, an adjusting hole is formed in the middle of the support frame, an adjusting rod is fixed at the front end and the rear end of the first mounting block, an adjusting groove is formed at the position of the front end and the rear end of the support frame corresponding to the adjusting rod, a mounting seat is fixed at the middle side of, and mounting plates are fixed between the placing seats.
Preferably, the front end and the rear end of the upper end of the placing plate are respectively provided with a baffle plate, the upper end of each baffle plate is fixedly provided with a supporting rod, and the positions of the left end and the right end of the inner part of the installing frame, which correspond to the baffle plates, are respectively provided with a second rotating hole.
Preferably, the left end and the right end of the baffle are respectively fixed with a second rotating rod at the position corresponding to the second rotating hole, and the middle side in the mounting frame is respectively fixed with a partition plate.
Preferably, the first mounting blocks are arranged in the corresponding adjusting holes, the adjusting rods are arranged in the corresponding adjusting grooves, the positions of the front end and the rear end of the supporting frame corresponding to the adjusting rods are respectively provided with a rotating buckle, the positions of the front side and the rear side of the supporting frame corresponding to the rotating buckles are respectively fixed with a rotating seat, the left side and the right side of the rotating seat are respectively provided with a first rotating hole, and the rotating buckles are movably connected with the first rotating holes on the rotating seat.
Preferably, the second installation blocks are arranged in the corresponding installation grooves, third rotation holes are formed in positions, corresponding to the installation grooves, of the front end and the rear end of the installation frame, and first rotation rods are arranged in positions, corresponding to the third rotation holes, of the front end and the rear end of the second installation blocks.
Preferably, the front end and the rear end of the second mounting block are provided with placing holes corresponding to the positions of the first rotating rod, the placing holes are provided with movable holes, the movable holes are provided with movable plates, the springs are fixed at the positions of the movable plates corresponding to the movable holes, and one end of the first rotating rod is fixed on the corresponding movable plates.
(III) advantageous effects
The utility model provides a scaffold device for tunnel construction possesses following beneficial effect:
(1) the utility model is provided with the mounting frame, the adjusting groove, the adjusting rod, the first mounting block and the adjusting opening, when the device is not used, the baffle plate is firstly rotated, the baffle plate drives the second rotating rod to rotate in the second rotating hole, the baffle plate is further rotated to the placing plate, the baffle plate is further accommodated, then the rotating buckle is rotated to rotate on the first rotating hole on the rotating seat, the rotating buckle is taken down on the adjusting rod, the placing seat is taken down on the mounting seat, the mounting plate is taken down from the mounting frame and the supporting frame, the mounting frame and the supporting frame are not fixed by external force, one end of the mounting frame close to the supporting frame moves downwards, the first mounting block is driven to move downwards in the adjusting opening, the adjusting rod moves downwards in the adjusting groove, and the first rotating rod on the second mounting block rotates in the third rotating hole, make the distance between mounting bracket and the support frame to shorten simultaneously to reach folding device's effect, solved not possess the problem of the folding function of being convenient for among the scaffold assembly for tunnel construction, possessed simple structure simultaneously, the benefit of the operation of being convenient for.
Drawings
FIG. 1 is a block diagram of the present invention;
FIG. 2 is a schematic view of the support frame of FIG. 1;
FIG. 3 is a block diagram of the mounting frame of FIG. 1 according to the present invention;
FIG. 4 is a block diagram of the mounting bracket of FIG. 1 according to the present invention;
FIG. 5 is a block diagram of the second mounting block of FIG. 3 according to the present invention;
fig. 6 is a structural view of the first rotating rod in fig. 3 according to the present invention;
FIG. 7 is a block diagram of the baffle of FIG. 1 according to the present invention;
fig. 8 is a structural view of the mounting plate of fig. 1 according to the present invention.
The reference numbers in the figures are: 1. a mounting frame; 2. a baffle plate; 3. rotating the buckle; 4. installing a frame; 5. a mounting seat; 6. mounting a plate; 7. a support frame; 8. an adjustment groove; 9. a base; 10. a rotating seat; 11. a first rotation hole; 12. a second rotation hole; 13. placing the plate; 14. a partition plate; 15. adjusting a rod; 16. a first mounting block; 17. a first rotating lever; 18. a second mounting block; 19. mounting grooves; 20. a movable hole; 21. placing holes; 22. a spring; 23. a movable plate; 24. a support rod; 25. a second rotating lever; 26. a placing seat; 27. an adjustment port; 28. and a third rotation hole.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-8, the present invention provides a technical solution: a scaffold device for tunnel construction comprises a mounting frame 1, a supporting frame 7 and a base 9, wherein the left side and the right side of the supporting frame 7 are respectively provided with the mounting frame 1, the base 9 is respectively fixed on the lower sides of the mounting frame 1 and the supporting frame 7, a mounting frame 4 is respectively arranged between the mounting frame 1 and the supporting frame 7, a placing plate 13 is fixed on the inner side of the mounting frame 4, one end of the mounting frame 4 corresponding to the supporting frame 7 is respectively fixed with a first mounting block 16, one end of the mounting frame 4 corresponding to the mounting frame 1 is respectively fixed with a second mounting block 18, one side of the mounting frame 1 is respectively provided with a mounting groove 19 corresponding to the second mounting block 18, the middle part of the supporting frame 7 is provided with an adjusting opening 27, when a rotary buckle 3 is taken down on the adjusting rod 15, the first mounting block 16 can move in the adjusting opening 27, so that the adjusting rod 15 can move in the adjusting groove 8, the, the adjusting groove 8 has all been seted up to the front and back end of support frame 7 corresponding position department of adjusting pole 15, the well side of 1 front and back ends of mounting bracket all is fixed with mount pad 5, the upper end of mount pad 5 all is provided with places seat 26, place seat 26 and place and all be fixed with mounting panel 6 between the seat 26, seat 26 will be placed and place on mount pad 5, and then make mounting panel 6 support mount pad 5, thereby make the distance between mounting bracket 1 and the support frame 7 fixed, thereby prevent that the distance between mounting bracket 1 and the support frame 7 from shortening.
Place the front and back end of board 13 upper end and all be provided with baffle 2, the upper end of baffle 2 all is fixed with holds up pole 24, makes things convenient for the staff to walk on placing board 13 through holding up pole 24, and the second rotation hole 12 has all been seted up to the inside left and right sides end department of the corresponding baffle 2 of installing frame 4, rotates hole 12 through the second for second dwang 25 on the baffle 2 can rotate downthehole 12 rotations at the second.
The left end and the right end of the baffle 2 are respectively fixed with a second rotating rod 25 corresponding to the position of the second rotating hole 12, the inside middle side of the mounting frame 4 is respectively fixed with a partition plate 14, and after the baffle 2 rotates to the placing plate 13, the baffle 2 is separated by the partition plate 14.
First installation piece 16 sets up in corresponding regulation mouth 27, adjust the pole 15 and set up in corresponding adjustment tank 8, the front and back end of support frame 7 all is provided with rotatory knot 3 corresponding to the position department of adjusting pole 15, when adjusting pole 15 and move the top in adjustment tank 8, detain 3 with the rotation again and detain on adjusting pole 15, and then make and adjust pole 15 can't remove in adjustment tank 8, the corresponding rotatory position department of detaining 3 in the front and back side upper end of support frame 7 all is fixed with and rotates seat 10, first rotation hole 11 has all been seted up on the left and right sides of rotating seat 10, rotatory knot 3 and the first rotation hole 11 swing joint on rotating seat 10.
Second installation piece 18 sets up in corresponding mounting groove 19, and third rotation hole 28 has all been seted up to the corresponding mounting groove 19's of the front and back end position department of mounting bracket 1, and when installing frame 4 was rotating, and then made second installation piece 18 drive first rotation pole 17 at third rotation hole 28 internal rotation, the corresponding third rotation hole 28's of the front and back end position department of second installation piece 18 all is provided with first rotation pole 17.
The front end and the rear end of the second installation block 18 are provided with a placing hole 21 corresponding to the position of the first rotation rod 17, the placing hole 21 is provided with a movable hole 20, the movable hole 20 is provided with a movable plate 23, when the second installation block 18 needs to be taken out from the installation groove 19, the first rotation rod 17 is moved towards the placing hole 21, the first rotation rod 17 drives the movable plate 23 to move, the movable plate 23 extrudes the spring 22, the first rotation rod 17 is moved out from the third rotation hole 28, the second installation block 18 can be taken out from the installation groove 19, the position of the movable plate 23 corresponding to the movable hole 20 is fixed with the spring 22, and one end of the first rotation rod 17 is fixed on the corresponding movable plate 23.
The working principle is as follows: when the utility model is used, when the device is not used, firstly the baffle 2 is rotated, and then the baffle 2 drives the second rotating rod 25 to rotate in the second rotating hole 12, and then the baffle 2 is rotated to the placing plate 13, and then the baffle 2 is stored, and then the rotating buckle 3 is rotated, and then the rotating buckle 3 rotates in the first rotating hole 11 on the rotating seat 10, so that the rotating buckle 3 is taken down on the adjusting rod 15, at the same time, the placing seat 26 is taken down on the mounting seat 5, and then the mounting plate 6 is taken down from the mounting frame 1 and the supporting frame 7, so that the mounting frame 1 and the supporting frame 7 are not fixed by external force, at the moment, one end of the mounting frame 4 close to the supporting frame 7 moves downwards, thereby driving the first mounting block 16 to move downwards in the adjusting opening 27, and further causing the adjusting rod 15 to move downwards in the adjusting groove 8, and further causing the first rotating rod 17 on the second mounting block 18 to rotate in the third rotating hole 28, make the distance between mounting bracket 1 and the support frame 7 shorten simultaneously, thereby reach folding device's effect, when the use device, detain rotatory 3 on adjusting pole 15, and then make first installation piece 16 can not adjust rocking in the mouth 27 again, will place seat 26 again and place at mount pad 5, the fender through mounting panel 6 simultaneously, thereby make the condition that the distance between mounting bracket 1 and the support frame 7 can not appear shortening, and then make the stability of device strengthen, and then the operative installations that can be safe.
The above is only the preferred embodiment of the present invention, and the present invention is not limited thereto, any technical solution recorded in the foregoing embodiments is modified, and some technical features are replaced by equivalent, all belonging to the protection scope of the present invention.

Claims (6)

1. The utility model provides a scaffold device for tunnel construction, includes mounting bracket (1), support frame (7) and base (9), its characterized in that: the left side and the right side of the support frame (7) are respectively provided with a mounting frame (1), the lower sides of the mounting frame (1) and the support frame (7) are respectively fixed with a base (9), an installation frame (4) is arranged between the mounting frame (1) and the support frame (7), the inner side of the installation frame (4) is fixed with a placing plate (13), one end of the corresponding support frame (7) of the installation frame (4) is respectively fixed with a first installation block (16), one end of the corresponding mounting frame (1) of the installation frame (4) is respectively fixed with a second installation block (18), the position of the corresponding second installation block (18) on one side of the mounting frame (1) is respectively provided with an installation groove (19), the middle part of the support frame (7) is provided with an adjusting port (27), the front end and the rear end of the first installation block (16) are respectively fixed with an adjusting rod (15), the front end and the rear end of the support frame (7) are respectively provided with an, the mounting rack is characterized in that mounting seats (5) are fixed on the middle sides of the front end and the rear end of the mounting rack (1), placing seats (26) are arranged on the upper ends of the mounting seats (5), and mounting plates (6) are fixed between the placing seats (26) and the placing seats (26).
2. The scaffolding device for tunnel construction according to claim 1, wherein: the front end and the rear end of the upper end of the placing plate (13) are respectively provided with a baffle (2), the upper end of each baffle (2) is fixedly provided with a supporting rod (24), and the positions of the left end and the right end of the inner part of the mounting frame (4) corresponding to the baffles (2) are respectively provided with a second rotating hole (12).
3. The scaffolding device for tunnel construction according to claim 2, wherein: the position department that the left and right sides end of baffle (2) corresponds second rotation hole (12) all is fixed with second dwang (25), the inside medial side of installing frame (4) all is fixed with baffle (14).
4. The scaffolding device for tunnel construction according to claim 1, wherein: first installation piece (16) set up in corresponding regulation mouth (27), adjust pole (15) and set up in corresponding adjustment tank (8), the front and back end of support frame (7) all is provided with rotatory knot (3) corresponding to the position department of adjusting pole (15), the position department that the corresponding rotatory knot (3) in side upper end all is fixed with rotates seat (10) around support frame (7), rotate the side about seat (10) and all seted up first rotation hole (11), rotatory knot (3) and the first rotation hole (11) swing joint that rotates on seat (10).
5. The scaffolding device for tunnel construction according to claim 1, wherein: the second installation piece (18) sets up in corresponding mounting groove (19), third rotation hole (28) have all been seted up to the position department that the front and back end of mounting bracket (1) corresponds mounting groove (19), the position department that the front and back end of second installation piece (18) corresponds third rotation hole (28) all is provided with first rotation pole (17).
6. The scaffolding device for tunnel construction according to claim 5, wherein: the position department that the front and back end of second installation piece (18) corresponds first rotation pole (17) has all seted up places hole (21), movable hole (20) have all been seted up to the inside of placing hole (21), the inside of movable hole (20) all is provided with fly leaf (23), the position department of the corresponding movable hole (20) of fly leaf (23) all is fixed with spring (22), the one end of first rotation pole (17) is all fixed on corresponding fly leaf (23).
CN202020372412.9U 2020-03-21 2020-03-21 Scaffold device for tunnel construction Expired - Fee Related CN211873771U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020372412.9U CN211873771U (en) 2020-03-21 2020-03-21 Scaffold device for tunnel construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020372412.9U CN211873771U (en) 2020-03-21 2020-03-21 Scaffold device for tunnel construction

Publications (1)

Publication Number Publication Date
CN211873771U true CN211873771U (en) 2020-11-06

Family

ID=73257781

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020372412.9U Expired - Fee Related CN211873771U (en) 2020-03-21 2020-03-21 Scaffold device for tunnel construction

Country Status (1)

Country Link
CN (1) CN211873771U (en)

Similar Documents

Publication Publication Date Title
CN211873771U (en) Scaffold device for tunnel construction
CN2900793Y (en) Tunnelling and anchoring integrated tunnelling machine
CN208502350U (en) A kind of rotation upright bicycle parking device
CN101070761A (en) Digging-protecting integrated digging-protecting machine
CN212567153U (en) Play multi-functional action target drone of falling formula for shooting training
CN205777851U (en) A kind of adjustable up-down tent post rod
CN211230514U (en) Make things convenient for height-adjusting's geotechnical engineering with supporting protection device
CN211806581U (en) Molding linkage die carrier of positive and negative pressure plastic suction molding machine
CN208970033U (en) A kind of alarm board fixing rack for building easy to remove
CN203345950U (en) Dismounting control system of tower crane
CN207686362U (en) A kind of mobile communication rack being easily installed
CN219316974U (en) Single hydraulic prop with auxiliary moving structure
CN217231538U (en) Warning device is used in hydraulic engineering construction
CN215170071U (en) Novel slag steel separation plate capable of preventing slag inclusion
CN217012061U (en) River course afforestation is with anti lodging device of trees
CN219753258U (en) Foundation ditch prevention of seepage supporting construction
CN220226153U (en) Safety protection structure for road
CN216649611U (en) Solar module with folding support
CN217378685U (en) But height-adjusting's limit for height pole for town road
CN213267868U (en) Pile cutting device of excavator
CN216078824U (en) Novel high altitude hanging pipe shutoff device
CN201794515U (en) Walking engineering driller seat
CN216077524U (en) Device for carrying diaphragm compressor during filling of high-purity deuterium gas
CN216811261U (en) Building guardrail for civil engineering
CN217999718U (en) Container type diesel generator set

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201106

Termination date: 20210321

CF01 Termination of patent right due to non-payment of annual fee