CN211872903U - Water conservancy project gate purifier - Google Patents

Water conservancy project gate purifier Download PDF

Info

Publication number
CN211872903U
CN211872903U CN201922416725.XU CN201922416725U CN211872903U CN 211872903 U CN211872903 U CN 211872903U CN 201922416725 U CN201922416725 U CN 201922416725U CN 211872903 U CN211872903 U CN 211872903U
Authority
CN
China
Prior art keywords
gate
welded
plate
thick bamboo
piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922416725.XU
Other languages
Chinese (zh)
Inventor
刘玲灵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Zoding Construction Engineering Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201922416725.XU priority Critical patent/CN211872903U/en
Application granted granted Critical
Publication of CN211872903U publication Critical patent/CN211872903U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Barrages (AREA)

Abstract

The utility model discloses a water conservancy project gate water purifying device, which comprises a stone pier plate, wherein the top end of the stone pier plate is fixedly connected with a top plate, the front vertical face of the top plate is provided with a gate, the inner wall of the gate is provided with a chute, two groups of chutes are provided with slide blocks in the groove openings, a door plate is welded between the two groups of slide blocks, a purifying plate is installed on the back surface of the door plate, right positioning blocks are welded on the left side and the right side of the purifying plate, a left positioning block is welded on one end of the right positioning block, the two groups of left positioning blocks are fixedly connected with the back surface of the gate, after a motor operates, a supporting frame moves upwards, and a tooth mouth rod also moves upwards, so that the door plate is pulled upwards, namely, the gate is opened, after the door plate receives external tensile force, the slide blocks welded on the two sides can be matched to displace in the, used for blocking garbage in water.

Description

Water conservancy project gate purifier
Technical Field
The utility model belongs to the technical field of the gate scope, specifically be a hydraulic engineering gate purifier.
Background
The gate is used for closing and opening the control facility of the drainage (discharging) water channel. The important components of hydraulic buildings can be used for intercepting water flow, controlling water level, regulating flow, discharging silt and floating objects and the like.
The utility model discloses improve to prior art, carrying out the water-proof in-process among the prior art, need use the gate, and when the gate used, need adopt gate and the gate body to dock, directly lead to the cylinder to promote among the prior art, have certain reduction on the life of cylinder to should not change the cylinder.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a: in order to solve the problem provided by the above, a water conservancy project gate purifier is provided.
The utility model adopts the technical scheme as follows:
the utility model provides a hydraulic engineering gate purifier, includes the stone pier plate, the top fixedly connected with roof of stone pier plate, the preceding facade of roof is provided with the gate, the spout has been seted up to the inner wall of gate, and is two sets of sliding connection has the slider in the notch of spout, and is two sets of the welding has the door plant between the slider, install the purification board on the back of door plant, right locating piece has all been welded to the left and right sides of purification board, the one end welding of right locating piece has left locating piece, and is two sets of the back fixed connection of left locating piece and gate.
The door plate is characterized in that a groove part is welded at the top end of the door plate, the center of the top end of the groove part is in an open shape, and a convex block is welded at the position of the opening.
The top welding of lug has the bracing piece, the outer wall of bracing piece is by upper portion position installation circular arc piece, the back of circular arc piece and the welding of stone pier board front elevation by upper portion position.
The left side and the right side of the arc block are fixedly connected with bolts, and the bolts are quickly positioned and fixed with the front vertical face of the stone pier plate through the bolts.
Wherein, the last fixed surface of roof is connected with the support frame, the top welding of support frame has a cavity section of thick bamboo, be provided with the motor on the left wall of a cavity section of thick bamboo, fixedly connected with handle on the right wall of a cavity section of thick bamboo, install a cavity section of thick bamboo between the drive end of motor and the top of a cavity section of thick bamboo, the last surface welding of a cavity section of thick bamboo has the cavity pillar.
The bottom fixedly connected with support frame of cavity section of thick bamboo, the bottom welding of support frame has tooth mouth pole, the bottom of tooth mouth pole and the top welding of bracing piece.
To sum up, owing to adopted above-mentioned technical scheme, the beneficial effects of the utility model are that:
1. the utility model discloses in, after the motor function, the support frame shifts up to the tooth mouth pole also shifts up, thereby realizes the upwards pulling of door plant, promptly for opening the floodgate, after the door plant received external pulling force, will cooperate the slider that goes up both sides welded and carry out the displacement in the notch of spout, when the door plant after rising, will show the one side of purifying plate out for rubbish in to quality of water carries out the check and keeps off.
2. The utility model discloses in, it is fixed that the purifying plate passes through the outer wall that the connecting block realized and the gate, also strengthens fixedly through right locating piece and left locating piece, avoids rivers too big, leads to the purifying plate to appear damaging or drop.
Drawings
FIG. 1 is a schematic diagram of the structure of the present invention;
fig. 2 is a side view of the present invention;
fig. 3 is an enlarged view of a portion a of fig. 1 in the present invention.
The labels in the figure are: 1. a stone pier plate; 2. a gate; 3. a right positioning block; 4. a left locating block; 5. a purification plate; 6. connecting blocks; 7. a door panel; 8. a slider; 9. a chute; 10. a support bar; 11. a groove member; 12. a bump; 13. an arc block; 14. a bolt positioning block; 15. a notched bar; 16. a top plate; 17. a cavity pillar; 18. a handle; 19. a support frame; 20. a hollow cylinder; 21. a motor; 22. a cavity cylinder.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the invention.
Referring to fig. 1-3, a water conservancy project gate water purifying device comprises a stone pier plate 1, a top plate 16 is fixedly connected to the top end of the stone pier plate 1, a support frame 19 is fixedly connected to the upper surface of the top plate 16, a hollow cylinder 20 is welded to the top end of the support frame 19, a support frame 19 is fixedly connected to the bottom end of the hollow cylinder 20, a tooth mouth rod 15 is welded to the bottom end of the support frame 19, the bottom end of the tooth mouth rod 15 is welded to the top end of a support rod 10, a motor 21 is arranged on the left wall of the hollow cylinder 20, a handle 18 is fixedly connected to the right wall of the hollow cylinder 20, a cavity cylinder 22 is arranged between the driving end of the motor 21 and the top end of the hollow cylinder 20, a cavity support column 17 is welded to the upper surface of the cavity cylinder 22, a front vertical face gate 2 is arranged on the top plate 16, a sliding groove 9 is, the welding of door plant 7's top has groove part 11, groove part 11's top central point is the opening form, and it has lug 12 to lie in the opening part welding, the top welding of lug 12 has bracing piece 10, the outer wall of bracing piece 10 leans on upper portion position to install circular arc piece 13, the equal fixedly connected with bolt location in the left and right sides of circular arc piece 13 is fast 14, bolt location is fast 14 through the preceding facade thread tightening of bolt with stone pier stud 1, the back of circular arc piece 13 leans on upper portion position welding with stone pier stud 1 preceding facade, install purifying plate 5 on door plant 7's the back, right locating piece 3 has all been welded to purifying plate 5's the left and right sides, left locating piece 4 has been welded to right locating piece 3's one end, two sets of left locating pieces 4 and gate 2.
The working principle is as follows: when the lifting device is used, the motor 21 is controlled to operate, the driving rod of the motor 21 is positioned on the back surface of the supporting frame 19, the outer wall of the supporting frame 19 is provided with a tooth notch, the outer wall of the driving rod of the motor 21 is provided with a gear disc, so that the supporting frame 19 is driven to move upwards after the driving rod end of the motor 21 rotates, the cavity strut 17 is used for protecting the supporting frame 19, and the supporting frame 19 is positioned in a vertical direction in the lifting process;
the method comprises the following specific operations: after the motor 21 operates, the support frame 19 moves upwards, and the tooth mouth rod 15 also moves upwards, so that the door plate 7 is pulled upwards, namely, the door is opened, after the door plate 7 receives external pulling force, the door plate 7 can be matched with the sliding blocks 8 welded at the two sides to move in the groove opening of the sliding groove 9, and after the door plate 7 rises, one surface of the purification plate 5 can be displayed for blocking garbage in water quality;
wherein the purifying plate 5 is fixed with the outer wall of the gate 2 through the connecting block 6, and is also strengthened and fixed through the right positioning block 3 and the left positioning block 4, so that the phenomenon that water flows too much to cause the purifying plate 5 to be damaged or fall off is avoided.
The above description is only exemplary of the present invention and should not be taken as limiting the scope of the present invention, as any modifications, equivalents, improvements and the like made within the spirit and principles of the present invention are intended to be included within the scope of the present invention.

Claims (6)

1. The utility model provides a hydraulic engineering gate purifier, includes stone pier plate (1), its characterized in that: top fixedly connected with roof (16) of stone pier plate (1), the preceding facade of roof (16) is provided with gate (2), spout (9) have been seted up to the inner wall of gate (2), and are two sets of sliding connection has slider (8) in the notch of spout (9), and is two sets of door plant (7) have been welded between slider (8), install purification board (5) on the back of door plant (7), right locating piece (3) have all been welded to both sides about purification board (5), the one end welding of right locating piece (3) has left locating piece (4), and is two sets of the back fixed connection of left side locating piece (4) and gate (2).
2. The gate water purification device of the water conservancy project according to claim 1, wherein: the door comprises a door panel (7) and is characterized in that a groove piece (11) is welded at the top end of the door panel (7), the center of the top end of the groove piece (11) is in an open shape, and a convex block (12) is welded at the position of the opening.
3. The gate water purification device of the water conservancy project according to claim 2, wherein: the top welding of lug (12) has bracing piece (10), the outer wall of bracing piece (10) is by upper portion position-mounting circular arc piece (13), the back of circular arc piece (13) and stone pier board (1) preceding facade lean on upper portion position welding.
4. A water conservancy project gate water purification device of claim 3, characterized in that: the equal fixedly connected with bolt location of the left and right sides of arc piece (13) is fast (14), bolt location is fast (14) through the preceding facade thread tightening of bolt and stone pier plate (1).
5. The gate water purification device of the water conservancy project according to claim 1, wherein: the last fixed surface of roof (16) is connected with support frame (19), the top welding of support frame (19) has a cavity section of thick bamboo (20), be provided with motor (21) on the left wall of cavity section of thick bamboo (20), fixedly connected with handle (18) on the right wall of cavity section of thick bamboo (20), it has cavity section of thick bamboo (22) to install between the drive end of motor (21) and the top of cavity section of thick bamboo (20), and the last skin weld of cavity section of thick bamboo (22) has cavity pillar (17).
6. The gate water purification device of the water conservancy project according to claim 5, wherein: the bottom fixedly connected with support frame (19) of cavity section of thick bamboo (20), the bottom welding of support frame (19) has tooth mouth pole (15), the bottom of tooth mouth pole (15) and the top welding of bracing piece (10).
CN201922416725.XU 2019-12-29 2019-12-29 Water conservancy project gate purifier Expired - Fee Related CN211872903U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922416725.XU CN211872903U (en) 2019-12-29 2019-12-29 Water conservancy project gate purifier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922416725.XU CN211872903U (en) 2019-12-29 2019-12-29 Water conservancy project gate purifier

Publications (1)

Publication Number Publication Date
CN211872903U true CN211872903U (en) 2020-11-06

Family

ID=73262444

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922416725.XU Expired - Fee Related CN211872903U (en) 2019-12-29 2019-12-29 Water conservancy project gate purifier

Country Status (1)

Country Link
CN (1) CN211872903U (en)

Similar Documents

Publication Publication Date Title
CN112962542B (en) Water sluicegate convenient to adjust discharge
CN211872903U (en) Water conservancy project gate purifier
CN101761082B (en) Compulsory pouring device and construction method of bored pile underwater concrete
CN209368791U (en) A kind of water conservancy construction flashboard convenient to use
CN204849698U (en) Water -stop dam
CN212641385U (en) Flexible opening and closing bidirectional control gate for urban municipal drainage
CN206512686U (en) A kind of water conservancy gate
CN221072526U (en) Sluice structure
CN106759140A (en) A kind of water conservancy gate
CN221276543U (en) Hydraulic engineering steel gate
CN213296268U (en) Novel dykes and dams structure gate of hydraulic engineering
CN216586369U (en) River course water conservancy barricade
CN211472419U (en) High strength water conservancy project steel gate convenient to installation
CN212925974U (en) Flood spillway gate for reservoir
CN203307814U (en) Novel forcing type casting device capable of reducing concrete slump
CN220057828U (en) Sluice door frame fixing device
CN217998000U (en) Cut-off equipment is used in hydraulic engineering construction
CN220318462U (en) River course flood control water conservancy gate
CN210887138U (en) Water conservancy flashboard
CN216194505U (en) Lower opening weir gate
CN211228393U (en) Water flow speed control gate
CN220767956U (en) Lifting type water conservancy gate
CN221877997U (en) Stable cut-off device for water conservancy construction
CN221877993U (en) Sectional sluice that can make up
CN220301278U (en) Water conservancy gate elevating gear

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201130

Address after: B218, 2 / F, Baiwang e-commerce center, 6 Hedong Avenue, Jianchang Town, Nancheng County, Fuzhou City, Jiangxi Province

Patentee after: Jiangxi zoding Construction Engineering Co.,Ltd.

Address before: 1703, building 6, Dezhou City, lincun, Tangxia Town, Dongguan City, Guangdong Province 523000

Patentee before: Liu Lingling

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201106

Termination date: 20211229