CN211837207U
CN211837207U CN201922247658.3U CN201922247658U CN211837207U CN 211837207 U CN211837207 U CN 211837207U CN 201922247658 U CN201922247658 U CN 201922247658U CN 211837207 U CN211837207 U CN 211837207U
Authority
CN
China
Prior art keywords
waste gas
treatment
plate
thick bamboo
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922247658.3U
Other languages
Chinese (zh)
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG RUIYI ENVIRONMENTAL TECHNOLOGY Co.,Ltd.
Original Assignee
Lou Yanxiu
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lou Yanxiu filed Critical Lou Yanxiu
Priority to CN201922247658.3U priority Critical patent/CN211837207U/en
Application granted granted Critical
Publication of CN211837207U publication Critical patent/CN211837207U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Treating Waste Gases (AREA)

Abstract

The utility model discloses an industrial production exhaust-gas treatment equipment, including the frame plate, waste gas immersion fluid processing structure, waste gas sprays purification structure and adsorbs purification structure, and the correspondence is equipped with a processing section of thick bamboo in the mid-mounting mouth of frame plate, and the bottom of handling a section of thick bamboo is the circular arc structure, and the upper end nozzle department of handling a section of thick bamboo corresponds through the bolt and installs the closing cap, and the wall body center department of closing cap is equipped with the gas outlet, and waste gas immersion fluid processing structure sets up in the inside bottom of handling a section of thick bamboo, and waste gas sprays purification structure and sets up in the inside center department of handling a section of thick bamboo, adsorbs: still include control switch group and solenoid valve, control switch group sets up on the last wall of frame plate, and this industrial production exhaust-gas treatment equipment realizes the immersion fluid of waste gas, sprays, adsorbs and dry continuity is handled, has guaranteed the exhaust-gas treatment quality, and each structure is dismantled to maintain and is changed the convenience, has alleviateed personnel's work burden.

Description

Industrial production exhaust-gas treatment equipment
Technical Field
The utility model relates to a waste gas treatment technical field specifically is an industrial production exhaust-gas treatment equipment.
Background
Industrial waste gas refers to a general term of various pollutant-containing gases discharged into air in the process of fuel combustion and production in an enterprise factory, the waste gas is discharged into the atmosphere to pollute the air, the substances enter the human body through different paths, some substances directly cause harm, some substances have accumulation effect to further seriously harm the health of people, different substances have different influences, in order to ensure the physical and mental health of people and good environment, special waste gas treatment equipment is often required for assistance, however, the traditional waste gas treatment equipment has a plurality of defects and complex operation, can not realize the continuous treatment of immersion, spraying, adsorption and drying of waste gas, can not meet the waste gas treatment requirement, the treatment quality of the waste gas is difficult to guarantee, the disassembly, the maintenance and the replacement of each structure are inconvenient, the workload of personnel is increased invisibly, therefore, it is imperative to realize an industrial waste gas treatment apparatus capable of solving such problems.
SUMMERY OF THE UTILITY MODEL
The to-be-solved technical problem of the utility model is to overcome current defect, provide an industrial production exhaust-gas treatment equipment, realize the immersion fluid of waste gas, spray, adsorb and dry continuity is handled, guaranteed the exhaust-gas treatment quality, each structure dismantles and maintains the change convenience, has alleviateed personnel's work burden, can effectively solve the problem in the background art.
In order to achieve the above object, the utility model provides a following technical scheme: an industrial production waste gas treatment device comprises a frame plate, a waste gas immersion liquid treatment structure, a waste gas spraying purification structure and an adsorption purification structure;
frame plate: a treatment barrel is correspondingly arranged in the middle mounting port of the frame plate, the bottom end of the treatment barrel is of an arc structure, a sealing cover is correspondingly arranged at the barrel port at the upper end of the treatment barrel through a bolt, and an air outlet is formed in the center of the wall body of the sealing cover;
exhaust gas immersion fluid handles structure: the waste gas immersion liquid treatment structure is arranged at the bottom end of the treatment cylinder;
waste gas sprays purification structure: the waste gas spraying and purifying structure is arranged at the center of the interior of the treatment cylinder;
adsorption purification structure: the adsorption purification structure is arranged at the upper end of the inside of the treatment cylinder;
wherein: still include control switch group and solenoid valve, control switch group sets up on the last wall of frame plate, and the solenoid valve is established ties in the inside of handling bobbin end fluid-discharge tube, and external power source is connected to control switch group's input electricity, and control switch group's output is connected to the input electricity of solenoid valve, and easy operation realizes the immersion fluid to waste gas, sprays, adsorbs and dry continuity is handled, has satisfied the exhaust-gas treatment demand, has guaranteed the exhaust-gas treatment quality, and each structure dismantles to maintain and changes the convenience, has alleviateed personnel's work burden.
Further, the structure is handled to waste gas immersion fluid includes small opening bottom plate, coiled pipe and suction fan, the small opening bottom plate corresponds and sets up in the inside bottom of handling a section of thick bamboo, and the coiled pipe corresponds and sets up in the upper end of small opening bottom plate, is equipped with evenly distributed's gas pocket on the wall body of coiled pipe, and the suction fan sets up in the upper wall right side of frame plate, and the gas outlet of suction fan passes through the air inlet of trachea with the coiled pipe and links to each other, and the trachea runs through the inner wall of handling a section of thick bamboo, and the output of the input electricity connection control switch group of suction fan realizes gaseous immersion.
Further, waste gas sprays purification structure includes ring plate, ring pipe, shower head, branch pipe and drawing liquid pump, ring plate sets up in the inner wall middle part of a processing section of thick bamboo, and the ring pipe passes through the installation pipe ring and corresponds to set up on ring plate's inner wall, and the shower head is even to correspond and sets up on ring plate's bottom surface, and the water inlet of shower head links to each other with the delivery port of ring pipe through the branch pipe that corresponds, and the drawing liquid pump sets up on processing section of thick bamboo's outer arc wall, and the inlet of drawing liquid pump passes through the inlet of pipe with the ring pipe and links to each other, and the pipe runs through processing section of thick bamboo's inner wall, and the output of drawing liquid pump's input electricity connection control switch.
Further, adsorb purification structure includes filter plate, a screw thread section of thick bamboo, screw rod, small opening clamp plate and active carbon ball, filter plate corresponds and sets up in the inside upper end of handling a section of thick bamboo, and screw thread section of thick bamboo symmetry sets up in filter plate's upper end, the bottom of screw rod and the screw thread section of thick bamboo threaded connection who corresponds, and the screw rod passes the perforation that corresponds on the small opening clamp plate wall body, and the preforming on the screw rod wall body is located the top of small opening clamp plate, and the active carbon ball is filled in filter plate and small opening clamp plate's clearance department, and the small opening clamp plate corresponds the setting with the inner chamber of handling a section of thick bamboo, realizes gaseous.
Further, still include drying cabinet, quick lime, case lid and gas-supply pipe, the drying cabinet sets up in the upper wall left side of frame plate, and the upper end of drying cabinet is open structure, and quick lime is put in the inside small opening backup pad of drying cabinet, and the case lid passes through the bolt correspondence to be installed in the upper end opening part of drying cabinet, and the upper end exhaust port department of case lid is equipped with the blast pipe, and the air inlet of drying cabinet right side wall bottom passes through the gas-supply pipe and links to each other with the gas outlet at closing cap wall body center, realizes gas drying.
Compared with the prior art, the beneficial effects of the utility model are that: the industrial production waste gas treatment equipment has the following advantages:
1. the industrial waste gas pipeline to be treated is connected with an air inlet pipeline of a suction fan, a purified treatment liquid pipeline is connected with an air inlet of a liquid pump, when the device is used, the liquid pump is regulated and controlled in advance through a control switch group, the liquid pump runs, a treatment cylinder is pumped into a proper amount of purified treatment liquid through a guide pipe, a circular ring pipe, a branch pipe and a spray head until a coiled pipe is submerged, waste gas is pumped into the coiled pipe through the suction fan, is input into a drain hole bottom plate through an air pipe, is discharged through air holes in the wall body of the coiled pipe in a turnover mode, fully reacts with the purified treatment liquid, the contact area of the waste gas with the purified treatment liquid is increased, and therefore the purifying effect.
2. After first layer immersion fluid reaction purifies, gaseous rising, the drawing liquid pump is with outside purification treatment liquid suction, through the pipe, the ring pipe, the branch pipe is carried, spray all-round through evenly distributed's shower head, further contact reaction with the gas that rises, realize spraying gaseous purification high-efficiently, at the in-process that sprays the purification, need the solenoid valve circular telegram, discharge in proper amount the waste liquid of the inside bottom of a treatment section of thick bamboo, keep bottom liquid relative balance all the time, realize spraying purified gas high-efficiently, the exhaust-gas treatment demand has been satisfied, personnel's work burden has been alleviateed, the exhaust-gas treatment quality has been guaranteed.
3. The gas after the dual purification reaction is firstly filtered through the filter screen plate, and then is adsorbed and purified through the activated carbon pellets, so that the rapid and comprehensive purification and adsorption treatment are realized, the screw rod penetrates through a corresponding perforation on the wall body of the leak hole pressing plate and is in threaded connection with a corresponding threaded cylinder, the screw thread moves downwards, the pressing plate on the screw rod wall body presses and holds the leak hole pressing plate to move downwards appropriately, so that the activated carbon pellets at the gap between the filter screen plate and the leak hole pressing plate are pressed, the adsorption material is convenient to place, disassemble, maintain and replace, the purified gas is conveyed through the gas conveying pipe and is dried through the quicklime water absorption of the leak hole supporting plate in the drying box, then the gas is discharged through the gas outlet pipe on the box cover, the operation is simple, the immersion of the waste gas is realized, the spraying, the adsorption and the dry continuity treatment are.
Drawings
FIG. 1 is a schematic structural view of the present invention;
fig. 2 is the utility model discloses waste gas sprays the inside sectional plane structure sketch map of purification structure.
In the figure: the device comprises a frame plate 1, a treatment barrel 2, a waste gas immersion treatment structure 3, a leakage hole bottom plate 31, a coiled pipe 32, a suction fan 33, a waste gas spraying and purifying structure 4, a circular ring plate 41, a circular ring pipe 42, a spray head 43, a branch pipe 44, a liquid pump 45, an adsorption and purifying structure 5, a filter screen plate 51, a threaded barrel 52, a screw 53, a leakage hole pressing plate 54, an active carbon ball 55, a sealing cover 6, a control switch group 7, a drying box 8, quick lime 9, a box cover 10, a gas delivery pipe 11 and an electromagnetic valve 12.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-2, the present invention provides a technical solution: an industrial production waste gas treatment device comprises a frame plate 1, a waste gas immersion liquid treatment structure 3, a waste gas spraying purification structure 4 and an adsorption purification structure 5;
frame plate 1: the frame plate 1 provides a supporting and mounting place, a treatment barrel 2 is correspondingly arranged in a mounting port in the middle of the frame plate 1, the treatment barrel 2 provides a waste gas treatment place, the bottom end of the treatment barrel 2 is of an arc structure, a sealing cover 6 is correspondingly mounted at a barrel port at the upper end of the treatment barrel 2 through bolts, the mounting and dismounting are convenient, and a gas outlet is formed in the center of a wall body of the sealing cover 6 to realize the discharge of treated gas;
exhaust gas immersion liquid treatment structure 3: the waste gas immersion liquid treatment structure 3 is arranged at the inner bottom end of the treatment barrel 2, the waste gas immersion liquid treatment structure 3 comprises a leak hole bottom plate 31, a coiled pipe 32 and a suction fan 33, the leak hole bottom plate 31 is correspondingly arranged at the inner bottom end of the treatment barrel 2, the coiled pipe 32 is correspondingly arranged at the upper end of the leak hole bottom plate 31, air holes which are uniformly distributed are formed in the wall body of the coiled pipe 32, the suction fan 33 is arranged on the right side of the upper wall of the frame plate 1, the air outlet of the suction fan 33 is connected with the air inlet of the coiled pipe 32 through an air pipe, the air pipe penetrates through the inner wall of the treatment barrel 2, waste gas is sucked in through the suction fan 33, is input into the coiled pipe 32 on the leak hole bottom plate 31 through the air pipe, is discharged through the air holes in the wall body of the coiled pipe 32;
exhaust gas sprays purification structure 4: the waste gas spraying purification structure 4 is arranged at the center of the inner part of the treatment cylinder 2, the waste gas spraying purification structure 4 comprises a circular ring-shaped plate 41, a circular ring tube 42, a spraying head 43, a branch tube 44 and a liquid pump 45, the circular ring-shaped plate 41 is arranged at the middle part of the inner wall of the treatment cylinder 2, the circular ring tube 42 is correspondingly arranged on the inner wall of the circular ring-shaped plate 41 through a mounting tube ring, the spraying head 43 is uniformly and correspondingly arranged on the bottom surface of the circular ring-shaped plate 41, a water inlet of the spraying head 43 is connected with a water outlet of the circular ring tube 42 through the corresponding branch tube 44, the liquid pump 45 is arranged on the outer arc wall of the treatment cylinder 2, a liquid inlet of the liquid pump 45 is connected with a liquid inlet of the circular ring tube 42 through a guide tube, the guide tube penetrates through the inner wall of the treatment cylinder 2, the liquid pump 45 pumps external purification treatment liquid, the purification treatment liquid is conveyed through, the spraying gas purification is realized efficiently;
adsorption purification structure 5: the adsorption and purification structure 5 is arranged at the upper end of the interior of the treatment cylinder 2, the adsorption and purification structure 5 comprises a filter screen plate 51, a threaded cylinder 52, a screw 53, a leak hole pressing plate 54 and activated carbon balls 55, the filter screen plate 51 is correspondingly arranged at the upper end of the interior of the treatment cylinder 2, the threaded cylinder 52 is symmetrically arranged at the upper end of the filter screen plate 51, the bottom end of the screw 53 is in threaded connection with the corresponding threaded cylinder 52, the screw 53 passes through the corresponding perforation on the wall body of the leak hole pressing plate 54, the pressing sheet on the wall body of the screw 53 is positioned above the leak hole pressing plate 54, the activated carbon balls 55 are filled in the gap between the filter screen plate 51 and the leak hole pressing plate 54, the leak hole pressing plate 54 is correspondingly arranged with the inner cavity of the treatment cylinder 2, gas is firstly filtered by the filter screen plate 51 and then adsorbed and purified by the activated carbon balls 55, so as to realize rapid and comprehensive purification and adsorption treatment, because the screw 53 passes through, the screw 53 moves downwards in a threaded manner, and the pressing sheet on the wall body of the screw 53 presses and holds the small active carbon balls 55 at the gap between the filter screen plate 51 and the small leak hole pressing plate 54 to move downwards moderately, so that the adsorption material is convenient to place, disassemble, maintain and replace;
wherein: still include control switch group 7 and solenoid valve 12, the normal operating of each structure is regulated and control to control switch group 7, the circular telegram and the outage of solenoid valve 12, realize the switching of 2 bottom fluid-discharge tubes of a processing section of thick bamboo, control switch group 7 sets up on the last wall of frame plate 1, solenoid valve 12 is established ties in the inside of 2 bottom fluid-discharge tubes of a processing section of thick bamboo, external power source is connected to control switch group 7's input electricity, solenoid valve 12, the equal electric connection control switch group 7's of input of suction fan 33 and drawing liquid pump 45 output.
Wherein: still include the drying cabinet 8, quick lime 9, case lid 10 and gas-supply pipe 11, drying cabinet 8 provides dry place, quick lime 9 is dry moist gaseous, 8 upper end open-ended switchings of drying cabinet are realized to case lid 10, gas-supply pipe 11 realizes gaseous transport, drying cabinet 8 sets up in the upper wall left side of frame plate 1, drying cabinet 8's upper end is open structure, quick lime 9 is put in the inside small opening backup pad of drying cabinet 8, case lid 10 corresponds through the bolt and installs in drying cabinet 8's upper end opening part, the upper end exhaust port department of case lid 10 is equipped with the blast pipe, the air inlet of 8 right walls bottoms of drying cabinet passes through the gas-supply pipe 11 and links to each other with the gas outlet at 6 wall body centers.
When in use: when the industrial waste gas pipeline to be treated is connected with the air inlet pipeline of the suction fan 33, the purified treatment liquid pipeline is connected with the air inlet of the liquid pump 45, when the device is used, the liquid pump 45 is regulated and controlled by the control switch group 7 in advance, a proper amount of purified treatment liquid is pumped into the treatment cylinder 2 through the guide pipe, the circular ring pipe 42, the branch pipe 44 and the spray header 43 until the serpentine pipe 32 is submerged, waste gas is pumped into the serpentine pipe 32 on the leak bottom plate 31 through the air pipe, is discharged through the air holes on the wall body of the serpentine pipe 32 in a turning way, fully reacts with the purified treatment liquid, increases the contact area with the purified treatment liquid, thereby improving the purification effect, after the purification through the first layer of immersion liquid reaction, the gas rises, the liquid pump 45 pumps the external purified treatment liquid, conveys the liquid through the guide pipe, the circular ring pipe 42 and the branch pipe 44, and sprays all-directionally through the uniformly distributed spray headers 43, the gas purification is realized by further contact reaction with the rising gas, in the process of spraying purification, the electromagnetic valve 12 is needed to be electrified to discharge the waste liquid at the bottom end in the treatment cylinder 2 in proper amount, the liquid at the bottom is kept relatively balanced all the time, the coiled pipe 32 is submerged in proper amount, the gas after double purification reaction is filtered by the filter screen plate 51 and then is adsorbed and purified by the active carbon small ball 55 to realize rapid and comprehensive purification and adsorption treatment, because the screw 53 passes through the corresponding perforation on the wall body of the leak hole pressing plate 54 and is in threaded connection with the corresponding threaded cylinder 52, the screw 53 is threaded downwards, the pressing sheet on the wall body of the screw 53 presses and holds the leak hole pressing plate 54 to be properly downwards moved, thereby pressing the active carbon small ball 55 at the gap between the filter screen plate 51 and the leak hole pressing plate 54, the adsorption material is convenient to place, disassemble and maintain the gas transmission pipe, the purified gas is transmitted by the gas transmission pipe 11 and then is dried by the quicklime, then, the exhaust pipe on the box cover 10 is used for exhausting, so that the immersion, spraying, adsorption and drying continuity treatment of the waste gas are realized, the waste gas treatment quality is ensured, the workload of personnel is reduced, each structural material is maintained and replaced regularly, and after the use is finished, each structure is recovered to the original shape.
It should be noted that the control switch group 7 disclosed in this embodiment controls the operation of the electromagnetic valve 12, the suction fan 33 and the liquid pump 45 by using a method commonly used in the prior art, and the electromagnetic valve 12, the suction fan 33 and the liquid pump 45 are all common elements of industrial waste gas treatment equipment in the prior art.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. An industrial production waste gas treatment equipment which characterized in that: comprises a frame plate (1), a waste gas immersion liquid treatment structure (3), a waste gas spraying purification structure (4) and an adsorption purification structure (5);
frame plate (1): a treatment barrel (2) is correspondingly arranged in a middle mounting port of the frame plate (1), the bottom end of the treatment barrel (2) is of an arc structure, a sealing cover (6) is correspondingly arranged at the upper end opening of the treatment barrel (2) through a bolt, and an air outlet is formed in the center of a wall body of the sealing cover (6);
exhaust gas immersion treatment structure (3): the waste gas immersion liquid treatment structure (3) is arranged at the bottom end of the interior of the treatment cylinder (2);
exhaust gas spraying purification structure (4): the waste gas spraying and purifying structure (4) is arranged at the center of the interior of the treatment cylinder (2);
adsorption purification structure (5): the adsorption purification structure (5) is arranged at the upper end of the interior of the treatment cylinder (2);
wherein: still include control switch group (7) and solenoid valve (12), control switch group (7) set up on the last wall of frame plate (1), and solenoid valve (12) are established ties in the inside of handling a section of thick bamboo (2) bottom fluid-discharge tube, and external power source is connected to the input electricity of control switch group (7), and the output of control switch group (7) is connected to the input electricity of solenoid valve (12).
2. The industrial process waste gas treatment plant of claim 1, wherein: waste gas immersion fluid processing structure (3) includes small opening bottom plate (31), coiled pipe (32) and suction fan (33), small opening bottom plate (31) correspond to set up in the inside bottom of handling a section of thick bamboo (2), and coiled pipe (32) correspond to set up in the upper end of small opening bottom plate (31), is equipped with evenly distributed's gas pocket on the wall body of coiled pipe (32), and suction fan (33) set up in the upper wall right side of frame plate (1), and the gas outlet of suction fan (33) passes through the air inlet of trachea with coiled pipe (32) and links to each other, and the trachea runs through the inner wall of handling a section of thick bamboo (2), and the output of input electricity connection control switch group (7) of suction fan (33).
3. The industrial process waste gas treatment plant of claim 1, wherein: waste gas sprays purification structure (4) including annular plate (41), ring tube (42), shower head (43), be in charge of (44) and drawing liquid pump (45), annular plate (41) set up in the inner wall middle part of handling a section of thick bamboo (2), ring tube (42) set up on the inner wall of annular plate (41) through the installation pipe ring correspondence, shower head (43) even correspond and set up on the bottom surface of annular plate (41), the water inlet of shower head (43) links to each other through the delivery port that corresponds be in charge of (44) and ring tube (42), drawing liquid pump (45) set up on the outer arc wall of handling a section of thick bamboo (2), the inlet of drawing liquid pump (45) passes through the inlet of pipe and ring tube (42) and links to each other, the pipe runs through the inner wall of handling a section of thick bamboo (2), the output of input electricity connection control switch group (7) of drawing liquid pump (45).
4. The industrial process waste gas treatment plant of claim 1, wherein: the adsorption purification structure (5) comprises a filter screen plate (51), a threaded cylinder (52), a screw rod (53), a leak hole pressing plate (54) and small active carbon balls (55), wherein the filter screen plate (51) is correspondingly arranged at the upper end of the interior of the treatment cylinder (2), the threaded cylinder (52) is symmetrically arranged at the upper end of the filter screen plate (51), the bottom end of the screw rod (53) is in threaded connection with the corresponding threaded cylinder (52), the screw rod (53) penetrates through a corresponding through hole in the wall body of the leak hole pressing plate (54), pressing sheets on the wall body of the screw rod (53) are positioned above the leak hole pressing plate (54), the small active carbon balls (55) are filled in a gap between the filter screen plate (51) and the leak hole pressing plate (54), and the leak hole pressing plate (54) is correspondingly arranged with the inner cavity of the treatment cylinder (2).
5. The industrial process waste gas treatment plant of claim 1, wherein: still include drying cabinet (8), quick lime (9), case lid (10) and gas-supply pipe (11), drying cabinet (8) set up in the upper wall left side of frame plate (1), and the upper end of drying cabinet (8) is open structure, and quick lime (9) are put in the inside small opening backup pad of drying cabinet (8), and case lid (10) correspond through the bolt and install in the upper end opening part of drying cabinet (8), and the upper end exhaust port department of case lid (10) is equipped with the blast pipe, and the air inlet of drying cabinet (8) right wall bottom passes through gas-supply pipe (11) and links to each other with the gas outlet at closing cap (6) wall body center.
CN201922247658.3U 2019-12-16 2019-12-16 Industrial production exhaust-gas treatment equipment Active CN211837207U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922247658.3U CN211837207U (en) 2019-12-16 2019-12-16 Industrial production exhaust-gas treatment equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922247658.3U CN211837207U (en) 2019-12-16 2019-12-16 Industrial production exhaust-gas treatment equipment

Publications (1)

Publication Number Publication Date
CN211837207U true CN211837207U (en) 2020-11-03

Family

ID=73215932

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922247658.3U Active CN211837207U (en) 2019-12-16 2019-12-16 Industrial production exhaust-gas treatment equipment

Country Status (1)

Country Link
CN (1) CN211837207U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113274813A (en) * 2021-05-31 2021-08-20 宋振钰 Sack cleaner of intermittent type formula clearance sack

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113274813A (en) * 2021-05-31 2021-08-20 宋振钰 Sack cleaner of intermittent type formula clearance sack

Similar Documents

Publication Publication Date Title
CN211837207U (en) Industrial production exhaust-gas treatment equipment
CN108619848A (en) A kind of pretreatment reaction tower of industrial waste gas
CN207533046U (en) A kind of paint spray booth waste gas treatment equipment
CN206980439U (en) A kind of coal chemical industry waste gas pollution control and treatment is atomized humidification cycle equipment
CN214914843U (en) Processing apparatus for processing waste oil regeneration waste gas
CN213643453U (en) RTO exhaust treatment device
CN210434289U (en) Environmental protection chemical waste gas treatment device
CN211328886U (en) Chemical gas recovery device
CN208711338U (en) A kind of pretreatment reaction tower of industrial waste gas
CN207667411U (en) A kind of plasma Composite sodium light emission-control equipment
CN218191453U (en) Waste discharge device for lost foam casting
CN212974685U (en) Waste gas treatment device capable of utilizing waste heat
CN207237628U (en) Industrial organic exhaust gas integrated wastewater treatment plant
CN219964446U (en) VOCs processing apparatus in storage tank
CN218358338U (en) Acid-base neutralization and cooling waste gas treatment equipment
CN216537783U (en) Waste incineration smoke dust filtering device for industrial waste treatment
CN216825530U (en) Industrial waste gas treatment equipment
CN220153291U (en) Treatment device for waste gas of refractory kiln
CN214513736U (en) Waste gas treatment device for angle steel welding
CN217526942U (en) Catalytic combustion treatment device for organic waste gas
CN216654040U (en) Active carbon adsorption tower of curing oven exhaust-gas treatment system
CN213761130U (en) Harmful gas processing apparatus for environmental protection engineering
CN210905621U (en) Flue gas pretreatment system for desulfurization and denitrification
CN212417520U (en) Energy-saving and environment-friendly flue gas purification device
CN212188581U (en) Photosensitive catalysis exhaust treatment device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210827

Address after: 264000 room 1101, scientific research and production building, No. 2766, Yingxiu Road, high tech Zone, Jinan City, Shandong Province

Patentee after: SHANDONG RUIYI ENVIRONMENTAL TECHNOLOGY Co.,Ltd.

Address before: No. 555, beiwaihuan Road, Bincheng District, Binzhou City, Shandong Province

Patentee before: Lou Yanxiu