Steel structure climbing frame
Technical Field
The utility model relates to a construction technical field specifically is a steel construction climbing frame.
Background
The climbing frame is also called a lifting frame, and can be divided into several main types such as hydraulic type, electric type, manual pulling type and the like according to the power source, and is generally used for climbing from a low position to a high position. The frame is climbed to current steel construction mostly appears for fixed flexible ascending nature, and this kind of frame structure that climbs is complicated fixed, is difficult for dismantling it, and the cost is with high costs, and application scope is less, and general scene is hardly used this kind and is climbed the frame, and is difficult for putting, and occupation space is big.
SUMMERY OF THE UTILITY MODEL
The utility model provides a frame is climbed to steel construction, this steel construction climb the frame, the steel construction that has solved fixed flexible ascending nature climbs the frame structure complicacy fixed, non-detachability, the cost is with high costs, application scope is less, the problem that occupation space is big.
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: a steel structure climbing frame comprises a first support frame, a second support frame, a climbing rod and a folding clamping mechanism, wherein the climbing rod is movably connected to one side of the first support frame, the second support frame is movably connected to one end of the climbing rod, and the folding clamping mechanism is arranged at one end of the climbing rod;
folding latch mechanism includes arc draw-in groove, arc elasticity card, first rotatory ring, joint dead lever, first bolt, first thread groove and second thread groove, the arc draw-in groove has been seted up to one side of first support frame, the inner chamber activity joint of arc draw-in groove has arc elasticity card, the one end fixedly connected with climbing pole of arc elasticity card, the one end swing joint of climbing pole has first rotatory ring, the top surface swing joint of first rotatory ring has the joint dead lever, one side top through-hole department swing joint of joint dead lever has first bolt, the one end of first bolt has first support frame through first thread groove swing joint, the one end swing joint of first bolt has the second thread groove, the bottom at the climbing pole is seted up to the second thread groove.
Preferably, one side of joint dead lever and one side activity laminating of first support frame, one side and the pole-climbing activity laminating of joint dead lever.
Preferably, one end fixedly connected with second rotatory ring of pole climbing, the surface of second rotatory ring and one side swing joint of second support frame.
Preferably, hinge mechanisms are fixedly mounted at the middle parts of the first support frame and the second support frame respectively, each hinge mechanism comprises a leaf and a hinge rotating ring, the leaves are fixedly mounted on the front surfaces of the first support frame and the second support frame, and the through holes of the leaves are movably connected with the hinge rotating rings.
Preferably, the bottoms of the front sides of the first support frame and the second support frame are both provided with third thread grooves, and the inner walls of the third thread grooves are movably connected with second bolts.
Preferably, the outer surface of the second bolt is movably connected with a bottom fixing plate, and the back surface of the bottom fixing plate is movably attached to the front surfaces of the first support frame and the second support frame.
Borrow by above-mentioned technical scheme, the utility model provides a steel construction climbs frame. The method at least has the following beneficial effects:
(1) this steel construction climbing frame, the folding joint mechanism of application can carry out split and combination to the pole of climbing and the first bracing piece of connection on the second bracing piece, and the application is convenient for it is nimble quick detachable and cost little more to climb between the structure of frame, practices thrift the cost, and application scope is wide.
(2) This steel construction climbs the frame, application hinge mechanism can extend and fold first bracing piece and second bracing piece, has reduced and has climbed the holistic space that takes up an area of frame.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this application:
fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of a portion A of FIG. 1 according to the present invention;
FIG. 3 is a schematic view of a portion B of FIG. 1 according to the present invention;
FIG. 4 is a schematic view of a portion C of FIG. 1 according to the present invention;
fig. 5 is a schematic structural view of the bottom fixing plate portion in fig. 1 according to the present invention.
In the figure: 1, a first support frame, 2, a second support frame, 3, a climbing pole and 4, a bottom fixing plate;
5, a folding clamping mechanism, a 51 arc-shaped clamping groove, a 52 arc-shaped elastic clamping piece, a 53 first rotating ring, a 54 clamping fixing rod, a 55 first bolt, a 56 first thread groove and a 57 second thread groove;
6, a second rotating ring, 7 hinge mechanisms, 71 leaves and 72 hinge rotating rings;
8 third thread groove, 9 second bolt.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-5, the present invention provides a technical solution: a steel structure climbing frame comprises a first support frame 1, a second support frame 2, a climbing rod 3 and a folding clamping mechanism 5, wherein the climbing rod 3 is movably connected to one side of the first support frame 1, the second support frame 2 is movably connected to one end of the climbing rod 3, and the folding clamping mechanism 5 is arranged at one end of the climbing rod 3;
folding latch mechanism 5 includes arc draw-in groove 51, arc elasticity card 52, first rotatory ring 53, joint dead lever 54, first bolt 55, first thread groove 56 and second thread groove 57, arc draw-in groove 51 has been seted up to one side of first support frame 1, the inner chamber activity joint of arc draw-in groove 51 has arc elasticity card 52, the one end fixedly connected with climbing rod 3 of arc elasticity card 52, the one end swing joint of climbing rod 3 has first rotatory ring 53, the top surface swing joint of first rotatory ring 53 has joint dead lever 54, one side top through-hole department swing joint of joint dead lever 54 has first bolt 55, the one end of first bolt 55 has first support frame 1 through first thread groove 56 swing joint, the one end swing joint of first bolt 55 has second thread groove 57, second thread groove 57 is seted up in the bottom of climbing rod 3.
One side of the clamping fixing rod 54 is movably attached to one side of the first support frame 1, and one side of the clamping fixing rod 54 is movably attached to the climbing rod 3 and used for fixing the climbing frame during splitting and combining.
The one end fixedly connected with second rotary ring 6 of pole-climbing 3, the surface of second rotary ring 6 and one side swing joint of second support frame 2, when the frame is made up to climbing, the rotatory effect through second rotary ring 6 rotates the split and the combination that are used for climbing the frame to pole-climbing 3.
Hinge mechanisms 7 are fixedly mounted at the middle parts of the first support frame 1 and the second support frame 2, each hinge mechanism 7 comprises a leaf 71 and a hinge rotating ring 72, the leaf 71 is fixedly mounted on the front surfaces of the first support frame 1 and the second support frame 2, through holes of the leaf 71 are movably connected with the hinge rotating ring 72, and the first support rod 1 and the second support rod 2 can be folded through the hinge mechanisms 7.
The bottoms of the front sides of the first support frame 1 and the second support frame 2 are both provided with a third thread groove 8, the inner wall of the third thread groove 8 is movably connected with a second bolt 9, and the bottom fixing plate 4 is fixed at the bottoms of the front sides of the first support frame 1 and the second support frame 2 through the connection of the second bolt 9 and the third thread groove 8.
The outer surface of the second bolt 9 is movably connected with a bottom fixing plate 4, and the back of the bottom fixing plate 4 and the front surfaces of the first support frame 1 and the second support frame 2 are movably attached to the bottom fixing plate 4 for fixing the connection between the first support rod 1 and the second support rod 2.
When in use, firstly, the climbing frame is combined, the first support frame 1 and the second support frame 2 are unfolded and extended to 180 degrees through the hinge mechanism 7 to be linearly and parallelly placed, then the climbing rod 3 is rotated by 90 degrees through the second rotating ring 6 to be vertical to the first support rod 1 and the second support rod 2, the arc elastic clamping piece 52 fixedly installed at one end of the climbing rod 3 is inserted into the arc clamping groove 51 to be connected to one side of the first support rod 1, then the first bolt 55 originally fixed at the through hole of the clamping fixing rod 54 at the top and the bottom of the climbing rod 3 is taken down from the second thread groove 57, the clamping fixing rod 54 rotates anticlockwise by 90 degrees to be attached to one side of the first support rod 1, the first bolt 55 is inserted into the first thread groove 56 on the first support rod 1 through the clamping fixing rod 54, the climbing rod 3 is fixed at one side of the first support rod, and finally the second bolt 9 is inserted into the third thread groove 8 through the bottom fixing plate 4, the first supporting rod 1, the second supporting rod 2 and the climbing rod 3 are fixedly connected through the bottom fixing plate 4, and when the climbing rod needs to be disassembled, the climbing rod can be disassembled through the reverse steps.
It is right above the utility model provides a steel construction climbs the frame and has introduced in detail. The utility model discloses it is right to have used specific individual example the utility model discloses a principle and implementation have been elucidated, and the explanation of above embodiment is only used for helping understanding the utility model discloses a method and core thought thereof. It should be noted that, for those skilled in the art, without departing from the principle of the present invention, the present invention can be further modified and modified, and such modifications and modifications also fall within the protection scope of the appended claims.