CN211807045U - Building engineering drilling equipment - Google Patents

Building engineering drilling equipment Download PDF

Info

Publication number
CN211807045U
CN211807045U CN201921883816.8U CN201921883816U CN211807045U CN 211807045 U CN211807045 U CN 211807045U CN 201921883816 U CN201921883816 U CN 201921883816U CN 211807045 U CN211807045 U CN 211807045U
Authority
CN
China
Prior art keywords
slide rail
supporting
bearing plate
fixed mounting
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921883816.8U
Other languages
Chinese (zh)
Inventor
唐进财
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Zhongqiang Construction Engineering Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201921883816.8U priority Critical patent/CN211807045U/en
Application granted granted Critical
Publication of CN211807045U publication Critical patent/CN211807045U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a building engineering drilling equipment, including bearing plate and line wheel, the equal fixed mounting in bearing plate upper end left and right sides has slide rail group, the common fixed mounting in slide rail group upper end has the backup pad, backup pad upper end fixed mounting has the cylinder, the equal fixed mounting of cylinder output has the pillar, the equal fixed mounting in pillar upper end has the rest pad, there is a supporting box through pivot swing joint between the rest pad, there is drilling equipment at supporting box middle part interlude, supporting box front end fixedly connected with collection ash device, the equal fixed mounting in bearing plate lower extreme four corners department has the universal wheel. A building engineering drilling equipment, through setting up cylinder and slide rail group, can whole device reduce user's intensity of labour, through setting up album grey device, can collect the ash bed that the operation in-process produced, can ensure user's healthy effectively.

Description

Building engineering drilling equipment
Technical Field
The utility model relates to a building engineering construction technical field, in particular to building engineering drilling equipment.
Background
In the building construction process, a drilling device is a common building construction device, and for example, the drilling device is used for drilling a foundation, a plate and a building wall.
However, when the existing drilling tool is used for drilling a wall body, the existing drilling tool is not easy to position and needs to be adjusted repeatedly, generated dust is not easy to collect, the generated dust easily harms the health of a user, and meanwhile, in the using process, a constructor needs to hold the drilling device to perform drilling operation, the constructor is heavy in construction labor load and easy to fatigue, and the efficiency of the drilling operation is reduced. Therefore, a novel drilling device for construction engineering is provided.
SUMMERY OF THE UTILITY MODEL
A primary object of the utility model is to provide a building engineering drilling equipment can effectively solve the problem in the background art.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
a drilling device for building engineering comprises a bearing plate and a wire wheel, wherein slide rail sets are fixedly mounted on the left side and the right side of the upper end of the bearing plate, a support plate is fixedly mounted at the upper end of the slide rail sets, two groups of cylinders are fixedly mounted at the upper end of the support plate, a support post is fixedly mounted at the output end of the cylinders, support blocks are fixedly mounted at the upper end of the support post, a support box is movably connected between the support blocks through a rotating shaft, a drilling device is fixedly inserted in the middle of the support box, an ash collecting device is fixedly connected to the front end of the support box, two groups of supports are fixedly mounted at the rear part of the upper end of the bearing plate, the supports are fixedly connected with connecting rods through rotating shafts, a lead is arranged in the middle of the wire wheel in a surrounding manner, a rotating shaft is fixedly, and universal wheels are fixedly arranged at four corners of the lower end of the bearing plate.
Preferably, the perforator includes the perforator body, the output fixedly connected with drill bit of the perforator body, perforator body rear end fixedly connected with handle, perforator body surface upper portion fixed mounting has switch knob, perforator body surface right part fixed mounting has power source, power source and wire electric connection.
Preferably, the ash collecting device comprises supporting rods, the supporting rods are arranged into four groups, supporting columns are arranged at the front ends of the supporting rods in an alternating mode, ash collecting bags are connected to the outer surfaces of the supporting columns in a common mode, and the rear ends of the supporting rods are fixedly connected with the front end of the supporting box.
Preferably, the support column is movably inserted into the support rod, an ash collecting cavity is arranged inside the ash collecting bag, and the ash collecting bag is wrapped outside the output end of the drilling device body.
Preferably, slide rail group is including lower slide rail and last slide rail, and lower slide rail and last slide rail all set up to two sets of, go up slide rail and lower slide rail sliding connection, go up the slide rail upper end common with backup pad lower extreme fixed connection, the slide rail lower extreme common with bearing plate upper end fixed connection down.
Preferably, the front end face of the upper slide rail and the end face of the output end of the drill body are on the same horizontal plane.
Compared with the prior art, the utility model discloses following beneficial effect has:
1. the utility model discloses in, through setting up universal wheel, connecting rod and with connecting rod fixed connection's handrail, can the person of facilitating the use this drilling equipment in the removal of whole device operation in-process, the rethread sets up slide rail group and cylinder, can be in a flexible way at horizontal plane and perpendicular ground slip perforator, hand the perforator with the manpower change into and hold the perforator through mechanical device, be favorable to reducing user's intensity of labour, be favorable to improving drilling efficiency.
2. The utility model discloses in, through setting up the ash collecting device, the ash collecting device sets up in supporting box the place ahead, and the ash collecting bag wraps up the output shaft and the drill bit of perforator, can in time collect the dust that produces in the drilling process, has protected the construction environment not polluted by the dust, is favorable to ensuring that user's is healthy.
Drawings
Fig. 1 is a schematic view of the whole structure of a drilling device for construction engineering of the present invention;
fig. 2 is a schematic view of the whole structure of the drilling device for construction engineering of the present invention;
fig. 3 is a schematic view of the overall structure of the drilling device for construction engineering according to the present invention;
fig. 4 is the utility model relates to a building engineering drilling equipment's collection ash device's overall structure schematic diagram.
In the figure: 1. a bearing plate; 2. a slide rail set; 3. a support plate; 4. a cylinder; 5. a pillar; 6. a support block; 7. a support box; 8. a drill; 9. a dust collecting device; 10. a universal wheel; 11. a support; 12. a connecting rod; 13. a rotating shaft; 14. a wire wheel; 15. a wire; 16. a hand wheel; 21. a lower slide rail; 22. an upper slide rail; 81. a reamer body; 82. a drill bit; 83. a handle; 84. a switch knob; 85. a power interface; 91. a support bar; 92. a support pillar; 93. an ash collecting bag.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "both ends", "one end", "the other end" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element to which the reference is made must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "disposed," "connected," and the like are to be construed broadly, and for example, "connected" may be either fixedly connected or detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
As shown in fig. 1-4, a drilling device for building engineering comprises a bearing plate 1 and a wire wheel 14, wherein the left side and the right side of the upper end of the bearing plate 1 are fixedly provided with a slide rail set 2, the upper ends of the slide rail set 2 are fixedly provided with a support plate 3, the upper end of the support plate 3 is fixedly provided with two sets of cylinders 4, the output ends of the cylinders 4 are fixedly provided with pillars 5, the upper ends of the pillars 5 are fixedly provided with support blocks 6, the support blocks 6 are movably connected with a support box 7 through a rotating shaft, the middle part of the support box 7 is fixedly inserted with a drill 8, the front end of the support box 7 is fixedly connected with an ash collecting device 9, the rear part of the upper end of the bearing plate 1 is fixedly provided with two sets of supports 11, the supports 11 are fixedly connected with connecting rods 12 through rotating shafts, the middle part of the wire wheel 14 is surrounded with a conducting wire 15, the four corners of the lower end of the bearing plate 1 are fixedly provided with universal wheels 10.
The borer 8 comprises a borer body 81, wherein the output end of the borer body 81 is fixedly connected with a drill 82, the rear end of the borer body 81 is fixedly connected with a handle 83, the upper part of the outer surface of the borer body 81 is fixedly provided with a switch knob 84, the right part of the outer surface of the borer body 81 is fixedly provided with a power supply interface 85, the power supply interface 85 is matched with the interface of the lead 15, and the power supply interface 85 is electrically connected with the lead 15; the dust collecting device 9 comprises four groups of supporting rods 91, the front ends of the supporting rods 91 are respectively and alternately connected with supporting columns 92, the outer surfaces of the supporting columns 92 are jointly connected with dust collecting bags 93, the dust collecting bags 93 can collect dust generated in drilled holes, and the rear ends of the supporting rods 91 are fixedly connected with the front ends of the supporting boxes 7; the supporting column 92 is movably inserted into the supporting rod 91, an ash collecting cavity is arranged in the ash collecting bag 93 and used for temporarily storing collected dust, and the ash collecting bag 93 is wrapped outside the output end of the drilling device body 81, so that the dust generated in the operation process can be effectively collected; the slide rail group 2 comprises a lower slide rail 21 and an upper slide rail 22, the lower slide rail 21 and the upper slide rail 22 are respectively arranged into two groups, the upper slide rail 22 is connected with the lower slide rail 21 in a sliding manner, the upper ends of the upper slide rails 22 are fixedly connected with the lower end of the supporting plate 3, and the lower ends of the lower slide rails 21 are fixedly connected with the upper end of the bearing plate 1; the front end face of the upper slide rail 22 and the end face of the output end of the drilling device body 81 are in the same horizontal plane, and the upper end of the connecting rod 12 is fixedly provided with a handrail which can facilitate a user to push the whole device.
It should be noted that, the utility model relates to a building engineering drilling device, can make things convenient for whole device to move in the construction work region through setting up universal wheel 10, can collect the dust that produces in the drilling operation through setting up dust collecting device 9, in the use, the user moves whole device to the construction region that needs to carry out the drilling operation through universal wheel 10 and connecting rod 12 and the handrail of installing on connecting rod 12, take off wire 15 from line wheel 14 and make one end of wire 15 and power source 85 on perforator 8 fixed connection, switch on the other end of wire 15 with external power, start cylinder 4 and rise perforator 8, make the front end of drill bit 82 of perforator 8 aim at the position that needs to drill, then close cylinder 4 and make the height of perforator 8 fixed, then, the user holds handle 83, promote perforator 8 to the direction that needs to drill the hole and make perforator 8 move through slide rail group 2, until the drill bit 82 of the drill 8 contacts the drill point, the switch knob 84 is twisted to start the drill 8, and the drilling operation is started, so that the whole device reduces the labor intensity of a user and can effectively ensure the physical health of the user.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (6)

1. The utility model provides a building engineering drilling equipment, includes bearing plate (1) and line wheel (14), its characterized in that: the bearing plate is characterized in that the left side and the right side of the upper end of the bearing plate (1) are respectively and fixedly provided with a sliding rail group (2), the upper end of the sliding rail group (2) is fixedly provided with a supporting plate (3) in common, the upper end of the supporting plate (3) is fixedly provided with two groups of cylinders (4), the output end of each cylinder (4) is fixedly provided with a pillar (5), the upper end of each pillar (5) is fixedly provided with a supporting block (6), the supporting blocks (6) are connected with supporting boxes (7) through rotating shafts in a movable manner, drilling devices (8) are fixed in the middle of the supporting boxes (7) in an alternating manner, the front ends of the supporting boxes (7) are fixedly connected with ash collecting devices (9), the rear part of the upper end of the bearing plate (1) is fixedly provided with two groups of supports (11), the supports (11), fixedly connected with axis of rotation (13) alternates in the middle of line wheel (14), axis of rotation (13) one end and left side connecting rod (12) swing joint and the other end pass right side connecting rod (12) fixedly connected with hand wheel (16), the equal fixed mounting in bearing plate (1) lower extreme four corners department has universal wheel (10).
2. A construction drilling device according to claim 1, wherein: the drill (8) comprises a drill body (81), an output end fixedly connected with drill bit (82) of the drill body (81), a handle (83) is fixedly connected with the rear end of the drill body (81), a switch knob (84) is fixedly mounted on the upper portion of the outer surface of the drill body (81), a power source interface (85) is fixedly mounted on the right portion of the outer surface of the drill body (81), and the power source interface (85) is electrically connected with a wire (15).
3. A construction drilling device according to claim 1, wherein: the ash collecting device (9) comprises a supporting rod (91), the supporting rod (91) is set into four groups, supporting columns (92) are connected to the front ends of the supporting rods (91) in an alternating mode, ash collecting bags (93) are connected to the outer surfaces of the supporting columns (92) in a common mode, and the rear ends of the supporting rods (91) are fixedly connected with the front end of the supporting box (7).
4. A construction drilling device according to claim 3, wherein: the dust collection bag (93) is internally provided with a dust collection cavity, and the dust collection bag (93) is wrapped outside the output end of the drilling device body (81).
5. A construction drilling device according to claim 4, wherein: slide rail group (2) are including lower slide rail (21) and last slide rail (22), and slide rail (21) and last slide rail (22) all set up to two sets of down, go up slide rail (22) and lower slide rail (21) sliding connection, go up slide rail (22) upper end common and backup pad (3) lower extreme fixed connection, slide rail (21) lower extreme common and bearing plate (1) upper end fixed connection down.
6. A construction drilling device according to claim 5, wherein: the front end face of the upper sliding rail (22) and the end face of the output end of the drilling device body (81) are on the same horizontal plane.
CN201921883816.8U 2019-11-04 2019-11-04 Building engineering drilling equipment Expired - Fee Related CN211807045U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921883816.8U CN211807045U (en) 2019-11-04 2019-11-04 Building engineering drilling equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921883816.8U CN211807045U (en) 2019-11-04 2019-11-04 Building engineering drilling equipment

Publications (1)

Publication Number Publication Date
CN211807045U true CN211807045U (en) 2020-10-30

Family

ID=73147139

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921883816.8U Expired - Fee Related CN211807045U (en) 2019-11-04 2019-11-04 Building engineering drilling equipment

Country Status (1)

Country Link
CN (1) CN211807045U (en)

Similar Documents

Publication Publication Date Title
CN106837169A (en) The broken rig of building construction
CN206502421U (en) A kind of medical discarded medicine bottle quantitative Treatment device
CN211807045U (en) Building engineering drilling equipment
CN212917626U (en) Horizontal lathe with dustproof construction
CN211598499U (en) Geology reconnaissance probing device
CN212105766U (en) Novel internal drilling machine
CN212169590U (en) Plate drilling device for hydraulic engineering
CN211362571U (en) Intelligent mobile phone assembly production line
CN212803224U (en) Smooth blasting tool for tunneling
CN206581962U (en) A kind of constructing tunnel top shield structure
CN210798838U (en) Subway construction roof drilling equipment
CN211144368U (en) Geological detection drilling equipment
CN209727512U (en) A kind of highway engineering soil sampling apparatus
CN212458307U (en) Road bridge crack detection device
CN213328594U (en) Roadbed detects uses thickness measurement device
CN208239110U (en) A kind of mining geology rock sampler
CN211081699U (en) Drilling rig for geotechnical engineering investigation
CN215790884U (en) Drilling equipment convenient to adjusting position for building engineering
CN112806721A (en) Drawing device is assisted with scene to environmental design
CN215880031U (en) Interface chamfering device for machining hydraulic pipe fitting joint
CN218629082U (en) Drilling machine for building detection sampling
CN215281301U (en) Guardrail grinding device for highway engineering
CN210243003U (en) Portable multifunctional power temperature measuring instrument
CN206643390U (en) A kind of bench drill with stopping means
CN215718460U (en) Portable device replacing groove with drill

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20210608

Address after: 242000 No.14, building D, Zhenxing East Street, Wuxing Township, Xuanzhou District, Xuancheng City, Anhui Province

Patentee after: Anhui Zhongqiang Construction Engineering Co.,Ltd.

Address before: No. 1, shanzhutang, Henggang village committee, Lishao Town, Luoding City, Yunfu City, Guangdong Province, 527239

Patentee before: Tang Jincai

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201030

Termination date: 20211104

CF01 Termination of patent right due to non-payment of annual fee