CN211773828U - Steel constructs concatenation formula base of factory building - Google Patents
Steel constructs concatenation formula base of factory building Download PDFInfo
- Publication number
- CN211773828U CN211773828U CN201922164075.4U CN201922164075U CN211773828U CN 211773828 U CN211773828 U CN 211773828U CN 201922164075 U CN201922164075 U CN 201922164075U CN 211773828 U CN211773828 U CN 211773828U
- Authority
- CN
- China
- Prior art keywords
- jack
- base
- connecting arm
- clamping
- linking
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
The utility model discloses a steel constructs concatenation formula base of factory building, including the horn base and with horn base fixed connection's linking arm, be provided with the bottom surface purlin on the linking arm and prop the post, the one end of keeping away from the horn base on the linking arm is provided with two jacks and the square tube of linking of lining up from top to bottom, the both ends of the square tube of linking are all pegged graft and are had the linking arm, the upper and lower surperficial jack one that is provided with two axials of jack of the square tube of linking, the tip of propping the post is tightly inserted in jack two and jack one. Has the advantages that: the concatenation formula base of steel structure factory building adopt plug-in connection's mounting means to replace bolted connection and welded connection's the mounting means commonly used at present, not only the installation is firm reliable, has saved moreover and has beaten bolt and welded trouble, shortens installation time by a wide margin, installation cost is showing and is reducing, the practicality is good.
Description
Technical Field
The utility model relates to a steel construction factory building apparatus technical field, concretely relates to steel constructs concatenation formula base of factory building.
Background
The steel structure factory building becomes the mainstream of the current factory building construction method due to the advantages of light building weight, high strength, large span, short construction period, low investment cost, high fire resistance, strong corrosion resistance, convenient movement, no pollution in recycling and the like.
The base of current steel structure factory building generally adopts the concatenation formula design, uses the bolt to be in the same place the main component of base such as angle seat, linking arm, corner post, bottom surface purlin, strut fixed connection, because the component part of base is more, consequently beats the bolt and need spend longer time, so the base installation is consuming time longer.
In addition, in order to ensure that the base is stably installed, the joint of the base component parts is generally welded after bolts are screwed, so that the installation time of the base is further prolonged, the installation cost of the base is improved, welding lines formed at the joint of the base component parts are quite tortuous, the requirement on the operation capacity of a welder is high, and otherwise, the welding position is easy to open for a long time.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a steel constructs concatenation formula base of factory building just for solving above-mentioned problem to solve current steel and construct the concatenation formula base of factory building and adopt bolted connection installation and welded connection installation time long, problem such as installation cost height. The utility model provides a steel constructs the concatenation formula base of factory building adopts the mounting means of plug-in connection, does not adopt bolted connection and welded connection, and the installation is firm reliable, has saved the trouble of beating bolt and welded, and installation time shortens by a wide margin, and installation cost is showing and is reducing, and the practicality is good, sees the explanation below in detail.
In order to achieve the above purpose, the utility model provides a following technical scheme:
the utility model provides a pair of steel constructs concatenation formula base of factory building, including the horn base and with horn base fixed connection's linking arm, be provided with the bottom surface purlin on the linking arm and prop the post, the one end of keeping away from the horn base on the linking arm is provided with two jacks and the square tube of linking of lining up from top to bottom, the both ends of the square tube of linking are all pegged graft and are had the linking arm, the upper and lower surperficial jack one that is provided with two axials of jack of the square tube of linking, the tip of propping the post is tightly inserted in jack two and jack one.
As an important design of the scheme, an insertion block is processed at the end part of the support column and is tightly inserted into the second insertion hole and the first insertion hole, and the end face of the support column is pressed on the outer surface of the connecting square pipe.
As the optimized design of the scheme, a baffle is arranged in the connecting square pipe.
As the optimized design of the scheme, the side face of the connecting arm is provided with a clamping groove, the upper end and the lower end of the clamping groove are respectively located on the upper surface and the lower surface of the connecting arm, the two ends of the bottom surface purline are provided with clamping blocks, and the clamping blocks are located in the clamping grooves.
As the optimized design of the scheme, the clamping block is clamped in the clamping groove.
As an optimized design of the scheme, the clamping block is slidably inserted into the clamping groove, and the upper end and the lower end of the clamping block are flush with the upper end and the lower end of the clamping groove; the C-shaped sleeve is slidably sleeved on the connecting arm, the inner wall of the C-shaped sleeve is tightly attached to the upper end and the lower end of the clamping block, and a locking screw used for preventing the C-shaped sleeve from sliding on the connecting arm is arranged on the C-shaped sleeve.
As the optimization design of the scheme, the corner seat is provided with a corner post connecting groove.
Has the advantages that: the concatenation formula base of steel structure factory building adopt plug-in connection's mounting means to replace bolted connection and welded connection's the mounting means commonly used at present, not only the installation is firm reliable, has saved moreover and has beaten bolt and welded trouble, shortens installation time by a wide margin, installation cost is showing and is reducing, the practicality is good.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic structural diagram of the present invention;
FIG. 2 is a schematic structural view of the present invention, with the connecting square tube removed, of FIG. 1;
FIG. 3 is a front view of the hinge of the present invention;
FIG. 4 is a top view of the hinge of the present invention;
FIG. 5 is a front view of the C-shaped sleeve of the present invention;
FIG. 6 is a right side view of the C-shaped sleeve of the present invention;
fig. 7 is a top view of the C-shaped jacket of the present invention;
FIG. 8 is a front view of the square connecting tube of the present invention;
fig. 9 is a top view of the connecting square tube of the present invention;
fig. 10 is a left side view of the connecting square tube of the present invention;
figure 11 is a cross-sectional view a-a of figure 9 in accordance with the present invention;
fig. 12 is an assembly diagram of the brace, the connecting arm, and the connecting square tube of the present invention.
The reference numerals are explained below:
1. a corner seat; 2. a connecting arm; 3. corner post connecting grooves; 4. a card slot; 5. a second jack; 6. inserting a block; 7. c-shaped sleeves; 8. locking the screw; 9. a bottom surface purlin; 10. a clamping block; 11. bracing columns; 12. a baffle plate; 13. a first jack; 14. and connecting the square pipes.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention clearer, the technical solutions of the present invention will be described in detail below. It is to be understood that the embodiments described are only some embodiments of the invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
Referring to fig. 1-2 and 8-11, the splicing type base of a steel structure factory building provided by the present invention comprises a corner base 1 and a connecting arm 2 fixedly connected with the corner base 1, wherein a bottom purlin 9 and a brace 11 are arranged on the connecting arm 2, one end of the connecting arm 2 far away from the corner base 1 is provided with a jack two 5 and a connecting square tube 14 which are communicated up and down, both ends of the connecting square tube 14 are tightly inserted with the connecting arm 2, so that the connecting arms 2 on four corner bases 1 of the splicing type base of the whole steel structure factory building are connected together through the connecting square tube 14, that is, the connecting arms 2 on two adjacent corner bases 1 are inserted and fixedly connected through the connecting square tube 14, the upper surface and the lower surface of the connecting square tube 14 are provided with a jack one 13 which is coaxial with the jack two 5, that is, the upper jack one 13 and the lower jack one 13 are respectively located right above and right below the jack two 5, the tip of brace 11 tightly inserts in jack two 5 and jack one 13, can effectively prevent the one end of linking arm 2 from following the interior roll-off of connecting square pipe 14 through with brace 11 cross-under in jack two 5 and jack one 13, the one end of brace 11 tightly inserts in jack two 5 and jack one 13 in addition, the one end of linking arm 2 tightly inserts in connecting square pipe 14, so brace 11, connecting square pipe 14, linking arm 2 is pegged graft and is assembled together after very firm reliable, can not become flexible, the problem of linking arm 2 slippage more can not take place, compare current bolted connection and welded connection's mounting means commonly used, the trouble of beating the bolt and welding has been saved, shorten installation time by a wide margin, installation cost is showing and is reducing, and the practicality is good.
In order to prevent the support column 11 from moving up and down in the second jack 5 and the first jack 13 to affect the connection stability of the square connecting tube 14 and the connecting arm 2 in the installation process of the splicing type base, an insert block 6 can be processed at the end part of the support column 11, as shown in fig. 3 and 4, the cross section area of the insert block 6 is smaller than that of the support column 11, the insert block 6 can be tightly inserted in the second jack 5 and the first jack 13, and the end surface of the support column 11 is tightly pressed on the outer surface of the square connecting tube 14, as shown in fig. 12, so that the end part of the support column 11 can be prevented from moving up and down in the second jack 5 and the first jack 13 to affect the connection stability of the square connecting tube 14 and the connecting arm 2, and the support column 11, the square connecting tube 14 and the connecting arm 2 are further ensured to be very.
Referring to fig. 11, the baffle 12 is disposed in the square connecting pipe 14, so as to enhance the mechanical strength of the whole square connecting pipe 14.
Referring to fig. 1-2, a clamping groove 4 is formed in the side face of the connecting arm 2, the upper end and the lower end of the clamping groove 4 are respectively located on the upper surface and the lower surface of the connecting arm 2, preferably, the clamping groove 4 is a dovetail groove, clamping blocks 10 are arranged at the two ends of the bottom surface purlin 9, the clamping blocks 10 can be welded at the end portions of the bottom surface purlin 9 and can be integrated with the bottom surface purlin 9, the clamping blocks 10 are machined at the end portions of the bottom surface purlin 9, the clamping blocks 10 are located in the clamping grooves 4, preferably, the clamping blocks 10 are dovetail joints, the design is achieved, the bottom surface purlin 9 and the connecting arm 2 can be conveniently detached and connected, and reliable connection can be guaranteed.
The fixture block 10 is clamped in the clamping groove 4.
Referring to fig. 1-2 and 5-7, the C-shaped sleeve 7 is slidably sleeved on the connecting arm 2, and the fixture block 10 is tightly slidably inserted into the slot 4, so that the design of the tight sliding connection between the fixture block 10 and the slot 4 is mainly to facilitate later disassembly, the upper and lower ends of the fixture block 10 are flush with the upper and lower ends of the slot 4, when the C-shaped sleeve 7 is moved to the clamping groove 4 of the connecting arm 2, the upper end and the lower end of the clamping block 10 can be tightly attached to the inner wall of the C-shaped sleeve 7, the clamping block 10 cannot shake in the clamping groove 4, the bottom purline 9 is stably connected with the connecting arm 2, the C-shaped sleeve 7 is provided with a locking screw 8 for preventing the C-shaped sleeve 7 from sliding on the connecting arm 2, when the locking screw 8 is screwed to enable the locking screw 8 to tightly push against the connecting arm 2, the C-shaped sleeve 7 cannot slide on the connecting arm 2, and otherwise, the C-shaped sleeve 7 can slide.
Referring to fig. 1-2, the corner base 1 is provided with a corner post connecting groove 3, and the corner post connecting groove 3 is used for inserting and mounting a corner post.
The above description is only for the specific embodiments of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art can easily think of the changes or substitutions within the technical scope of the present invention, and all should be covered within the protection scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.
Claims (7)
1. The utility model provides a steel constructs concatenation formula base of factory building, include angle seat (1) and with angle seat (1) fixed connection's linking arm (2), be provided with bottom surface purlin (9) and dagger (11) on linking arm (2), its characterized in that: one end, far away from the corner seat (1), of the connecting arm (2) is provided with a second jack (5) and a square connecting pipe (14) which are communicated up and down, the two ends of the square connecting pipe (14) are respectively spliced with the connecting arm (2), a first jack (13) coaxial with the second jack (5) is arranged on the upper surface and the lower surface of the square connecting pipe (14), and the end part of the support column (11) is tightly inserted into the second jack (5) and the first jack (13).
2. The spliced base of a steel building according to claim 1, characterized in that: an inserting block (6) is processed at the end part of the supporting column (11), the inserting block (6) is tightly inserted into the second inserting hole (5) and the first inserting hole (13), and the end face of the supporting column (11) is pressed on the outer surface of the connecting square pipe (14).
3. The spliced base of a steel building according to claim 1, characterized in that: and a baffle (12) is arranged in the connecting square pipe (14).
4. The spliced foundation of a steel building according to any one of claims 1-3, wherein: the connecting arm is characterized in that a clamping groove (4) is formed in the side face of the connecting arm (2), the upper end and the lower end of the clamping groove (4) are respectively located on the upper surface and the lower surface of the connecting arm (2), clamping blocks (10) are arranged at the two ends of the bottom purline (9), and the clamping blocks (10) are located in the clamping groove (4).
5. The spliced base of a steel building according to claim 4, characterized in that: the clamping block (10) is clamped in the clamping groove (4).
6. The spliced base of a steel building according to claim 4, characterized in that: the clamping block (10) is slidably inserted into the clamping groove (4), and the upper end and the lower end of the clamping block (10) are flush with the upper end and the lower end of the clamping groove (4); the sliding sleeve is provided with a C-shaped sleeve (7) on the connecting arm (2), the inner wall of the C-shaped sleeve (7) is tightly attached to the upper end and the lower end of the clamping block (10), and a locking screw (8) used for preventing the C-shaped sleeve (7) from sliding on the connecting arm (2) is arranged on the C-shaped sleeve (7).
7. The spliced base of a steel building according to claim 1, characterized in that: the corner seat (1) is provided with a corner post connecting groove (3).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201922164075.4U CN211773828U (en) | 2019-12-06 | 2019-12-06 | Steel constructs concatenation formula base of factory building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201922164075.4U CN211773828U (en) | 2019-12-06 | 2019-12-06 | Steel constructs concatenation formula base of factory building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211773828U true CN211773828U (en) | 2020-10-27 |
Family
ID=72973074
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201922164075.4U Active CN211773828U (en) | 2019-12-06 | 2019-12-06 | Steel constructs concatenation formula base of factory building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211773828U (en) |
-
2019
- 2019-12-06 CN CN201922164075.4U patent/CN211773828U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR200479716Y1 (en) | system scaffold for architecture | |
CN112196122A (en) | Bamboo joint type energy-consumption concrete-filled steel tube node and mounting method | |
CN106939690A (en) | The anti-load-bearing scaffold that inclines of one kind | |
CN202324565U (en) | Novel steel pipe scaffold | |
CN211773828U (en) | Steel constructs concatenation formula base of factory building | |
CN208347296U (en) | A kind of belt lacing rod piece | |
CN218540957U (en) | Square pipe butt joint connecting piece for steel structure modular house | |
CN107605142B (en) | Attached lifting scaffold structure | |
CN214834739U (en) | Quick-assembly early-dismantling plate strip-shaped supporting structure | |
CN215406599U (en) | Unit embedded part | |
CN211522831U (en) | Municipal bridge bearing fixed knot constructs | |
CN219952626U (en) | Novel overhanging scaffold | |
CN219241143U (en) | Connection structure for dry hanging large plate convenient to install | |
CN210976239U (en) | Self-locking beam pin bolt system | |
CN220815056U (en) | Supporting device for concrete replacement reinforcement | |
CN211691084U (en) | Constructional engineering reinforcing bar split heads | |
CN219011617U (en) | Hinged fixing device for curtain wall | |
CN215594401U (en) | Pre-embedded anchoring mechanism for heavy bracket | |
CN216276168U (en) | Building steel structure supporting beam | |
CN219863658U (en) | Assembled truss | |
CN221001924U (en) | Scaffold wall connecting piece | |
CN219220954U (en) | Reinforced steel structure of steel structure joint | |
CN216304904U (en) | Energy-saving steel structure system | |
CN220225739U (en) | Building steel structure connection structure | |
CN216892431U (en) | Foundation construction is with supporting plate that foundation lateral wall prevented collapsing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |