CN211773568U - Civil engineering supports stake with construction - Google Patents
Civil engineering supports stake with construction Download PDFInfo
- Publication number
- CN211773568U CN211773568U CN202020289619.XU CN202020289619U CN211773568U CN 211773568 U CN211773568 U CN 211773568U CN 202020289619 U CN202020289619 U CN 202020289619U CN 211773568 U CN211773568 U CN 211773568U
- Authority
- CN
- China
- Prior art keywords
- frame main
- civil engineering
- frame
- main body
- outer frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The utility model discloses a construction supporting pile for civil engineering, which comprises an outer frame main body and an inner frame main body, wherein the outer frame main body is sleeved outside a reinforcing steel bar frame, four corners of the upper surface are symmetrically provided with pull rod pieces, and eight pull rod pieces are matched with stirrups on the reinforcing steel bar frame; the inner frame main part is located the inside of hacksaw frame, and keeps unified water flat line with outer frame main part to fix through the fixing bolt that four adjacent outer wall axis departments set up, the inner wall fixed mounting of inner frame main part has cross track frame, and the symmetry is equipped with the limiting plate on one of them track of cross track frame. The utility model provides a civil engineering supports stake with construction can provide joint strength well and vertical fixation's assurance to installing the reinforcing bar frame on the ground, and the device installation is simple simultaneously, and concrete implementation convenient and fast can regard as the reinforcing bar frame partly of support column simultaneously to the bulk strength and the antidetonation grade of support column have been increased.
Description
Technical Field
The utility model relates to a construction technical field relates to a civil engineering supports stake with construction particularly.
Background
The foundation is very important in the civil engineering construction process, and the support of the pile foundation is very important in the piling process, so that the demand of people on the foundation pile support structure for civil engineering construction is increasingly large, and the quality requirement is also increasingly high.
But ordinary foundation pile bearing structure for civil engineering construction is not convenient for fix the steel-pipe pile of different diameters, and is not convenient for assemble this bearing structure, can not effectual straightness that hangs down to the steel-pipe pile moreover corrects.
SUMMERY OF THE UTILITY MODEL
In view of the above problems in the prior art, an aspect of the present invention is to provide a construction supporting pile for civil engineering for solving the problems presented by the above background art.
Technical scheme
In order to realize above-mentioned purpose, the utility model provides a pair of civil engineering supports stake with construction, include:
the outer frame main body is sleeved outside the steel bar frame, the four corners of the upper surface of the outer frame main body are symmetrically provided with pull rod pieces, and the eight pull rod pieces are matched with the stirrups on the steel bar frame;
the inner frame main part, the inner frame main part is located the inside of hacksaw frame, and with the outer frame main part keeps unified water flat line to fixing bolt through four adjacent outer wall axis departments sets up fixes, the inner wall fixed mounting of inner frame main part has cross track frame, the symmetry is equipped with the limiting plate on one of them track of cross track frame, and the symmetry is equipped with the touch ware on another track, two the limiting plate contacts with the reinforcing bar frame inner wall, and through two touch ware and two the limiting plate cooperatees.
Preferably, the outer frame body is made of a channel steel with a hollow structure.
Preferably, the eight traction rod pieces comprise positioning rods and nuts, and the positioning rods are specifically eight steel bars.
Preferably, two the bottom symmetry of limiting plate is equipped with the card foot, the card foot specifically is "L" type structure, four the card foot all is located the inboard of outer frame main part, and with the inner wall of outer frame main part contacts, the card foot with outer frame main part lower surface forms the joint area, and the stirrup on the steel reinforcement frame imbed in the joint area.
Preferably, the back surfaces of the two limiting plates are symmetrically provided with clamping plates, each abutting device comprises a sliding block and clamping arms symmetrically hinged to the top of the sliding block, and the clamping arms on one abutting device are clamped on the clamping plates on the two limiting plates.
Preferably, the two limiting plates are of carbon steel structure.
Preferably, the construction support pile for civil engineering is, at the time of construction and installation:
firstly, mounting a steel bar frame and a foundation, then placing an inner frame main body into the steel bar frame, then placing an outer frame main body outside the steel bar frame, and finally fixing the two frames by using fixing bolts, wherein the stirrups are positioned between the clamping feet and the outer frame main body to form a clamping area;
secondly, sequentially mounting the positioning rods on the outer frame main body, fixing the positioning rods through nuts, and clamping the stirrups fixing the positioning rods on the reinforcing steel bar frames;
and thirdly, sliding the two limiting plates to move along the inner walls of the steel bar frames, and then fixing the limiting plates by using the touch devices to firmly fix the steel bar frames between the limiting plates and the positioning rods.
Advantageous effects
Compared with the prior art, the utility model provides a pair of civil engineering supports stake with construction possesses following beneficial effect: can provide the assurance of good joint strength and vertical fixation to the reinforcing bar frame of installing on the ground, the device installation is simple simultaneously, and concrete implementation convenient and fast can regard as the reinforcing bar frame part of support column simultaneously to the bulk strength and the antidetonation grade of support column have been increased.
It is to be understood that both the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the disclosure.
This document provides an overview of various implementations or examples of the technology described in this disclosure, and is not a comprehensive disclosure of the full scope or all features of the disclosed technology.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the bottom view structure of the present invention;
fig. 3 is a schematic view of the top view structure of the present invention.
The main reference numbers:
1. an outer frame main body; 2. a pulling rod member; 21. positioning a rod; 22. a nut; 3. an inner frame body; 4. fixing the bolt; 5. a cross-shaped track frame; 6. a limiting plate; 61. clamping a pin; 62. a clamping area; 63. a clamping and connecting plate; 7. a contactor; 71. a slider; 72. a clamping arm.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present disclosure more clear, the technical solutions of the embodiments of the present disclosure will be described below clearly and completely with reference to the accompanying drawings of the embodiments of the present disclosure. It is to be understood that the described embodiments are only a few embodiments of the present disclosure, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the described embodiments of the disclosure without any inventive step, are within the scope of protection of the disclosure.
Unless otherwise defined, technical or scientific terms used herein shall have the ordinary meaning as understood by one of ordinary skill in the art to which this disclosure belongs. The use of the word "comprising" or "comprises", and the like, in this disclosure is intended to mean that the elements or items listed before that word, include the elements or items listed after that word, and their equivalents, without excluding other elements or items. The terms "connected" or "coupled" and the like are not restricted to physical or mechanical connections, but may also include electrical connections, whether direct or indirect. "upper", "lower", "left", "right", and the like are used merely to indicate relative positional relationships, and when the absolute position of the object being described is changed, the relative positional relationships may also be changed accordingly.
To maintain the following description of the embodiments of the present disclosure clear and concise, a detailed description of known functions and known components have been omitted from the present disclosure.
Referring to fig. 1 to 3, a construction support pile for civil engineering includes an outer frame body 1 and an inner frame body 3, which can provide a good connection strength and a guarantee of vertical fixation to a reinforcing cage installed on a foundation, and is simple to install, convenient and fast to implement, and can be used as a part of the reinforcing cage of a support column, thereby increasing the overall strength and the seismic rating of the support column.
As shown in fig. 1, in the further proposed technical solution of the present invention, the outer frame body 1 is sleeved outside the steel bar frame, and the four corners of the upper surface are symmetrically provided with the pull rod members 2, and the eight pull rod members 2 are matched with the stirrups on the steel bar frame.
The outer frame body 1 is specifically made of channel steel with a hollow structure.
The eight traction rod pieces 2 are composed of positioning rods 21 and nuts 22, and the positioning rods 21 are specifically eight-size steel bars.
As shown in fig. 3, the utility model discloses among the further technical scheme that provides, internal frame main part 3 is located the inside of hacksaw frame, and keep unified water flat line with external frame main part 1, and fix through fixing bolt 4 that four adjacent outer wall axis departments set up, the inner wall fixed mounting of internal frame main part 3 has cross track frame 5, the symmetry is equipped with limiting plate 6 on one of them track of cross track frame 5, the symmetry is equipped with to touch ware 7 on another track, two limiting plates 6 contact with the reinforcing bar frame inner wall, and cooperate with two limiting plates 6 through two touch ware 7.
The bottom of the two limiting plates 6 is symmetrically provided with clamping legs 61, the clamping legs 61 are specifically of an L-shaped structure, the four clamping legs 61 are located on the inner side of the outer frame main body 1 and are in contact with the inner wall of the outer frame main body 1, the clamping legs 61 and the lower surface of the outer frame main body 1 form a clamping area 62, and the stirrups on the steel bar frames are embedded in the clamping area 62.
The back surfaces of the two limiting plates 6 are symmetrically provided with clamping plates 63, each abutting device 7 comprises a sliding block 71 and clamping arms 72 symmetrically hinged to the top of the sliding block 71, and the clamping arms 72 on one abutting device 7 are clamped on the clamping plates 63 on the two limiting plates 6.
Wherein, two limiting plates 6 are carbon steel structures.
Civil engineering supports stake with construction when construction installation:
1) firstly, installing the steel bar frames and the foundation, then placing the inner frame main body 3 into the steel bar frames, then placing the outer frame main body 1 outside the steel bar frames, and finally fixing the two frames by using the fixing bolts 4, wherein the stirrups are positioned between the clamping feet 61 and the outer frame main body 1 to form a clamping area 62;
2) sequentially mounting the positioning rods 21 on the outer frame main body 1, fixing the positioning rods through nuts 22, and clamping the stirrups fixing the positioning rods 21 on the reinforcing steel bar frames;
3) and sliding the two limiting plates 6 to move along the inner walls of the steel bar frames, and then fixing the limiting plates 63 by using the contactors 7 to firmly fix the steel bar frames between the limiting plates 6 and the positioning rods 21.
It will be appreciated by those skilled in the art that other similar connections may be used to implement the present invention. Such as welding, bonding, or screwing.
The above embodiments are merely exemplary embodiments of the present invention, which is not intended to limit the present invention, and the scope of the present invention is defined by the appended claims. Various modifications and equivalents may be made by those skilled in the art to the present invention without departing from the spirit and scope of the invention, and such modifications and equivalents should be considered to be within the scope of the invention.
Claims (6)
1. The utility model provides a civil engineering supports stake with construction which characterized in that includes:
the outer frame main body (1) is sleeved outside the steel bar frame, the four corners of the upper surface of the outer frame main body (1) are symmetrically provided with pull rod pieces (2), and the eight pull rod pieces (2) are matched with stirrups on the steel bar frame;
inner frame main part (3), inner frame main part (3) are located the inside of hacksaw frame, and with outer frame main part (1) keep unified water flat line to fixing bolt (4) through the setting of four adjacent outer wall axis departments fix, the inner wall fixed mounting of inner frame main part (3) has cross track frame (5), the symmetry is equipped with limiting plate (6) on one of them track of cross track frame (5), and the symmetry is equipped with to tentacle (7), two on another track limiting plate (6) contact with the reinforcing bar frame inner wall, and through two to tentacle (7) and two limiting plate (6) cooperate.
2. The construction support pile for civil engineering as claimed in claim 1, wherein the outer frame body (1) is made of channel steel of a hollow structure.
3. The construction support pile for civil engineering as claimed in claim 1, wherein the eight tie rod members (2) are comprised of a tie rod (21) and a nut (22), the tie rod (21) being embodied as an eight-gauge steel bar.
4. The civil engineering construction support pile according to claim 1, characterized in that two of the limiting plates (6) are symmetrically provided with a clamping foot (61) at the bottom, the clamping foot (61) is specifically of an "L" type structure, four of the clamping feet (61) are all located on the inner side of the outer frame main body (1) and are in contact with the inner wall of the outer frame main body (1), the clamping feet (61) and the lower surface of the outer frame main body (1) form a clamping area (62), and the stirrups on the reinforcing steel bar frame are embedded in the clamping area (62).
5. The construction support pile for civil engineering according to claim 1, characterized in that the back of two of the limit plates (6) is symmetrically provided with a snap plate (63), the contactor (7) comprises a slide block (71) and snap arms (72) hinged symmetrically on the top of the slide block (71), wherein the snap arm (72) on one of the contactors (7) is snapped on the snap plate (63) on two of the limit plates (6).
6. A construction support pile for civil engineering according to claim 1, characterised in that the two limit plates (6) are in particular of carbon steel construction.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020289619.XU CN211773568U (en) | 2020-03-11 | 2020-03-11 | Civil engineering supports stake with construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020289619.XU CN211773568U (en) | 2020-03-11 | 2020-03-11 | Civil engineering supports stake with construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211773568U true CN211773568U (en) | 2020-10-27 |
Family
ID=72938462
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020289619.XU Expired - Fee Related CN211773568U (en) | 2020-03-11 | 2020-03-11 | Civil engineering supports stake with construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211773568U (en) |
-
2020
- 2020-03-11 CN CN202020289619.XU patent/CN211773568U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN213682497U (en) | Steel construction support truss convenient to equipment | |
CN211773568U (en) | Civil engineering supports stake with construction | |
CN216109909U (en) | Concrete floor supports transform structure | |
CN215629917U (en) | Combined type reinforcing structure based on building pile foundation | |
CN210029721U (en) | Prefabricated bridge deck hoisting frame | |
CN208293585U (en) | High strength fish belly sill support base | |
CN208561457U (en) | A kind of fixed device of crane | |
CN217000198U (en) | Fixing structure for upright post connecting beam | |
CN112376882A (en) | Hydraulic climbing type outer wall scaffold | |
CN214695654U (en) | Prestressed supporting rod for foundation pit enclosure | |
CN220667043U (en) | Floor beam reinforcing structure | |
CN210458956U (en) | Template of prefabricated bent cap | |
CN212388964U (en) | Additional support for lifting of continuous high and large structural space climbing frame | |
CN207419234U (en) | A kind of concrete pier base moulding bed for the assembly of large-scale steel structure body | |
CN210914885U (en) | Retaining wall rod fixing device of construction elevator | |
CN215519306U (en) | Anti-seismic building structure with steel frame and crossed central support of energy dissipation beam | |
CN217924236U (en) | Novel steel constructs wall structure | |
CN213233805U (en) | Steel frame for factory building installation | |
CN216787420U (en) | Stand column for steel structure supporting | |
CN211776015U (en) | Steel roof's transformation reinforced structure | |
CN217000946U (en) | Steel reinforcement cage is fixed deposits support convenient to remove | |
CN218643672U (en) | Assembled steel structure crossbeam | |
CN218881663U (en) | Prefabricated wallboard supporting structure of assembly type structure | |
CN220978331U (en) | Beam column bearing structure with high strength bearing function | |
CN214246744U (en) | H shaped steel bottom fixed bolster |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20201027 Termination date: 20210311 |