CN211735753U - Be applied to keel connection structure of building base - Google Patents

Be applied to keel connection structure of building base Download PDF

Info

Publication number
CN211735753U
CN211735753U CN201921742912.0U CN201921742912U CN211735753U CN 211735753 U CN211735753 U CN 211735753U CN 201921742912 U CN201921742912 U CN 201921742912U CN 211735753 U CN211735753 U CN 211735753U
Authority
CN
China
Prior art keywords
plug
skeleton
groove
components
fastener
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921742912.0U
Other languages
Chinese (zh)
Inventor
杨化斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei jinxia'an Construction Technology Co.,Ltd.
Original Assignee
杨化斌
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 杨化斌 filed Critical 杨化斌
Priority to CN201921742912.0U priority Critical patent/CN211735753U/en
Application granted granted Critical
Publication of CN211735753U publication Critical patent/CN211735753U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a be applied to keel connecting structure of building base, including first skeleton, be provided with the draw-in groove on the first skeleton, and the draw-in groove upper end is provided with the plug-in components, be provided with the fastener on the outer wall of plug-in components, and be provided with the jack on the fastener to the lower extreme of jack is provided with the recess, one side of plug-in components is provided with the slider, and is provided with the spout on the outer wall of slider to be provided with first skeleton on the spout, the through-hole structure has been seted up on the plug-in components. This be applied to keel connection structure of building base adopts the draw-in groove on second skeleton and the first skeleton to carry out the block, will promote the slider to the left side after that, then the slider can remove plug-in components to the left side, and the plug-in components can pass the fastener after that, then can be to the jack with the bolt that has prepared in, the bolt can enter into the recess after that, like this plug-in components just obtain effectual fixed through bolt and draw-in groove to first skeleton and second skeleton have just obtained effectually fixed.

Description

Be applied to keel connection structure of building base
Technical Field
The utility model relates to a building base equipment technical field specifically is a be applied to keel connection structure of building base.
Background
Building base refers to the land that the land management authority approves for the use of the building. The building base should be given a surrounding range of dimensions or coordinates. The base is connected with the red line of the road, otherwise, a passage is arranged to be connected with the red line of the road, and the keel connecting structure applied to the building base is a skeleton connecting structure in the building foundation.
The keel of the building base on the market at present can not be fixed conveniently when being installed, thereby being incapable of meeting the use of people.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a be applied to keel connection structure of building base to the keel of the building base that proposes in solving above-mentioned background art can not be convenient when installing obtain the problem fixed with the fossil fragments.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a be applied to keel connecting structure of building base, includes first skeleton, be provided with the draw-in groove on the first skeleton, and the draw-in groove upper end is provided with the plug-in components, be provided with the fastener on the outer wall of plug-in components, and be provided with the jack on the fastener to the lower extreme of jack is provided with the recess, one side of plug-in components is provided with the slider, and is provided with the spout on the outer wall of slider to be provided with first skeleton on the spout.
Preferably, the insertion holes on the fasteners correspond to the grooves.
Preferably, the plug-in is provided with a through hole structure, and the through hole structure on the plug-in corresponds to the groove and the jack respectively.
Preferably, the insert and the sliding block can form a T-shaped structure, and the sliding block and the sliding groove can form a sliding structure.
Preferably, a second framework is arranged in the clamping groove, and the second framework and the clamping groove are clamped with each other.
Compared with the prior art, the beneficial effects of the utility model are that: this be applied to keel connection structure of building base adopts the draw-in groove on second skeleton and the first skeleton to carry out the block, can promote the slider to the left side after that, then the slider can remove plug-in components to the left side, and the plug-in components can pass the fastener after that, then can be to the jack with the bolt of preparing in, the bolt can enter into the recess after that, like this plug-in components just obtain effectual fixed through bolt and draw-in groove to first skeleton and second skeleton have just obtained effectually fixed.
Drawings
Fig. 1 is a front view of a first framework of a keel connecting structure applied to a building base of the utility model;
fig. 2 is a connection diagram of a first framework and a second framework of a keel connection structure applied to a building base of the utility model;
fig. 3 is a side view of a first framework of a keel connecting structure applied to a building base;
fig. 4 is the utility model relates to a be applied to keel connection structure picture 2 of building base in A department enlarged structure sketch map.
In the figure: 1. the groove, 2, the fastener, 3, the plug-in components, 4, the slider, 5, the spout, 6, first skeleton, 7, draw-in groove, 8, second skeleton, 9, the jack.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: a keel connecting structure applied to a building base comprises a first framework 6, wherein a clamping groove 7 is formed in the first framework 6, the clamping groove 7 is formed in the first framework 6, a second framework 8 is arranged in the clamping groove 7, the second framework 8 and the clamping groove 7 are clamped with each other, an inserting piece 3 is arranged at the upper end of the clamping groove 7, the inserting piece 3 of a fastener 2 and the fastener 2 are arranged on the outer wall of the inserting piece 3 and are mutually sleeved, a jack 9 on the fastener 2 corresponds to a groove 1, the inserting piece 3 can be inserted into the fastener 2 when the first framework 6 and the second framework 8 are clamped and connected, then, a prepared bolt is aligned to the jack 9 on the fastener 2, then, the bolt rotates clockwise, then, the bolt can enter a through hole structure on the inserting piece 3 through the through hole structure and rotates clockwise, and then, the inserting piece 3 can close and fix the second framework 8 in the clamping groove 7, the fastener 2 is provided with an insertion hole 9, the fastener 2 is provided with the insertion hole 9, the lower end of the insertion hole 9 is provided with a groove 1, the first framework 6 is provided with the groove 1, one side of the plug-in 3 is provided with a sliding block 4, the left side of the plug-in 3 is connected with the sliding block 4 through welding, the plug-in 3 is provided with a through hole structure, the through hole structure on the plug-in 3 is respectively corresponding to the groove 1 and the insertion hole 9, the plug-in 3 and the sliding block 4 can form a T-shaped structure, and the sliding block 4 and the sliding groove 5 can form a sliding structure, so that when the upper end of the second framework 8 needs to be closed, the sliding block 4 can slide towards the left side in the sliding groove 5, then the plug-in 3 at the left side of the sliding block 4 can be inserted into the fastener 2, then the groove 1 is rotationally fixed through a bolt, the sliding groove 5 is arranged on the outer wall of the, seted up spout 5 on first skeleton 6, this structure makes this be applied to keel connection structure of building base adopt second skeleton 8 and draw-in groove 7 on the first skeleton 6 to carry out the block, will promote slider 4 to the left side after that, then slider 4 can remove plug-in components 3 to the left side, plug-in components 3 can pass fastener 2 after that, then can be to the bolt that has prepared in jack 9, the bolt can enter into in recess 1 after that, plug-in components 3 just obtain effectual fixed through bolt and draw-in groove 7 like this, thereby first skeleton 6 and second skeleton 8 just obtained effectually fixed.
The working principle is as follows: when the keel connecting structure applied to the building base is used, whether parts are damaged or not are not firmly connected is firstly checked, the keel connecting structure is used after error is checked, when the first framework 6 and the second framework 8 are clamped and connected, the second framework 8 can be aligned to the clamping groove 7, then the second framework 8 is clamped with the clamping groove 7 on the first framework 6, then the sliding block 4 can be pushed to the left side, then the sliding block 4 can move the plug-in component 3 to the left side, then the plug-in component 3 can pass through the fastener 2, then the prepared bolt can be aligned into the inserting hole 9, then the bolt can enter the groove 1, so that the plug-in component 3 can be effectively fixed through the bolt and the clamping groove 7, and therefore the first framework 6 and the second framework 8 can be effectively fixed, this is the working principle of the keel connecting structure applied to the building base.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.

Claims (5)

1. The utility model provides a be applied to keel connection structure of building base which characterized in that: including first skeleton (6), be provided with draw-in groove (7) on first skeleton (6), and draw-in groove (7) upper end is provided with plug-in components (3), be provided with fastener (2) on the outer wall of plug-in components (3), and be provided with jack (9) on fastener (2) to the lower extreme of jack (9) is provided with recess (1), one side of plug-in components (3) is provided with slider (4), and is provided with spout (5) on the outer wall of slider (4) to be provided with first skeleton (6) on spout (5).
2. A keel connection structure for a building site according to claim 1, wherein: the insertion hole (9) on the fastener (2) corresponds to the groove (1).
3. A keel connection structure for a building site according to claim 1, wherein: the plug-in (3) is provided with a through hole structure, and the through hole structure on the plug-in (3) corresponds to the groove (1) and the jack (9) respectively.
4. A keel connection structure for a building site according to claim 1, wherein: the plug-in components (3) and the sliding blocks (4) can form a T-shaped structure, and the sliding blocks (4) and the sliding grooves (5) can form a sliding structure.
5. A keel connection structure for a building site according to claim 1, wherein: and a second framework (8) is arranged in the clamping groove (7), and the second framework (8) and the clamping groove (7) are mutually clamped.
CN201921742912.0U 2019-10-17 2019-10-17 Be applied to keel connection structure of building base Active CN211735753U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921742912.0U CN211735753U (en) 2019-10-17 2019-10-17 Be applied to keel connection structure of building base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921742912.0U CN211735753U (en) 2019-10-17 2019-10-17 Be applied to keel connection structure of building base

Publications (1)

Publication Number Publication Date
CN211735753U true CN211735753U (en) 2020-10-23

Family

ID=72850090

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921742912.0U Active CN211735753U (en) 2019-10-17 2019-10-17 Be applied to keel connection structure of building base

Country Status (1)

Country Link
CN (1) CN211735753U (en)

Similar Documents

Publication Publication Date Title
CN211735753U (en) Be applied to keel connection structure of building base
CN218904145U (en) Lamp post welding fixture
CN205063103U (en) Partition wall
CN212317169U (en) Connecting device for building
CN111623221A (en) Case is settled in building engineering check out test set's heat dissipation protection
CN205120791U (en) Adopt two forked tail plug -in components to connect ammeter case of box
CN212053227U (en) Mounting structure for gusset plate
CN205660424U (en) Skeleton key anchor clamps
CN211297236U (en) Electrical cabinet easy to assemble
CN206888745U (en) A kind of locking connecting rod of closed guard gate
CN211297208U (en) Regulator cubicle convenient to concatenation
CN211665983U (en) Building sound insulation building board
CN212358764U (en) Curtain wall with connecting structure
CN216146550U (en) High-toughness one-key built-in buckle
CN218029499U (en) Prefabricated pin-connected panel building enclosure
CN210519178U (en) Network cabinet with folding storage door
CN210477275U (en) Integral forming machine for wooden coffin main body
CN203348249U (en) Connecting device for square pipe support
CN210888130U (en) Floor protection network for construction
CN215646863U (en) Anti-interference telephone equipment for tunnel
CN210600456U (en) A quick fixed plate of pipeline for inciting somebody to action pipeline is fixed fast at corner
CN210318053U (en) Self-locking three-in-one connecting piece for aluminum alloy furniture
CN218449332U (en) Male and female groove plug-in type cable bridge
CN209959106U (en) Novel solderless clamping positioning door frame connecting plate
CN210322368U (en) Asphalt smoke sampling tube cooling device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20211119

Address after: No. 137-138, Lane 456, Duiqiao Road, Pudong New Area, Shanghai, 200120

Patentee after: Shanghai jieqiting Information Technology Co.,Ltd.

Address before: 550001 10th floor, block a, Qilong CBD center, Bihai South Road, guanshanhu District, Guiyang City, Guizhou Province

Patentee before: Yang Huabin

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20211216

Address after: 441000 room 004, 17 / F, building 4, Hongxing international, Dengcheng Avenue, high tech Development Zone, Xiangyang City, Hubei Province

Patentee after: Hubei jinxia'an Construction Technology Co.,Ltd.

Address before: No. 137-138, Lane 456, Duiqiao Road, Pudong New Area, Shanghai, 200120

Patentee before: Shanghai jieqiting Information Technology Co.,Ltd.

TR01 Transfer of patent right