CN211735400U - A stabilising arrangement for building pile - Google Patents

A stabilising arrangement for building pile Download PDF

Info

Publication number
CN211735400U
CN211735400U CN202020047282.1U CN202020047282U CN211735400U CN 211735400 U CN211735400 U CN 211735400U CN 202020047282 U CN202020047282 U CN 202020047282U CN 211735400 U CN211735400 U CN 211735400U
Authority
CN
China
Prior art keywords
fixed establishment
frame
arc
connecting rod
fixing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020047282.1U
Other languages
Chinese (zh)
Inventor
张容浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Zhenju Network Technology Co ltd
Original Assignee
Zhiyu Hangzhou Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhiyu Hangzhou Technology Co Ltd filed Critical Zhiyu Hangzhou Technology Co Ltd
Priority to CN202020047282.1U priority Critical patent/CN211735400U/en
Application granted granted Critical
Publication of CN211735400U publication Critical patent/CN211735400U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a stabilising arrangement for building pile, including fixed establishment, fixed establishment is provided with two places on single building pile at least, and sets up be used for joint support on the fixed establishment's coupling mechanism is located the downside be provided with on the fixed establishment and be used for supporting the supporting mechanism of fixed establishment stability. The utility model discloses a setting of fixed establishment, coupling mechanism holds fixed establishment to the pile body upper and lower end tightly earlier, and rethread coupling mechanism reaches the adjacency from top to bottom to fixed establishment and connects fixedly, makes the pile body become whole from top to bottom, improves the stability of the whole support of pile body.

Description

A stabilising arrangement for building pile
Technical Field
The utility model relates to a construction field especially relates to a stabilising arrangement for building pile.
Background
The pile is a force-transferring member which can transfer all or part of load of building to foundation soil and has a certain rigidity and bending resistance, its cross-section size is far less than its length, and the pile foundation is formed from two portions of several piles buried in the ground and pile platform which can be used for combining pile group together. However, as the pile body is heightened, stability between upper portions of the pile body is gradually deteriorated, and quality of a building is affected when the upper portion is constructed.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a stabilising arrangement for building pile in order to solve above-mentioned problem, the utility model discloses a setting of fixed establishment, coupling mechanism holds the upper and lower end of pile body with fixed establishment earlier, and rethread coupling mechanism reaches the adjacency about fixed establishment and connects fixedly, makes the pile body become whole from top to bottom, improves the stability that the pile body wholly supported.
The utility model discloses a following technical scheme realizes above-mentioned purpose:
the utility model provides a stabilising arrangement for building pile, includes fixed establishment, fixed establishment is provided with two places at least on single building pile, and sets up be used for joint support on the fixed establishment's coupling mechanism is located the downside be provided with on the fixed establishment and be used for supporting the supporting mechanism of fixed establishment stability.
Further setting: fixing mechanism includes first arc frame, second arc frame, first arc frame the inboard intermediate position of second arc frame all is provided with the arc clamp plate, arc clamp plate one end is provided with the locking bolt, the locking bolt passes first arc frame second arc frame, and threaded connection, first arc frame both ends are passed through fixing bolt and are connected around the second arc frame, first arc frame second arc frame with coupling mechanism connects.
So set up, make first arc frame second arc frame pass through fixing bolt fixes in the circular pile outside, the rethread locking bolt ejection first arc frame second arc frame is held tightly the pile.
Further setting: fixing mechanism includes first right-angle frame, second right-angle frame, first right-angle frame second right-angle frame is the L type, and the opposite face inboard is provided with the clamp plate, be provided with the locking bolt on the clamp plate, this locking bolt passes first right-angle frame second right-angle frame, and all pass through threaded connection, first right-angle frame pass through fixing bolt between the second right-angle frame.
So set up, make first right angle frame the second right angle frame pass through fixing bolt fixes in the square pile outside, the rethread locking bolt ejection the clamp plate is held tightly to the pile.
Further setting: coupling mechanism includes vertical connecting rod, vertical connecting rod sets up on the fixed establishment, just connect through first adapter sleeve between the vertical connecting rod, the fixed establishment outside is provided with the go-between, it has the oblique connecting rod to articulate on the go-between, the oblique connecting rod is kept away from fixed establishment one end is provided with the second adapter sleeve, be provided with the four places between the fixed establishment vertical connecting rod, both ends are provided with the screw thread on the vertical connecting rod, oblique connecting rod one end with second adapter sleeve threaded connection, the other end are provided with the couple.
According to the arrangement, the vertical connecting rod and the first connecting sleeve are used for connecting and supporting the fixing mechanism up and down, and the oblique connecting rod and the second connecting sleeve are used for connecting and supporting the fixing mechanism on the adjacent pile columns, so that the pile columns are integrated.
Further setting: the supporting mechanism comprises a fixed seat, an adjusting seat is arranged on the inner side of the fixed seat, the adjusting seat is in threaded connection with the fixed seat, and the fixed seat is welded at the lower end of the fixed mechanism.
So set up, be convenient for through the rotation of adjusting the seat is right fixed establishment carries out the horizontally adjustment, makes fixed establishment is parallel with the stake central line.
Compared with the prior art, the beneficial effects of the utility model are as follows:
through the setting of fixed establishment, coupling mechanism, hold the upper and lower end of pile body tightly earlier with fixed establishment, rethread coupling mechanism is fixed the fixed establishment upper and lower reaches adjacently and is connected, makes the pile body become whole from top to bottom, improves the stability that the pile body wholly supported.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings needed to be used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without inventive exercise.
Figure 1 is an isometric view of an embodiment 1 of a stabilizing device for a construction pile according to the present invention;
fig. 2 is a schematic structural view of a fixing mechanism of embodiment 1 of a stabilizing device for a construction pile according to the present invention;
fig. 3 is a front view schematically showing the structure of an embodiment 1 of the stabilizing device for a construction pile according to the present invention;
fig. 4 is a partially enlarged structural view of a supporting mechanism of a stabilizing device for a construction pile according to the present invention;
figure 5 is a schematic structural view of the fixing mechanism of embodiment 2 of a stabilizing device for a construction pile according to the present invention.
The reference numerals are explained below:
1. a fixing mechanism; 11. a first arc frame; 12. a second arc frame; 13. locking the bolt; 14. an arc-shaped clamping plate; 15. fixing the bolt; 16. a first right-angle frame; 17. a second right-angle frame; 18. a clamping plate; 2. a connecting mechanism; 21. a vertical connecting rod; 22. a first connecting sleeve; 23. a connecting ring; 24. an oblique connecting rod; 25. a second connecting sleeve; 3. a support mechanism; 31. a fixed seat; 32. an adjusting seat.
Detailed Description
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", and the like, indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are used merely for convenience of description and for simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention. Furthermore, the terms "first", "second", etc. are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first," "second," etc. may explicitly or implicitly include one or more of that feature. In the description of the present invention, "a plurality" means two or more unless otherwise specified.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood by those of ordinary skill in the art through specific situations.
The present invention will be further explained with reference to the accompanying drawings:
example 1
As shown in fig. 1 to 4, a stabilizing device for building piles includes a fixing mechanism 1, the fixing mechanism 1 is provided with at least two positions on a single building pile, and a connecting mechanism 2 for connecting and supporting the fixing mechanism 1 is provided on the fixing mechanism 1, and a supporting mechanism 3 for supporting the stability of the fixing mechanism 1 is provided on the fixing mechanism 1 located at the lower side.
Preferably: the fixing mechanism 1 comprises a first arc-shaped frame 11 and a second arc-shaped frame 12, arc-shaped clamping plates 14 are arranged at the middle positions of the inner sides of the first arc-shaped frame 11 and the second arc-shaped frame 12, locking bolts 13 are arranged at one ends of the arc-shaped clamping plates 14, the locking bolts 13 penetrate through the first arc-shaped frame 11 and the second arc-shaped frame 12 and are in threaded connection, the front ends and the rear ends of the first arc-shaped frame 11 and the second arc-shaped frame 12 are connected through fixing bolts 15, the first arc-shaped frame 11 and the second arc-shaped frame 12 are connected with vertical connecting rods 21 and connecting rings 23 of the connecting mechanism 2, the first arc-shaped frame 11 and the second arc-shaped frame 12 are fixed on the outer side of the circular pile through the fixing bolts 15, and the first arc-shaped frame 11 and the second arc-shaped frame 12 are pushed; the connecting mechanism 2 comprises vertical connecting rods 21, the vertical connecting rods 21 are arranged on the fixing mechanism 1, the vertical connecting rods 21 are connected through first connecting sleeves 22, connecting rings 23 are arranged on the outer sides of the fixing mechanism 1, inclined connecting rods 24 are hung on the connecting rings 23, one ends, far away from the fixing mechanism 1, of the inclined connecting rods 24 are provided with second connecting sleeves 25, four vertical connecting rods 21 are arranged between the fixing mechanisms 1, threads are arranged at two ends of each vertical connecting rod 21, one ends of the inclined connecting rods 24 are in threaded connection with the second connecting sleeves 25, hooks are arranged at the other ends of the inclined connecting rods 24, the vertical connecting rods 21 and the first connecting sleeves 22 are used for connecting and supporting the upper fixing mechanism 1 and the lower fixing mechanism 1, the inclined connecting rods 24 and the second connecting sleeves 25 are used for connecting and supporting the; supporting mechanism 3 includes fixing base 31, and fixing base 31 inboard is provided with adjusts seat 32, adjusts seat 32 and 31 threaded connection of fixing base, and fixing base 31 welding is at the first arc frame 11 of fixing mechanism 1, 12 lower extremes of second arc frame, is convenient for carry out horizontally adjustment through the rotation of adjusting seat 32 to fixing mechanism 1, makes fixing mechanism 1 parallel with the stake central line.
Example 2
As shown in fig. 4-5, a stabilizing device for building piles comprises a fixing mechanism 1, wherein the fixing mechanism 1 is provided with at least two positions on a single building pile, a connecting mechanism 2 which is arranged on the fixing mechanism 1 and used for connecting and supporting the fixing mechanism 1 is arranged, and a supporting mechanism 3 which is arranged on the fixing mechanism 1 at the lower side and used for supporting the stability of the fixing mechanism 1 is arranged on the fixing mechanism 1 at the lower side.
Preferably: the fixing mechanism 1 comprises a first right-angle frame 16 and a second right-angle frame 17, the first right-angle frame 16 and the second right-angle frame 17 are L-shaped, clamping plates 18 are arranged on the inner sides of opposite surfaces, locking bolts 13 are arranged on the clamping plates 18, the locking bolts 13 penetrate through the first right-angle frame 16 and the second right-angle frame 17 and are connected through threads, the first right-angle frame 16 and the second right-angle frame 17 are connected through fixing bolts 15, the first right-angle frame 16 and the second right-angle frame 17 are fixed on the outer sides of the square pile through the fixing bolts 15, and the clamping plates 18 are pushed through the locking bolts 13 to clamp the pile; the connecting mechanism 2 comprises vertical connecting rods 21, the vertical connecting rods 21 are arranged on the fixing mechanism 1, the vertical connecting rods 21 are connected through first connecting sleeves 22, connecting rings 23 are arranged on the outer sides of the fixing mechanism 1, inclined connecting rods 24 are hung on the connecting rings 23, one ends, far away from the fixing mechanism 1, of the inclined connecting rods 24 are provided with second connecting sleeves 25, four vertical connecting rods 21 are arranged between the fixing mechanisms 1, threads are arranged at two ends of each vertical connecting rod 21, one ends of the inclined connecting rods 24 are in threaded connection with the second connecting sleeves 25, hooks are arranged at the other ends of the inclined connecting rods 24, the vertical connecting rods 21 and the first connecting sleeves 22 are used for connecting and supporting the upper fixing mechanism 1 and the lower fixing mechanism 1, the inclined connecting rods 24 and the second connecting sleeves 25 are used for connecting and supporting the; supporting mechanism 3 includes fixing base 31, and fixing base 31 inboard is provided with adjusts seat 32, adjusts seat 32 and 31 threaded connection of fixing base, and fixing base 31 welding is at the first right-angle frame 16 of fixing mechanism 1, the 17 lower extremes of second right-angle frame, is convenient for carry out horizontally adjustment to fixing mechanism 1 through the rotation of adjusting seat 32, makes fixing mechanism 1 parallel with the stake central line.
The utility model discloses theory of operation and use flow: the pile body supporting structure is characterized in that a first arc-shaped frame 11, a second arc-shaped frame 12 or a first right-angle frame 16 and a second right-angle frame 17 are arranged around the outer side of the pile body and are locked through a fixing bolt 15, then an arc-shaped clamping plate 14 or a clamping plate 18 is pushed to tightly hold the pile body through rotation of a locking bolt 13, then the upper fixing mechanism 1 and the lower fixing mechanism 1 are connected through a vertical connecting rod 21 and a first connecting sleeve 22, an oblique connecting rod 24 and a second connecting sleeve 25 are connected with the adjacent fixing mechanisms 1, the pile body is integrated up and down, and the stability of integral support of the pile body is improved.
The foregoing illustrates and describes the principles, general features, and advantages of the present invention. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention.

Claims (5)

1. A stabilising arrangement for a building pile which is characterized in that: including fixed establishment (1), fixed establishment (1) is provided with two at least on single building pile, and sets up be used for joint support on fixed establishment (1) coupling mechanism (2) of fixed establishment (1) are located the downside be provided with on fixed establishment (1) and be used for supporting mechanism (3) of fixed establishment (1) stability.
2. A stabilising arrangement for a building pile according to claim 1, wherein: fixing mechanism (1) includes first arc frame (11), second arc frame (12), first arc frame (11) the inboard intermediate position of second arc frame (12) all is provided with arc pinch-off blades (14), arc pinch-off blades (14) one end is provided with locking bolt (13), locking bolt (13) are passed first arc frame (11) second arc frame (12), and threaded connection, first arc frame (11) both ends are passed through fixing bolt (15) and are connected around second arc frame (12), first arc frame (11) second arc frame (12) with coupling mechanism (2) are connected.
3. A stabilising arrangement for a building pile according to claim 1, wherein: fixing mechanism (1) includes first right angle frame (16), second right angle frame (17), first right angle frame (16) second right angle frame (17) are the L type, and opposite face inboard is provided with clamp plate (18), be provided with locking bolt (13) on clamp plate (18), this locking bolt (13) pass first right angle frame (16) second right angle frame (17), and all through threaded connection, first right angle frame (16) connect through fixing bolt (15) between second right angle frame (17).
4. A stabilising arrangement for a building pile according to claim 1, wherein: coupling mechanism (2) include vertical connecting rod (21), vertical connecting rod (21) set up on fixed establishment (1), just connect through first adapter sleeve (22) between vertical connecting rod (21), fixed establishment (1) outside is provided with go-between (23), it has oblique connecting rod (24) to articulate on go-between (23), oblique connecting rod (24) are kept away from fixed establishment (1) one end is provided with second adapter sleeve (25), be provided with the four places between fixed establishment (1) vertical connecting rod (21), both ends are provided with the screw thread on vertical connecting rod (21), oblique connecting rod (24) one end with second adapter sleeve (25) threaded connection, the other end is provided with the couple.
5. A stabilising arrangement for a building pile according to claim 1, wherein: supporting mechanism (3) are including fixing base (31), fixing base (31) inboard is provided with adjusts seat (32), adjust seat (32) with fixing base (31) threaded connection, fixing base (31) welding is in fixed establishment (1) lower extreme.
CN202020047282.1U 2020-01-10 2020-01-10 A stabilising arrangement for building pile Active CN211735400U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020047282.1U CN211735400U (en) 2020-01-10 2020-01-10 A stabilising arrangement for building pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020047282.1U CN211735400U (en) 2020-01-10 2020-01-10 A stabilising arrangement for building pile

Publications (1)

Publication Number Publication Date
CN211735400U true CN211735400U (en) 2020-10-23

Family

ID=72882573

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020047282.1U Active CN211735400U (en) 2020-01-10 2020-01-10 A stabilising arrangement for building pile

Country Status (1)

Country Link
CN (1) CN211735400U (en)

Similar Documents

Publication Publication Date Title
CN211735400U (en) A stabilising arrangement for building pile
CN102877635A (en) Improved scaffold
CN102191851B (en) Novel support system
CN219689108U (en) Steel beam hoisting and stabilizing device
CN215884763U (en) Modular prefabricated wallboard piling bin
CN213742332U (en) Template anchor clamps for construction
CN211080215U (en) Steel-pipe pile extension connection structure
CN214996326U (en) Stiff shaped steel post installation adjustable bracing fixing device
CN211597625U (en) Scaffold platform
CN216380534U (en) Road bridge construction is with scaffold frame that can quick detach
CN113622640A (en) Foldable scaffold of constructional steel structure
CN211867773U (en) Detachable telescopic combined storage rack
CN219316380U (en) Liftable auxiliary stand that encorbelments based on scaffold frame
CN111960299A (en) Cantilever crane and crawler crane
CN112502120A (en) Internal river lock bottom plate top layer reinforcing bar strutting arrangement
CN218408782U (en) Mud pipe support
CN216190584U (en) Tower crane tower head
CN217480148U (en) Square pile with multiple reinforcing rib structures
CN220286141U (en) Upright post butt joint device
CN214739257U (en) Improved truss supporting beam
CN220117254U (en) Strip foundation and photovoltaic board braced system for photovoltaic support
CN212425221U (en) Cantilever crane and crawler crane
CN216811726U (en) Simple and easy bearing structure of tunnel bow member temporary fixation
CN214879472U (en) Pipeline is to mouthful supplementary mounting bracket
CN217991433U (en) Annular reinforcing steel bar processing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210518

Address after: Room 203, building 5, 2685 tanglu Road, Pudong New Area, Shanghai, 200120

Patentee after: Shanghai Qingyuan architectural decoration Group Co.,Ltd.

Address before: Room 506-1, South Building, Huilong venture building, 828 Wusu street, Jinbei street, Lin'an District, Hangzhou, Zhejiang 311300

Patentee before: ZHIYU (HANGZHOU) TECHNOLOGY Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240418

Address after: No. 778 Chuangxin West Road, China (Shanghai) Pilot Free Trade Zone, Pudong New Area, Shanghai, January 2012

Patentee after: Shanghai Zhenju Network Technology Co.,Ltd.

Country or region after: China

Address before: Room 203, building 5, 2685 tanglu Road, Pudong New Area, Shanghai, 200120

Patentee before: Shanghai Qingyuan architectural decoration Group Co.,Ltd.

Country or region before: China