CN211717453U - Building engineering measuring equipment - Google Patents
Building engineering measuring equipment Download PDFInfo
- Publication number
- CN211717453U CN211717453U CN202020666090.9U CN202020666090U CN211717453U CN 211717453 U CN211717453 U CN 211717453U CN 202020666090 U CN202020666090 U CN 202020666090U CN 211717453 U CN211717453 U CN 211717453U
- Authority
- CN
- China
- Prior art keywords
- movable
- limiting
- adjusting
- hanging bracket
- connecting frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model belongs to the technical field of building engineering, in particular to a building engineering measuring device, which comprises a lifting rope and a pendant, and also comprises a base, wherein the top surface of the base is fixed with a stand column, the surface of the stand column is provided with a movable connecting frame, and a detachable hanging component is connected below the movable connecting frame; the hanging assembly comprises a movable hanging bracket, a winding wheel is supported and erected on the inner side of the movable hanging bracket through a bearing, a lead hole is formed in the bottom surface of the movable hanging bracket, the top end of the lifting rope is fixedly connected with the winding wheel, and the bottom end of the lifting rope is fixedly connected with the pendant after penetrating through the lead hole; the building engineering measuring equipment of the utility model, the adjusting component arranged at the same time, is convenient for adjusting the initial height of the suspension component according to the height of the building, ensures the measuring precision, realizes the height adjustment through the adjusting component, is convenient to operate and easy to realize; the suspension assembly is detachable, can be used independently, is provided with a sucker, is easy to be connected with a building, and improves the application range of the measuring device.
Description
Technical Field
The utility model belongs to the technical field of building engineering, concretely relates to building engineering measuring equipment.
Background
The building engineering is an engineering entity formed by the construction of various building constructions and their auxiliary facilities and the installation of lines, pipelines and equipment matched with them, in which the building construction is a project which has top cover, beam column, wall and foundation and can form internal space, and can meet the requirements of production, living, learning and public activities of people, and the suspension wire pendant is a tool equipment for measuring building verticality in the building engineering.
The suspension wire that original building engineering measured weighs down when using, and it is very troublesome to the altitude mixture control that the suspension wire weighs down, no matter the height of building, all need construction worker to climb to the eminence and weigh down fixedly to the suspension wire, has very big potential safety hazard.
SUMMERY OF THE UTILITY MODEL
For solving the above-mentioned problem that exists among the prior art, the utility model provides a building engineering measuring equipment has convenient to use, is convenient for remove, easily adjusts and application scope is extensive characteristics.
In order to achieve the above object, the utility model provides a following technical scheme: the building engineering measuring equipment comprises a lifting rope, a pendant and a base, wherein four corners of the bottom surface of the base are respectively provided with a movable wheel, the top surface of the base is vertically fixed with an upright post, the surface of the upright post is provided with a movable connecting frame capable of moving up and down, and a detachable suspension assembly is connected below the movable connecting frame; the hanging assembly comprises a movable hanging bracket, the longitudinal section of the movable hanging bracket is of a U-shaped structure, a winding wheel is supported and erected on the inner side of the movable hanging bracket through a bearing, a lead hole is formed in the bottom surface of the movable hanging bracket, the top end of the lifting rope is fixedly connected with the winding wheel, and the bottom end of the lifting rope is fixedly connected with the pendant after penetrating through the lead hole.
As a preferred technical proposal of the utility model, the transverse section of the movable connecting frame is in a U-shaped structure; the upper part of the movable hanging bracket is hinged with a hook, and a hanging rod matched with the hook is transversely fixed on the inner side of the movable connecting bracket.
As an optimized technical scheme of the utility model, still include the sucking disc, the lateral surface of activity gallows is fixed with the lug, the sucking disc articulates on this lug.
As a preferred technical scheme of the utility model, the winding device further comprises a limiting component, and the limiting component comprises a limiting disc, a limiting pin and a connecting rope, the limiting disc is distributed outside the movable hanger and is fixedly connected with the central shaft of the winding wheel, and a handle is fixed at the eccentric position on the surface of the limiting disc; one end of the connecting rope is fixedly connected with the movable hanging bracket, the other end of the connecting rope is fixedly connected with the limiting pin, a through hole for the limiting pin to penetrate through is formed in the handle, a positioning hole for the limiting pin to penetrate through is formed in the movable hanging bracket, and the positioning holes are formed in an equidistant annular mode.
As an optimized technical scheme of the utility model, install the regulation on the stand the adjusting part of swing joint frame initial height.
As a preferred technical scheme of the utility model, adjusting part includes adjusting screw and limit slider the spacing spout along longitudinal distribution is seted up on the stand surface, limit slider fixes swing joint frame tail end, just can follow in the limit slider embedding limit spout the activity of limit spout, adjusting screw passes through the bearing and supports along vertically installing in the limit spout set up the confession in the limit slider the screw hole that adjusting screw runs through, just adjusting screw through this screw hole with limit slider screw thread closes soon and links to each other.
As a preferred technical scheme of the utility model, adjusting part still includes adjusting handle, initiative umbelliform gear and driven umbelliform gear, adjusting handle passes through the bearing support to be installed the stand surface, the initiative umbelliform gear is fixed adjusting handle's center pin is last and be in the spacing spout, driven umbelliform gear is fixed adjusting screw is last, just driven umbelliform gear with initiative umbelliform gear engagement links to each other.
Compared with the prior art, the beneficial effects of the utility model are that: the building engineering measuring equipment of the utility model, the adjusting component arranged at the same time, is convenient for adjusting the initial height of the suspension component according to the height of the building, ensures the measuring precision, realizes the height adjustment through the adjusting component, is convenient to operate and easy to realize; the suspension assembly is detachable, can be used independently, is provided with a sucker, is easy to be connected with a building, and improves the application range of the measuring device.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention. In the drawings:
fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic side view of the present invention;
FIG. 3 is a schematic side sectional view of the movable connecting frame of the present invention;
fig. 4 is a schematic view of the front structure of the movable hanger of the present invention;
in the figure: 1. a base; 101. a column; 2. a moving wheel; 3. an adjustment assembly; 4. a movable connecting frame; 5. a suspension assembly; 6. a lifting rope; 7. a pendant; 8. adjusting a hand wheel; 9. a drive bevel gear; 10. a driven bevel gear; 11. adjusting the screw rod; 12. a threaded hole; 13. a limiting slide block; 102. a limiting chute; 14. a hanging rod; 15. hooking; 16. a movable hanger; 17. a winding wheel; 18. lifting lugs; 19. a suction cup; 20. connecting ropes; 21. a spacing pin; 22. a wire hole; 23. a limiting disc; 24. a handle; 25. perforating; 26. and (7) positioning the holes.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Examples
Referring to fig. 1-4, the present invention provides the following technical solutions: a building engineering measuring device comprises a lifting rope 6, a pendant 7 and a base 1, wherein four corners of the bottom surface of the base 1 are respectively provided with a movable wheel 2, the top surface of the base 1 is vertically fixed with a stand column 101, the surface of the stand column 101 is provided with a movable connecting frame 4 capable of moving up and down, and a detachable suspension assembly 5 is connected below the movable connecting frame 4; the suspension assembly 5 comprises a movable hanger 16, the longitudinal section of the movable hanger 16 is in a U-shaped structure, a winding wheel 17 is supported and erected on the inner side of the movable hanging bracket 16 through a bearing, a lead hole 22 is arranged on the bottom surface of the movable hanging bracket 16, the top end of the lifting rope 6 is fixedly connected with the winding wheel 17, the bottom end of the lifting rope penetrates through the lead hole 22 and then is fixedly connected with the pendant 7, firstly, the position of the movable connecting frame 4 is lowered, the detachable suspension component 5 is arranged at the lower part of the movable connecting frame 4, then the initial height of the movable connecting frame 4 is adjusted according to the height of the building, the initial height of the hanging component 5 is that the hanging pendant 7 is in a suspended position, meanwhile, the hanging rope 6 needs to be paid off through the winding wheel 17, the proper length is released, the corresponding part needing to be measured is guaranteed, then the measuring device is moved to the position of the building needing to be measured, and the building is calibrated through the hanging rope 6.
Specifically, according to fig. 1 and 3, in the present embodiment, the transverse section of the movable connecting frame 4 is a U-shaped structure; the upper part of the movable hanging bracket 16 is hinged with a hook 15, the inner side of the movable connecting frame 4 is transversely fixed with a hanging rod 14 matched with the hook 15, the hook 15 is matched with the hanging rod 14, the movable hanging bracket 16 can be detached, and meanwhile, the installation is also more convenient.
Specifically, as shown in fig. 1 and fig. 3, in this embodiment, the present invention further includes a suction cup 19, a lifting lug 18 is fixed on an outer side surface of the movable hanger 16, the suction cup 19 is hinged to the lifting lug 18, the movable hanger 16 can be used alone after being detached, and the suction cup 19 is used to connect the movable hanger 16 with a building surface.
Specifically, as shown in fig. 1 and fig. 4, in this embodiment, the winding device further includes a limiting assembly, and the limiting assembly includes a limiting disc 23, a limiting pin 21 and a connecting rope 20, the limiting disc 23 is distributed outside the movable hanger 16 and is fixedly connected with the central shaft of the winding wheel 17, and a handle 24 is fixed at an eccentric position on the surface of the limiting disc 23; connect the one end and the activity gallows 16 fixed connection of rope 20, the other end and spacer pin 21 fixed connection, set up the perforation 25 that supplies spacer pin 21 to run through on handle 24, set up the locating hole 26 that supplies spacer pin 21 to run through on activity gallows 16, and locating hole 26 is equidistant annular and has seted up a plurality ofly, drive winding wheel 17 through rotating handle 24 and rotate and to receive and release line to lifting rope 6, and receive and release line back to lifting rope 6 through winding wheel 17, run through perforation 25 and locating hole 26 with spacer pin 21 in proper order, restriction winding wheel 17 rotates.
Specifically, according to fig. 1, in the present embodiment, an adjusting assembly 3 for adjusting the initial height of the movable connecting frame 4 is installed on the upright post 101, and the adjustment of the initial height of the movable connecting frame 4 can be realized through the adjusting assembly 3.
Specifically, according to fig. 1 and fig. 2, in this embodiment, the adjusting assembly 3 includes an adjusting screw 11 and a limiting slider 13, a limiting sliding groove 102 longitudinally distributed is formed on the surface of the upright post 101, the limiting slider 13 is fixed at the tail end of the movable connecting frame 4, the limiting slider 13 is embedded in the limiting sliding groove 102 and can move along the limiting sliding groove 102, the adjusting screw 11 is supported by a bearing and longitudinally mounted in the limiting sliding groove 102, a threaded hole 12 for the adjusting screw 11 to penetrate is formed in the limiting slider 13, and the adjusting screw 11 is screwed with the limiting slider 13 through the threaded hole 12, when the initial height of the movable connecting frame 4 is adjusted, the adjusting screw 11 is rotated, and under the screwing fit of the threads, the movable connecting frame 4 can be driven by the limiting slider 13 to move along the limiting sliding groove 102.
Specifically, as shown in fig. 1 and fig. 2, in this embodiment, the adjusting assembly 3 further includes an adjusting hand wheel 8, a driving bevel gear 9 and a driven bevel gear 10, the adjusting hand wheel 8 is supported and mounted on the surface of the column 101 through a bearing, the driving bevel gear 9 is fixed on a central shaft of the adjusting hand wheel 8 and is located in the limiting chute 102, the driven bevel gear 10 is fixed on the adjusting screw 11, and the driven bevel gear 10 is meshed and connected with the driving bevel gear 9, when the initial height of the movable connecting frame 4 is adjusted, the adjusting hand wheel 8 on the outer side is rotated, the adjusting hand wheel 8 drives the driving bevel gear 9 to rotate, and in a meshed relationship, the adjusting screw 11 can be driven to rotate, so that the movable connecting frame 4 can be moved by using a thread screwing relationship.
The utility model discloses a theory of operation and use flow: the utility model discloses a building engineering measuring equipment, during the use, utilize adjusting part 3 to reduce the position of swing joint frame 4 earlier, install detachable suspension assembly 5 in swing joint frame 4 lower part, again to the initial height of the height adjustment swing joint frame 4 of building, namely, the initial height of suspension assembly 5, it can to make pendant 7 be in unsettled position, simultaneously, still need to receive and release the lifting rope 6 through wind-up wheel 17, emit suitable length, guarantee to correspond the part that needs the measurement on the building, utilize, later remove measuring device to the building position that needs the measurement, calibrate the building through lifting rope 6, rely on the cooperation of swing joint frame 4 and wind-up wheel 17 to realize adjusting the height of 7 and lifting rope 6 unwrapping wire length, the control range is more extensive, the measuring range enlarges pendant;
the hook 15 is matched with the hanging rod 14 to realize the disassembly of the movable hanging bracket 16, the movable hanging bracket 16 can be used independently after being disassembled, and the movable hanging bracket 16 is connected with the surface of a building for use by utilizing the suction disc 19.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims (7)
1. A building engineering measuring equipment, includes lifting rope (6) and pendant (7), its characterized in that: the movable hanging device is characterized by further comprising a base (1), wherein four corners of the bottom surface of the base (1) are respectively provided with a movable wheel (2), the top surface of the base (1) is vertically fixed with a stand column (101), the surface of the stand column (101) is provided with a movable connecting frame (4) capable of moving up and down, and a detachable hanging component (5) is connected below the movable connecting frame (4); the hanging assembly (5) comprises a movable hanging bracket (16), the longitudinal section of the movable hanging bracket (16) is of a U-shaped structure, a winding wheel (17) is supported and erected on the inner side of the movable hanging bracket (16) through a bearing, a lead hole (22) is formed in the bottom surface of the movable hanging bracket (16), the top end of the lifting rope (6) is fixedly connected with the winding wheel (17), and the bottom end of the lifting rope penetrates through the lead hole (22) and then is fixedly connected with the pendant (7).
2. A construction engineering measuring device according to claim 1, characterized in that: the transverse section of the movable connecting frame (4) is of a U-shaped structure; a hook (15) is hinged on the upper part of the movable hanging bracket (16), and a hanging rod (14) matched with the hook (15) is transversely fixed on the inner side of the movable connecting frame (4).
3. A construction engineering measuring device according to claim 1, characterized in that: the lifting device is characterized by further comprising a sucking disc (19), a lifting lug (18) is fixed on the outer side face of the movable hanging bracket (16), and the sucking disc (19) is hinged to the lifting lug (18).
4. A construction engineering measuring device according to claim 1, characterized in that: the winding device is characterized by further comprising a limiting assembly, wherein the limiting assembly comprises a limiting disc (23), a limiting pin (21) and a connecting rope (20), the limiting disc (23) is distributed on the outer side of the movable hanging bracket (16) and is fixedly connected with a central shaft of the winding wheel (17), and a handle (24) is fixed at an eccentric position on the surface of the limiting disc (23); one end of the connecting rope (20) is fixedly connected with the movable hanging bracket (16), the other end of the connecting rope is fixedly connected with the limiting pin (21), a through hole (25) for the limiting pin (21) to penetrate through is formed in the handle (24), a positioning hole (26) for the limiting pin (21) to penetrate through is formed in the movable hanging bracket (16), and the positioning holes (26) are formed in an equidistant annular mode.
5. A construction engineering measuring device according to claim 1, characterized in that: and the upright post (101) is provided with an adjusting component (3) for adjusting the initial height of the movable connecting frame (4).
6. A construction engineering measuring device according to claim 5, characterized in that: adjusting part (3) include adjusting screw (11) and limiting slide block (13) spacing spout (102) along longitudinal distribution are seted up on stand (101) surface, limiting slide block (13) are fixed swing joint frame (4) tail end, just limiting slide block (13) embedding limiting slide block (102) are interior and can be followed limiting slide block (102) activity, adjusting screw (11) support through the bearing and vertically install in limiting slide block (102) seted up the confession in limiting slide block (13) screw hole (12) that adjusting screw (11) run through, just adjusting screw (11) through this screw hole (12) with limiting slide block (13) screw thread closes soon links to each other.
7. A construction engineering measuring device according to claim 6, characterized in that: adjusting part (3) still include adjusting handle wheel (8), initiative umbelliform gear (9) and driven umbelliform gear (10), adjusting handle wheel (8) are passed through bearing support and are installed stand (101) surface, initiative umbelliform gear (9) are fixed on the center pin of adjusting handle wheel (8) and be in spacing spout (102), driven umbelliform gear (10) are fixed on adjusting screw (11), just driven umbelliform gear (10) with initiative umbelliform gear (9) meshing links to each other.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020666090.9U CN211717453U (en) | 2020-04-27 | 2020-04-27 | Building engineering measuring equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020666090.9U CN211717453U (en) | 2020-04-27 | 2020-04-27 | Building engineering measuring equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211717453U true CN211717453U (en) | 2020-10-20 |
Family
ID=72835989
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020666090.9U Expired - Fee Related CN211717453U (en) | 2020-04-27 | 2020-04-27 | Building engineering measuring equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211717453U (en) |
-
2020
- 2020-04-27 CN CN202020666090.9U patent/CN211717453U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN211717453U (en) | Building engineering measuring equipment | |
CN114934684A (en) | Intelligent adjusting method for splicing verticality of prefabricated vertical component of building structure | |
CN201421539Y (en) | Portable mobile ground projection screen rod device | |
CN109896388A (en) | A kind of traction sheave horizontal position monitoring device and its installation method | |
CN211121238U (en) | Special sighting rod is used in survey and drawing | |
CN211176522U (en) | Structure convenient to adjust ceiling lamp mounting height | |
CN205294724U (en) | Can tertiary formula flexible frame of lifting | |
CN209958773U (en) | Formwork removing tool for floor aluminum alloy building formwork | |
CN206769822U (en) | Well head control tower | |
CN211775918U (en) | Building engineering datum line pay-off | |
CN211877009U (en) | Special measuring device of civil engineering construction | |
CN204549127U (en) | Glass handling erecting device | |
CN210105248U (en) | Leveling ruler with tracks | |
CN110329924A (en) | Air condensing units hoist device | |
CN221296013U (en) | Lighting installation support structure | |
CN218581220U (en) | Support frame is adjusted in housing construction | |
CN219567425U (en) | Bidirectional unloading type heightening falling frame | |
CN216664870U (en) | Suspended ceiling suspender mounting tool | |
CN217203708U (en) | Guide guideboard for highway construction | |
CN220601429U (en) | Novel street lamp support | |
CN217928561U (en) | High-pole lamp convenient to lift and maintain | |
CN220226148U (en) | Support frame for building engineering convenient to altitude mixture control | |
CN217872000U (en) | Construction ladder with protective structure for building engineering | |
CN113247777B (en) | Level tower crane body of tower straightness alarm device that hangs down | |
CN221548588U (en) | Road view lighting device at night |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |