CN211714728U - Cable suspension bracket for construction site - Google Patents

Cable suspension bracket for construction site Download PDF

Info

Publication number
CN211714728U
CN211714728U CN201922459582.0U CN201922459582U CN211714728U CN 211714728 U CN211714728 U CN 211714728U CN 201922459582 U CN201922459582 U CN 201922459582U CN 211714728 U CN211714728 U CN 211714728U
Authority
CN
China
Prior art keywords
base
cable
ring
opening
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922459582.0U
Other languages
Chinese (zh)
Inventor
郭广全
孙伟达
夏冬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201922459582.0U priority Critical patent/CN211714728U/en
Application granted granted Critical
Publication of CN211714728U publication Critical patent/CN211714728U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Installation Of Indoor Wiring (AREA)

Abstract

The utility model provides a cable hanging bracket for building site, which effectively integrates the cable, avoids the cable from being trampled and damaged, and can adjust the height according to different construction machines to avoid influencing the construction; the technical scheme includes that the device comprises a base, wherein the base is of a cylindrical structure, a telescopic rod is arranged above the base, a support is arranged at the top end of the telescopic rod and comprises a main support rod which is horizontally arranged, a plurality of circular rings with different diameters are arranged on the main support rod, and an opening is formed in the side wall of each circular ring; the utility model discloses can hang and play the chucking fixed action of removal to the cable of difference, can effectual integration cable.

Description

Cable suspension bracket for construction site
Technical Field
The utility model relates to a construction technical field, specifically speaking relates to cable lift kits for building site.
Background
In the building construction process, various cables are often used for assisting mechanical equipment to work, the working condition is severe in a construction site, most of the existing cables are buried on the ground and protected by covering a pressure-proof layer, but along with the operation of various machines, the protection still has high damage risk, the equipment cannot be used and the danger to workers is easily caused, the cables are placed on the ground and are easily contacted with sewage, and the electric leakage phenomenon is easily generated; at present, some devices suspend cables at high altitude for protection and arrangement, but most of the devices suspend the cables in a messy way, and the cables are the same in thickness and cannot be suspended well; it is therefore necessary to design a device that can suspend the cables in the construction site well.
SUMMERY OF THE UTILITY MODEL
To the above situation, for overcoming prior art's defect, the utility model provides a cable lift kits for building site, effectual integration cable avoids the cable to trample impairedly, can carry out the adjustment of height according to the construction machinery of difference simultaneously, avoids influencing the construction.
The technical scheme who its solve includes the base, the base be cask shape structure, the top of base is equipped with the telescopic link, the top of telescopic link is equipped with the support, the support include the main tributary vaulting pole that a level was placed, be equipped with the ring of a plurality of diameters variation in size on the main tributary vaulting pole, an opening has all been seted up on the lateral wall on every ring.
Preferably, the inside of base be hollow structure, be equipped with the water filling port on the lateral wall of base, the end cap is installed at the water filling port position, the base adopts the plastics material to support, the end cap adopts the rubber material to support, realization that can be fine is to the sealed of water filling port, in the use, can increase the weight of base through water filling port to inside injected water of base or sand, make whole device more stable placing the in-process.
Preferably, the bottom of the base is provided with a water outlet, the water outlet is provided with a cover body, and water added into the base can be discharged through the water outlet.
Preferably, the wall thickness of the opening position both sides of every ring be less than the wall thickness of other positions of ring, the ring adopts plastics to support, can block the cable that needs hang to the inside card of ring through opening position, the size difference of a plurality of rings can adapt to the demand of different diameter cables.
Preferably, the upper portion of bracing piece be equipped with by the montant with the mouth that hangs that the zigzag branch constitutes, montant and zigzag branch form a square joint mouth, can adapt to the suspension of special-shaped cable.
Preferably, the supporting rod, the circular rings, the vertical rod and the Z-shaped supporting rod are integrally cast by plastic.
The utility model discloses can hang and play the chucking fixed action of removal to the cable of difference, can effectually integrate the cable, avoid the cable to trample impairedly, can carry out the adjustment of height according to the construction machinery of difference simultaneously, avoid influencing the construction.
Drawings
Fig. 1 is a front view of the present invention.
Fig. 2 is a top view of the present invention.
Fig. 3 is a partial schematic view of the stent of fig. 1 according to the present invention.
Fig. 4 is a partially enlarged view of fig. 1 according to the present invention.
Fig. 5 is a schematic bottom view of the base of the present invention.
Detailed Description
Embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
According to the attached drawings 1-5, the utility model discloses a base 1, base 1 be cask shape structure, base 1's top is equipped with telescopic link 2, the top of telescopic link 2 is equipped with support 3, support 3 include main tributary vaulting pole 4 that a level was placed, be equipped with the ring 5 of a plurality of diameter variation in size on the main tributary vaulting pole 4, an opening 6 has all been seted up on every ring 5 on the lateral wall.
In order to realize the stability of whole device when placing, the inside of base be hollow structure, be equipped with water filling port 7 on the lateral wall of base, end cap 8 is installed at 7 positions of water filling port, the base adopts the plastics material to support, end cap 8 adopts the rubber material to support, realization that can be fine is to the sealed of water filling port 7, in the use, can increase the weight of base through water filling port 7 to the inside injected water of base or sand, makes whole device more stable placing the in-process.
The bottom of base be equipped with outlet 9, install the lid on the outlet 9, the accessible outlet 9 is discharged the water that the base inside was added.
The wall thickness of 6 position both sides of opening of every ring 5 be less than 5 other position wall thicknesses of ring, ring 5 adopts plastics to support, can block into the cable that needs hang to 5 inside cards of ring through 6 positions of opening, the demand of different diameter cables can be adapted to the variation in size of a plurality of rings 5.
The upper portion of bracing piece be equipped with by the montant and the mouth that hangs that zigzag branch constitutes, montant and zigzag branch form a square joint mouth, can adapt to the suspension of special-shaped cable.
The support rod, the circular rings 5, the vertical rods and the Z-shaped support rods are integrally cast by plastic, so that the overall strength of the support can be effectively guaranteed.
This use is novel when specifically using, at first places the device in spacious position to do not hinder the construction as the standard, through water filling port 7 to the inside water or sand that adds of base, strengthen the holistic stability of device, when using, according to the rotatory corresponding ring 5 of the specification of different cables or hang the mouth, adaptability is wide.
The utility model discloses can hang and play the chucking fixed action of removal to the cable of difference, can effectually integrate the cable, avoid the cable to trample impairedly, can carry out the adjustment of height according to the construction machinery of difference simultaneously, avoid influencing the construction.

Claims (6)

1. Cable suspended support for building site, its characterized in that, including base (1), base (1) be cask shape structure, the top of base (1) is equipped with telescopic link (2), the top of telescopic link (2) is equipped with support (3), support (3) main tributary vaulting pole (4) including a level is placed, be equipped with ring (5) that a plurality of diameters variation in size on main tributary vaulting pole (4), an opening (6) has all been seted up on every ring (5) the lateral wall.
2. The cable hanging bracket for the construction site as claimed in claim 1, wherein the base is hollow, a water injection port (7) is arranged on the side wall of the base, a plug (8) is installed at the position of the water injection port (7), the base is supported by plastic materials, and the plug (8) is supported by rubber materials.
3. The cable hanging bracket for the construction site as claimed in claim 1, wherein a water discharge opening (9) is provided at the bottom of the base, and a cover is installed on the water discharge opening (9).
4. The cable suspension bracket for construction sites as claimed in claim 1, wherein the wall thickness of the two sides of the opening (6) of the ring (5) is smaller than the wall thickness of the other parts of the ring (5), and the ring (5) is supported by plastic.
5. The cable suspension bracket for construction sites according to claim 1, wherein a suspension opening is formed by the vertical rod and the Z-shaped supporting rod above the supporting rod, and the vertical rod and the Z-shaped supporting rod form a square clamping opening.
6. The cable suspension bracket for construction sites according to claim 1, wherein the support rod and the plurality of rings (5) and the vertical rod and the Z-shaped support rod are integrally cast from plastic.
CN201922459582.0U 2019-12-31 2019-12-31 Cable suspension bracket for construction site Active CN211714728U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922459582.0U CN211714728U (en) 2019-12-31 2019-12-31 Cable suspension bracket for construction site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922459582.0U CN211714728U (en) 2019-12-31 2019-12-31 Cable suspension bracket for construction site

Publications (1)

Publication Number Publication Date
CN211714728U true CN211714728U (en) 2020-10-20

Family

ID=72821301

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922459582.0U Active CN211714728U (en) 2019-12-31 2019-12-31 Cable suspension bracket for construction site

Country Status (1)

Country Link
CN (1) CN211714728U (en)

Similar Documents

Publication Publication Date Title
CN112012180B (en) Water surface floating garbage collecting device
CN206444863U (en) A kind of spin vibration sieve for easily changing sieve selects machine
CN211714728U (en) Cable suspension bracket for construction site
CN212002323U (en) Telescopic string cylinder for pouring super-thick concrete
CN203846858U (en) Sucking disc fixed type fence ground stake
CN204864614U (en) Telescopic safety belt hook support
CN110258540A (en) A kind of construction method of cast-in-situ bored pile
CN207163441U (en) Adjustable sopwith staff
CN206110196U (en) Well lid device for highway engineering
CN216362727U (en) Plant support frame with height adjusting function
CN206909229U (en) It is a kind of to be fixed on the flowerpot that and can is hung on balcony guardrail edge
CN210434108U (en) Pesticide production is with partial shipment filter equipment
CN207597997U (en) A kind of envelope road device of traffic engineering maintenance
CN207383109U (en) It is a kind of that there is the irrigation rig of tree straightening
CN209924414U (en) Construction platform with blocking net for building
CN210507499U (en) Foundation pit dewatering well construction platform
CN104612413B (en) Static pressure pipe pile hole protecting device
CN208650088U (en) A kind of street lamp post installation armored concrete prefabricated foundation structure
CN205975620U (en) Underwater concrete pours device
CN207659063U (en) A kind of barreled honey tilting device
CN207991573U (en) A kind of convenient thermometer screen of disassembly and installation
CN207022698U (en) Dragon fruit post
CN208754878U (en) A kind of roadside greening tree transplanting protection device
CN208948713U (en) A kind of construction site is used to the support frame of lifting machinery equipment
CN216194234U (en) High stability way awl

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant