CN211714654U CN202020059994.5U CN202020059994U CN211714654U CN 211714654 U CN211714654 U CN 211714654U CN 202020059994 U CN202020059994 U CN 202020059994U CN 211714654 U CN211714654 U CN 211714654U
Authority
CN
China
Prior art keywords
vestibule
corridor
bottom platform
elevator
roof beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020059994.5U
Other languages
Chinese (zh)
Inventor
余志成
余惠成
余冲
罗丽英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020059994.5U priority Critical patent/CN211714654U/en
Application granted granted Critical
Publication of CN211714654U publication Critical patent/CN211714654U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The utility model relates to a vestibule structure of outdoor elevator, including vestibule mounting bracket, vestibule bottom platform and bearing diagonal post, vestibule mounting bracket one side horizontal mounting have vestibule bottom platform, the lower terminal surface of vestibule bottom platform before the rear portion side by side the symmetry install the bearing diagonal post that two lower extremes link to each other with the vestibule mounting bracket, form 10 ~ 80 slope contained angles between bearing diagonal post and the vestibule bottom platform. The utility model discloses a set up elevator vestibule focus stress point on the well stand, through flexible structure, can avoid forming hard the connection between vestibule and the existing building, can not cause the damage to existing building when making the elevator derrick take place to subside, under the earthquake condition, can avoid elevator derrick vestibule's pulling force to cause secondary damage to existing building, the vestibule adopts the closed structure of taking the window simultaneously, waterproof performance, the printing opacity ventilation effect is good, can effectively protect the resident family private, and have simple structure, it is safe firm, the installation is simple and easy, characteristics such as maintenance cost hangs down.

Description

Vestibule structure of outdoor elevator
Technical Field
The utility model relates to an elevator vestibule technical field especially relates to a vestibule structure of outdoor elevator.
Background
At present, a large number of multi-storey stair buildings without elevators are arranged in our country, elevator structures are not arranged in the buildings, so that residents are inconvenient to come in and go out, in order to solve the problem, outdoor elevators need to be additionally arranged on the existing stair buildings, and accordingly residents can come in and go out conveniently, in order to enable the buildings to be in butt joint with the outdoor elevators, an elevator corridor structure is generally adopted, a common elevator corridor structure generally adopts a hard connecting structure to achieve butt joint of the outdoor elevators and the existing buildings, the hard connecting structure has a great defect, namely when the elevators sink, the corridor structure can pull the existing buildings to sink, the effect of tensile fracture is generated at the joints, the potential safety hazard of the existing buildings is damaged, and the maintenance cost of the buildings is increased; in addition, the existing outdoor elevator adopting a hard connection structure is easy to cause secondary damage to the existing building due to the tensile force of an elevator derrick corridor under the condition of an earthquake; some outdoor elevator vestibules adopt open structure, and its security, protectiveness, privacy are all relatively poor.
Under the condition, due to the worry about the influence of the existing building structure after the elevator is additionally arranged and the worry about the safety and privacy in living use, the existing outdoor elevator additionally arranged technology is difficult to be accepted by people and popularized in a large amount, and the technology innovation is urgently needed to improve the existing outdoor elevator additionally arranged technology in China so as to meet the requirement of people on good life.
Disclosure of Invention
The utility model aims to solve the technical problem that a vestibule structure of outdoor elevator is provided, have characteristics such as simple structure is firm, simple to operate, maintenance cost are low.
The utility model provides a technical scheme that its technical problem adopted is: the utility model provides a vestibule structure of outdoor elevator, including vestibule mounting bracket, vestibule bottom platform and bearing diagonal post, vestibule mounting bracket one side horizontal installation have vestibule bottom platform, the front and back portion of lower extreme face of vestibule bottom platform side by side the symmetry install the bearing diagonal post that two lower extremes and vestibule mounting bracket link to each other, form 10 ~ 80 slope contained angles between bearing diagonal post and the vestibule bottom platform, the end that stretches out of vestibule bottom platform passes through flexible construction and links to each other with existing building.
The vestibule mounting bracket include well crossbeam and well stand, well crossbeam downside around install two well stands side by side, the well crossbeam docks with vestibule bottom platform.
Vestibule bottom platform include the horizontal roof beam structure of vestibule and the vertical roof beam structure of vestibule, the horizontal roof beam structure of vestibule total two be and transversely arrange side by side around, evenly install the vertical roof beam structure of a plurality of vestibules between the horizontal roof beam structure of two vestibules, install anti-skidding bottom plate on the horizontal roof beam structure of vestibule and the vertical roof beam structure of vestibule.
The corridor bottom platform on install closed frame, closed frame is last around side department install the wall body.
And ventilation windows are arranged on the wall bodies of the closed frames.
And a ventilation opening bracket is arranged on the closed frame of the elevator corridor structure positioned on the top floor of the building, and an inclined ceiling is arranged on the ventilation opening bracket.
The upper end face of the platform at the bottom of the corridor is provided with handrail rails corresponding to the front side face and the rear side face of the platform.
The corridor mounting frame, the corridor bottom platform and the oblique supporting columns are all connected in a welding mode.
The corridor mounting frame, the corridor bottom platform and the inclined supporting columns are connected through hinge joints.
The flexible structure between the extending end of the platform at the bottom of the corridor and the existing building is a flexible colloid structure formed by filling a butt joint gap with waterproof sealant and curing.
Has the advantages that: the utility model relates to a vestibule structure of outdoor elevator, specific beneficial effect is as follows:
(1) the corridor mounting frame, the corridor bottom platform and the oblique supporting columns are designed to be in a tripod structure, so that the strength of the corridor structure is improved, and the corridor is ensured to be normally used;
(2) the gravity center stress point of the elevator corridor is arranged on the shaft upright post and is in flexible butt joint with the existing building, so that the elevator corridor is prevented from being in hard connection with the existing building, the existing building is not damaged due to the settlement difference of the elevator derrick and the existing building, and secondary damage to the existing building due to the tension of the elevator derrick corridor is avoided under the condition of an earthquake;
(3) the window closed frame wall body, the baffle plate and the handrail are arranged, so that the corridor structure is sealed, safety and convenience in use are also taken into consideration, and the safety protection performance of the corridor is enhanced.
(4) The window glass of the corridor frame wall body is made of the glass material with good light transmission but opaque, the ventilation window can be freely opened and closed, and ventilation and light transmission of the corridor can be achieved under the condition that a user is effectively protected to be private.
Drawings
Fig. 1 is a structural view of an elevator corridor when located at the top floor of the present invention;
fig. 2 is a structural view of the louver of the present invention;
fig. 3 is a structural view of the vestibule floor platform according to the present invention;
fig. 4 is a structural view of the vestibule mount of the present invention;
FIG. 5 is a schematic structural view of the present invention in butt joint with an existing building;
fig. 6 is a front view of the present invention;
fig. 7 is a structural view of the hinge connection structure of the present invention.
The figure is as follows: 1. elevator vestibule, 2, existing building, 3, elevator derrick, 4, elevartor shaft base, 5, vestibule mounting bracket, 6, vestibule bottom platform, 7, bearing diagonal post, 8, closed frame, 9, handrail, 10, vent support, 11, slope ceiling, 12, the vertical roof beam structure of vestibule, 13, the horizontal roof beam structure of vestibule, 14, well stand, 15, well crossbeam, 16, ventilation window, 17, hinge joint.
Detailed Description
The present invention will be further described with reference to the following specific examples. It should be understood that these examples are for illustrative purposes only and are not intended to limit the scope of the present invention. Furthermore, it should be understood that various changes and modifications of the present invention may be made by those skilled in the art after reading the teachings of the present invention, and these equivalents also fall within the scope of the appended claims.
The utility model discloses an embodiment relates to vestibule structure of outdoor elevator, as shown in fig. 1-7, including vestibule mounting bracket 5, vestibule bottom platform 6 and bearing diagonal post 7, 5 one side horizontal mounting of vestibule mounting bracket have vestibule bottom platform 6, the lower terminal surface front and back portion of vestibule bottom platform 6 side by side the symmetry install two lower extremes and the bearing diagonal post 7 that vestibule mounting bracket 5 links to each other, form 10 ~ 80 slope contained angles between bearing diagonal post 7 and the vestibule bottom platform 6, the end that stretches out of vestibule bottom platform 6 links to each other with existing building 2 through flexible construction.
Through vestibule mounting bracket 5, vestibule bottom platform 6 and bearing diagonal 7 realize the support to elevator vestibule 1's tripod form among this technical scheme, when guaranteeing elevator vestibule 1's intensity, avoid elevator vestibule 1 and existing building 2 to form the hard joint, eliminated the potential safety hazard, avoided elevator vestibule 1 to pull out because the elevator subsides and splits existing building 2, also reduced the maintenance cost.
Preferably, corridor mounting bracket 5 include well crossbeam 15 and well stand 14, well crossbeam 15 downside install two well stands 14 side by side around, well crossbeam 15 docks with corridor bottom platform 6.
Preferably, vestibule bottom platform 6 include the horizontal roof beam structure 13 of vestibule and the vertical roof beam structure 12 of vestibule, the horizontal roof beam structure 13 of vestibule total two be horizontal front and back and arrange side by side, evenly install the vertical roof beam structure 12 of a plurality of vestibules between the horizontal roof beam structure 13 of two vestibules, install anti-skidding bottom plate on the horizontal roof beam structure 13 of vestibule and the vertical roof beam structure 12 of vestibule.
Preferably, corridor bottom platform 6 on install closed frame 8, closed frame 8 is last around the side department install the wall body, through installation closed frame 8 among this technical scheme, realize the closed processing to corridor structure 4, realize building security, protection nature and privacy's requirement, increased the ventilation window simultaneously and ensured good ventilation and light transmittance.
Preferably, the walls of the closed frame 8 are all provided with ventilation windows 16.
Preferably, a vent support 10 is mounted on the closed frame 8, and an inclined ceiling 11 is mounted on the vent support 10.
Preferably, the handrail 9 corresponding to the front and rear side surfaces of the corridor bottom platform 6 is arranged on the upper end surface of the corridor bottom platform.
Preferably, the corridor mounting frame 5, the corridor bottom platform 6 and the inclined supporting columns 7 are all connected through welding.
Preferably, the corridor mounting frame 5, the corridor bottom platform 6 and the inclined supporting columns 7 are connected through hinge joints 17.
The flexible structure between the extending end of the corridor bottom platform 6 and the existing building 2 is a flexible colloid structure formed by filling a butt joint gap with waterproof sealant and curing.
The front side and the rear side of the closed frame 9 are provided with ventilation windows, glass windows are arranged in the ventilation windows, the glass windows generally adopt opaque materials with good light transmission as main bodies, and therefore the privacy of users can be protected, and the light transmission performance can be guaranteed. The glass window close to the diagonal bracing column 8 is fixedly installed, and the glass window close to the corridor platform is installed as shown in fig. 4, and can be turned and opened at a small angle to realize ventilation.
The ventilation window can also adopt a conventional aluminum alloy window body structure which is opened and closed by moving left and right, and can also select a common turnover window structure with the middle part opened and turned over outwards at the left and right sides.
In the installation, at first carry out the installation of elevartor shaft base 4 in existing building 2 one side, install elevator shaft 3 after installing on elevartor shaft base 4, elevator shaft 3 forms through many steel structure support welding equipment, later carry out the installation of elevator vestibule 1, the realization is to the butt joint of existing building 2, elevator vestibule 1 comes to carry out waterproof sealing to the gap of butt joint through waterproof sealed glue, make elevator vestibule 1 and existing building 2 form the flexonics, avoid because the elevator subsides to draw and splits existing building 2.

Claims (10)

1. The utility model provides a vestibule structure of outdoor elevator, includes vestibule mounting bracket (5), vestibule bottom platform (6) and bearing diagonal (7), its characterized in that: vestibule mounting bracket (5) one side horizontal installation have vestibule bottom platform (6), the lower terminal surface front rear portion of vestibule bottom platform (6) side by side the symmetry install two lower extremes and vestibule mounting bracket (5) continuous bearing diagonal (7), form 10 ~ 80 slope contained angle between bearing diagonal (7) and vestibule bottom platform (6), the end that stretches out of vestibule bottom platform (6) passes through flexible construction and links to each other with existing building (2).
2. The corridor structure of an outdoor elevator according to claim 1, characterized in that: vestibule mounting bracket (5) include well crossbeam (15) and well stand (14), well crossbeam (15) downside around install two well stands (14) side by side, well crossbeam (15) and vestibule bottom platform (6) butt joint.
3. The corridor structure of an outdoor elevator according to claim 1, characterized in that: vestibule bottom platform (6) including the horizontal roof beam structure of vestibule (13) and the vertical roof beam structure of vestibule (12), the horizontal roof beam structure of vestibule (13) total two be and transversely arrange side by side around being, evenly install the vertical roof beam structure of a plurality of vestibules (12) between the horizontal roof beam structure of two vestibules (13), install anti-skidding bottom plate on the horizontal roof beam structure of vestibule (13) and the vertical roof beam structure of vestibule (12).
4. The corridor structure of an outdoor elevator according to claim 1, characterized in that: vestibule bottom platform (6) on install closed frame (8), closed frame (8) are gone up the front and back side department and are installed the wall body.
5. The corridor structure of an outdoor elevator according to claim 4, wherein: and ventilation windows (16) are arranged on the wall bodies of the closed frames (8).
6. The corridor structure of an outdoor elevator according to claim 4, wherein: the closed frame (8) is provided with a vent support (10), and the vent support (10) is provided with an inclined ceiling (11).
7. The corridor structure of an outdoor elevator according to claim 1, characterized in that: the upper end face of the corridor bottom platform (6) is provided with a handrail (9) corresponding to the front side face and the rear side face of the corridor bottom platform.
8. The corridor structure of an outdoor elevator according to claim 1, characterized in that: the corridor mounting rack (5), the corridor bottom platform (6) and the inclined supporting columns (7) are all connected in a welding mode.
9. The corridor structure of an outdoor elevator according to claim 1, characterized in that: the corridor mounting frame (5), the corridor bottom platform (6) and the inclined supporting columns (7) are connected through hinge joints (17).
10. The corridor structure of an outdoor elevator according to claim 1, characterized in that: the flexible structure between the extending end of the corridor bottom platform (6) and the existing building (2) is a flexible colloid structure formed by filling a butt joint gap with waterproof sealant and curing.
CN202020059994.5U 2020-01-13 2020-01-13 Vestibule structure of outdoor elevator Expired - Fee Related CN211714654U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020059994.5U CN211714654U (en) 2020-01-13 2020-01-13 Vestibule structure of outdoor elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020059994.5U CN211714654U (en) 2020-01-13 2020-01-13 Vestibule structure of outdoor elevator

Publications (1)

Publication Number Publication Date
CN211714654U true CN211714654U (en) 2020-10-20

Family

ID=72823115

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020059994.5U Expired - Fee Related CN211714654U (en) 2020-01-13 2020-01-13 Vestibule structure of outdoor elevator

Country Status (1)

Country Link
CN (1) CN211714654U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114541796A (en) * 2021-12-23 2022-05-27 广东奥菱电梯有限公司 Installation method for additionally installing elevator corridor

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114541796A (en) * 2021-12-23 2022-05-27 广东奥菱电梯有限公司 Installation method for additionally installing elevator corridor

Similar Documents

Publication Publication Date Title
CN109095330B (en) Aluminum alloy sightseeing elevator derrick upright column section bar
CN102180394B (en) Integrated building-block-type lift of strip steel structure
JPH0215903Y2 (en)
CN111188507A (en) Corridor structure of elevator hoistway and installation method thereof
CN211714654U (en) Vestibule structure of outdoor elevator
CN109944371A (en) Double rope net steel-beam combination structures of Super High macroplate curtain wall
CN107338892A (en) The dismantled and assembled plate of type unitized curtain wall and dismounting, installation method
CN214302811U (en) Self-adaptive all-steel attached lifting scaffold in micro-tilt building
CN214462401U (en) Double-layer protection frame with novel structure
CN208039787U (en) High-altitude edge-facing operation assembly operation platform
CN205652958U (en) Be applied to derrick on villa elevator
CN207536962U (en) A kind of car external passenger elevators
CN207526054U (en) A kind of hoistway soft connection device
CN208668914U (en) A kind of safety-type high external hanging basket for building
CN206901555U (en) A kind of elevator drainage arrangement
CN207017595U (en) A kind of pin-connected panel installs the outer hoistway of elevator additional
CN217151349U (en) Safety protection structure in elevator shaft
WO2012138161A2 (en) Exterior wall with double window for building
CN211444637U (en) Steel frame hoistway
CN213509397U (en) Install elevator well and elevator well glass installation component additional
CN213296667U (en) Steel ladder connecting structure for steel skeleton light roof maintenance
CN204960054U (en) Bright frame glass curtain wall node structure and bright frame glass curtain wall
CN211341342U (en) Anti-falling system for glass of hidden frame curtain wall
CN212129798U (en) Steel structure of elevator outside building
CN107419831A (en) A kind of dry method quick assembling unit of glass curtain wall or window

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201020