CN211714246U - Building wall body convenient to calandria wiring installation and preparation template, and mounting - Google Patents
Building wall body convenient to calandria wiring installation and preparation template, and mounting Download PDFInfo
- Publication number
- CN211714246U CN211714246U CN201922026745.6U CN201922026745U CN211714246U CN 211714246 U CN211714246 U CN 211714246U CN 201922026745 U CN201922026745 U CN 201922026745U CN 211714246 U CN211714246 U CN 211714246U
- Authority
- CN
- China
- Prior art keywords
- mounting groove
- wall body
- nail
- staple
- fixed strip
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The utility model provides a building wall and preparation template convenient to calandria wiring installation, and mounting, can make things convenient for the later stage to carry out calandria wiring construction on the wall body, including the wall body, the surface reservation of wall body is provided with horizontal mounting groove and vertical mounting groove one, horizontal mounting groove is in cross state with vertical mounting groove, reserves horizontal mounting groove and vertical mounting groove promptly when constructing the wall body construction, makes things convenient for the pipeline to lay, the later stage only need a small amount of fluting can, greatly save manpower and the time that later stage water and electricity installation consumes, still including the preparation template that is used for making this wall body and the mounting of the fixed pipeline of being convenient for in addition.
Description
Technical Field
The utility model relates to a building wall technical field especially relates to a building wall and preparation template and mounting convenient to calandria wiring installation.
Background
The cast-in-place construction of the concrete is suitable for building industrialization, the structure body formed by cast-in-place has plastic shape, high bearing strength and high rigidity strength, the existing high-rise building basically adopts the cast-in-place construction of the concrete, many walls are also constructed by cast-in-place concrete, especially the frame shear wall structure, but the rigidity of the surface of the wall formed by cast-in-place is high, which brings trouble to the later construction of arranging the pipes on the wall, because the control panels such as socket switches and the like need to be installed on the wall surface during later decoration, the electric wire pipes need to be arranged on the wall surface, and in order to ensure the beauty and smoothness, the conduits need to be embedded into the wall body, which involves later wall surface grooving, which is a very tedious and labor-consuming task, because the surface of the concrete wall has high rigidity and strength, the slotting process is very troublesome, and the efficiency is low, the problem of later-stage pipeline installation needs to be considered when the wall is constructed.
SUMMERY OF THE UTILITY MODEL
The utility model discloses the technical problem that needs to solve provides a building wall body and preparation template and mounting convenient to calandria wiring installation, and it can make things convenient for the later stage to carry out calandria wiring construction on the wall body.
A building wall convenient for arranging and installing calandria wires comprises a wall body, wherein a transverse mounting groove and a longitudinal mounting groove are reserved on the outer surface of the wall body, the transverse mounting groove is transversely arranged, the longitudinal mounting groove is longitudinally arranged, the transverse mounting groove and the longitudinal mounting groove are in a crossed state, the cross sections of the transverse mounting groove and the longitudinal mounting groove are rectangular, the depth of the two grooves is more than 2cm, pipelines needing to be laid on the wall body are generally a wire pipe and a network pipe and are used for connecting a switch socket and the like on the wall surface, manual grooving can be only carried out on a structural wall surface in order to ensure that the completion surface of the wall surface is not protruded during construction, the pipelines are laid, the grooving process is time-consuming and labor-consuming, particularly, the difficulty is higher in concrete structure wall body, the utility model has the beneficial effects that the transverse mounting groove and the longitudinal mounting groove are reserved during construction of, general pipeline is laid in ground position or furred ceiling position, only need in unison lay horizontal mounting groove again through vertical mounting groove when laying the wall like this in can, even the height of switch or socket is highly inconsistent with horizontal mounting groove, that also only need a small amount of fluting can, for example the height of horizontal mounting groove is 1m, and the height that switch or socket need be installed is 1.1m, that just the position manual work fluting 0.1m at installation switch or socket can, the manpower and the time that the hydroelectric installation of very big later stage consumes are saved.
Specifically, the height of the transverse installation groove from the bottom side of the wall body is 1.1m, which is the height most suitable for installing the switch according to the requirements of human engineering, so that the switch is installed without grooving, and the switch is arranged on the wall surface most relatively.
Specifically, the interior width of vertical mounting groove is greater than the interior width of horizontal mounting groove because lay the spool on the wall and need all pass through from vertical mounting groove position, and it is more from the downward spool in furred ceiling position, all need lay through vertical mounting groove, and it needs to set up the interior width that is relatively bigger.
A manufacturing template comprises a template, a first fixing strip and a second fixing strip, wherein the first fixing strip and the second fixing strip are long strips with rectangular sections, the sum of the thicknesses of the first fixing strip and the second fixing strip is equal to the depth of a transverse mounting groove or a longitudinal mounting groove in a wall body, the width of the first fixing strip is larger than that of the second fixing strip, edgings are fixedly arranged on the upper sides of the two side edges of the first fixing strip, the height of each edgings is equal to that of the second fixing strip, the width of the second fixing strip is equal to the inner width between the two side edgings, the first fixing strip is fixed to the corresponding position of the template through a gun nail during construction, the second fixing strip is embedded between the edgings and fixed to the second fixing strip through the gun nail, the first fixing strip and the second fixing strip form an integral strip, and the arrangement position of the first fixing strip and the second fixing strip is required to correspond to the positions of the transverse mounting groove and, then the template assembly pours the wall body that the concrete formed again behind the corresponding position and can directly reserve out horizontal mounting groove and vertical mounting groove, wherein with the purpose that first fixed strip and second fixed strip separately set up be convenient for the rifle nail fixed, because the rifle nail length that generally facilitates the use is less than 2cm, and the sunken degree of the horizontal mounting groove that needs to reserve or vertical mounting groove needs to be greater than 2cm, the total thickness that first fixed strip and second fixed strip formed just needs to be greater than 2cm like this, separate set up between them more convenient accurate fixed.
A fixing piece comprises fixing nails, hammering nails and connecting wires, wherein the fixing nails and the hammering nails are in a column shape, the fixing nails have two paths, the bottom ends of the fixing nails are sharp and are used for nailing into a wall body, a circle of fixing groove is arranged on the periphery of the top positions of the fixing nails, the two ends of the connecting wires are wound and fixed in the fixing groove of the top positions of the fixing nails so that the fixing nails are connected together, after the fixing nails are nailed into the wall body, a connecting rope can limit a spool and play a role in fixing the spool, a concave port is arranged at the top end of each fixing nail, the concave port is in a column shape, the cross section shape and the size of each hammering nail are the same as those of the concave port, the hammering nails can extend into the concave port, lugs are arranged at the top end of each hammering nail, and the fixing nails can be nailed into the wall body through the hammering nails, because the spool needs to lay in horizontal mounting groove and vertical mounting groove, then the staple need be nailed into the mounting groove, because the width is limited in the notch, the hammer is not convenient for directly hammer the staple and nail it completely, through setting up the hammer and strike the nail then can help the staple conveniently by being nailed into, the hammer can reuse many times, need not with the staple one-to-one, only need the size the same can.
Specifically, the connecting wire is made of metal materials, such as iron wires and the like, has higher strength and durability and is not easy to break.
Specifically, the cross-sectional shape of the sunken mouth on fixation nail top and hammering nail is non-circular form, and hammering nail can not rotate relative fixation nail after inserting into sunken mouthful like this, is favorable to the steadiness of hammering process.
Drawings
Fig. 1 is a schematic perspective view of a wall body of a building of the present invention.
Fig. 2 is a schematic perspective view of the conduit of the utility model.
Fig. 3 is a schematic perspective view of the middle-made template of the present invention.
Fig. 4 is a schematic partial cross-sectional view of the template according to the present invention.
Fig. 5 is a schematic perspective view of the middle fixing member of the present invention.
Detailed Description
The following detailed description of embodiments of the present invention will be made with reference to the accompanying drawings.
A building wall convenient for arranging pipes in a wiring way is disclosed, as shown in figure 1, comprising a wall body 1, wherein a transverse mounting groove 11 and a longitudinal mounting groove 12 are reserved on the outer surface of the wall body 1, the transverse mounting groove 11 is transversely arranged, the longitudinal mounting groove 12 is longitudinally arranged, the transverse mounting groove 11 and the longitudinal mounting groove 12 are in a crossed state, the cross sections of the transverse mounting groove 11 and the longitudinal mounting groove 12 are rectangular, the depth of the depression of the transverse mounting groove 11 and the depth of the depression of the longitudinal mounting groove 12 are both larger than 2cm, pipelines needing to be laid on the wall body are generally an electric wire pipe and a network pipe and are used for connecting a switch socket and the like on the wall surface, the horizontal mounting groove 11 and the longitudinal mounting groove 12 are reserved during construction, the pipeline can only be manually grooved on the structural wall surface to lay the pipeline, the grooving process is time-consuming and labor-consuming, especially a concrete structural wall body is more difficult, the utility model has the beneficial, ordinary pipeline is laid in ground position or furred ceiling position, only need in unison lay horizontal mounting groove 11 again through vertical mounting groove 12 when laying the wall like this can, as shown in fig. 2 promptly, even the height of switch or socket is not consistent with the height of horizontal mounting groove 11, that also only need a small amount of fluting can, for example the height of horizontal mounting groove 11 is 1m, and the height that switch or socket need be installed is 1.1m, that just the position manual fluting 0.1m of installation switch or socket can, greatly save manpower and the time that later stage water and electricity installation consumed.
Specifically, the height of the transverse installation groove 11 from the bottom side of the wall body 1 is 1.1m, which is the height most suitable for installing a switch according to the requirements of human engineering, so that the switch is installed without grooving, and the switch is arranged on the wall surface most relatively.
Specifically, the interior width of vertical mounting groove 12 is greater than the interior width of horizontal mounting groove 11, as shown in fig. 2, because lay the spool on the wall and need all pass through from vertical mounting groove 12 position, from the decurrent spool in furred ceiling position, all need lay through vertical mounting groove 12, and it needs to set up relatively bigger interior width.
A template for manufacturing is shown in fig. 3 and comprises a template 2, a first fixing strip 21 and a second fixing strip 22, wherein the first fixing strip 21 and the second fixing strip 22 are both long strip-shaped structures with rectangular sections, the sum of the thicknesses of the first fixing strip 21 and the second fixing strip 22 is equal to the depth of a transverse installation groove 11 or a longitudinal installation groove 12 on a wall body 1, as shown in a sectional view in fig. 4, the width of the first fixing strip 21 is larger than that of the second fixing strip 22, edge strips 23 are fixedly arranged on the upper sides of two side edges of the first fixing strip 21, the height of the edge strips 23 is equal to that of the second fixing strip 22, the width of the second fixing strip 22 is equal to the inner width between the edge strips 23, the first fixing strip 21 is fixed to the corresponding position of the template 2 through a gun nail during construction, the second fixing strip 22 is embedded between the edge strips 23 and fixed to the second fixing strip 22 through the gun nail, and the position of the strip arrangement formed by the first fixing strip 21 and the second fixing strip 22 integrally needs to be matched with the transverse installation groove 11 The position of vertical mounting groove 12 corresponds, then 1 wall body 1 that the concreting formed after assembling to corresponding position of template 1 can directly reserve out horizontal mounting groove 11 and vertical mounting groove 12, wherein with the purpose that first fixed strip 21 and second fixed strip 22 separately set up be convenient for the rifle nail fixed, because the rifle nail length that generally facilitates the use is less than 2cm, and the sunken degree of depth of horizontal mounting groove 11 or vertical mounting groove 12 that need reserve needs to be greater than 2cm, the total thickness that first fixed strip 21 and second fixed strip 22 formed just needs to be greater than 2cm like this, separate set up with both can make things convenient for accurate fixed more.
A fixing part, as shown in FIG. 5, comprises a fixing nail 3, a hammering nail 4 and a connecting wire 5, wherein the fixing nail 3 and the hammering nail 4 are in a column shape, the fixing nail 3 has two ends, the bottom end of the fixing nail is sharp and is used for driving into a wall body 1, a circle of fixing groove 31 is arranged on the periphery of the top position of the fixing nail 3, two ends of the connecting wire 5 are wound and fixed in the fixing groove 31 of the top position of the two fixing nails 3 to enable the two fixing nails 3 to be connected together, then after the two fixing nails 3 are driven into the wall body 1, a connecting rope 5 can limit a spool to play a role of fixing the spool, a recess port 32 is arranged on the top position of the fixing nail 3, the recess port 32 is in a column shape, the cross section shape and size of the hammering nail 4 are the same as the cross section shape and size of the recess port 32, then the hammering nail 4 can extend into the recess port 32, a lug 41 is arranged on the top end of the hammering nail 4, then can drive the nail 4 through the hammering and can drive into wall body 1 with staple 3 on, because the spool needs to lay in horizontal mounting groove 11 and vertical mounting groove 12, then the staple needs to be driven into the mounting groove, because the width is limited in the notch, the hammer is not convenient for directly drive the staple 3 and drive it into completely, drive the nail 4 through setting up the hammering and then can help staple 3 conveniently by the nail, hammering nail 4 can reuse many times, need not with 3 one-to-one of staple, only need the size the same can.
Specifically, the connecting wire 5 is made of metal, such as iron wire, and has higher strength and durability and is not easy to break.
Specifically, the cross-sectional shapes of the recessed opening 32 at the top end of the fixing nail 3 and the hammering nail 4 are non-circular, as shown in fig. 5, so that the hammering nail 4 cannot rotate relative to the fixing nail 3 after being inserted into the recessed opening 32, which is beneficial to the stability of the hammering process.
It is obvious that the described embodiments are only some of the embodiments of the present invention, and not all of them. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts shall belong to the protection scope of the present invention.
Claims (7)
1. The utility model provides a building wall convenient to calandria wiring installation which characterized in that: including wall body (1), the surface of wall body (1) is reserved and is provided with one horizontal mounting groove (11) and one vertical mounting groove (12), horizontal mounting groove (11) are horizontal setting, vertical mounting groove (12) are vertical setting, then horizontal mounting groove (11) are in the cross state with vertical mounting groove (12), the cross sectional shape of horizontal mounting groove (11) and vertical mounting groove (12) is the rectangle form, and both sunken degree of depth all are greater than 2 cm.
2. The building wall convenient for piping installation according to claim 1, wherein: the height of the transverse installation groove (11) from the bottom side of the wall body (1) is 1.1 m.
3. The building wall convenient for piping installation according to claim 1, wherein: the inner width of the longitudinal mounting groove (12) is larger than that of the transverse mounting groove (11).
4. A form for a building wall to facilitate installation of calandria wiring according to claim 1, wherein: including template (2), first fixed strip (21), second fixed strip (22), first fixed strip (21) are the rectangular form structure of cross-section for the rectangle with second fixed strip (22), and the thickness sum between them equals the degree of depth of horizontal mounting groove (11) or vertical mounting groove (12) on wall body (1), the width of first fixed strip (21) is greater than the width of second fixed strip (22), the upside of first fixed strip (21) both sides border is fixed and is provided with strake (23), the height of strake (23) equals the thickness of second fixed strip (22), and the width of second fixed strip (22) equals the interior width between both sides strake (23).
5. A fixture for a building wall to facilitate installation of calandria wiring according to claim 1, wherein: including staple (3), hammering nail (4), connecting wire (5), staple (3) are the post shape with hammering nail (4), there is twice staple (3), and its bottom is sharp-pointed form, the top position periphery of staple (3) is provided with round fixed slot (31), the both ends winding of connecting wire (5) is fixed and is made twice staple (3) connect together in fixed slot (31) of twice staple (3) top position, the top position of staple (3) is provided with sunken mouthful (32), sunken mouthful (32) are the cylindricality form, the cross sectional shape and the size of hammering nail (4) are the same with the cross sectional shape and the size of sunken mouthful (32), and hammering nail (4) can stretch into in sunken mouthful (32), the top of hammering nail (4) is provided with lug (41).
6. The fastener of claim 5, wherein: the connecting wire (5) is made of metal.
7. The fastener of claim 5, wherein: the cross section shapes of the sunken port (32) at the top end of the fixing nail (3) and the hammering nail (4) are non-circular.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201922026745.6U CN211714246U (en) | 2019-11-21 | 2019-11-21 | Building wall body convenient to calandria wiring installation and preparation template, and mounting |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201922026745.6U CN211714246U (en) | 2019-11-21 | 2019-11-21 | Building wall body convenient to calandria wiring installation and preparation template, and mounting |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211714246U true CN211714246U (en) | 2020-10-20 |
Family
ID=72815834
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201922026745.6U Expired - Fee Related CN211714246U (en) | 2019-11-21 | 2019-11-21 | Building wall body convenient to calandria wiring installation and preparation template, and mounting |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211714246U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117027422A (en) * | 2023-08-24 | 2023-11-10 | 滕州市工程建设服务中心 | Construction method of modularized assembly type green integrated building and wall module prefabricated member |
-
2019
- 2019-11-21 CN CN201922026745.6U patent/CN211714246U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117027422A (en) * | 2023-08-24 | 2023-11-10 | 滕州市工程建设服务中心 | Construction method of modularized assembly type green integrated building and wall module prefabricated member |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN211714246U (en) | Building wall body convenient to calandria wiring installation and preparation template, and mounting | |
CN202324501U (en) | Full clamping piece connecting member for mounting low carbon board on building outer brim | |
CN206971476U (en) | A kind of assembled wall increases structure | |
CN207846659U (en) | A kind of slot connection and keel connecting structure | |
CN110206194B (en) | Blank partition wall | |
CN115198929B (en) | Wall body mounting frame structure | |
CN209227594U (en) | A kind of aluminum wood gang form applied to pipe gallery construction | |
CN209760529U (en) | Assembled building built-up plate | |
CN211200747U (en) | Heat preservation wallboard for prefabricated building | |
CN210798016U (en) | From excellent floor that takes split heads to hold | |
CN110761483B (en) | Installation method of partition board with good anti-seismic performance | |
CN110761484B (en) | Partition plate with good anti-seismic performance | |
CN201087491Y (en) | Floor structure | |
KR20120111825A (en) | Fixing device of lightweight steel for underground double wall | |
CN203113633U (en) | Assembling structure of profiling plate of metal roof | |
CN209976015U (en) | Concrete floor dismantling-free steel bar truss template and template combined structure | |
CN213868699U (en) | Wallboard connecting buckle | |
CN216865595U (en) | Metal connecting component for light partition wall board | |
CN2931637Y (en) | Horizontal lock buckle for building | |
CN110670787A (en) | Groove profile special for ceiling gypsum board suspended ceiling and mounting method thereof | |
CN220184365U (en) | Polyethylene modified concrete grouting structure for filling steel structure building | |
CN220100262U (en) | Assembled wall of integrated pipeline of skirting | |
CN215406718U (en) | Assembled building wall | |
CN212027243U (en) | Keel frame structure for container and container | |
CN115012560B (en) | Assembled partition wall with decorative surface and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20201112 Address after: 518052 Nantou Street Nanshan District, Shenzhen City, Guangdong Province Patentee after: SHENZHEN XINLANG CONSTRUCTION ENGINEERING Co.,Ltd. Address before: Shanghai Yunjiu building materials Co., Ltd., No. 17, Zhongbei Road, Zhangjiagang City, Suzhou City, Jiangsu Province Patentee before: Qiu Zhenhua |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20201020 Termination date: 20211121 |