CN211712455U - Steel-concrete combined beam lifting station - Google Patents

Steel-concrete combined beam lifting station Download PDF

Info

Publication number
CN211712455U
CN211712455U CN202020274715.7U CN202020274715U CN211712455U CN 211712455 U CN211712455 U CN 211712455U CN 202020274715 U CN202020274715 U CN 202020274715U CN 211712455 U CN211712455 U CN 211712455U
Authority
CN
China
Prior art keywords
steel pipe
lifting
pipe pile
main
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020274715.7U
Other languages
Chinese (zh)
Inventor
肖黎
王东伟
吕牧
潘强
王海龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Engineering Co Ltd
No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Original Assignee
CCCC First Highway Engineering Co Ltd
No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd, No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN202020274715.7U priority Critical patent/CN211712455U/en
Application granted granted Critical
Publication of CN211712455U publication Critical patent/CN211712455U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to a reinforced concrete composite beam lifting station, which comprises two rows of steel pipe pile rows arranged at two sides of a constructed bridge, wherein each row of steel pipe pile rows comprises at least two steel pipe piles arranged in parallel, and each steel pipe pile is vertical to the ground where the constructed bridge is located; each steel pipe pile is provided with a lifting device; each row of main trusses is hoisted to the corresponding row of steel pipe pile rows by the hoisting device, and the main trusses are positioned above the position of the bridge deck of the bridge to be constructed; and the gantry lifting appliance comprises lifting frames and a movable lifting appliance, the lifting frames are transversely arranged on the two rows of main trusses, the longitudinal direction of each lifting frame is vertical to the longitudinal direction of each main truss, and the movable lifting appliance is movably arranged on each lifting frame and can move on the lifting frame along the longitudinal direction of the corresponding lifting frame.

Description

Steel-concrete combined beam lifting station
Technical Field
The utility model relates to a reinforced concrete composite beam hoisting station.
Background
The steel-concrete composite beam used for the bridge deck generally consists of a steel beam stage and a bridge deck, the conventional steel beam adopts a hollow-web type channel beam, the bridge deck is a solid concrete slab, the weight of the steel beam can reach 1.9 ten thousand tons, the weight of the bridge deck can reach 100 tons, and the bridge deck has a large construction span, so that the implementation difficulty is large if a conventional crane is adopted under the common condition.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a simple structure and be convenient for implementation's steel-concrete composite beam hoisting station.
In order to achieve the above purpose, the utility model provides a following technical scheme: a steel-concrete combined beam lifting station comprises
Two rows of steel pipe pile rows are arranged on two sides of a constructed bridge, each row of steel pipe pile rows comprises at least two steel pipe piles which are arranged in parallel, and each steel pipe pile is vertical to the ground where the constructed bridge is located;
each steel pipe pile is provided with a lifting device;
each row of main trusses is hoisted to the corresponding row of steel pipe pile rows by the hoisting device, and the main trusses are positioned above the position of the bridge deck of the bridge to be constructed; and the number of the first and second groups,
the gantry lifting appliance comprises lifting frames and a movable lifting appliance, the lifting frames are transversely arranged on the two rows of main trusses, the longitudinal direction of the lifting frames is vertical to the longitudinal direction of the main trusses, and the movable lifting appliance is movably arranged on the lifting frames and can move on the lifting frames along the longitudinal direction of the lifting frames.
Furthermore, each steel pipe pile is connected with the main truss through a distribution beam, each steel pipe pile comprises a first frame body and a second frame body which are arranged oppositely, the main truss can move between the first frame body and the second frame body along the height direction of the steel pipe pile, and the distribution beam has a first position which enables the distribution beam not to be connected with the steel pipe pile and a second position which enables the distribution beam to be connected with the steel pipe pile relative to the main truss; and when the distribution beam moves to the preset installation position of the steel pipe pile along with the main truss, the distribution beam rotates relative to the truss section to be converted from the first position to the second position.
Furthermore, each row of the main truss is formed by splicing a plurality of sections of truss sections, each section of truss section is fixed between two adjacent steel pipe piles, and the distribution beam is arranged between each section of truss section and each steel pipe pile.
Furthermore, the distribution beam is abutted against the lower part of the main truss, and in the first position, the distribution beam is hung below the main truss through a steel wire rope.
Further, the distribution beam is rotatable relative to the main girder to move from a first position to a second position.
Furthermore, the hanger is provided with a slide rail, and the movable hanger is provided with a movable seat matched with the slide rail.
Furthermore, the steel-concrete composite beam lifting station further comprises connecting beams transversely arranged on the two rows of main trusses.
Further, the lifting device is a jack.
Furthermore, the main truss and the gantry lifting appliance are firstly installed into an integral structure, and then the lifting device lifts the main truss and the gantry lifting appliance to the preset installation position of the steel pipe pile.
Further, when the main truss and the gantry lifting appliance are lifted to the preset installation position of the steel pipe pile together, the lifting device and part of the steel pipe pile are removed.
The beneficial effects of the utility model reside in that: through the utility model discloses a reinforced concrete composite beam lifting station simple structure can directly realize building implementation and build and dismantle on the ground, and can improve work efficiency through adopting reinforced concrete composite beam lifting station, in the construction of specially adapted large-scale bridge (like the overhead). Moreover, the steel-concrete composite beam lifting station has low geological requirement and wide adaptability.
The above description is only an overview of the technical solution of the present invention, and in order to make the technical means of the present invention clearer and can be implemented according to the content of the description, the following detailed description is made with reference to the preferred embodiments of the present invention and accompanying drawings.
Drawings
Fig. 1 is a front view of a steel-concrete composite beam lifting station according to an embodiment of the present invention;
FIG. 2 is a side view of the steel and concrete composite beam lift station shown in FIG. 1;
FIG. 3 is a top view of the steel and concrete composite beam lift station shown in FIG. 1;
FIG. 4 is a schematic view of the assembled main truss and gantry spreader in a lifted state by a lifting device;
FIG. 5 is a schematic view showing the state of the main truss and the gantry crane passing through the lower part of the lifting device to the bridge floor.
Detailed Description
The following detailed description of the embodiments of the present invention is provided with reference to the accompanying drawings and examples. The following examples are intended to illustrate the invention, but are not intended to limit the scope of the invention.
Referring to fig. 1 to 3 in combination with fig. 4, a steel-concrete composite beam lifting station according to a preferred embodiment of the present invention includes: two rows of steel pipe pile rows 10, several lifting devices 50 (as shown in fig. 4), two rows of main trusses 20, and a gantry spreader 30. Two rows of steel pipe pile rows 10 are arranged on two sides of a constructed bridge, each row of steel pipe pile rows 10 comprises at least two steel pipe piles 11 arranged in parallel, and each steel pipe pile 11 is perpendicular to the ground where the constructed bridge is located. Each steel pipe pile 11 is provided with a lifting device 50. Each row of the main trusses 20 is hoisted to a corresponding row of the steel pipe pile rows 10 by the hoisting device 50, and the main trusses 20 are located above a position where a deck (not shown) of a bridge to be constructed is located. The gantry crane 30 comprises a hanger 31 and a mobile crane 32, the hanger 31 is transversely arranged on two rows of the main trusses 20, the longitudinal direction of the hanger 31 is vertical to the longitudinal direction of the main trusses 20, the mobile crane 32 is movably arranged on the hanger 31 and can move on the hanger 31 along the longitudinal direction of the hanger 31, and the connection mode between the hanger 31 and the mobile crane 32 is as follows: the hanger 31 is provided with a slide rail 33, the mobile lifting appliance 32 is provided with a mobile seat 34 matched with the slide rail 33, and the mobile seat 34 is driven by a driving device 35 to move on the slide rail 33 along the longitudinal direction of the hanger 31.
In this embodiment, in order to reinforce the strength of the integral steel-concrete composite girder lifting station, the steel-concrete composite girder lifting station further includes a connection beam 40 transversely disposed on the two rows of the main trusses 20. In the present embodiment, the lifting device 50 is a jack, but in other embodiments, other lifting devices 50 may be used.
In this embodiment, each of the steel pipe piles 11 is connected to the main truss 20 by a distribution beam (not numbered), each of the steel pipe piles 11 includes a first frame body 12 and a second frame body 13 which are disposed opposite to each other, the main truss 20 is movable in a height direction of the steel pipe pile 11 between the first frame body 12 and the second frame body 13, and the distribution beam has a first position (not shown) where the distribution beam is not connected to the steel pipe pile 11 and a second position (not numbered) where the distribution beam is connected to the steel pipe pile 11 with respect to the main truss 20; after the distributor beam is moved with the main girder 20 to a predetermined installation position of the steel pipe pile 11 (a position indicated by an arrow a in fig. 4, which is lower than a position where the jack 50 is located, in a conventional arrangement, the jack 50 is usually located at the top of the steel pipe pile 11), the distributor beam is rotated with respect to the girder segments to be transferred from the first position to the second position. Specifically, each row of the main truss 20 is formed by splicing a plurality of truss sections (not numbered), each truss section is fixed between two adjacent steel pipe piles 11, and the distribution beam is arranged between each truss section and each steel pipe pile 11. The distributor beams rest against the underside of the main girder 20, although in practice it is of course possible to arrange the distributor beams above or at the sides of the main girder 20, but by arranging the distributor beams below the main girder 20, so that the forces of the main girder 20 are directly received by the distributor beams, and the 'arrangement of the distributor beams below the main girder 20' does not require consideration of the force-receiving problem, as compared with the 'arrangement of the distributor beams above the main girder 20', and the connection between the distribution beam and the main girder 20 can be accomplished by a simple fastener or a wire rope, or they may be disconnected from each other, but when the distribution beam is at the second position, the distribution beam is connected to the steel pipe pile 11, the main truss 20 is connected to the steel pipe pile 11, in addition, regardless of whether the distributor beam is directly connected to the main girder 20 or the distributor beam and the main girder 20 are respectively connected to the steel pipe piles, the connection method may be any method as long as the main truss 20 is restricted from moving in the longitudinal direction of the main truss 20 with respect to the steel pipe pile.
In the first position, the distributor beam is suspended below the main girder 20 by a wire rope (not shown), but in other embodiments, the distributor beam may be connected below the main girder 20 by another structure. In addition, in this embodiment, the distribution beam is rotatable relative to the main girder 20 to move from the first position to the second position. In other embodiments, the spreader beam may be a pull-out connection with the main truss 20, etc. In actual operation, the main truss 20 and the gantry crane 30 are usually installed as an integral structure, and then lifted together by the jack 50 to a predetermined installation position of the steel pipe pile 11 (as indicated by arrow a in fig. 4), and finally, the jack 50 and the portion of the steel pipe pile 11 above the position a are removed (the final effect is shown in fig. 1).
The materials and characteristics of the steel pipe pile 11, the main truss 20, the distribution beam, the jack 50 and the gantry hanger 30 are selected according to actual requirements, wherein the steel pipe pile 11 can be of two different types, the two types are divided into a main bearing structure and an auxiliary structure, and the bearing performance of the materials of the main bearing structure is superior to that of the auxiliary structure. The main truss 20 can adopt a triangular main truss 20 structure, two adjacent truss sections are connected through high-strength bolts, the upper chord member and the lower chord member of the triangular main truss 20 can be made of Q345 steel, and the middle reinforcing rods and the web members adopt Q235 steel. The main truss girder is of a space truss structure as a whole. And in order to ensure the overall stability of the lifting station, the method adopts
Figure BDA0002403887100000041
The 630 multiplied by 6mm steel pipe connects and fixes two adjacent truss sections.
The assembling and disassembling method of the steel-concrete composite beam lifting station comprises an assembling method and a disassembling method.
Referring to fig. 1 to 4, the installation method includes:
s1: two rows of steel pipe pile rows 10 are laid on two sides of a constructed bridge, each row of steel pipe pile rows 10 comprises at least two steel pipe piles 11 arranged in parallel, and each steel pipe pile 11 is vertical to the ground where the constructed bridge is located;
s2: installing a lifting device 50 on each steel pipe pile 11;
s3: assembling two rows of main trusses 20 and a gantry hanger 30: splicing two rows of main trusses 20 between two rows of steel pipe pile rows 10, wherein each row of trusses is composed of a plurality of truss sections, installing a gantry hanger 30 on the two rows of main trusses 20, wherein the gantry hanger 30 comprises a hanger 31 installed between the two rows of main trusses 20 and a movable hanger 32 installed on the hanger 31, the movable hanger 32 can move on the hanger 31, and distribution beams are arranged on the main trusses 20;
s4: and synchronously lifting two rows of main trusses 20 and a gantry lifting appliance 30 by adopting a lifting device 50 until the distribution beam moves to the preset installation position of the steel pipe pile along with the main trusses 20, and moving the distribution beam to enable the distribution beam to be in butt joint with the corresponding steel pipe pile 11.
Referring to fig. 1 to 3 and fig. 5, the disassembling method includes:
arranging a temporary buttress 70 on the bridge floor 60 as a fulcrum for detaching the overhead crane beam after the lowering, moving the overhead crane beam to the position right above the buttress of the bridge floor 60, lowering the gantry lifting appliance 30 to the position below the girder station main truss 20, and cutting off the middle part of the temporary buttress 70 above the bridge floor 60 in a parallel connection manner; forming temporary supporting points which are used as main trusses 20 and are lowered to the rear end part of the bridge deck 60 between the pipe piles close to the outer side of the temporary buttress 70 and are as high as the bridge deck 60 plate;
the main truss 20 and the gantry crane 30 are put down to the bridge floor 60; the gap between the temporary buttress 70 of the bridge deck 60 and the gantry crane 30 is padded by steel plates;
removing the lifting device 50, and cutting the steel pipe pile 11 to be equal to the bridge floor 60 in height; the truck is hoisted to the bridge; dismantling a section of the main truss 20 on the bridge deck 60;
the truck crane drives into the gap between the main trusses 20; dismantling the gantry crane 30; dismantling the crown block beam section by section; continuing to demolish the remaining main girders 20 on the deck 60; and (5) removing the temporary buttress 70 and the rest of the steel pipe pile 11.
In this embodiment, the step S2 includes:
placing a distribution beam at a corresponding position on the ground where the steel pipe pile 11 is located;
assembling a multi-section truss and a gantry lifting appliance 30 into an integral structure at corresponding positions of the two rows of steel pipe pile rows 10;
hoisting each row of main trusses 20 a distance relative to the ground;
and the distribution beam is hung below the truss by using a steel wire rope.
In this embodiment, the step S3 includes:
synchronously lifting two rows of main trusses 20 by using a lifting device 50 until a distribution beam moves to a preset installation position of the steel pipe pile along with the main trusses 20;
and rotating the distribution beam by 90 degrees relative to the main truss 20 to enable the distribution beam to be in butt joint with the corresponding steel pipe pile 11.
To sum up, through the utility model discloses a reinforced concrete combination beam lifting station simple structure can directly realize building implementation and build and dismantle on the ground, and can improve work efficiency through adopting reinforced concrete combination beam lifting station, and the specially adapted is in the construction of large-scale bridge (like overhead). Moreover, the steel-concrete composite beam lifting station has low geological requirement and wide adaptability.
The technical features of the embodiments described above may be arbitrarily combined, and for the sake of brevity, all possible combinations of the technical features in the embodiments described above are not described, but should be considered as being within the scope of the present specification as long as there is no contradiction between the combinations of the technical features.
The above-mentioned embodiments only represent some embodiments of the present invention, and the description thereof is specific and detailed, but not to be construed as limiting the scope of the present invention. It should be noted that, for those skilled in the art, without departing from the spirit of the present invention, several variations and modifications can be made, which are within the scope of the present invention. Therefore, the protection scope of the present invention should be subject to the appended claims.

Claims (10)

1. A steel-concrete combined beam lifting station is characterized by comprising
Two rows of steel pipe pile rows are arranged on two sides of a constructed bridge, each row of steel pipe pile rows comprises at least two steel pipe piles which are arranged in parallel, and each steel pipe pile is vertical to the ground where the constructed bridge is located;
each steel pipe pile is provided with a lifting device;
each row of main trusses is hoisted to the corresponding row of steel pipe pile rows by the hoisting device, and the main trusses are positioned above the position of the bridge deck of the bridge to be constructed; and the number of the first and second groups,
the gantry lifting appliance comprises lifting frames and a movable lifting appliance, the lifting frames are transversely arranged on the two rows of main trusses, the longitudinal direction of the lifting frames is vertical to the longitudinal direction of the main trusses, and the movable lifting appliance is movably arranged on the lifting frames and can move on the lifting frames along the longitudinal direction of the lifting frames.
2. The steel-concrete composite beam lifting station according to claim 1, wherein each of the steel pipe piles is connected to the main girder by a distribution beam, each of the steel pipe piles includes a first frame body and a second frame body which are disposed opposite to each other, the main girder is movable in a height direction of the steel pipe pile between the first frame body and the second frame body, and the distribution beam has a first position where the distribution beam is not connected to the steel pipe pile and a second position where the distribution beam is connected to the steel pipe pile with respect to the main girder; and when the distribution beam moves to the preset installation position of the steel pipe pile along with the main truss, the distribution beam rotates relative to the truss section to be converted from the first position to the second position.
3. The steel-concrete composite beam lifting station according to claim 2, wherein each row of the main truss is formed by splicing a plurality of truss sections, each truss section is fixed between two adjacent steel pipe piles, and the distribution beam is arranged between each truss section and each steel pipe pile.
4. The reinforced concrete composite beam lift station of claim 2, wherein the spreader beam rests below the main truss, and in the first position, the spreader beam is suspended below the main truss by wire rope.
5. The steel and concrete composite beam lift station of claim 2, wherein the distributor beam is rotatable relative to the main truss to move from a first position to a second position.
6. The steel-concrete composite beam lifting station as claimed in claim 1, wherein the hanger is provided with a slide rail, and the mobile spreader is provided with a mobile seat engaged with the slide rail.
7. The steel-concrete composite beam lift station of claim 1, further comprising a tie beam disposed across the two rows of the main trusses.
8. The steel-concrete composite beam lifting station of claim 1, wherein the lifting means is a jack.
9. The reinforced concrete composite beam lifting station according to claim 1, wherein the main truss and the gantry crane are installed as an integral structure, and then the main truss and the gantry crane are lifted together to a preset installation position of the steel pipe pile by the lifting device.
10. The steel-concrete composite beam lifting station of claim 9, wherein when the main truss and the gantry spreader are lifted together to a predetermined installation position of the steel pipe pile, the lifting device and a portion of the steel pipe pile are removed.
CN202020274715.7U 2020-03-09 2020-03-09 Steel-concrete combined beam lifting station Expired - Fee Related CN211712455U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020274715.7U CN211712455U (en) 2020-03-09 2020-03-09 Steel-concrete combined beam lifting station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020274715.7U CN211712455U (en) 2020-03-09 2020-03-09 Steel-concrete combined beam lifting station

Publications (1)

Publication Number Publication Date
CN211712455U true CN211712455U (en) 2020-10-20

Family

ID=73396933

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020274715.7U Expired - Fee Related CN211712455U (en) 2020-03-09 2020-03-09 Steel-concrete combined beam lifting station

Country Status (1)

Country Link
CN (1) CN211712455U (en)

Similar Documents

Publication Publication Date Title
US11634877B2 (en) Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor
CN202936736U (en) Cable-stayed bridge composite beam construction bridge floor crane
CN106948268B (en) Variable-section steel box girder pushing combined device and using method thereof
CN110847062A (en) Construction method for whole-hole assembly double-width erection in 80-meter-span wide steel box girder factory
CN113585075A (en) Cast-in-place bridge deck formwork for steel-concrete composite beam
CN110700113B (en) Construction method of prestress applying device of non-prestressed beam bridge
CN108999427B (en) Support structure for moving load during building migration in place and construction method thereof
CN214740171U (en) Ancient building wall body hoist and mount migration device
CN112144413B (en) Whole-span in-situ splicing and erecting method for steel-concrete composite beam in mountainous area
CN219218724U (en) Main girder hanging and paving integrated machine for combined girder cable-stayed bridge
CN211712455U (en) Steel-concrete combined beam lifting station
CN108221702B (en) Integral lifting device for arch rib of inward-tilting steel box arch bridge
CN112160246B (en) Method for installing composite beam
CN111232835A (en) Steel-concrete combined beam lifting station and assembling and disassembling method thereof
CN211285076U (en) Railway track overhead reinforcing structure
CN214573768U (en) Self-climbing sliding formwork pouring system for second-stage concrete pouring of gate slot
CN110438907B (en) Deck type arch bridge construction method based on steel arch frame
CN211142816U (en) Construction platform
CN108316119B (en) Steel construction overpass convenient to installation
CN220166651U (en) Unilateral steel trestle
CN220767752U (en) But full section construction of large-span overwater operation beam bottom is through-hole removal operation platform
CN115404786B (en) Pushing construction method for steel-concrete composite beam
CN217325044U (en) Cast-in-place crossbeam bracket of reassembling type
CN219637717U (en) Cable-stayed bridge cable guide pipe installation device
CN217652287U (en) Can have enough to meet need core section of thick bamboo well way operation platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201020

Termination date: 20210309