CN211693803U - Building pipeline auxiliary stay laying device - Google Patents

Building pipeline auxiliary stay laying device Download PDF

Info

Publication number
CN211693803U
CN211693803U CN202020175580.9U CN202020175580U CN211693803U CN 211693803 U CN211693803 U CN 211693803U CN 202020175580 U CN202020175580 U CN 202020175580U CN 211693803 U CN211693803 U CN 211693803U
Authority
CN
China
Prior art keywords
worm wheel
staple bolt
worm
building pipeline
laying device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020175580.9U
Other languages
Chinese (zh)
Inventor
王燕光
刘霁宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Wanderful Architectural Design And Consulting Co ltd
Original Assignee
Tianjin Wanderful Architectural Design And Consulting Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Wanderful Architectural Design And Consulting Co ltd filed Critical Tianjin Wanderful Architectural Design And Consulting Co ltd
Priority to CN202020175580.9U priority Critical patent/CN211693803U/en
Application granted granted Critical
Publication of CN211693803U publication Critical patent/CN211693803U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model relates to a building pipeline support equipment technical field discloses a building pipeline auxiliary stay laying device, comprising a base plate, the outer post, the transmission cavity, the worm wheel pivot, the hexagonal pole, the worm wheel, the worm, staple bolt mounting panel and staple bolt subassembly, the outer post welding is central in the bottom plate upper end, the transmission cavity sets up in the outer post upper end, worm wheel horizontal installation is in the transmission cavity, the both ends symmetry of worm wheel is provided with two worm wheel pivots, the outer end welding of one of them worm wheel pivot has rather than coaxial hexagonal pole, the hexagonal pole stretches out the outer post outside, the worm wheel pivot is rotatable to be installed in transmission cavity both sides, the worm cooperation is installed in the outer post, be connected through the worm wheel worm transmission between worm wheel and the worm, the staple bolt mounting panel is fixed at the worm top, the staple bolt subassembly passes through the bolt fastening in. The utility model discloses the support height of regulation building pipeline that can be convenient improves and supports the steadiness, and the part easy operation of device moreover dismantles the convenience.

Description

Building pipeline auxiliary stay laying device
Technical Field
The utility model relates to a building pipeline supports equipment technical field, especially relates to a building pipeline auxiliary stay laying device.
Background
When the floor of a high-rise building or a large-area basement is constructed, a ground pump is often used for being matched with a ground pump pipe to pour concrete, the ground pump pipe needs to be laid underground or on the ground when the concrete is poured, and the ground pump pipe is used as a concrete dredging pipeline after being connected. When the concrete ground pump pipe is laid, the concrete ground pump pipe is often required to be fixedly installed on a special support frame, so that the auxiliary support function of the concrete ground pump pipe can be fixed, and the pipeline can be protected. However, the height of the existing concrete pump pipe support frame cannot be adjusted when in use, wood boards or bricks are often needed to be laid for adjusting the height in use, so that the support of the concrete pump pipe is unstable, and the parts for fixedly mounting the concrete pump pipe are troublesome in design, inconvenient to assemble and disassemble, and inconvenient to replace and move the concrete pump pipe.
SUMMERY OF THE UTILITY MODEL
In order to overcome the defects of the prior art, the utility model aims to provide a building pipeline auxiliary stay laying device, the support height of regulation building pipeline that can be convenient improves and supports the steadiness, and the part easy operation of device moreover dismantles the convenience.
The utility model discloses a following technical scheme realizes: the utility model provides a building pipeline auxiliary stay laying device, includes bottom plate, outer post, transmission cavity, worm wheel pivot, hexagonal pole, worm wheel, worm, staple bolt mounting panel and staple bolt subassembly, the outer welding of post is central in the bottom plate upper end, the transmission cavity sets up in outer post upper end, worm wheel horizontal installation is in the transmission cavity, the both ends symmetry of worm wheel is provided with two worm wheel pivots, and the outer end welding of one of them worm wheel pivot has rather than coaxial hexagonal pole, and the hexagonal pole stretches out the outer post outside, the rotatable installation in transmission cavity both sides of worm wheel pivot, the worm passes through shaft hole clearance fit and installs in the outer post, be connected through the worm wheel worm transmission between worm wheel and the worm, the staple bolt mounting panel is fixed at the worm top, the staple bolt subassembly passes through the bolt fastening in staple bolt mounting panel upper end.
Further, the staple bolt subassembly includes staple bolt, last staple bolt, articulated piece, interior packing ring and connecting block down, the staple bolt passes through the bolt fastening in staple bolt mounting panel upper end down, the one end that staple bolt, last staple bolt correspond down respectively is provided with an articulated piece, and is articulated between two articulated pieces, the other end outside that staple bolt, last staple bolt correspond down respectively is provided with a connecting block, is connected through long double-screw bolt and bolt fit between two connecting blocks, the inboard of staple bolt and last staple bolt all is fixed with semicircular interior packing ring down.
Further, the bottom plate upper end is located the outer post outside symmetry and is provided with two and carries the ring.
Furthermore, a fastening column is installed on the side wall of the upper portion of the outer column in a threaded fit mode, friction threads are arranged on the front portion of the inner end of the fastening column, another hexagonal head rod coaxial with the fastening column is welded to the outer end of the fastening column, and the hexagonal head rod also extends out of the outer column.
Furthermore, four supporting blocks are symmetrically arranged on the outer edge of the lower end of the bottom plate.
Furthermore, a crank is detachably mounted on the outer side of the hexagonal head rod, an inner hexagonal slot matched with the hexagonal head rod is formed in the front end of the crank, and the inner hexagonal slot is connected with the hexagonal head rod in an inserting mode.
Compared with the prior art, the beneficial effects of the utility model reside in that: the building pipeline auxiliary stay laying device of design, it rotates to drive the worm wheel through outside drive equipment drive worm wheel pivot and rotates, through worm wheel and worm drive belt drive worm up-and-down motion between worm wheel and the worm, a lifting motion for driving staple bolt subassembly, install the crank on the hexagonal head pole in the worm wheel pivot outside, the front end of crank be provided with hexagonal head pole complex hexagon socket head, hexagon socket head pole pegs graft, rotate the lift that drives staple bolt subassembly through the crank, convenient to use, and easy operation, the support height of regulation building pipeline that can be convenient, improve and support the steadiness.
Drawings
FIG. 1 is a cross-sectional view of the auxiliary supporting and laying device for building pipelines of the present invention;
fig. 2 is a front view of the utility model of an auxiliary supporting and laying device for building pipelines.
In the figure: 3. a crank; 11. a base plate; 12. a support block; 13. a lifting ring; 14. an outer column; 15. a transmission cavity; 16. a worm gear shaft; 17. a hexagonal head rod; 18. a worm gear; 19. a worm; 110. fastening the column; 21. a hoop mounting plate; 22. a lower hoop; 23. an anchor ear is arranged; 24. a hinged block; 25. an inner gasket; 26. connecting blocks; 27. a long stud; 28. and (4) bolts.
Detailed Description
The present invention will be further described with reference to the accompanying drawings and the detailed description, and it should be noted that the embodiments or technical features described below can be arbitrarily combined to form a new embodiment without conflict.
As shown in fig. 1 and 2, a building pipeline auxiliary stay laying device, including bottom plate 11, outer post 14, transmission cavity 15, worm wheel pivot 16, hexagonal head pole 17, worm wheel 18, worm 19, staple bolt mounting panel 21 and staple bolt subassembly, outer post 14 welds at bottom plate 11 upper end central authorities, and bottom plate 11 upper end is located outer 14 outside symmetries of post and is provided with two handle rings 13, is used for removing the utility model discloses a building pipeline auxiliary stay laying device, bottom plate 11 lower extreme are provided with four supporting shoes 12 along the symmetry outward, and supporting shoe 12 uses the rubber support block commonly used among the prior art for vibration when slowing down the pump line fixedly. The transmission chamber 15 is arranged at the upper end of the outer column 14, the worm wheel 18 is horizontally arranged in the transmission chamber 15, two worm wheel rotating shafts 16 are symmetrically arranged at two ends of the worm wheel 18, a hexagonal head rod 17 which is coaxial with the worm wheel rotating shaft 16 is welded at the outer end of one worm wheel rotating shaft 16, the hexagonal head rod 17 extends out of the outer column 14, the worm wheel rotating shafts 16 are rotatably arranged at two sides of the transmission chamber 15, the worm 19 is arranged in the outer column 14 through shaft hole clearance fit, the worm wheel 18 and the worm 19 are in transmission connection through the worm wheel and the worm, the hoop mounting plate 21 is fixed at the top of the worm 19, the hoop component is fixed at the upper end of the hoop mounting plate 21 through bolts, when the building pipeline auxiliary support laying device is used, the worm wheel rotating shaft 16 is driven by external driving equipment to rotate to drive the worm wheel 18 to rotate, the worm wheel and the worm, in the use, installation crank 3 on the hexagonal head pole 17 in the worm wheel pivot 16 outside in this design, the front end of crank 3 be provided with hexagonal head pole 17 complex hexagon socket, the hexagon socket is pegged graft with hexagonal head pole 17, rotates the lift that drives the staple bolt subassembly through crank 3, and it is convenient to use, easy operation.
In order to improve the fixing effect on the worm 19, a fastening column 110 is installed on the side wall of the upper portion of the outer column 14 in a threaded fit mode, friction threads are arranged on the front portion of the inner end of the fastening column 110, another hexagonal head rod 17 coaxial with the fastening column 110 is welded to the outer end of the fastening column 110, the hexagonal head rod 17 also extends out of the outer column 14, the size of the hexagonal head rod 17 is the same as that of the hexagonal head rod 17 on the outer side of the worm wheel rotating shaft 16, the same crank 3 can be used for rotating, when the worm 19 is used, the fastening column 110 is adjusted to extend into the outer column 14, the worm 19 is fixed through the friction threads, and the fixing effect on the worm 19 is enhanced.
Staple bolt subassembly includes staple bolt 22 down, go up staple bolt 23, articulated piece 24, inner washer 25 and connecting block 26, staple bolt 22 passes through the bolt fastening in staple bolt mounting panel 21 upper end down, staple bolt 22 down, the one end that goes up staple bolt 23 and correspond respectively is provided with an articulated piece 24, it is articulated between two articulated pieces 24, staple bolt 22 down, the other end outside that goes up staple bolt 23 and correspond respectively is provided with a connecting block 26, be connected through long double-screw bolt 27 and bolt 28 cooperation between two connecting blocks 26, can be convenient through long double-screw bolt 27 and bolt 28 cooperation be connected and dismantle staple bolt 23 and staple bolt 22 down. A semicircular inner gasket 25 is fixed on the inner sides of the lower anchor ear 22 and the upper anchor ear 23, and the inner gasket 25 is a rubber gasket commonly used in the prior art and used for damping vibration when a pipeline is fixedly pumped.
Use the utility model discloses a during building pipeline auxiliary stay laying device, place concrete ground pump line under between staple bolt 22 and last staple bolt 23, through long double-screw bolt 27 and bolt 28 cooperation with concrete ground pump line fixed staple bolt subassembly within a definite time, according to the installation demand, it rotates and drives worm wheel 18 and rotate to drive worm wheel pivot 16 through crank 3, drive worm 19 up-and-down motion through the worm wheel worm gear transmission between worm wheel 18 and the worm 19, a lifting motion for driving the staple bolt subassembly, convenient regulation building pipeline's support height, improve the support steadiness.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (6)

1. The utility model provides a building pipeline auxiliary stay laying device which characterized in that: including bottom plate (11), outer post (14), transmission cavity (15), worm wheel pivot (16), hexagonal head pole (17), worm wheel (18), worm (19), staple bolt mounting panel (21) and staple bolt subassembly, outer post (14) welding is central in bottom plate (11) upper end, transmission cavity (15) set up in outer post (14) upper end, worm wheel (18) horizontal installation is in transmission cavity (15), the both ends symmetry of worm wheel (18) is provided with two worm wheel pivots (16), the outer end welding of one of them worm wheel pivot (16) has hexagonal head pole (17) rather than coaxial, and hexagonal head pole (17) stretch out the outer post (14) outside, rotatable the installing in transmission cavity (15) both sides of worm wheel pivot (16), worm (19) are installed in outer post (14) through shaft hole clearance fit, be connected through worm wheel transmission between worm wheel (18) and worm (19), staple bolt mounting panel (21) are fixed at worm (19) top, the staple bolt subassembly passes through the bolt fastening in staple bolt mounting panel (21) upper end.
2. The building pipeline auxiliary support laying device according to claim 1, wherein: staple bolt subassembly includes staple bolt (22) down, goes up staple bolt (23), articulated piece (24), interior packing ring (25) and connecting block (26), staple bolt (22) passes through the bolt fastening in staple bolt mounting panel (21) upper end down, staple bolt (22), the one end that goes up staple bolt (23) and correspond respectively are provided with an articulated piece (24) down, and it is articulated between two articulated pieces (24), the other end outside that staple bolt (22), last staple bolt (23) correspond respectively is provided with a connecting block (26) down, is connected through long double-screw bolt (27) and bolt (28) cooperation between two connecting blocks (26), staple bolt (22) and the inboard of last staple bolt (23) all are fixed with semicircular interior packing ring (25) down.
3. The building pipeline auxiliary support laying device according to claim 1 or 2, wherein: the upper end of the bottom plate (11) is symmetrically provided with two lifting rings (13) outside the outer column (14).
4. The building pipeline auxiliary support laying device of claim 3, wherein: the upper side wall of the outer column (14) is provided with a fastening column (110) in a threaded fit mode, the front portion of the inner end of the fastening column (110) is provided with a friction thread, the outer end of the fastening column (110) is welded with another hexagonal head rod (17) coaxial with the fastening column, and the hexagonal head rod (17) also extends out of the outer column (14).
5. The building pipeline auxiliary support laying device of claim 4, wherein: the outer edge of the lower end of the bottom plate (11) is symmetrically provided with four supporting blocks (12).
6. The building pipeline auxiliary support laying device of claim 4, wherein: the outer side of the hexagonal head rod (17) is detachably provided with the crank (3), the front end of the crank (3) is provided with an inner hexagonal slot matched with the hexagonal head rod (17), and the inner hexagonal slot is inserted into the hexagonal head rod (17).
CN202020175580.9U 2020-02-17 2020-02-17 Building pipeline auxiliary stay laying device Expired - Fee Related CN211693803U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020175580.9U CN211693803U (en) 2020-02-17 2020-02-17 Building pipeline auxiliary stay laying device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020175580.9U CN211693803U (en) 2020-02-17 2020-02-17 Building pipeline auxiliary stay laying device

Publications (1)

Publication Number Publication Date
CN211693803U true CN211693803U (en) 2020-10-16

Family

ID=72775531

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020175580.9U Expired - Fee Related CN211693803U (en) 2020-02-17 2020-02-17 Building pipeline auxiliary stay laying device

Country Status (1)

Country Link
CN (1) CN211693803U (en)

Similar Documents

Publication Publication Date Title
CN211058020U (en) Connecting device for building external hanging and building main body
CN211693803U (en) Building pipeline auxiliary stay laying device
CN101078202A (en) Integral sealing electric obstructing instrument
CN214303019U (en) Assembled building truss supporting structure
CN214958479U (en) Cable testing bridge trailing arm convenient to installation
CN215763642U (en) Pipeline positioning support frame with pipe hole diameter adjustable structure for drainage engineering
CN110759255B (en) Lifting frame convenient to disassemble and assemble for building construction
CN211091410U (en) Mariculture anticorrosion constant temperature unit
CN210193258U (en) Stable, high-efficiency and high-quality wall-attached device
CN213774603U (en) Building engineering is with consolidating strutting arrangement convenient to installation
CN220766342U (en) Winch slewing mechanism
CN216157105U (en) Mounting bracket is used in civil engineering construction
CN218912353U (en) Reinforcing device for building construction
CN221031538U (en) Installation reinforcing apparatus of steel construction built-in fitting
CN210577546U (en) Rotary supporting arm for cable bridge
CN213674623U (en) Prefabricated component production is with pouring device convenient to control roughness
CN220151377U (en) Anchor rod construction device
CN210536212U (en) Bracket arm for cable bridge and cable bridge with same
CN211078401U (en) Lifting device for construction
CN219410618U (en) Warning device for construction site
CN219136270U (en) Automatic lifting and installing device for pipeline support
CN220168762U (en) Concrete pump pipe fixing tool
CN216045803U (en) Height-adjustable pipeline hanger
CN213300311U (en) Air conditioner external unit convenient to install for air conditioner
CN215749876U (en) A rack for concrete curing room

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201016

Termination date: 20220217

CF01 Termination of patent right due to non-payment of annual fee