CN211655637U - Municipal works interlude cable special stand - Google Patents

Municipal works interlude cable special stand Download PDF

Info

Publication number
CN211655637U
CN211655637U CN202020579938.4U CN202020579938U CN211655637U CN 211655637 U CN211655637 U CN 211655637U CN 202020579938 U CN202020579938 U CN 202020579938U CN 211655637 U CN211655637 U CN 211655637U
Authority
CN
China
Prior art keywords
frame
screw rod
bolt
welded
triangle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020579938.4U
Other languages
Chinese (zh)
Inventor
齐月
邢烁
谢英杰
刘鸿福
尚鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Aihua Engineering Co ltd
Original Assignee
Qingdao Aihua Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Aihua Engineering Co ltd filed Critical Qingdao Aihua Engineering Co ltd
Priority to CN202020579938.4U priority Critical patent/CN211655637U/en
Application granted granted Critical
Publication of CN211655637U publication Critical patent/CN211655637U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)
  • Electric Cable Installation (AREA)

Abstract

The utility model relates to a municipal works technical field specifically discloses municipal works interlude cable special stand, which comprises a frame, the frame have threely, and three frame is triangle-shaped and arranges the equipment, the equal screw thread of triangle-shaped triangular wall body that the frame constitutes installs first screw rod, and two nuts are installed to the equal screw thread of the body of rod of first screw rod, and two nuts are located the inboard and the outside of triangle-shaped structure respectively, the first mounting bracket of U style of calligraphy is all welded to the one end of first screw rod. The utility model discloses a frame internal design's device can realize the regulation through first screw rod to adjust the distance of pinch roller, realize the cable of pinch roller adaptation different thickness, make device adaptability higher, the three pinch roller of design can play the effect of support moreover, and it is convenient to act as go-between when wearing to establish, reduces frictional force, and it is more convenient to use.

Description

Municipal works interlude cable special stand
Technical Field
The utility model relates to a municipal works technical field especially relates to municipal works interlude cable special stand.
Background
Installation cable engineering is many in the municipal works, and the installation is worn to establish through the cement pipeline to the cable moreover, but the problem that exists when alternating does not have good support exactly for the cable contacts with the wall body of cement pipeline, thereby causes the crust damaged, influences life-span and the safety of cable.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art, and providing a municipal engineering alternating cable special support.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
municipal works interlude cable special stand, including the frame, the frame have threely, and three frame is triangle-shaped and arranges the equipment, first screw rod is installed to the equal screw thread of triangle-shaped wall body that the frame constitutes, and two nuts are installed to the equal screw thread of the body of rod of first screw rod, the first mounting bracket of U style of calligraphy is all welded to the one end of first screw rod, rotates between the interior intraoral wall of first mounting bracket and installs the pinch roller, first bolt has all been welded at the three limit central point of the triangle-shaped structure that the frame constitutes, first support tube is installed to first bolt screw thread, and the second screw rod is installed to the one end screw thread of first support tube, and in the one end of second screw rod extended to first support tube, the one end welding of second screw rod.
Preferably, the first bolt is further matched with a second supporting pipe, and one end of the second supporting pipe is welded with the second bolt.
Preferably, the second bolt is matched with a third supporting pipe, a third screw is installed at one end of the third supporting pipe in a threaded mode, a U-shaped second mounting frame is welded at one end of the third screw, and a roller is installed at the opening of the second mounting frame in a rotating mode.
Preferably, the third supporting tube has the same structure as the first supporting tube and is matched with the first bolt.
Preferably, the nut is press-fitted to the frame.
Preferably, the frames are fixedly installed through bolts.
The utility model has the advantages that:
the device designed in the frame can adjust the distance of the pressing wheel through the first screw rod, so that the pressing wheel can adapt to cables with different thicknesses, the adaptability of the device is higher, the three designed pressing wheels can play a supporting role, and the wire drawing is convenient during the penetrating process, the friction force is reduced, and the use is more convenient;
the structure of frame outer design can adjustable length, thereby realize backup pad and pipeline inner wall contact, thereby reach strutting arrangement's effect, make the inner wall separation of cable and pipeline, but also adjustable, thereby the function is more perfect, and supporting gyro wheel, can realize that whole device can remove, thereby wear to establish the effect that the end of a thread extends in earlier stage, need not pull the cable at the pipeline other end with other equipment, be applicable to long straight pipeline.
Drawings
Fig. 1 is the utility model provides a municipal works interlude cable special stand's main visual structure schematic diagram.
Fig. 2 is a schematic view of a third support tube structure.
Fig. 3 is a schematic view of a second support tube structure.
The labels in the figure are: the roller mounting device comprises a frame 1, a first screw rod 2, a nut 3, a first mounting frame 4, a pressing wheel 5, a first supporting pipe 6, a second screw rod 7, a supporting plate 8, a first bolt 9, a second supporting pipe 10, a second bolt 11, a third supporting pipe 12, a third screw rod 13, a second mounting frame 14 and a roller 15.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-3, a municipal engineering interpenetration cable special support comprises three frames 1, wherein the three frames 1 are arranged and assembled in a triangular manner, the apexes of the triangles are of a flat plate type structure, as shown in fig. 1, the triangular wall bodies of the triangles formed by the frames 1 are all provided with a first screw rod 2 in a threaded manner, the length of the first screw rod 2 can be adjusted, the rod bodies of the first screw rod 2 are all provided with two screw caps 3 in a threaded manner, the two screw caps 3 are used for locking the first screw rod 2 after the length of the first screw rod 2 is adjusted, one end of the first screw rod 2 is welded with a U-shaped first mounting frame 4, the first mounting frame 4 is used for mounting a pinch roller 5, as shown in fig. 1, the pinch roller 5 is rotatably mounted between the inner walls of the first mounting frame 4, first bolts 9 are welded at the central parts of the three sides of the triangular structure formed by the frames 1, first bolt 9 threaded mounting has first support tube 6, and second screw 7 is installed to the one end screw thread of first support tube 6, and in the one end of second screw 7 extended to first support tube 6, the welding of the one end of second screw 7 has backup pad 8.
In this embodiment, the first bolt 9 is further provided with a second support tube 10, the second support tube 10 is designed to extend when the original length is not enough, so as to adapt to the large-diameter pipeline, as shown in fig. 3, a second bolt 11 is welded at one end of a second supporting pipe 10, the second bolt 11 is matched with a third supporting pipe 12, a third screw 13 is installed at one end of the third supporting pipe 12 in a threaded manner, a U-shaped second mounting frame 14 is welded at one end of the third screw 13, a roller 15 is rotatably installed at the mouth of the second mounting frame 14, the third supporting pipe 12 has the same structure as the first supporting pipe 6, and the third supporting pipe 12, the third screw 13, the second mounting frame 14 and the roller 15 are designed to be used for early-stage threading to extend the cable head, as shown in fig. 2 and matched with the first bolt 9, the nut 3 is installed with the frame 1 in a pressing way, and the frame 1 is fixedly installed through the bolt.
The working principle is as follows:
during the use, install the device as shown in fig. 1 to when first stay tube 6's length is not enough, can prolong through the mode of equipment second stay tube 10, thereby adapt to the pipeline of major diameter, when centre gripping cable, can be at the first overhead device in pipeline's both ends, when adjusting pinch roller 5, unscrew nut 3, make first screw rod 2 and frame 1 loosen, thereby the position has been adjusted, as shown in fig. 1, only need unscrew the bolt of one of them frame 1 during the installation cable, thereby guarantee that the cable can enter into in the frame 1 can.
The rollers 15 are configured to support the cable head by pushing a plurality of rollers 15 forward so that the lead head penetrates the other end of the pipeline in the earlier stage.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. Municipal works interlude cable special stand, including frame (1), its characterized in that, there is three frame (1), and three frame (1) is triangle-shaped and arranges the equipment, first screw rod (2) are installed to the equal screw thread of triangle-shaped wall body that frame (1) constitutes, and two nut (3) are installed to the equal screw thread of the body of rod of first screw rod (2), the first mounting bracket (4) of U style of calligraphy is all welded to the one end of first screw rod (2), rotates between the inner wall of the mouth of first mounting bracket (4) and installs pinch roller (5), first bolt (9) have all been welded at the three limit central point of the triangle-shaped structure that frame (1) constitutes, first support tube (6) is installed to first bolt (9) screw thread, and second screw rod (7) are installed to the one end screw thread of first support tube (6), and the one end of second screw rod (7) extends to in first support tube (6), one end of the second screw rod (7) is welded with a support plate (8).
2. The bracket special for the municipal engineering inserting cable according to claim 1, wherein the first bolt (9) is further matched with a second support pipe (10), and a second bolt (11) is welded at one end of the second support pipe (10).
3. The municipal engineering penetrating cable special support according to claim 2, wherein the second bolt (11) is matched with a third supporting pipe (12), a third screw (13) is installed at one end of the third supporting pipe (12) in a threaded mode, a U-shaped second mounting frame (14) is welded at one end of the third screw (13), and a roller (15) is rotatably installed at the opening portion of the second mounting frame (14).
4. The civil engineering penetrating cable special bracket according to claim 3, wherein the third supporting pipe (12) is the same structure as the first supporting pipe (6) and is matched with the first bolt (9).
5. The civil engineering penetrating cable special bracket according to claim 1, wherein the two nuts (3) are respectively positioned at the inner side and the outer side of the triangular structure.
6. The support special for the municipal engineering inserted cables according to claim 1, wherein the frames (1) are connected in an end-to-end manner, and the frames (1) are in an L-shaped structure in the end-to-end manner.
CN202020579938.4U 2020-04-17 2020-04-17 Municipal works interlude cable special stand Expired - Fee Related CN211655637U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020579938.4U CN211655637U (en) 2020-04-17 2020-04-17 Municipal works interlude cable special stand

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020579938.4U CN211655637U (en) 2020-04-17 2020-04-17 Municipal works interlude cable special stand

Publications (1)

Publication Number Publication Date
CN211655637U true CN211655637U (en) 2020-10-09

Family

ID=72689054

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020579938.4U Expired - Fee Related CN211655637U (en) 2020-04-17 2020-04-17 Municipal works interlude cable special stand

Country Status (1)

Country Link
CN (1) CN211655637U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113036669A (en) * 2021-04-07 2021-06-25 河南朗冠建筑工程有限公司 Line auxiliary stand for municipal road engineering

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113036669A (en) * 2021-04-07 2021-06-25 河南朗冠建筑工程有限公司 Line auxiliary stand for municipal road engineering
CN113036669B (en) * 2021-04-07 2022-05-17 河南朗冠建筑工程有限公司 Line auxiliary stand for municipal road engineering

Similar Documents

Publication Publication Date Title
CN211655637U (en) Municipal works interlude cable special stand
CN111600259A (en) Bypass cable temporary connection cross arm for iron tower
CN106451241A (en) Auxiliary device for replacing cable in threading pipe and cable replacement method
CN219498744U (en) Overhead wire-stringing device
CN218888065U (en) Cable laying protection device for power maintenance
CN110303290B (en) Be used for BOSS head welded special fixture
CN214946985U (en) Phosphogypsum composite HDPE three-layer co-extrusion drainage pipe
CN217129578U (en) Detection apparatus for be used for colliery ventilation blower wind pressure
CN210134934U (en) Protection device for underground pipeline during shield tunneling
CN210912390U (en) Parking braking stay wire assembly structure
CN200946470Y (en) Single conical surface anchor hanger
CN210404561U (en) Tightener for electric power engineering cable installation
CN207521499U (en) A kind of auxiliary device of steel pipe automatic grooving process equipment
CN218449173U (en) Combined tool for enabling ground wire to enter equipotential overhead ground wire through runaway
CN218335029U (en) Tightener with wire protection function for power transmission line
CN219119613U (en) Anti-skid and wear-resistant flexible stud bolt
CN218786947U (en) Novel upright column protective layer thickness control device
CN212304659U (en) Bypass cable temporary connection cross arm for iron tower
CN211624568U (en) Special stiffening component for vertical pull rod mechanism of anti-seismic support and hanger
CN219779663U (en) Vertical shaft steel wire rope suspension cable clamp
CN215061051U (en) Steel member detection device that detects a flaw
CN216598832U (en) Adjustable cable fixing support
CN220209812U (en) Self-adaptive device suitable for directly laying high-voltage cable on support
CN216265560U (en) V-shaped clamping device for environment-friendly building anti-seismic support
CN215321847U (en) Automobile swing arm bushing convenient to splice and use

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201009