CN211646741U - Building engineering concrete prefabricated component convenient to operation - Google Patents

Building engineering concrete prefabricated component convenient to operation Download PDF

Info

Publication number
CN211646741U
CN211646741U CN201921688738.6U CN201921688738U CN211646741U CN 211646741 U CN211646741 U CN 211646741U CN 201921688738 U CN201921688738 U CN 201921688738U CN 211646741 U CN211646741 U CN 211646741U
Authority
CN
China
Prior art keywords
prefabricated component
prefabricated
main part
component main
splice
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921688738.6U
Other languages
Chinese (zh)
Inventor
翁奕鸿
翁奕加
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foshan Jiannengtong Construction Engineering Co ltd
Original Assignee
Foshan Jiannengtong Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Foshan Jiannengtong Construction Engineering Co ltd filed Critical Foshan Jiannengtong Construction Engineering Co ltd
Priority to CN201921688738.6U priority Critical patent/CN211646741U/en
Application granted granted Critical
Publication of CN211646741U publication Critical patent/CN211646741U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model relates to a building engineering technical field just discloses a building engineering concrete prefabricated component convenient to operation, including the prefabricated component main part, a plurality of prefabricated holes have been seted up to the lateral wall of prefabricated component main part upside, a plurality of concatenation blocks of lateral wall fixedly connected with on prefabricated component main part right side, a plurality of and the corresponding splice groove of concatenation block have been seted up to the left lateral wall of prefabricated component main part, and are a plurality of the equal fixedly connected with intubate of pore wall that the prefabricated hole is close to the upper end, the prefabricated hole is stretched out to the upper end of intubate. The utility model provides the high convenience of operation is assembled to prefabricated component, the effectual construction speed that has improved.

Description

Building engineering concrete prefabricated component convenient to operation
Technical Field
The utility model relates to a building engineering technical field especially relates to a building engineering concrete prefabricated component convenient to operation.
Background
The precast concrete member is a building material commonly used in construction engineering, is a concrete member supported in advance in a factory or a construction site according to design specifications, and can be directly used in construction.
The existing concrete prefabricated parts need to be spliced together with a plurality of prefabricated parts when in use, but when the existing concrete prefabricated parts are spliced, two adjacent concrete prefabricated parts need to be aligned through manual observation, so that the installation and operation of the concrete prefabricated parts are inconvenient, and the construction speed is reduced.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the problem that two concrete prefabricated components concatenation operations are comparatively inconvenient among the prior art, and the building engineering concrete prefabricated component convenient to operation that provides.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a building engineering concrete prefabricated component convenient to operation, includes the prefabricated component main part, a plurality of prefabricated holes have been seted up to the lateral wall of prefabricated component main part upside, a plurality of splice blocks of lateral wall fixedly connected with on prefabricated component main part right side, a plurality of splice grooves corresponding with the splice block have been seted up to the left lateral wall of prefabricated component main part, and is a plurality of the equal fixedly connected with intubate of pore wall that the prefabricated hole is close to the upper end, the prefabricated hole is stretched out to the upper end of intubate.
Preferably, two steel bars are inserted between the splicing blocks and the prefabricated part main body.
Preferably, the specific material of the cannula is stainless steel.
Preferably, the splicing blocks are integrally formed with the prefabricated component body.
Compared with the prior art, the utility model provides a building engineering concrete prefabricated component convenient to operation possesses following beneficial effect:
this building engineering concrete prefabricated component convenient to operation, through the prefabricated component main part that sets up, the prefabricated hole, the splice piece, splice groove and intubate, when splicing two prefabricated components, be close to the splice groove in another prefabricated component main part with the splice piece in the prefabricated component main part, promote two prefabricated component main parts, make a plurality of splice pieces insert in the splice groove that corresponds, mutually support through a plurality of splice pieces and a plurality of splice grooves, can make two prefabricated components closely laminate, the intubate can insert in the prefabricated hole of another prefabricated component, make four faces of prefabricated component all be convenient for assemble, the convenience of prefabricated component assembly operation has been improved, the effectual construction speed that has improved.
The part that does not relate to in the device all is the same with prior art or can adopt prior art to realize, the utility model provides the high convenience of prefabricated component assembly operation, the effectual construction speed that has improved.
Drawings
Fig. 1 is a schematic structural view of a construction engineering concrete prefabricated part convenient to operate according to the present invention;
fig. 2 is a schematic structural view of a portion a in fig. 1.
In the figure: the prefabricated steel pipe comprises a prefabricated part main body 1, prefabricated holes 2, splicing blocks 3, splicing grooves 4, insertion pipes 5 and reinforcing steel bars 6.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
In the description of the present invention, it is to be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
Referring to fig. 1-2, a building engineering concrete prefabricated component convenient to operation, includes prefabricated component main part 1, and a plurality of prefabricated holes 2 have been seted up to the lateral wall of prefabricated component main part 1 upside, and a plurality of splice blocks 3 of lateral wall fixedly connected with on prefabricated component main part 1 right side, and a plurality of splice grooves 4 corresponding with splice blocks 3 have been seted up to the left lateral wall of prefabricated component main part 1, and the equal fixedly connected with intubate 5 of pore wall that a plurality of prefabricated holes 2 are close to the upper end, and prefabricated hole 2 is stretched out to the upper end of intubate 5.
Two reinforcing steel bars 6 are inserted between the splicing blocks 3 and the prefabricated component main body 1, so that the connection stability of the splicing blocks 3 and the prefabricated component main body 1 is improved.
The specific material of intubate 5 is stainless steel, improves the rust-resistant performance of intubate 5.
The splicing blocks 3 are integrally formed with the prefabricated component main body 1, so that the prefabricated component is convenient to manufacture.
The utility model discloses in, when splicing two prefabricated components, splice 3 on the prefabricated component main part 1 and be close to the splice groove on another prefabricated component main part 1, promote two prefabricated component main parts 1, make during a plurality of splice blocks 3 insert the splice groove 4 that corresponds, mutually support through a plurality of splice blocks 3 and a plurality of splice grooves 4, can make two prefabricated components closely laminate, intubate 5 can insert in the prefabricated hole 2 of another prefabricated component, make four faces of prefabricated component all be convenient for assemble, the convenience of the operation is assembled to the prefabricated component has been improved, the effectual construction speed that has improved.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (4)

1. The utility model provides a building engineering concrete prefabricated component convenient to operation, includes prefabricated component main part (1), its characterized in that, a plurality of prefabricated holes (2) have been seted up to the lateral wall of prefabricated component main part (1) upside, a plurality of splice pieces of lateral wall fixedly connected with (3) on prefabricated component main part (1) right side, a plurality of splice groove (4) corresponding with splice piece (3) have been seted up to the left lateral wall of prefabricated component main part (1), and is a plurality of equal fixedly connected with intubate (5) of pore wall that prefabricated hole (2) are close to the upper end, prefabricated hole (2) are stretched out to the upper end of intubate (5).
2. An easy-to-handle precast concrete unit for construction engineering according to claim 1, characterized in that two reinforcing bars (6) are inserted between the splicing blocks (3) and the precast unit body (1).
3. An easy-to-handle precast concrete unit for construction engineering according to claim 1, characterized in that the specific material of the insertion pipe (5) is stainless steel.
4. An easy-to-handle precast concrete unit for construction engineering according to claim 1, characterized in that the splice block (3) is integrally formed with the precast unit body (1).
CN201921688738.6U 2019-10-10 2019-10-10 Building engineering concrete prefabricated component convenient to operation Expired - Fee Related CN211646741U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921688738.6U CN211646741U (en) 2019-10-10 2019-10-10 Building engineering concrete prefabricated component convenient to operation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921688738.6U CN211646741U (en) 2019-10-10 2019-10-10 Building engineering concrete prefabricated component convenient to operation

Publications (1)

Publication Number Publication Date
CN211646741U true CN211646741U (en) 2020-10-09

Family

ID=72680881

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921688738.6U Expired - Fee Related CN211646741U (en) 2019-10-10 2019-10-10 Building engineering concrete prefabricated component convenient to operation

Country Status (1)

Country Link
CN (1) CN211646741U (en)

Similar Documents

Publication Publication Date Title
CN211143504U (en) Reinforcing steel bar connecting assembly
CN211646741U (en) Building engineering concrete prefabricated component convenient to operation
CN213927101U (en) Novel connector for connecting concrete frame beam and steel bar at node of strength column
CN210421512U (en) Positioning, mounting and connecting structure of PC prefabricated wall board
CN203613562U (en) Flexible joint for underground continuous wall
CN201202200Y (en) Anti-seismic brick
CN211691486U (en) Novel telescopic connecting piece for steel back ribs
CN201588401U (en) Improved construction template
CN213297157U (en) Stupefied right angle connecting piece of back of body
JPH0110538Y2 (en)
CN209742232U (en) Grout sleeve for assembly type building construction
CN210361814U (en) Prefabricated coincide board mould of building PC with thick liquid mechanism is leaked in side direction
KR101277066B1 (en) Connector for assembly structure
CN212897596U (en) Novel back ridge connecting assembly and template assembly thereof
CN112127551A (en) Novel connector for connecting reinforcing steel bars at joints of super high-rise concrete frame beams and strength columns
CN211499468U (en) Steel structure support column for building
CN221399473U (en) Assembled building structure
CN216108945U (en) Bridge cut-off connecting piece, board component of encorbelmenting and mounting structure of board of encorbelmenting
CN209800943U (en) Four-way joint for drain board
CN213952602U (en) Assembled wall for house building construction
CN212897549U (en) Template support frame connecting piece and template support device
CN209837471U (en) Special-shaped steel pipe concrete combined column
CN214195088U (en) Four-side mortise module for assembled wall
CN220058369U (en) Paying-off hole plugging device
CN214658132U (en) Building structure floor reinforcing structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201009

Termination date: 20211010

CF01 Termination of patent right due to non-payment of annual fee