CN211639751U - Device for replacing grinding stone of steel rail grinding wagon - Google Patents

Device for replacing grinding stone of steel rail grinding wagon Download PDF

Info

Publication number
CN211639751U
CN211639751U CN202020177063.5U CN202020177063U CN211639751U CN 211639751 U CN211639751 U CN 211639751U CN 202020177063 U CN202020177063 U CN 202020177063U CN 211639751 U CN211639751 U CN 211639751U
Authority
CN
China
Prior art keywords
platform
grindstone
base
rail grinding
grinding wagon
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020177063.5U
Other languages
Chinese (zh)
Inventor
陈辉
万壮
胡传
陈诚
曾宗刚
梁阳
周兴龙
胡江
邹浪平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Metro Operation Co ltd
Original Assignee
Chengdu Metro Operation Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Metro Operation Co ltd filed Critical Chengdu Metro Operation Co ltd
Priority to CN202020177063.5U priority Critical patent/CN211639751U/en
Application granted granted Critical
Publication of CN211639751U publication Critical patent/CN211639751U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Grinding Of Cylindrical And Plane Surfaces (AREA)

Abstract

The utility model belongs to the technical field of the rail maintenance equipment and specifically relates to a swift, safe rail grinding wagon grindstone of realization rail grinding wagon grindstone change operation changes device, include base, lift platform, set up in the rotary platform and the elevating system of lift platform top surface, lift platform passes through elevating system and is connected with the base, and wherein, lift platform place plane remains parallel with base place plane throughout. The utility model discloses structural design retrencies, thinks about ingeniously, fine realization the change of grindstone, improved actual operation's security and operating efficiency greatly. The utility model discloses be particularly useful for among the grindstone change that subway rail repair equipment is the representative.

Description

Device for replacing grinding stone of steel rail grinding wagon
Technical Field
The utility model belongs to the technical field of rail maintenance equipment and specifically relates to a device is changed to rail grinding wagon grindstone.
Background
At present, the replacement of the grinding stone of the subway steel rail grinding wagon adopts bare-handed operation, and no auxiliary tool except a chain wrench is provided. The grinding stone replacement operation space is limited, the distance between the grinding stone mounting screw at the top and the ground is only 130mm, when an operator replaces the grinding stone, the sight cannot reach the grinding head mounting screw (shielded by equipment), therefore, the grinding stone threaded hole can be aligned to the grinding head mounting screw by frequently trying for many times, and the operation efficiency is extremely low. In addition, the grinding stone is lifted by hands for multiple times to be aligned with the hole, the arm is weak, the grinding stone is likely to slide down to injure fingers or other accidents, and the safety risk is high. Therefore, the current approach mainly forms the following technical drawbacks: firstly, a special grindstone replacing tool is not used, and the operation difficulty is high; secondly, the grindstone is lifted manually, so that the safety risk is high; thirdly, the hole positions can be aligned only by repeating the steps, and the operation efficiency is low. At present, no corresponding equipment capable of well solving the technical problems is available.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the technical problem that a swift, safe rail grinding wagon grindstone of realization rail grinding wagon grindstone is changed operation and is changed device is provided.
The utility model provides a technical scheme that its technical problem adopted is: the device for replacing the grinding stones of the steel rail grinding wagon comprises a base, a lifting platform, a rotary platform and a lifting mechanism, wherein the rotary platform and the lifting mechanism are arranged on the top surface of the lifting platform, the lifting platform is connected with the base through the lifting mechanism, and the plane where the lifting platform is located is always parallel to the plane where the base is located.
Further, the method comprises the following steps: the lifting platform is provided with a platform rotating shaft, and a bearing is arranged between the rotating platform and the platform rotating shaft.
Further, the method comprises the following steps: and a positioning boss is arranged at the geometric center of the rotating platform.
Further, the method comprises the following steps: the bearing is arranged below the positioning boss.
Further, the method comprises the following steps: the lifting mechanism is composed of a pair of lifting rods, wherein each lifting rod comprises two supporting rods and a connecting rod connected with the two supporting rods, the free ends of the supporting rods are hinged to the bottom surface of the lifting platform, and the connecting rods are rotatably arranged on the base through shaft seats.
Further, the method comprises the following steps: the connecting rod is provided with a lever handle connecting end, and the lever handle connecting end is sleeved with a handle.
Further, the method comprises the following steps: the periphery of the connecting end of the lever handle is provided with threads, and a threaded connection structure is arranged between the connecting end of the lever handle and the handle.
Further, the method comprises the following steps: the base is provided with a handle.
Further, the method comprises the following steps: the outer edge of the base is provided with a bending structure.
Further, the method comprises the following steps: and the top surface of the base is provided with a positioning reference layer along the direction of the central axis.
The utility model has the advantages that: in practical use, firstly, the lifting mechanism is in a compressed state, the base and the lifting platform are tightly attached at the moment, and the new grinding stone is arranged on the rotating platform. And then, the base is placed below the position where the grinding stone needs to be installed, and the lifting mechanism is driven to lift the lifting platform and the rotating platform upwards until the grinding stone realizes accurate positioning of the installation position. Finally, the rotary platform is rotated, the grinding stone on the rotary platform also rotates along with the rotary platform, and the grinding stone is arranged at the working position of the rotary platform in the rotating process, so that the grinding stone is smoothly replaced. The utility model discloses structural design retrencies, thinks about ingeniously, fine realization the change of grindstone, improved actual operation's security and operating efficiency greatly. The utility model discloses be particularly useful for among the grindstone change that subway rail repair equipment is the representative.
Drawings
Fig. 1 is a schematic structural view of the lifting platform of the present invention during lifting.
Fig. 2 is a schematic structural view of the lifting platform of the present invention after it is lowered.
Fig. 3 is a schematic structural view of the lifting rod of the present invention.
Fig. 4 is a schematic diagram of the internal structure of the lifting platform and the rotating platform of the present invention.
Fig. 5 is a schematic structural diagram of the base of the present invention.
Labeled as: the lifting platform comprises a base, a handle 11, a positioning reference layer 12, a bending structure 13, a lifting mechanism 2, a shaft seat 21, a handle 22, a lever handle connecting end 23, a supporting rod 24, a connecting rod 25, a lifting platform 3, a rotating platform 4, a positioning boss 41, a bearing 42 and a platform rotating shaft 43.
Detailed Description
The present invention will be further explained with reference to the accompanying drawings.
The device for replacing the grinding stone of the steel rail grinding wagon shown in fig. 1 to 5 comprises a base 1, a lifting platform 3, a rotating platform 4 arranged on the top surface of the lifting platform 3 and a lifting mechanism 2, wherein the lifting platform 3 is connected with the base 1 through the lifting mechanism 2, and the plane where the lifting platform 3 is located is always parallel to the plane where the base 1 is located.
A rail grinding wagon is mainly used for grinding railway rails to eliminate defects such as corrugation, flash, fine cracks on the surface, decarburized layers and the like, and can also be used for repairing the profile of the rails. The grinding stone is a tool used by the rail grinding wagon for grinding the rail, belongs to a consumable product and is similar to a grinding wheel of a grinding machine. The utility model discloses when in-service use, only need set up the grindstone on rotary platform 4 at first, drive 3 parallel lifting of lift platform and realize the accurate location of grindstone afterwards, rotate rotary platform 4 at last and let the grindstone on rotary platform 4 follow the installation that rotates and realize the grindstone. The general grindstone is provided with threads for rotary installation, so that convenient and efficient installation is realized. Because the rotary platform can rotate 360 degrees, the labor intensity of the installation of the grinding stone is greatly reduced.
In order to realize the simplification of the structure on the premise of ensuring the corresponding functions, the following scheme can be selected: the lifting platform 3 is provided with a platform rotating shaft 43, and a bearing 42 is arranged between the rotating platform 4 and the platform rotating shaft 43. As shown in fig. 4, the rotating platform 4 has a bearing 42, so that convenient rotation can be realized, and the installation of the grinding stone is convenient. In general, deep groove ball bearings are preferred for the bearings 42.
In order to realize more accurate positioning of the grinding stone and prevent the grinding stone from sliding off the platform, the following scheme can be selected: a positioning boss 41 is arranged at the geometric center of the rotating platform 4. As shown in fig. 1, 2 and 4, a cavity is provided at the center of the general grinding stone to be matched with the positioning boss 41, and the cavity at the center of the grinding stone can also be provided with a mounting thread, so that the assembly of the boundary during rotation is realized. For the purpose of optimizing the structural arrangement, it is preferable that the bearing 42 is disposed below the positioning boss 41, thereby making the structure more compact.
In order to further simplify the structure of the lifting mechanism 2, the following options may be selected: the lifting mechanism 2 is composed of a pair of lifting rods, wherein each lifting rod comprises two support rods 24 and a connecting rod 25 connected with the two support rods 24, the free ends of the support rods 24 are hinged with the bottom surface of the lifting platform 3, and the connecting rods 25 are rotatably arranged on the base 1 through a shaft seat 21. As shown in fig. 1, 2 and 3, the lifting mechanism 2 is formed by a pair of lifting rods, each of which includes two support rods 24 and a connecting rod 25 connecting the two support rods 24, and the two support rods 24 and the connecting rod 25 form a "U" shaped structure. The supporting rod 24, the lifting platform 3 and the base 1 form a parallel lifting structure, so that the plane where the lifting platform 3 is located is always kept parallel to the plane where the base 1 is located.
On the basis of the structure, in order to realize convenient and easy lifting and descending by utilizing a lever principle, the following scheme can be selected: the connecting rod 25 is provided with a lever handle connecting end 23, and the lever handle connecting end 23 is sleeved with a handle 22. As shown in fig. 1 and 2, the lifting platform 3 can be easily lifted or lowered by rotating the handle 22, so that the whole process is more labor-saving and safer. In order to realize the detachable connection between the handle 22 and the lever handle connecting end 23, a thread may be optionally arranged on the periphery of the lever handle connecting end 23, and a thread connection structure is arranged between the lever handle connecting end 23 and the handle 22.
In addition, in order to facilitate the movement of the base 1, such a scheme may be selected: the base 1 is provided with a handle 11. In actual operation, the position of the grinding stone can be accurately adjusted only through the handle 11. In order to provide the base 1 with stronger structural strength, a bending structure 13 may be optionally arranged on the outer edge of the base 1. The outer edge of the base 1 is turned outwards to form a bending structure 13, so that a stronger structure is formed, and the integral strength of the base 1 is ensured. In order to realize accurate positioning of the grinding stone, a positioning reference layer 12 is preferably arranged on the top surface of the base 1 along the central axis direction. As shown in fig. 1, the additional positioning reference layer 12 may be an attached positioning layer or a groove, and only needs to be ensured to be in the direction of the central axis of the base 1.
The utility model discloses structural design is ingenious, retrench, and the installation that reduces current grindstone that can be fine is torn open and is traded the degree of difficulty, guarantees that production operation safety, efficient go on, and market promotion prospect is very wide.

Claims (10)

1. Rail grinding wagon grindstone changes device, its characterized in that: including base (1), lift platform (3), set up in rotary platform (4) and elevating system (2) of lift platform (3) top surface, lift platform (3) are connected with base (1) through elevating system (2), and wherein, lift platform (3) place plane remains parallel with base (1) place plane all the time.
2. A rail grinding wagon grindstone replacing apparatus according to claim 1, characterized in that: the lifting platform (3) is provided with a platform rotating shaft (43), and a bearing (42) is arranged between the rotating platform (4) and the platform rotating shaft (43).
3. A rail grinding wagon grindstone replacing apparatus according to claim 2, characterized in that: and a positioning boss (41) is arranged at the geometric center of the rotating platform (4).
4. A rail grinding wagon grindstone replacing apparatus according to claim 3, characterized in that: the bearing (42) is arranged below the positioning boss (41).
5. A rail grinding wagon stone changer as defined in claim 1, 2, 3 or 4, wherein: the lifting mechanism (2) is composed of a pair of lifting rods, wherein each lifting rod comprises two supporting rods (24) and a connecting rod (25) connected with the two supporting rods (24), the free ends of the supporting rods (24) are hinged to the bottom surface of the lifting platform (3), and the connecting rods (25) are rotatably arranged on the base (1) through shaft seats (21).
6. A rail grinding wagon grindstone replacing apparatus as defined in claim 5, wherein: the connecting rod (25) is provided with a lever handle connecting end (23), and the lever handle connecting end (23) is sleeved with a handle (22).
7. A rail grinding wagon grindstone replacing apparatus as defined in claim 6, wherein: the periphery of the lever handle connecting end (23) is provided with threads, and a threaded connection structure is arranged between the lever handle connecting end (23) and the handle (22).
8. A rail grinding wagon stone changer as defined in claim 1, 2, 3 or 4, wherein: the base (1) is provided with a handle (11).
9. A rail grinding wagon stone changer as defined in claim 1, 2, 3 or 4, wherein: the outer edge of the base (1) is provided with a bending structure (13).
10. A rail grinding wagon stone changer as defined in claim 1, 2, 3 or 4, wherein: the top surface of the base (1) is provided with a positioning reference layer (12) along the direction of the central axis.
CN202020177063.5U 2020-02-17 2020-02-17 Device for replacing grinding stone of steel rail grinding wagon Active CN211639751U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020177063.5U CN211639751U (en) 2020-02-17 2020-02-17 Device for replacing grinding stone of steel rail grinding wagon

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020177063.5U CN211639751U (en) 2020-02-17 2020-02-17 Device for replacing grinding stone of steel rail grinding wagon

Publications (1)

Publication Number Publication Date
CN211639751U true CN211639751U (en) 2020-10-09

Family

ID=72686355

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020177063.5U Active CN211639751U (en) 2020-02-17 2020-02-17 Device for replacing grinding stone of steel rail grinding wagon

Country Status (1)

Country Link
CN (1) CN211639751U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113478213A (en) * 2021-06-02 2021-10-08 西安理工大学 Automatic radial dismouting device of rail grinding wagon grindstone

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113478213A (en) * 2021-06-02 2021-10-08 西安理工大学 Automatic radial dismouting device of rail grinding wagon grindstone
CN113478213B (en) * 2021-06-02 2022-06-07 西安理工大学 Automatic radial dismouting device of rail grinding wagon grindstone

Similar Documents

Publication Publication Date Title
CN206662951U (en) A kind of efficient automobile metal plate arc polissoir
CN211639751U (en) Device for replacing grinding stone of steel rail grinding wagon
CN108792610A (en) A kind of grasping mechanism of special-shaped workpiece
CN112048951A (en) Sleeper replacing device for railway track traffic
CN112340266A (en) Assembling device and assembling method for tank body swash plate
CN210173203U (en) Automatic burr scraping device for rubber tire
CN208897109U (en) A kind of crane accessory handling device
CN103273403B (en) A kind of glass scratch repair machine
CN211387227U (en) Rotary workbench for gear blank machining
CN209078693U (en) A kind of aluminum profile extrusion die workbench
CN111926637A (en) Railway switch polishing trolley
CN216422065U (en) Wine bottle frosting treatment equipment
CN203284325U (en) Glass scratch restoring machine
CN212769619U (en) Lifting device for electromechanical device maintenance
CN210648501U (en) Rotary kiln tyre turning and repairing device
CN210766217U (en) Steel rail internal combustion copying grinding machine with high repairing precision
CN209635801U (en) A kind of shipping yard lifting transfer car(buggy)
CN221235156U (en) Composite spinning assembly loading device
CN207552881U (en) A kind of cement box beam road surface grinder
CN207140400U (en) A kind of tire sander
CN217143490U (en) Novel deruster for oxygen cylinder
CN220943960U (en) Quick repairing, loading and unloading structure for crown block wheels
CN218225933U (en) Grinding machine is used in auto-parts processing
CN212335672U (en) Railway switch polishing trolley
CN220432205U (en) Power equipment hoisting device for power engineering construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant