CN211622523U - A construction platform for the facade of steel beams - Google Patents

A construction platform for the facade of steel beams Download PDF

Info

Publication number
CN211622523U
CN211622523U CN201922129260.XU CN201922129260U CN211622523U CN 211622523 U CN211622523 U CN 211622523U CN 201922129260 U CN201922129260 U CN 201922129260U CN 211622523 U CN211622523 U CN 211622523U
Authority
CN
China
Prior art keywords
ladder
steel beam
construction platform
straight ladder
fence
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922129260.XU
Other languages
Chinese (zh)
Inventor
张鹏
周阳
田延华
杨帆
岳爱敏
高明生
马少军
林雪冰
曲金原
杨俊涛
杨琳斌
杨在锐
吴昊
任志海
王斌
郭丽榕
贾海霞
崔少光
白伟
王潇赛
陈聪
张冰
张帆
李尧
王海章
武赛男
解超
刘召东
汤明
王宁
赵建康
陈克伟
张全贺
崔玉凤
张�林
刘健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Third Bureau First Engineering Co ltd
Beijing Municipal Construction Co Ltd
Original Assignee
Beijing Municipal Third Bureau First Engineering Co ltd
Beijing Municipal Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Third Bureau First Engineering Co ltd, Beijing Municipal Construction Co Ltd filed Critical Beijing Municipal Third Bureau First Engineering Co ltd
Priority to CN201922129260.XU priority Critical patent/CN211622523U/en
Application granted granted Critical
Publication of CN211622523U publication Critical patent/CN211622523U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Ladders (AREA)

Abstract

The utility model relates to a construction platform for outer facade of girder steel, including the vertical ladder of vertical setting, the upper end of vertical ladder is provided with perpendicularly and takes the atress subassembly of putting at channel steel roof beam upper surface and shear force nail hasp. The utility model has the advantages that: greatly improving the painting or welding efficiency of workers and reducing the cost of painting or welding work.

Description

一种用于钢梁外立面的施工平台A construction platform for the facade of steel beams

技术领域technical field

本实用新型涉及桥梁建筑领域,尤其是涉及一种用于钢梁外立面的施工平台。The utility model relates to the field of bridge construction, in particular to a construction platform used for the outer facade of steel beams.

背景技术Background technique

钢结构桥梁桥面除了在两岸链接运用广泛外,在陆地同样也普遍存在;钢结构桥梁桥面成为空中马路,为缓解交通带来很大的便利。我们都知道钢结构常年暴露于空气中容易腐蚀与生锈,给钢结构桥梁桥面穿上保护衣是一项重要的工序。油漆能够有效的缓解钢结构腐蚀的状况,怎样快速高效的对钢结构桥梁桥体进行喷漆是目前所有解决的关键技术问题之一。In addition to being widely used in cross-strait links, steel structure bridge decks are also common on land; steel structure bridge decks have become air roads, bringing great convenience to ease traffic. We all know that the steel structure is easily corroded and rusted when exposed to the air all the year round. It is an important process to put on protective clothing for the bridge deck of the steel structure. Paint can effectively alleviate the corrosion of steel structures. How to quickly and efficiently paint steel structure bridges is one of the key technical problems to be solved at present.

现有施工单位要对钢结构桥梁进行喷漆或焊接处理时,都需要租赁升降车,施工人员需要站立在升降车的车斗中,再通过升降车将车斗抬升至喷涂区域,以便工作人员进行喷漆或焊接工作。When the existing construction units want to paint or weld steel structure bridges, they all need to rent lift trucks. The construction workers need to stand in the bucket of the lift truck, and then lift the bucket to the spraying area through the lift truck, so that the staff can carry out the work. Painting or welding work.

但是一辆升降车同一时间仅能供一个区域的工作,工作人员需要完成一个区域的喷漆或焊接的作业后,才能够进行下一区域的喷漆或焊接的工作,施工效率低;若是要提高喷漆效率,施工单位需要租赁更多的升降车,这无疑会增加喷漆或焊接工作的成本。However, a lift truck can only work in one area at the same time. The staff needs to complete the painting or welding of one area before they can paint or weld the next area. The construction efficiency is low; Efficiency, the construction unit needs to rent more lift trucks, which will undoubtedly increase the cost of painting or welding work.

实用新型内容Utility model content

针对现有技术存在的不足,本实用新型的目的之一是提供一种用于钢梁外立面的施工平台,其优点是大大提高工作人员的喷漆或焊接效率,降低了喷漆或焊接工作的成本。Aiming at the deficiencies of the prior art, one of the purposes of the present invention is to provide a construction platform for the exterior facade of steel beams, which has the advantages of greatly improving the painting or welding efficiency of workers and reducing the cost of painting or welding.

本实用新型的上述实用新型目的是通过以下技术方案得以实现的:一种用于钢梁外立面的施工平台,用于槽型钢梁上,槽型钢梁上设置有若干排剪力钉,其特征在于,施工平台包括竖直设置的直梯,直梯的上端垂直设置有搭放在槽型钢梁上表面与剪力钉限位抵靠受力组件。The above utility model purpose of the present utility model is achieved through the following technical solutions: a construction platform for the outer facade of a steel beam, used on a channel-shaped steel beam, and several rows of shear nails are arranged on the channel-shaped steel beam, which It is characterized in that the construction platform includes a vertically arranged straight ladder, and the upper end of the straight ladder is vertically arranged with a force-bearing component that is placed on the upper surface of the channel-shaped steel beam and the shear nails are limited and abutted.

通过采用上述技术方案,工作人员若要对槽型钢梁的外立面进行喷漆或焊接作业时,只需人工将受力组件搭放在槽型钢梁的上表面,并使直梯竖直的悬空在钢梁的一侧,从而便于人工攀爬在直梯上对槽型钢梁的外立面进行喷漆或焊接的工作,为了提高工作效率,工作人员也可将若干个施工平台固定在槽型钢梁上,以便于工作人员的同时工作,大大增加了喷漆或焊接工作的效率,而且施工平台结构简单,相较于租赁吊车而言,成本低廉。By adopting the above technical solution, if the staff wants to paint or weld the outer surface of the channel-shaped steel beam, they only need to manually place the force-bearing components on the upper surface of the channel-shaped steel beam, and make the vertical ladder vertical. It is suspended on one side of the steel beam, so that it is convenient for manual climbing on the straight ladder to paint or weld the outer facade of the channel-shaped steel beam. In order to improve the work efficiency, the staff can also fix several construction platforms on the On the channel-shaped steel beam, it is convenient for the staff to work at the same time, which greatly increases the efficiency of painting or welding work, and the construction platform has a simple structure, which is cheaper than renting a crane.

本实用新型在一较佳示例中可以进一步配置为:所述受力组件包括两个平行设置在延长杆,以及固接在两个延长杆之间的若干个与剪力钉抵靠的受力杆,所述延长杆的一端与直梯的侧壁相互铰接,直梯的端部垂直固接有一限制延长杆与直梯铰接角度的限位板。In a preferred example of the present invention, it can be further configured as follows: the force-bearing component includes two extension rods arranged in parallel, and a plurality of force-bearing elements abutting against the shear nails fixed between the two extension rods One end of the extension rod is mutually hinged with the side wall of the straight ladder, and the end of the straight ladder is vertically fixed with a limit plate that limits the hinge angle between the extension rod and the straight ladder.

通过采用上述技术方案,延长杆起到了与直梯端部连接的作用,而且延长杆越长与槽型钢梁上表面的接触范围越广,提高了直梯挂设的稳定性,而受力杆设置在剪力钉之间,在直梯重力的作用下,受力杆会牢牢的抵靠在剪力钉的一侧,从而保障了直梯立设的稳定性,而且延长杆与直梯端部相互铰接,使得在对施工平台运输时,便于将受力组件收纳在直梯的一侧,减少了额外的空间占用,从而提高了施工平台运输的便利性。限位板的设置限制了延长杆铰接的最大张合角度,保证了直梯的正常立设,保障了施工平台的正常工作。By adopting the above technical solution, the extension rod plays the role of connecting with the end of the straight ladder, and the longer the extension rod is, the wider the contact range with the upper surface of the channel-shaped steel beam is, which improves the hanging stability of the straight ladder, and the stress The rod is set between the shearing nails. Under the action of the gravity of the vertical ladder, the force-bearing rod will firmly abut one side of the shearing nails, thus ensuring the stability of the vertical ladder. The ends of the ladder are hinged to each other, so that when the construction platform is transported, it is convenient to store the force-bearing components on one side of the straight ladder, which reduces the occupation of extra space and improves the convenience of transportation of the construction platform. The setting of the limit plate limits the maximum opening and closing angle of the hinge of the extension rod, which ensures the normal erection of the straight ladder and the normal operation of the construction platform.

本实用新型在一较佳示例中可以进一步配置为:所述直梯背离受力组件的一侧设置有一围护架,围护架与直梯之间通过若干个连接杆相互连接。In a preferred example of the present invention, an enclosure frame is provided on the side of the straight ladder away from the force-receiving component, and the enclosure frame and the straight ladder are connected to each other through a plurality of connecting rods.

通过采用上述技术方案,当人员踩踏在直梯上工作的过程中,围护架的设置对人员的周面进行了包覆,从而提高了人员在直梯上工作的安全性。By adopting the above technical solution, when a person steps on the straight ladder to work, the surrounding surface of the person is covered by the setting of the enclosure, thereby improving the safety of the person working on the straight ladder.

本实用新型在一较佳示例中可以进一步配置为:所述连接杆的两端分别与围护栏和直梯转动连接,所述直梯的两侧设置有若干个对围护栏转动角度限位的支设组件。In a preferred example of the present invention, it can be further configured as follows: the two ends of the connecting rod are respectively connected to the fence and the straight ladder for rotation, and the two sides of the straight ladder are provided with a number of limiters for the rotation angle of the fence. Support components.

通过采用上述技术方案,连接杆的两端分别与直梯和围护栏相互铰接,使得施工平台在不使用时,工作人员可通过连接杆的转动使围护栏挨靠在直梯的一侧,从而节省了额外的空间占用,不仅便于收放,而且便于运输,支设组件的设置,限制了连接杆与直梯的转动角度,对围护栏起到了支撑的作用,使得围护栏对人员起到了围设保护的作用。By adopting the above technical solution, both ends of the connecting rod are hinged with the straight ladder and the guardrail, so that when the construction platform is not in use, the staff can make the guardrail lean against one side of the straight ladder through the rotation of the connecting rod. It saves additional space occupation, which is not only convenient for storage and transportation, but also for transportation. The setting of the supporting components limits the rotation angle of the connecting rod and the straight ladder, and plays a supporting role for the fence, making the fence play a role in protecting the personnel. The role of protection.

本实用新型在一较佳示例中可以进一步配置为:所述支设组件包括第一支杆和与第一支杆一端铰接的第二支杆,第一支杆的另一端铰接在直梯的侧壁上,第二支杆的另一端铰接在围护栏的侧壁上,并且第一支杆与直梯的连接处高于第二支杆与围护栏的连接处,当第一支杆和第二支杆位于同一直线时,围护栏与直梯之间留有空间。In a preferred example of the present invention, it can be further configured as follows: the support assembly includes a first support rod and a second support rod hinged with one end of the first support rod, and the other end of the first support rod is hinged on the vertical ladder. On the side wall, the other end of the second pole is hinged on the side wall of the fence, and the connection between the first pole and the straight ladder is higher than the connection between the second pole and the fence. When the second pole is in the same line, there is a space between the fence and the straight ladder.

通过采用上述技术方案,当围护栏靠近在直梯的一侧时,第一支杆和第二支杆处于折叠状态,当围护栏远离直梯处于支设状态时,第一支杆和第二支杆位于同一直线上,并对围护栏起到了支撑作用,支设组件结构简单,便于工作人员的安装和维护。By adopting the above technical solution, when the fence is close to one side of the straight ladder, the first pole and the second pole are in a folded state, and when the fence is far away from the straight ladder and in a supported state, the first pole and the second pole are in a folded state. The support rods are located on the same straight line and play a supporting role for the fence. The structure of the support assembly is simple, which is convenient for the installation and maintenance of the staff.

本实用新型在一较佳示例中可以进一步配置为:所述围护栏朝向受力组件的一侧设置有若干个支撑在槽型钢梁侧壁的稳定支杆,稳定支杆的端部与围护栏转动连接,稳定支杆的侧壁与直梯的侧部转动连接。In a preferred example of the present invention, it can be further configured as follows: the side of the guardrail facing the force-bearing component is provided with a number of stabilizing struts supported on the side walls of the channel-shaped steel beam, and the ends of the stabilizing struts are connected to the enclosure. The guardrail is rotatably connected, and the side wall of the stabilizing strut is rotatably connected with the side part of the straight ladder.

通过采用上述技术方案,当围护栏位于展开状态时,稳定支杆的端部抵触在槽型钢梁的侧壁上,从而对直梯起到了辅助支撑的作用,提高了直梯立设的稳定性,提高了工作人员在喷漆或焊接作业中的安全性。By adopting the above technical solution, when the fence is in the unfolded state, the end of the stabilizing strut abuts on the side wall of the channel-shaped steel beam, thereby playing an auxiliary supporting role for the vertical ladder and improving the vertical stability of the vertical ladder. It improves the safety of workers in painting or welding operations.

本实用新型在一较佳示例中可以进一步配置为:其中两个稳定支杆设置在围护栏的末端,两个稳定支撑之间设置有若干个支撑人体的支撑杆。In a preferred example of the present invention, it can be further configured as follows: two stabilizing struts are arranged at the end of the guardrail, and several struts for supporting the human body are arranged between the two stabilizing supports.

通过采用上述技术方案,当围护栏位于展开状态时,支撑杆位于直梯的底部,对工作人员起到了支撑作用,增加了工作人员的活动空间,也提供了工具放置的平台,从而提高了工作中的灵活性。By adopting the above technical solution, when the fence is in the unfolded state, the support rod is located at the bottom of the straight ladder, which supports the staff, increases the activity space of the staff, and also provides a platform for placing tools, thereby improving the work efficiency. flexibility in .

本实用新型在一较佳示例中可以进一步配置为:所述稳定支杆朝向槽型钢梁的端部固接有一橡胶块。In a preferred example of the present invention, it can be further configured that: a rubber block is fixedly connected to the end of the stabilizing strut toward the channel-shaped steel beam.

通过采用上述技术方案,稳定支杆是刚性材质,稳定支杆端部与槽型钢梁的外立面直接接触有可能会漆液造成刮蹭,所以橡胶块的设置替代了稳定支杆与槽型钢梁的硬性接触,不仅起到了缓冲作用,而且还能够减少稳定支杆端部棱角与槽型钢梁外立面的直接接触。By adopting the above technical solution, the stabilizing strut is made of rigid material, and the direct contact between the end of the stabilizing strut and the outer façade of the channel-shaped steel beam may cause scratches by the paint liquid, so the setting of the rubber block replaces the stabilizing strut and the groove. The rigid contact of the profiled steel beam not only acts as a buffer, but also reduces the direct contact between the edges and corners of the end of the stabilizing strut and the outer façade of the channel-shaped steel beam.

综上所述,本实用新型包括以下至少一种有益技术效果:To sum up, the present utility model includes at least one of the following beneficial technical effects:

一、提高了施工效率。工作人员若要对槽型钢梁的外立面进行喷漆或焊接作业时,只需人工将受力组件搭放在槽型钢梁的上表面,并使直梯竖直的悬空在钢梁的一侧,从而便于人工攀爬在直梯上对槽型钢梁的外立面进行喷漆或焊接工作,为了提高工作效率,工作人员也可将若干个施工平台固定在槽型钢梁上,以便于工作人员的同时工作,大大增加了喷漆或焊接工作的效率;1. Improve the construction efficiency. When the staff wants to paint or weld the outer surface of the channel-shaped steel beam, they only need to manually place the force-bearing components on the upper surface of the channel-shaped steel beam, and make the vertical ladder hang vertically on the steel beam. On one side, it is convenient for manual climbing on the straight ladder to paint or weld the outer surface of the channel-shaped steel beam. In order to improve work efficiency, the staff can also fix several construction platforms on the channel-shaped steel beam, so as to Work at the same time as the staff, which greatly increases the efficiency of painting or welding work;

二、收纳方便,便于运输。连接杆的两端分别与直梯和围护栏相互铰接,使得施工平台在不使用时,工作人员可通过连接杆的转动使围护栏挨靠在直梯的一侧,从而节省了额外的空间占用,不仅便于收放,而且便于运输。Second, the storage is convenient, easy to transport. Both ends of the connecting rod are hinged with the straight ladder and the fence respectively, so that when the construction platform is not in use, the staff can make the fence against the side of the straight ladder through the rotation of the connecting rod, thus saving extra space occupation , not only easy to put away, but also easy to transport.

附图说明Description of drawings

图1是施工平台与槽型钢梁配合关系示意图;Figure 1 is a schematic diagram of the cooperation relationship between the construction platform and the channel-shaped steel beam;

图2是施工平台的整体结构示意图;Figure 2 is a schematic diagram of the overall structure of the construction platform;

图3是施工平台收纳状态示意图。FIG. 3 is a schematic diagram of the storage state of the construction platform.

图中,1、直梯;11、竖杆;12、横杆;2、受力组件;21、延长杆;22、受力杆;23、限位板;32、受力钉;31、槽型钢梁;4、围护栏;41、连接杆;5、支设组件;51、第一支杆;52、第二支杆;6、稳定支杆;61、橡胶块;62、支撑杆。In the figure, 1, straight ladder; 11, vertical rod; 12, horizontal rod; 2, stress component; 21, extension rod; 22, stress rod; 23, limit plate; 32, stress nail; 31, groove Sectional steel beam; 4. Fence; 41. Connecting rod; 5. Supporting components; 51. First strut; 52. Second strut; 6. Stabilizing strut; 61. Rubber block; 62. Support rod.

具体实施方式Detailed ways

以下结合附图对本实用新型作进一步详细说明。The present utility model will be described in further detail below in conjunction with the accompanying drawings.

一种用于钢梁外立面的施工平台,如图1和图2所示,包括竖直设置的直梯1,以及设置在直梯1上端的受力组件2。A construction platform for the exterior facade of a steel beam, as shown in Figures 1 and 2, includes a vertical ladder 1, and a force bearing assembly 2 disposed on the upper end of the straight ladder 1.

如图2所示,直梯1包括两根竖直设置的竖杆11,以及水平设置在两根竖杆11之间的若干个横杆12(本实施例中横杆12设置有四个,并沿竖杆11的高度方向均匀布设)。上述受力组件2包括两个相互平行设置的延长杆21,以及固接在两个延长杆21之间的两个受力杆22,受力杆22的两端垂直固接在对应的延长杆21的侧壁上,并且两个受力杆22之间的间隔等于每排受力钉32之间的间隔。两个延长杆21的端部铰接在对应竖杆11端部的侧壁上,并且延长杆21与竖杆11的铰接轴与横杆12的中心线相互平行。每个竖杆11的上端固接有一L型的限位板23,限位板23的两侧分别焊接在竖杆11侧壁和端面上,使得延长杆21与竖杆11铰接开合后,竖杆11的上表面贴靠在限位板23的下表面,从而限制了受力组件2的最大开合角度。As shown in FIG. 2 , the vertical ladder 1 includes two vertical bars 11 arranged vertically, and several horizontal bars 12 arranged between the two vertical bars 11 (in this embodiment, there are four horizontal bars 12, and evenly arranged along the height direction of the vertical rod 11). The above-mentioned force-bearing assembly 2 includes two extension rods 21 arranged in parallel to each other, and two force-bearing rods 22 fixed between the two extension rods 21, and both ends of the force-bearing rods 22 are vertically fixed to the corresponding extension rods. 21, and the interval between the two force-bearing rods 22 is equal to the interval between each row of force-bearing pins 32. The ends of the two extension rods 21 are hinged on the side walls corresponding to the ends of the vertical rod 11 , and the hinge axes of the extension rods 21 and the vertical rod 11 and the center line of the horizontal rod 12 are parallel to each other. An L-shaped limit plate 23 is fixed to the upper end of each vertical rod 11, and both sides of the limit plate 23 are welded to the side wall and end surface of the vertical rod 11 respectively, so that after the extension rod 21 is hingedly opened and closed with the vertical rod 11, The upper surface of the vertical rod 11 abuts against the lower surface of the limiting plate 23 , thereby limiting the maximum opening and closing angle of the force-receiving component 2 .

当对施工平台固定时,可转动延长杆21,使受力组件2在限位板23的限制下与直梯1呈90度,然后将两个受力杆22从两排剪力钉之间的缝隙处放置在槽型钢梁31的上表面,在直梯1重力作用下,使受力杆22紧紧的挨靠在剪力钉的一侧,从而保障了直梯1悬挂的稳定性。由于受力组件2与直梯1相互铰接,使得在对施工平台运输时,可将受力组件2铰接贴靠在直梯1的侧壁上,从而便于直梯1的运输收纳。When fixing the construction platform, the extension rod 21 can be rotated so that the force-bearing assembly 2 is 90 degrees from the vertical ladder 1 under the restriction of the limit plate 23, and then the two force-bearing rods 22 are inserted between the two rows of shear nails. The gap is placed on the upper surface of the channel-shaped steel beam 31. Under the action of the gravity of the straight ladder 1, the force-receiving rod 22 is tightly abutted on the side of the shear nail, thereby ensuring the stability of the straight ladder 1 suspension. . Because the force-bearing assembly 2 and the vertical ladder 1 are hinged to each other, when the construction platform is transported, the force-bearing assembly 2 can be hingedly attached to the side wall of the vertical ladder 1, thereby facilitating the transportation and storage of the straight ladder 1.

如图2所示,直梯1背离受力组件2的一侧设置有一围护栏4,围护栏4与直梯1所在平面相互平行,围护栏4的两侧各设置有两个连接杆41,连接杆41的一端与围护栏4的侧壁转动连接,连接杆41的另一端与直梯1侧壁转动连接,连接杆41两端的转动轴都与竖杆11和延长杆21的转动轴相互平行,两个连接杆41间隔设置,并且四个连接杆41相互平行,从而对直梯1的两侧起到了围设作用。As shown in FIG. 2 , the side of the straight ladder 1 away from the force-receiving component 2 is provided with a fence 4, the fence 4 and the plane of the straight ladder 1 are parallel to each other, and two connecting rods 41 are provided on both sides of the fence 4, One end of the connecting rod 41 is rotatably connected to the side wall of the fence 4, the other end of the connecting rod 41 is rotatably connected to the side wall of the straight ladder 1, and the rotating shafts at both ends of the connecting rod 41 are mutually connected with the rotating shafts of the vertical rod 11 and the extension rod 21. In parallel, the two connecting rods 41 are arranged at intervals, and the four connecting rods 41 are parallel to each other, so that the two sides of the straight ladder 1 are enclosed.

如图2所示,直梯1的两侧各设置有两组对围护栏4支撑的支设组件5。支设组件5包括第一支杆51和与第一支杆51一端铰接的第二支杆52,第一支杆51的另一端与直梯1侧壁转动连接,第二支杆52背离第一支杆51的另一端与围护栏4侧壁转动连接上,第一支杆51与直梯1的铰接轴和第二支杆52与围护栏4的铰接轴都与横杆12相互平行,并且第一支杆51与直梯1的固定点高于第二支杆52与直梯1的固定点,而且两侧的支设组件5位置相互对应。As shown in FIG. 2 , two sets of supporting components 5 for supporting the fence 4 are provided on both sides of the straight ladder 1 . The support assembly 5 includes a first support rod 51 and a second support rod 52 hinged with one end of the first support rod 51. The other end of the first support rod 51 is rotatably connected to the side wall of the straight ladder 1, and the second support rod 52 is away from the first support rod 51. The other end of the support rod 51 is rotatably connected to the side wall of the fence 4. The hinge shaft of the first support rod 51 and the straight ladder 1 and the hinge shaft of the second support rod 52 and the guard rail 4 are all parallel to the cross bar 12. And the fixed point of the first support rod 51 and the straight ladder 1 is higher than the fixed point of the second support rod 52 and the straight ladder 1 , and the positions of the support components 5 on both sides correspond to each other.

当连接杆41转动到与直梯1所在平面相互垂直时,第一支杆51和第二支杆52处于同一直线上,从而限制了连接杆41与直梯1的相互转动,保障了围护栏4支设的稳定性;而且当人员踩踏在直梯1上时,围栏的设置同样提高了人员工作的安全性。When the connecting rod 41 is rotated to be perpendicular to the plane where the straight ladder 1 is located, the first support rod 51 and the second support rod 52 are on the same straight line, thereby restricting the mutual rotation of the connecting rod 41 and the straight ladder 1 and ensuring the fence The stability of the 4 supports; and when the personnel step on the straight ladder 1, the setting of the fence also improves the safety of the personnel work.

如图1和图2所示,围护栏4的两侧各设置有两个稳定支杆6,四个稳定支杆6与连接杆41相互平行,稳定支杆6的一端与围护栏4的侧壁转动连接,稳定支杆6的另一端抵靠在槽型钢梁31的外立面上,并且稳定支杆6与直梯1贴靠的区域与直梯1侧壁转动连接,并且稳定支杆6与围护栏4的转动轴和稳定支杆6与直梯1的转动轴都与横杆12的长度方向相互平行。而且左右两侧的稳定支杆6位置相互对应,并且其中一对稳定支杆6都位于围护栏4和直梯1的末端,两个底部的稳定支杆6之间设置有若干个相互平行的支撑杆62,支撑杆62的两端分别与稳定支杆6的侧壁垂直固接。当四个稳定支杆6支设在槽型钢梁31的外立面时,对直梯1起到了稳定支撑的作用,提高了直梯1支设的稳定性,而且支撑杆62水平位于直梯1的底部,便于人员在支撑杆62踩踏走动,不仅增加了人员的活动空间,而且腾出了手部对直梯1的扶持,提高了喷涂工作的灵活性。As shown in FIG. 1 and FIG. 2 , two stabilizing struts 6 are provided on both sides of the fence 4 . The four stabilizing struts 6 and the connecting rod 41 are parallel to each other. The wall is rotatably connected, the other end of the stabilizing strut 6 abuts on the outer façade of the channel steel beam 31, and the area where the stabilizing strut 6 abuts against the vertical ladder 1 is rotatably connected with the side wall of the straight ladder 1, and the stable supporting The rotation axes of the rod 6 and the fence 4 and the rotation axes of the stabilizing strut 6 and the vertical ladder 1 are parallel to the longitudinal direction of the cross bar 12 . Moreover, the positions of the stabilizing struts 6 on the left and right sides correspond to each other, and a pair of the stabilizing struts 6 are located at the ends of the guardrail 4 and the straight ladder 1. A number of mutually parallel stabilizing struts 6 are arranged between the two bottom stabilizing struts 6. A support rod 62, two ends of the support rod 62 are vertically fixed to the side wall of the stabilizing rod 6 respectively. When the four stabilizing struts 6 are supported on the outer façade of the channel steel beam 31, they play a role in stably supporting the straight ladder 1, which improves the stability of the straight ladder 1, and the supporting rods 62 are positioned horizontally in the vertical direction. The bottom of the ladder 1 is convenient for people to step and walk on the support rod 62 , which not only increases the movement space of the personnel, but also frees up the support of the straight ladder 1 by the hands, which improves the flexibility of the spraying work.

如图2所示,每个稳定支杆6与槽型钢梁31贴靠的端面上还固定有一橡胶块61,通过橡胶块61与槽型钢梁31外立面的接触,使得稳定支杆6端部棱角不易与槽型钢梁31漆面造成滑蹭,而且还对直梯1的支设起到了缓冲作用,提高了施工平台施工时的稳定性。As shown in FIG. 2 , a rubber block 61 is also fixed on the end surface of each stabilizing strut 6 against the channel-shaped steel beam 31 . 6. The edges and corners of the ends are not easy to cause slippage with the paint surface of the channel-shaped steel beam 31, and also play a buffering role for the support of the straight ladder 1, which improves the stability of the construction platform during construction.

如图3所示,当工作人员对施工平台运输时,可将受力组件2通过延长杆21与竖杆11的铰接,使受力组件2收放在直梯1的一侧,通过连接杆41的转动,带动维护栏向直梯1的方向移动,并使第一支杆51和第二支杆52转动叠加,从而大大节省了施工平台的空间占用,提高了运输的便利性,而且施工平台结构简单,便于大规模的生产,在喷漆或焊接工作时,可将若干个施工平台同时架设,不仅操控便捷,而且大大提高喷漆或焊接工作的效率。As shown in Figure 3, when the worker transports the construction platform, the force-bearing component 2 can be hinged with the vertical rod 11 through the extension rod 21, so that the force-bearing component 2 can be stored on one side of the vertical ladder 1, and the connecting rod The rotation of 41 drives the maintenance bar to move in the direction of the straight ladder 1, and makes the first support rod 51 and the second support rod 52 rotate and overlap, thereby greatly saving the space occupation of the construction platform, improving the convenience of transportation, and the construction The platform has a simple structure, which is convenient for large-scale production. When painting or welding, several construction platforms can be erected at the same time, which is not only convenient to operate, but also greatly improves the efficiency of painting or welding.

本具体实施方式的实施例均为本实用新型的较佳实施例,并非依此限制本实用新型的保护范围,故:凡依本实用新型的结构、形状、原理所做的等效变化,均应涵盖于本实用新型的保护范围之内。The embodiments of this specific embodiment are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention, therefore: all equivalent changes made according to the structure, shape and principle of the present invention are It should be covered within the protection scope of the present invention.

Claims (8)

1.一种用于钢梁外立面的施工平台,用于槽型钢梁(31)上,槽型钢梁(31)上设置有若干排剪力钉,其特征在于,施工平台包括竖直设置的直梯(1),直梯(1)的上端垂直设置有搭放在槽型钢梁(31)上表面与剪力钉限位抵靠的受力组件(2)。1. a construction platform for the outer facade of the steel beam, used on the channel-shaped steel beam (31), the channel-shaped steel beam (31) is provided with several rows of shear nails, it is characterized in that, the construction platform comprises a vertical set The straight ladder (1) is provided vertically on the upper end of the straight ladder (1) with a force bearing component (2) which is placed on the upper surface of the channel-shaped steel beam (31) and abuts against the limit of the shear nails. 2.根据权利要求1所述的一种用于钢梁外立面的施工平台,其特征在于:所述受力组件(2)包括两个平行设置在延长杆(21),以及固接在两个延长杆(21)之间的若干个与剪力钉抵靠的受力杆(22),所述延长杆(21)的一端与直梯(1)的侧壁相互铰接,直梯(1)的端部垂直固接有一限制延长杆(21)与直梯(1)铰接角度的限位板(23)。2. A construction platform for steel girder façade according to claim 1, characterized in that: the force-bearing component (2) comprises two extension rods (21) arranged in parallel, and two A plurality of force-bearing rods (22) between the extension rods (21) abutting against the shear nails, one end of the extension rods (21) is mutually hinged with the side wall of the straight ladder (1), and the straight ladder (1) A limit plate (23) for limiting the hinge angle between the extension rod (21) and the vertical ladder (1) is fixed vertically at the end of the vertical ladder. 3.根据权利要求1所述的一种用于钢梁外立面的施工平台,其特征在于:所述直梯(1)背离受力组件(2)的一侧设置有一围护架,围护架与直梯(1)之间通过若干个连接杆(41)相互连接。3. A construction platform for steel beam façade according to claim 1, characterized in that: the side of the straight ladder (1) away from the force-receiving component (2) is provided with an enclosure, and the enclosure is The vertical ladder (1) is connected to each other through several connecting rods (41). 4.根据权利要求3所述的一种用于钢梁外立面的施工平台,其特征在于:所述连接杆(41)的两端分别与围护栏(4)和直梯(1)转动连接,所述直梯(1)的两侧设置有若干个对围护栏(4)转动角度限位的支设组件(5)。4. A construction platform for steel beam façade according to claim 3, characterized in that: the two ends of the connecting rod (41) are respectively rotatably connected with the fence (4) and the straight ladder (1), The two sides of the straight ladder (1) are provided with a plurality of supporting components (5) for limiting the rotation angle of the fence (4). 5.根据权利要求4所述的一种用于钢梁外立面的施工平台,其特征在于:所述支设组件(5)包括第一支杆(51)、和与第一支杆(51)一端铰接的第二支杆(52),第一支杆(51)的另一端铰接在直梯(1)的侧壁上,第二支杆(52)的另一端铰接在围护栏(4)的侧壁上,并且第一支杆(51)与直梯(1)的连接处高于第二支杆(52)与围护栏(4)的连接处,当第一支杆(51)和第二支杆(52)位于同一直线时,围护栏(4)与直梯(1)之间留有空间。5. A construction platform for steel beam facade according to claim 4, characterized in that: the support assembly (5) comprises a first support rod (51), and a first support rod (51) One end of the second support rod (52) is hinged, the other end of the first support rod (51) is hinged to the side wall of the straight ladder (1), and the other end of the second support rod (52) is hinged to the fence (4) on the side wall of the vertical ladder (1), and the connection between the first support rod (51) and the straight ladder (1) is higher than the connection between the second support rod (52) and the fence (4), when the first support rod (51) and the When the second struts (52) are located on the same straight line, a space is left between the fence (4) and the straight ladder (1). 6.根据权利要求5所述的一种用于钢梁外立面的施工平台,其特征在于:所述围护栏(4)朝向受力组件(2)的一侧设置有若干个支撑在槽型钢梁(31)侧壁的稳定支杆(6),稳定支杆(6)的端部与围护栏(4)转动连接,稳定支杆(6)的侧壁与直梯(1)的侧部转动连接。6. A construction platform for steel girder facade according to claim 5, characterized in that: the side of the guardrail (4) facing the force-bearing component (2) is provided with a plurality of channels supported on the channel steel A stabilizing strut (6) on the side wall of the beam (31), the end of the stabilizing strut (6) is rotatably connected with the fence (4), and the side wall of the stabilizing strut (6) is connected with the side of the straight ladder (1) Turn the connection. 7.根据权利要求6所述的一种用于钢梁外立面的施工平台,其特征在于:其中两个稳定支杆(6)设置在围护栏(4)的末端,两个稳定支撑之间设置有若干个支撑人体的支撑杆(62)。7. A construction platform for steel beam façade according to claim 6, characterized in that: wherein two stabilizing struts (6) are arranged at the ends of the fence (4), and between the two stabilizing supports There are several support rods (62) supporting the human body. 8.根据权利要求6所述的一种用于钢梁外立面的施工平台,其特征在于:所述稳定支杆(6)朝向槽型钢梁(31)的端部固接有一橡胶块(61)。8. A construction platform for steel beam façade according to claim 6, characterized in that: a rubber block (61) is fixedly connected to the end of the stabilizing strut (6) toward the channel-shaped steel beam (31). ).
CN201922129260.XU 2019-11-30 2019-11-30 A construction platform for the facade of steel beams Expired - Fee Related CN211622523U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922129260.XU CN211622523U (en) 2019-11-30 2019-11-30 A construction platform for the facade of steel beams

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922129260.XU CN211622523U (en) 2019-11-30 2019-11-30 A construction platform for the facade of steel beams

Publications (1)

Publication Number Publication Date
CN211622523U true CN211622523U (en) 2020-10-02

Family

ID=72627470

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922129260.XU Expired - Fee Related CN211622523U (en) 2019-11-30 2019-11-30 A construction platform for the facade of steel beams

Country Status (1)

Country Link
CN (1) CN211622523U (en)

Similar Documents

Publication Publication Date Title
CN206569235U (en) A kind of ship hanger bracket and boat scaffold
CN204126230U (en) Assembly scaffold unit
CN115288449B (en) Middle support installation construction method for large-span net rack
CN106522364B (en) 'garland' steel structure system for stadium periphery and installation process thereof
CN115306137B (en) Operation platform structure for installing suspended ceiling at bottom of high-altitude corridor and construction method thereof
CN205713096U (en) A kind of roofing cantilevered structure form bracing system
CN215212255U (en) Suspension type frame combined high-altitude operation platform
CN211691716U (en) Large-span closed stockyard structure for multiple stackers and reclaimers
CN214995779U (en) Improvement type scaffold frame for interior decoration design
CN205296801U (en) A operation platform that is used for curved surface building exterior window to install
CN221590338U (en) A construction scaffold for building engineering
CN213297074U (en) A convenient outer wall cantilever operation frame
CN203924655U (en) Novel elevator shaft operating platform frame
CN211472213U (en) An overhead type railway steel truss girder bridge construction hanging basket
CN220036048U (en) A kind of scaffolding for exhibition construction
CN209653548U (en) A kind of horizontal protective device of modularization for construction
CN208380046U (en) movable safety scaffold
CN222413928U (en) A convenient movable cantilever operating platform
CN222835310U (en) An operating platform protection device for slope construction
CN222227889U (en) A construction frame for building construction
CN222251773U (en) I-shaped steel-concrete composite beam bridge deck concrete construction support frame body
CN215829259U (en) Cantilever beam type support for high formwork operation
CN219604806U (en) Portable scaffold for house building
CN219118715U (en) Elevator well safety protection and operation platform integrated device
CN222276108U (en) Scaffold with layer-shrinking arc-shaped high-rise structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201002

CF01 Termination of patent right due to non-payment of annual fee