CN211599829U - Transmission pipeline of asphalt waterproof material - Google Patents
Transmission pipeline of asphalt waterproof material Download PDFInfo
- Publication number
- CN211599829U CN211599829U CN201922170721.8U CN201922170721U CN211599829U CN 211599829 U CN211599829 U CN 211599829U CN 201922170721 U CN201922170721 U CN 201922170721U CN 211599829 U CN211599829 U CN 211599829U
- Authority
- CN
- China
- Prior art keywords
- pipeline
- connecting piece
- conveying pipeline
- main connecting
- welded
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Abstract
The utility model discloses a transmission pipeline of pitch waterproof material, including first pipeline and second pipeline, the welding of one side of the outside of first pipeline has main connecting piece, and the welding of one side of the outside of second pipeline has vice connecting piece, and main connecting piece all bonds with the inside of vice connecting piece has the sealing washer, and first pipeline all is the equidistance with the inside of second pipeline and bonds and have the blotter, is provided with the cavity between two adjacent blotters. The utility model discloses a blotter and the heat preservation that sets up, the blotter cushions the shock attenuation when receiving external pressure, the cavity makes first pipeline and second pipeline's total weight reduction, be convenient for remove the transport, the heat preservation makes the material be in stable environment, avoid the difference in temperature to influence the material quality when great, the waterproof layer carries out water proof when first conveyer pipe and second pipeline inside wash, the leakproofness of sealing washer is better, reduce revealing of junction material.
Description
Technical Field
The utility model relates to a conveying equipment technical field especially relates to a transmission pipeline of pitch waterproof material.
Background
The asphalt is a black-brown complex mixture composed of hydrocarbons with different molecular weights and non-metallic derivatives thereof, is one of high-viscosity organic liquids, is in a liquid state, has a black surface, is soluble in carbon disulfide, is a waterproof, moistureproof and anticorrosive organic cementing material, is stored underground, is formed into a mineral layer or accumulated on the surface of a crust in some cases, is mainly used for industries such as paint, plastics, rubber and the like, pavements and the like, is a pipeline for specially conveying liquid and gas materials, is called pipeline transportation by adopting a pipeline material conveying method, is a transportation mode specially conveying petroleum, coal and chemical products from a production place to a market, and is a special component part of trunk transportation in a unified transportation network.
The transmission pipeline of current pitch waterproof material is at the in-process that uses, the water-proof effects when transmission pipeline washs is not good, and the heat insulating ability is relatively poor, easily receives external pressure's influence, and the junction of pipeline is connected not inseparably enough, causes revealing of material, and transmission pipeline washs comparatively inconveniently, uses some equipment to control the flow of transported substance material, but the use cost of equipment is higher, consequently, the transmission pipeline of pitch waterproof material that needs to design urgent need solves above-mentioned problem.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing a transmission pipeline of asphalt waterproof materials.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a transmission pipeline of pitch waterproof material, includes first pipeline and second pipeline, the welding of one side of the outside of first pipeline has main connecting piece, the welding of one side of the outside of second pipeline has vice connecting piece, main connecting piece has the sealing washer with vice connecting piece's inside all bonds, first pipeline all is the equidistance with the inside of second pipeline and bonds and has the blotter, adjacent two be provided with the cavity between the blotter, the inside welding of blotter has the transport inner tube, the inside welding of transport inner tube has the heat preservation, and the inside welding of heat preservation has the waterproof layer.
Furthermore, the main connecting piece is equidistant with the inside of auxiliary connecting piece and has seted up the mounting hole, and the inside threaded connection of mounting hole has the threaded rod, the outside threaded connection of threaded rod has fastening bolt.
Furthermore, the inserted bar is welded on one side of the main connecting piece, the jacks are formed in the auxiliary connecting piece, and the inserted bar is inserted in the jacks.
Furthermore, the both sides of main connecting piece all have the screw rod by threaded connection, the outside threaded connection of screw rod has fixing bolt, the screw rod runs through the sealing washer, and the tip welding of screw rod has the baffler.
Furthermore, one side welding of baffler has the mounting, and the outside cover of mounting is equipped with the rotor plate.
Further, the dwang is the annular equidistance with the inside of baffler and has seted up the opening, one side welding of dwang has the push rod.
The utility model has the advantages that:
1. through blotter and the heat preservation that sets up, the blotter cushions the shock attenuation when receiving external pressure, the cavity makes first pipeline and second pipeline's total weight reduction, be convenient for remove the transport, the heat preservation makes the material be in stable environment, avoid when the difference in temperature is great to produce the influence to the material quality, the waterproof layer carries out water protection when first conveyer pipe and second conveyer pipe inside wash, the leakproofness of sealing washer is better, reduce revealing of junction material.
2. Through the main connecting piece and the auxiliary connecting piece that set up, main connecting piece and auxiliary connecting piece make first pipeline and second pipeline fastening connection, can dismantle the washing after, and first pipeline and second pipeline's washing is more convenient.
3. Through the barrier plate and the rotating plate that set up, the material passes through from the opening, and the opening that pushes away behind the push rod rotating plate and barrier plate can't communicate with each other or leave certain space, makes the unable conveying of material or the delivery capacity of material reduce to the delivery capacity of control material, and use cost is lower, easy operation.
Drawings
Fig. 1 is a schematic structural diagram of a transmission pipeline made of asphalt waterproof material according to the present invention;
fig. 2 is a schematic structural view of a main connecting piece and an auxiliary connecting piece of a transmission pipeline made of asphalt waterproof material according to the present invention;
fig. 3 is a schematic structural view of a baffle plate and a rotating plate of a transmission pipeline of asphalt waterproof material according to the present invention;
fig. 4 is a schematic view of the internal structure of the first conveying pipeline of the conveying pipeline made of asphalt waterproof material according to the present invention.
In the figure: the sealing device comprises a first conveying pipeline 1, a second conveying pipeline 2, a main connecting piece 3, an auxiliary connecting piece 4, a threaded rod 5, a fastening bolt 6, a screw rod 7, a fixing bolt 8, a mounting hole 9, an inserting rod 10, an inserting hole 11, a barrier plate 12, a rotating plate 13, a flow hole 14, a push rod 15, a fixing piece 16, a cushion pad 17, an inner conveying pipe 18, a heat-insulating layer 19, a waterproof layer 20, a cavity 21 and a sealing ring 22.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
It will be understood that when an element is referred to as being "secured to" another element, it can be directly on the other element or intervening elements may also be present. When a component is referred to as being "connected" to another component, it can be directly connected to the other component or intervening components may also be present. When a component is referred to as being "disposed on" another component, it can be directly on the other component or intervening components may also be present. The terms "vertical," "horizontal," "left," "right," and the like as used herein are for illustrative purposes only.
Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs. The terminology used in the description of the invention herein is for the purpose of describing particular embodiments only and is not intended to be limiting of the invention. As used herein, the term "and/or" includes any and all combinations of one or more of the associated listed items.
Referring to fig. 1 to 4, a transmission pipeline made of asphalt waterproof material includes a first transmission pipeline 1 and a second transmission pipeline 2, a main connecting member 3 is welded to one side of the exterior of the first transmission pipeline 1, an auxiliary connecting member 4 is welded to one side of the exterior of the second transmission pipeline 2, a threaded rod 5 is rotated to connect the main connecting member 3 with the auxiliary connecting member 4, a fastening bolt 6 is screwed, an insert rod 10 is inserted into an insert hole 11, the first transmission pipeline 1 and the second transmission pipeline 2 are fastened, sealing rings 22 are bonded to the interiors of the main connecting member 3 and the auxiliary connecting member 4, the sealing rings 22 have good sealing performance, leakage of materials at a joint of the first transmission pipeline 1 and the second transmission pipeline 2 is reduced, buffering is performed on the buffering cushions 17 inside the first transmission pipeline 1 and the second transmission pipeline 2 at equal intervals, and buffering is performed on the buffering 17 when external pressure is applied to the cushions, be provided with cavity 21 between two adjacent blotters 17, cavity 21's setting makes first pipeline 1 and second pipeline 2's total weight alleviate, be convenient for remove the transport, the inside welding of blotter 17 has transport inner tube 18, the inside welding of transport inner tube 18 has heat preservation 19, the heat preservation 19 in the transport inner tube 18 makes the material be in stable environment, produce the influence to the material quality when avoiding the difference in temperature great, and the inside welding of heat preservation 19 has waterproof layer 20, waterproof layer 20 is when first conveyer pipe 1 and the inside washing of second conveyer pipe 2, reduce its inside damage, waterproof layer 20 carries out water proof protection.
Further, mounting hole 9 has been seted up to the inside of main connecting piece 3 and auxiliary connecting piece 4 to the equidistance, and the inside threaded connection of mounting hole 9 has threaded rod 5, the outside threaded connection of threaded rod 5 has fastening bolt 6, the main connecting piece 3 of 1 one end of first pipeline is placed in one side of auxiliary connecting piece 4 of 2 one ends of second pipeline, make main connecting piece 3 align with mounting hole 9 in the auxiliary connecting piece 4, it is connected with auxiliary connecting piece 4 to rotate threaded rod 5 to make main connecting piece 3, tighten fastening bolt 6, the inside of jack 11 is inserted to inserted bar 10, first pipeline 1 and 2 fastening connection of second pipeline.
Further, inserted bar 10 has all been welded to one side of main connecting piece 3, and jack 11 has all been seted up to the inside of vice connecting piece 4, and inserted bar 10 pegs graft in the inside of jack 11, and inserted bar 10 inserts the inside of jack 11, first pipeline 1 and 2 fastening connection of second pipeline.
Furthermore, both sides of the main connecting piece 3 are in threaded connection with screw rods 7, the outer threads of the screw rods 7 are connected with fixing bolts 8, the screw rods 7 penetrate through the sealing rings 22, the blocking plates 12 are welded at the end parts of the screw rods 7, the fixing bolts 8 are rotated, and the screw rods 7 and the blocking plates 12 at the end parts of the screw rods 7 can rotate inside the main connecting piece 3.
Furthermore, a fixing piece 16 is welded on one side of the blocking plate 12, a rotating plate 13 is sleeved outside the fixing piece 16, the blocking plate 12 and the rotating plate 13 are in the horizontal direction, the outer portions of the blocking plate 12 and the rotating plate 13 do not contact with the pipe wall to pass through materials, and the materials can also pass through the circulating hole 14 when the blocking plate 12 is communicated with the circulating hole 14 in the rotating plate 13.
Furthermore, circulation holes 14 are annularly and equidistantly formed in the rotating rod 13 and the blocking plate 12, a push rod 15 is welded on one side of the rotating rod 13, when the blocking plate 12 is communicated with the circulation holes 14 in the rotating plate 13, materials pass through the circulation holes 14 to push the push rod 15, so that the rotating plate 13 cannot be communicated with the circulation holes 14 of the blocking plate 12 or a certain gap is reserved, the materials cannot be conveyed or the conveying capacity of the materials is reduced, the conveying capacity of the materials is controlled, and the use cost is low.
The working principle is as follows: when the device is used, the main connecting piece 3 at one end of the first conveying pipeline 1 is placed on one side of the auxiliary connecting piece 4 at one end of the second conveying pipeline 2, the main connecting piece 3 is aligned with the mounting hole 9 in the auxiliary connecting piece 4, the threaded rod 5 is rotated to connect the main connecting piece 3 with the auxiliary connecting piece 4, the fastening bolt 6 is screwed, the inserted rod 10 is inserted into the jack 11, the first conveying pipeline 1 is fastened and connected with the second conveying pipeline 2, the sealing ring 22 has good sealing performance, leakage of materials at the joint of the first conveying pipeline 1 and the second conveying pipeline 2 is reduced, the buffer cushion 17 in the first conveying pipeline 1 and the second conveying pipeline 2 is used for buffering and damping when external pressure is applied, the cavity 21 is arranged to reduce the total weight of the first conveying pipeline 1 and the second conveying pipeline 2, the moving and carrying are convenient, the heat-insulating layer 19 in the conveying inner pipe 18 enables the materials to be in a stable environment, avoid when the temperature difference is great to produce the influence to the material quality, waterproof layer 20 when first conveyer pipe 1 and second conveyer pipe 2 are inside to be washd, reduce the damage of its inside, waterproof layer 20 carries out water proof protection, rotate fixing bolt 8, screw rod 7 can rotate in the inside of main connecting piece 3 with the baffling board 12 of its tip, baffling board 12 is in the horizontal direction with rotor plate 13, and baffling board 12 does not pass through with the pipe wall contact material with rotor plate 13 outside, the material also can pass through from circulation hole 14 when baffling board 12 communicates with each other with circulation hole 14 in rotor plate 13, promote push rod 15, make rotor plate 13 and baffling board 12's circulation hole 14 unable communicate with each other or leave certain space, make the unable transport or the volume of carrying of material reduce, thereby control the volume of carrying of material, and use cost is lower.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.
Claims (6)
1. A conveying pipeline of asphalt waterproof materials comprises a first conveying pipeline (1) and a second conveying pipeline (2), it is characterized in that one side of the outside of the first conveying pipeline (1) is welded with a main connecting piece (3), an auxiliary connecting piece (4) is welded at one side of the outer part of the second conveying pipeline (2), sealing rings (22) are bonded in the main connecting piece (3) and the auxiliary connecting piece (4), the interior of each of the first conveying pipeline (1) and the second conveying pipeline (2) is bonded with a cushion pad (17) at equal intervals, a cavity (21) is arranged between every two adjacent cushion pads (17), the inside welding of blotter (17) has transport inner tube (18), the inside welding of transport inner tube (18) has heat preservation (19), and the inside welding of heat preservation (19) has waterproof layer (20).
2. The asphalt waterproofing material conveying pipeline according to claim 1, wherein the main connecting piece (3) and the auxiliary connecting piece (4) are provided with mounting holes (9) at equal intervals, the inner threads of the mounting holes (9) are connected with threaded rods (5), and the outer threads of the threaded rods (5) are connected with fastening bolts (6).
3. The asphalt waterproof material conveying pipeline according to claim 1, wherein the insertion rods (10) are welded on one side of the main connecting piece (3), the insertion holes (11) are formed in the auxiliary connecting pieces (4), and the insertion rods (10) are inserted into the insertion holes (11).
4. The conveying pipeline of asphalt waterproof materials as claimed in claim 3, wherein both sides of the main connecting piece (3) are connected with screws (7) in a threaded manner, the outer threads of the screws (7) are connected with fixing bolts (8), the screws (7) penetrate through the sealing rings (22), and the end parts of the screws (7) are welded with the barrier plates (12).
5. The asphalt waterproofing material conveying pipeline according to claim 4, wherein a fixed part (16) is welded on one side of the barrier plate (12), and a rotating plate (13) is sleeved outside the fixed part (16).
6. The asphalt waterproofing material conveying pipeline according to claim 5, wherein the rotating plate (13) and the blocking plate (12) are provided with circulation holes (14) at equal intervals in a ring shape, and a push rod (15) is welded on one side of the rotating plate (13).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201922170721.8U CN211599829U (en) | 2019-12-06 | 2019-12-06 | Transmission pipeline of asphalt waterproof material |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201922170721.8U CN211599829U (en) | 2019-12-06 | 2019-12-06 | Transmission pipeline of asphalt waterproof material |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211599829U true CN211599829U (en) | 2020-09-29 |
Family
ID=72591022
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201922170721.8U Active CN211599829U (en) | 2019-12-06 | 2019-12-06 | Transmission pipeline of asphalt waterproof material |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211599829U (en) |
-
2019
- 2019-12-06 CN CN201922170721.8U patent/CN211599829U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN211599829U (en) | Transmission pipeline of asphalt waterproof material | |
CN103712005A (en) | Dual-seal flange plate | |
CN205383355U (en) | Add stationary high pressure petroleum transportation pipeline | |
CN220337699U (en) | Prefabricated directly buried heat preservation pipe joint structure | |
CN203940137U (en) | A kind of Pneumatic conveying pipeline | |
CN202914933U (en) | Double sealing flange | |
CN211976181U (en) | Petroleum pipeline joint connecting device | |
CN207673293U (en) | A kind of oil-gas mining casing | |
CN210830979U (en) | Petroleum pipeline sleeve | |
CN211821188U (en) | Plug-in type petroleum pipeline joint | |
CN206130523U (en) | Novel fluid loading and unloading arm | |
CN211371635U (en) | Tunnel construction prevents leaking device | |
CN215215179U (en) | Natural gas line erects device | |
CN204452835U (en) | A kind of single straight-through liquid in rotation passage being applicable to the outer communication system of spread mooring FPSO | |
CN203568836U (en) | Novel cryogenic fluid loading arm | |
CN201539664U (en) | Leakage stopping device | |
CN220894085U (en) | Impervious detection device of concrete lining segment | |
CN212107263U (en) | Steel bushing steel insulating pipe nipple joint with PE layer on outer wall of steel pipe | |
CN213332957U (en) | Standard sealing element for bearing positioning conveying pipe | |
CN104477335A (en) | Single straight-through liquid rotation passage applicable to multi-point mooring FPSO (Floating Production Storage and Offloading) system | |
CN211344342U (en) | Efficient sealing and corrosion-resistant flange for petroleum pipeline | |
CN212004679U (en) | Petroleum pipeline connecting device | |
CN213954992U (en) | Ship bank connecting device, ship bank connecting assembly and feeding and discharging system | |
CN214947051U (en) | Multilayer composite flexible low-permeability fuel pipe | |
CN203568837U (en) | Novel fluid loading and unloading arm |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |