Anchoring device for electric power transmission tower base Download PDFInfo
- Publication number
- CN211572845U CN211572845U CN201921892157.4U CN201921892157U CN211572845U CN 211572845 U CN211572845 U CN 211572845U CN 201921892157 U CN201921892157 U CN 201921892157U CN 211572845 U CN211572845 U CN 211572845U
- Authority
- CN
- China
- Prior art keywords
- limiting plate
- base
- bolt
- power transmission
- spliced pole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000005540 biological transmission Effects 0.000 title claims abstract description 31
- 238000004873 anchoring Methods 0.000 title claims description 18
- 230000007306 turnover Effects 0.000 claims description 2
- 230000003827 upregulation Effects 0.000 claims description 2
- 230000000694 effects Effects 0.000 abstract description 12
- 230000033228 biological regulation Effects 0.000 abstract description 10
- 230000003014 reinforcing effect Effects 0.000 abstract description 3
- 238000003780 insertion Methods 0.000 description 2
- 230000037431 insertion Effects 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000009977 dual effect Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000000087 stabilizing effect Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Images
Landscapes
- Electric Cable Installation (AREA)
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
The utility model provides an electric power transmission tower is anchor for base belongs to electric power transmission technical field, including the base, the base is trapezoidal base setting, and the outside fixed surface of base is connected with the connecting plate and has seted up the support groove, and the spout is transversely seted up on the surface of base, and the inside embedding of spout sets up the spliced pole, and the inside top embedding of spliced pole is provided with first limiting plate and second limiting plate, and the surface of first limiting plate and second limiting plate all imbeds and sets up first bolt and second bolt. Through the connecting plate that holds support groove and protrusion setting of indent setting, after being connected the bottom and the spliced pole of power transmission tower again, the base imbeds in ground, holds the effectual reinforcing ground of support groove and connecting plate and the pressure that the base was applyed, reaches and connects fixed effect, through the spliced pole of slidable position regulation, the person of being convenient for use adjusts the connection according to the bottom structure of carrying the tower.
Description
Technical Field
The utility model relates to an electric power transmission technical field, more specifically relates to an electric power transmission tower is anchor for base.
Background
The power transmission tower is a tower-shaped building in a trapezoid or triangle shape and the like, is of a steel frame structure, is mostly built near a power plant and a power distribution station in the field, is an important facility of a power department, can be used for overhead wire and plays a role in protection and support, and the design, manufacture, installation, maintenance and quality detection of the power transmission tower are important guarantees for the operation and development of a modern power system.
The anchoring device can be used for stabilizing the electric power transmission tower in the process of building the electric power transmission tower, but the operation process of the existing anchoring device is complicated, the working efficiency of workers is influenced, the labor intensity of the workers is increased, and meanwhile, when the existing anchoring device is limited and fixed, the effect of stable connection is far from insufficient by limiting and fixing the leakage structure position, so that a new anchoring device for the electric power transmission tower base is needed.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the problem in the background to a power transmission tower is anchor for base is provided.
In order to achieve the above object, the utility model provides a following technical scheme: the base is a trapezoidal base, the outside fixed surface of base is connected with the connecting plate and has been seted up and hold the groove, the spout is transversely seted up on the surface of base, the inside embedding of spout sets up the spliced pole, the embedding of the inside top of spliced pole is provided with first limiting plate and second limiting plate, the equal embedding in surface of first limiting plate and second limiting plate sets up first bolt and second bolt, the surface of spliced pole corresponds first bolt and sets up the embedding hole with second bolt position, the embedding in inside bottom of spliced pole sets up the regulation post and adjusts the pole, the top fixedly connected with fixed plate of pole adjusts.
Preferably, the supporting groove is arranged in a rectangular concave manner and is positioned on two sides of the surface of the base, and the connecting plate is transversely protruded and forms an included angle with the surface connecting position of the base.
Preferably, the connecting column is vertically arranged on the top surface of the base, and the connecting column is embedded in the sliding groove in a sliding mode.
Preferably, first limiting plate and second limiting plate set up respectively relatively, and first limiting plate and second limiting plate are located the inner wall all around of spliced pole, and the position setting between two parties in surface of first limiting plate is the setting of rectangle indent, and the second limiting plate is located the inboard both ends of first limiting plate.
Preferably, the first bolt penetrates through the surface of the connecting column and is fixedly connected with the first limiting plate, and the second bolt penetrates through the surface of the connecting column and simultaneously penetrates through one side of the first limiting plate and is fixedly connected with the second limiting plate.
Preferably, the insertion hole is arranged corresponding to the first bolt and the second bolt, and threads on the surfaces of the first bolt and the second bolt are arranged in a triangular flat shape.
Preferably, the adjusting column is transversely embedded and spirally connected with the connecting column, the adjusting column is positioned above the adjusting rod, and the inner end of the adjusting column is opposite to the surface of the adjusting rod.
Preferably, the adjusting rod is arranged to be inclined upwards, and the adjusting rod is connected with the inner wall of the connecting column in a turnover mode.
The utility model provides an electric power transmission tower is anchor for base has following beneficial effect:
1. this kind of anchoring device for electric power transmission tower base, through the connecting plate that holds the support groove and the protrusion setting that the indent set up, after being connected the bottom and the spliced pole of electric power transmission tower again, the base imbeds in ground, holds the effectual reinforcing ground of support groove and connecting plate and the applied pressure of base, reaches and connects fixed effect.
2. This kind of anchoring device for electric power transmission tower base, but through the spliced pole of slidable position regulation, the user of being convenient for adjusts the connection according to the substructure of conveying tower.
3. This kind of anchoring device for electric power transmission tower base, limiting plate and bolted construction through corresponding setting, when using, drive first limiting plate through first bolt, the second bolt drives the second limiting plate, accomplishes the spacing fixed to conveying tower bottom structure, and the stack setting of first limiting plate and second limiting plate strengthens the fixed effect to conveying tower bottom structure.
4. This kind of anchoring device for electric power transmission tower base, through the embedding hole that is connected for the bolt screw thread of triangle-shaped and corresponding embedding, effectively improve the joint strength between bolt and the embedding hole for the bolt is more stable with the crushing resistance who corresponds the hole, reaches effective fixed effect.
5. This kind of anchoring device for electric power transmission tower base contacts the regulation pole through adjusting the post internal rotation, exerts the external pressure to the regulation pole for adjust the upset of pole internal movement, drive the fixed plate and exert pressure to transport tower bottom structure, thereby reach fixed effect.
Drawings
Fig. 1 is a top view of the overall structure of the present invention.
Fig. 2 is a top view of the connection structure of the connection column of the present invention.
Fig. 3 is a sectional view of a connection structure of a first bolt and an insertion hole according to the present invention.
Fig. 4 is a sectional view of the internal structure of the connecting column of the present invention.
In FIGS. 1-4: 1-base, 2-supporting groove, 3-connecting plate, 4-connecting column, 5-first bolt, 6-first limiting plate, 7-second bolt, 8-second limiting plate, 9-embedding hole, 10-adjusting column, 11-fixing plate, 12-adjusting rod and 13-sliding chute.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Please refer to fig. 1 to 4, in the embodiment of the utility model, an electric power transmission tower is anchor for base, including base 1, base 1 is trapezoidal base setting, base 1's outside fixed surface is connected with connecting plate 3 and has seted up and hold support groove 2, spout 13 is transversely seted up on base 1's surface, spout 13's inside embedding sets up spliced pole 4, spliced pole 4's inside top embedding is provided with first limiting plate 6 and second limiting plate 8, first limiting plate 6 all imbeds with second limiting plate 8's surface and sets up first bolt 5 and second bolt 7, spliced pole 4's surface corresponds first bolt 5 and sets up embedding hole 9 with second bolt 7 position, spliced pole 4's inside bottom embedding sets up regulation post 10 and adjusts pole 12, the top fixedly connected with fixed plate 11 of adjusting pole 12.
In this embodiment, bearing groove 2 is the setting of rectangle indent, is located base 1's surface both sides, and connecting plate 3 is the setting of horizontal protrusion, is the contained angle with base 1's surperficial hookup location, and bearing groove 2 through the indent setting and the connecting plate 3 of protrusion setting are connected the bottom of power transmission tower and spliced pole 4 afterwards, and base 1 imbeds in the ground, and the effectual reinforcing ground of bearing groove 2 and connecting plate 3 reaches and connects fixed effect with the pressure that base 1 applyed.
In this embodiment, spliced pole 4 is perpendicular setting at the top surface of base 1, and spliced pole 4 slip embedding is in spout 13 simultaneously, and through the spliced pole 4 of slidable position, the user of being convenient for adjusts the connection according to the bottom structure of carrying the tower.
In this embodiment, first limiting plate 6 and second limiting plate 8 set up relatively separately, and first limiting plate 6 and second limiting plate 8 are located spliced pole 4 inner wall all around, and the position setting placed in the middle of the surface of first limiting plate 6 is the setting of rectangle indent, and second limiting plate 8 is located the inboard both ends of first limiting plate 6.
In this embodiment, first bolt 5 passes the first limiting plate 6 of 4 fixed surface connections of spliced pole, and second bolt 7 passes one side at first limiting plate 6 when passing 4 surfaces of spliced pole, fixed connection second limiting plate 8, limiting plate and bolt structure through corresponding setting, when using, drive first limiting plate 6 through first bolt 5, second bolt 7 drives second limiting plate 8, accomplish the spacing fixed to conveying tower bottom structure, and the stack setting of first limiting plate 6 and second limiting plate 8, reinforce the fixed effect to conveying tower bottom structure.
In this embodiment, the embedding hole 9 corresponds first bolt 5 and the setting of second bolt 7, and the screw thread on first bolt 5 and the surface of second bolt 7 is triangle platykurtic and sets up, and through the embedding hole 9 that is connected for the bolt screw thread of triangle-shaped and corresponding embedding, effectively improve the joint strength between bolt and the embedding hole 9 for the bolt is more stable with the crushing resistance who corresponds the hole, reaches effective fixed effect.
In this embodiment, adjust post 10 and be horizontal embedding setting, and be screwed connection with spliced pole 4, adjust the top that post 10 is located regulation pole 12 simultaneously, the inner is just to adjusting pole 12 surface, thereby contact regulation pole 12 through adjusting the inside rotation of post 10, apply the external pressure to regulation pole 12 for adjust pole 12 upset of inside activity, drive fixed plate 11 and exert pressure to transport tower bottom structure, thereby reach fixed effect.
In this embodiment, the adjusting rod 12 is disposed to be inclined upward, and the adjusting rod 12 is connected to the inner wall of the connecting column 4 in an overturned manner.
Use the utility model relates to an electric power transmission tower is during anchor for base, at first, user of service buries base 1 in the ground, it is fixed with holding groove 2 and carrying out the connection through outside fixed part to pass connecting plate 3, later adjust the position of spliced pole 4 in spout 13, user of service makes the embedding of transport tower bottom structure in spliced pole 4, rotatory first bolt 5 of user of service and second bolt 7, it is fixed to drive first limiting plate 6 and second limiting plate 8 and press from both sides the clamp to transport tower bottom structure, rotatory regulation post 10 simultaneously, exert pressure to adjusting pole 12 when adjusting post 10 rotatory, make and adjust pole 12 inside upset regulation, it contacts the bottom structure of transport tower to drive fixed plate 11, accomplish the dual fixed to transport tower bottom structure.
The above is only the preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, without departing from the concept of the present invention, several modifications and improvements can be made, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicability of the patent.
Claims (8)
1. The utility model provides an anchor for power transmission tower base, includes base (1), its characterized in that: base (1) is trapezoidal base setting, the outside fixed surface of base (1) is connected with connecting plate (3) and has seted up and hold support groove (2), spout (13) are transversely seted up on the surface of base (1), the inside embedding of spout (13) sets up spliced pole (4), the inside top embedding of spliced pole (4) is provided with first limiting plate (6) and second limiting plate (8), first limiting plate (6) all imbeds with the surface of second limiting plate (8) and sets up first bolt (5) and second bolt (7), the surface of spliced pole (4) corresponds first bolt (5) and sets up embedding hole (9) with second bolt (7) position, the inside bottom embedding of spliced pole (4) sets up regulation post (10) and adjusts pole (12), the top fixedly connected with fixed plate (11) of adjusting pole (12).
2. The anchoring device for a power transmission tower base according to claim 1, wherein: the supporting grooves (2) are arranged in a rectangular concave manner and are positioned on two sides of the surface of the base (1), and the connecting plates (3) are arranged in a transverse protruding manner and form included angles with the surface connecting positions of the base (1).
3. The anchoring device for a power transmission tower base according to claim 1, wherein: the connecting column (4) is vertically arranged on the top surface of the base (1), and the connecting column (4) is embedded into the sliding groove (13) in a sliding mode.
4. The anchoring device for a power transmission tower base according to claim 1, wherein: first limiting plate (6) and second limiting plate (8) set up relatively separately, and first limiting plate (6) and second limiting plate (8) are located the inner wall all around of spliced pole (4), and the surface position setting placed in the middle of first limiting plate (6) is the setting of rectangle indent, and second limiting plate (8) are located the inboard both ends of first limiting plate (6).
5. The anchoring device for a power transmission tower base according to claim 1, wherein: first bolt (5) pass spliced pole (4) surface fixed connection first limiting plate (6), and second bolt (7) pass in one side of first limiting plate (6), fixed connection second limiting plate (8) when passing spliced pole (4) surface.
6. The anchoring device for a power transmission tower base according to claim 1, wherein: the embedding hole (9) is arranged corresponding to the first bolt (5) and the second bolt (7), and threads on the surfaces of the first bolt (5) and the second bolt (7) are arranged in a triangular flat shape.
7. The anchoring device for a power transmission tower base according to claim 1, wherein: the adjusting column (10) is transversely embedded and is spirally connected with the connecting column (4), the adjusting column (10) is located above the adjusting rod (12), and the inner end of the adjusting column is opposite to the surface of the adjusting rod (12).
8. The anchoring device for a power transmission tower base according to claim 1, wherein: the adjusting rod (12) is arranged to be inclined upwards, and the adjusting rod (12) is connected with the inner wall of the connecting column (4) in a turnover mode.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921892157.4U CN211572845U (en) | 2019-11-05 | 2019-11-05 | Anchoring device for electric power transmission tower base |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921892157.4U CN211572845U (en) | 2019-11-05 | 2019-11-05 | Anchoring device for electric power transmission tower base |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211572845U true CN211572845U (en) | 2020-09-25 |
Family
ID=72531474
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921892157.4U Expired - Fee Related CN211572845U (en) | 2019-11-05 | 2019-11-05 | Anchoring device for electric power transmission tower base |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211572845U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113863765A (en) * | 2021-11-11 | 2021-12-31 | 中国电建集团河北省电力勘测设计研究院有限公司 | Power transmission tower base anchoring device and mounting and dismounting method thereof |
-
2019
- 2019-11-05 CN CN201921892157.4U patent/CN211572845U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113863765A (en) * | 2021-11-11 | 2021-12-31 | 中国电建集团河北省电力勘测设计研究院有限公司 | Power transmission tower base anchoring device and mounting and dismounting method thereof |
CN113863765B (en) * | 2021-11-11 | 2022-11-08 | 中国电建集团河北省电力勘测设计研究院有限公司 | Power transmission tower base anchoring device and mounting and dismounting method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205123185U (en) | Non -maintaining insulator wire fixation clamp | |
CN211572845U (en) | Anchoring device for electric power transmission tower base | |
CN106786314B (en) | A kind of cement pole ground wire resetting apparatus | |
CN205189428U (en) | Push -pull system is opened to bent panel mount carbon fiber plate ground tackle | |
CN104005410B (en) | A kind of stretching and anchoring device based on prestressing without bondn reinforced earth technology | |
CN110190551A (en) | A kind of route cleaning and maintenance equipment used for transmission line | |
CN203301067U (en) | Apparatus for replacing pin insulator | |
CN211646868U (en) | Curtain upper end cable tensioning structure | |
CN202259718U (en) | Movable-type grounding pile | |
CN201933695U (en) | Prestressed steel bar fixing anchorage device | |
CN211456475U (en) | Two cluster bent plate cards of sharp steel-pipe pole | |
CN206323110U (en) | A kind of cement pole ground wire resetting means | |
CN202181614U (en) | Steel pipe fixing device for joist steel | |
CN102086699B (en) | Anti-drop clamping apparatus for connecting assembled steel large formwork with dorsal bar | |
CN216687076U (en) | A hoist device for roofing material promotes | |
CN215169677U (en) | Climbing device for electric power tower | |
CN210944487U (en) | High-speed wire roller box lifting appliance | |
CN218088696U (en) | Tower passageway department perpendicular protector on tower crane | |
CN215496282U (en) | Transformer mounting structure convenient to maintenance | |
CN216516551U (en) | Adjustable fixing device for inclined-pulling steel wire rope of overhanging protective shed | |
CN210947784U (en) | Building embedded part | |
CN211572001U (en) | Steel structure stress structure for building | |
CN210860651U (en) | Support is used in gas holder installation convenient to adjust | |
CN216649579U (en) | Safe and reliable's guide rail photovoltaic board mounting of exempting from | |
CN218377202U (en) | Membrane boundary fixing device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20221104 Address after: 719315 Li Jia pan Cun, Daliuta Town, Shenmu City, Yulin City, Shaanxi Province Patentee after: Shenmu Rock Drilling Tools Co.,Ltd. Address before: No. 402, gate 1, building 10, Gongqian Dongyuan, Bawei Road, Hedong District, Tianjin Patentee before: Mao Aohua |
|
TR01 | Transfer of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200925 |
|
CF01 | Termination of patent right due to non-payment of annual fee |