CN211526066U - Gas storage well stabilizing system - Google Patents

Gas storage well stabilizing system Download PDF

Info

Publication number
CN211526066U
CN211526066U CN201922099170.0U CN201922099170U CN211526066U CN 211526066 U CN211526066 U CN 211526066U CN 201922099170 U CN201922099170 U CN 201922099170U CN 211526066 U CN211526066 U CN 211526066U
Authority
CN
China
Prior art keywords
gas storage
storage well
concrete layer
structural
well body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922099170.0U
Other languages
Chinese (zh)
Inventor
陈伟
陈玮晟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Oil Natural Gas Technology Co ltd
Original Assignee
Sichuan Oil Natural Gas Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Oil Natural Gas Technology Co ltd filed Critical Sichuan Oil Natural Gas Technology Co ltd
Priority to CN201922099170.0U priority Critical patent/CN211526066U/en
Application granted granted Critical
Publication of CN211526066U publication Critical patent/CN211526066U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

The utility model provides a gas storage well firm system relates to gas storage well technical field. The gas storage wells are generally provided with a plurality of gas storage wells, and after a period of time, other instability phenomena such as rising or sinking and the like can occur in individual gas storage wells, so that safety accidents are easy to happen. The utility model discloses an at least two gas storage well bodies, gas storage well body part is buried underground, the gas storage well body is located and is equipped with one deck concrete layer around the underground part, concrete layer surrounds the gas storage well body, the cover is equipped with a plurality of sleeves on the gas storage well body, the corresponding structural slab that is equipped with corresponding quantity in the concrete layer, it is equipped with the through-hole that supplies the sleeve pipe to pass and connect to correspond the position on the structural slab, the concrete layer side still is equipped with a plurality of firm boards, firm board extends to its underground on every side in by concrete layer, the structural slab makes a plurality of gas storage well bodies form a stable overall structure in concrete layer, prevent local or individual gas storage well from emitting or sinking, the structural slab prevents the concrete layer unstability.

Description

Gas storage well stabilizing system
Technical Field
Relate to gas storage well technical field, concretely relates to gas storage well stable system.
Background
At present, natural gas energy construction is greatly promoted in various places, the policy of reducing environmental pollution is met, CNG gas stations, factories and other CNG peak shaving stations are constructed, and high-pressure underground gas storage wells are the first choice of a plurality of gas storage modes.
High pressure underground gas storage well generally is provided with a plurality ofly, and wherein some potential safety hazards will appear after the use of a period of time in individual gas storage well, for example the pit shaft of individual gas storage well takes place to rise or sink other unstability phenomena, leads to the emergence of incident, needs solve urgently.
Disclosure of Invention
The utility model aims at developing a gas storage well stabilizing system which enables a plurality of gas storage wells to form a stable integral structure so as to further stabilize the structure of the gas storage well.
The utility model discloses a following technical scheme realizes:
gas storage well firm system, including two at least gas storage well bodies, gas storage well body part is buried underground, the gas storage well body is located and is equipped with one deck concrete layer around the underground part, concrete layer surrounds the gas storage well body, the cover is equipped with a plurality of sleeves on the gas storage well body, correspond the structural slab that is equipped with corresponding quantity in the concrete layer, correspond the position on the structural slab and be equipped with the through-hole that supplies the sleeve pipe to pass and connect, the concrete layer side still is equipped with a plurality of firm boards, firm board extends to its underground on every side by the concrete layer in, and the structural slab makes a plurality of gas storage well bodies form a stable overall structure in the concrete layer, prevents to spill or sink on local or individual gas storage well, and the structural slab prevents concrete layer unstability.
Further, the gas storage well body is sleeved with a plurality of anchor ears, and a plurality of structure cross rods are circumferentially arranged on the anchor ears.
Further, a structural cross rod is arranged between the plurality of structural plates and connects the plurality of structural plates.
Furthermore, the structure vertical rods are connected with a plurality of structure cross rods which are arranged up and down on the same gas storage well body.
Further, the upper portion and the lower portion of the gas storage well body are respectively sleeved with a sleeve, two structural plates are correspondingly arranged in the concrete layer, and through holes for the sleeves to penetrate through and be connected are formed in the structural plates in opposite positions.
Further, the cover is equipped with two staple bolts on the gas storage well body, staple bolt circumference equidistant is equipped with four structure horizontal poles.
Further, the structure horizontal pole of two staple bolts on the gas storage well body sets up relatively, makes the tip of the structure horizontal pole of two staple bolts on same vertical line, gas storage well body circumference correspondence is equipped with four structure montants, four the structure montant is respectively with the end connection of the structure horizontal pole of two staple bolts.
Furthermore, it is a plurality of the firm board includes the steel reinforcement cage of a plurality of irregular locating concrete layer sides, be equipped with the concrete on the steel reinforcement cage.
The utility model has the advantages that:
the utility model discloses a structural slab buries a plurality of gas storage well integration underground in concrete layer, makes to form stable overall structure between the gas storage well, restricts each other, prevents to emit or sink on local or the gas storage well individually to this overall structure stability who strengthens a plurality of gas storage wells, and the firm board of concrete layer side makes concrete layer stabilize and locates the underground, prevents concrete layer unstability.
Drawings
In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present application, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
FIG. 1 is a view of the structure of the present invention;
fig. 2 is a hoop structure diagram.
Detailed Description
In the following, only certain exemplary embodiments are briefly described. As those skilled in the art can appreciate, the described embodiments may be modified in various different ways, without departing from the spirit or scope of the invention. Accordingly, the drawings and description are to be regarded as illustrative in nature, and not as restrictive.
In the description of the present invention, it is to be understood that the terms "central," "longitudinal," "lateral," "length," "width," "thickness," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," "clockwise," "counterclockwise," "axial," "radial," "circumferential," and the like are used in the orientations and positional relationships indicated in the drawings for convenience in describing the present invention, and are not intended to indicate or imply that the referenced devices or elements must have a particular orientation, be constructed and operated in a particular orientation, and are therefore not to be considered limiting of the present invention.
Embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
As shown in fig. 1 and 2, the embodiment discloses a gas storage well stabilizing system, which comprises at least two gas storage well bodies 1, the gas storage well body 1 is partially buried underground, a concrete layer 7 is arranged around the underground part of the gas storage well body 1, the concrete layer 7 surrounds the gas storage well body 1, a plurality of sleeves 8 are sleeved on the gas storage well body 1, a corresponding number of structural plates 6 are correspondingly arranged in the concrete layer 7, through holes for the sleeves 8 to pass through and be connected are correspondingly arranged on the structural plates 6, the side of the concrete layer 7 is also provided with a plurality of stabilizing plates 2, the stabilizing plates 2 extend from the interior of the concrete layer 7 to the underground surrounding the concrete layer, the structural plates 6 enable the plurality of gas storage well bodies 1 to form a stable integral structure in the concrete layer 7, the local or individual gas storage wells are prevented from rising or sinking, and the structural plates 6 prevent the instability of the concrete layer 7.
Specifically, this embodiment includes two the same gas storage well bodies 1, corresponding parts such as fluid-discharge tube, manometer and inlet/outlet duct are equipped with at 1 top of gas storage well body, gas storage well body 1 is vertically buried underground.
Concrete layer 7 is made by the concrete material, and concrete layer 7's top surface and bottom surface coplanar, concrete layer 7 side is the arcwall face, concrete layer 7 side is equipped with a plurality of platelike structure's steadying board 2, steadying board 2 includes the steel reinforcement cage as its inner structure, steel reinforcement cage part is located concrete layer 7, and other part extends to the underground in the concrete layer 7 outside, steel reinforcement cage is irregularly arranged on concrete layer 7 side, the steel reinforcement cage pours concrete, makes it become steadying board 2, steadying board 2 multiplicable concrete layer 7 and its circumference's area of contact makes concrete layer 7 more firm with its circumference's underground connection, prevents concrete layer 7 unstability.
1 upper portion and lower part of gas storage well body are equipped with two sleeve pipes 8 respectively, 8 covers of sleeve pipe are established at 1 outer wall of gas storage well body, and sleeve pipe 8 and 1 fixed connection of gas storage well body are located its top surface of sleeve pipe 8 on 1 upper portion of gas storage well body is coplanar with 7 top surfaces of concrete layer, it is equipped with two structure boards 6 of arranging from top to bottom and being connected with 1 upper portion sleeve pipe 8 of gas storage well body and lower part sleeve pipe 8 respectively to correspond the position in the concrete layer 7, correspond the position on structure board 6 and be equipped with the through-hole with 8 complex of sleeve pipe, sleeve pipe 8 is located the through-hole of structure board 6, 8 outer walls of sleeve pipe and through-hole inner wall fixed connection, 6 horizontal arrangements of structure board, structure board 6 becomes a whole with sleeve pipe 8 and 1 fixed connection of gas.
The gas storage well body 1 is sleeved with two hoops 5, the two hoops 5 are arranged up and down, the hoops 5 are provided with four structural cross rods 4, the four structural cross rods 4 are arranged in the circumferential direction of the hoops 5 at equal intervals, the structural cross rods 4 are horizontally arranged, the structural cross rods 4 of the two hoops 5 on the same gas storage well body 1 are correspondingly arranged, so that the end parts of the structural cross rods 4 on the two hoops 5 are on the same vertical line, the gas storage well body 1 is also correspondingly provided with four structural vertical rods 3 connected with the structural cross rods 4 in the circumferential direction, the top ends and the bottom ends of the structural vertical rods 3 are respectively connected with two structural plates 6, the end parts of the two structural cross rods 4 which are adjacent up and down are also connected, the structural cross rods 4 are arranged, so that the gas storage well body 1 is further stably arranged in a concrete layer 7, and the gas storage well body 1 is further integrated, the structure montant 3 not only strengthens the steadiness between two structural slab 6 to it is firm to further make gas storage well body 1 be connected with the structural rod, prevents that two structural slab 6 from taking place relative displacement in concrete layer 7, makes gas storage well body 1 and structural slab 6 further integration.
The utility model discloses a structural slab 6 buries a plurality of gas storage well integration underground in concrete layer 7, makes to form stable overall structure between the gas storage well, restricts each other, prevents to emit or sink on local or the gas storage well individually to this overall structure stability who strengthens a plurality of gas storage wells, and the firm board 2 that stabilizes of concrete layer 7 side makes concrete layer 7 firm locate the underground, prevents concrete layer 7 unstability.
The above-mentioned embodiment is only the preferred embodiment of the present invention, and is not to the limitation of the technical solution of the present invention, as long as the technical solution can be realized on the basis of the above-mentioned embodiment without creative work, all should be regarded as falling into the protection scope of the right of the present invention.

Claims (7)

1. Gas storage well firm system, its characterized in that includes two at least gas storage well bodies, gas storage well body part is buried underground, the gas storage well body is located and is equipped with one deck concrete layer around the underground part, concrete layer surrounds the gas storage well body, the cover is equipped with a plurality of sleeves on the gas storage well body, correspond the structural slab that is equipped with corresponding quantity in the concrete layer, correspond the position on the structural slab and be equipped with the through-hole that supplies the sleeve pipe to pass and connect, the concrete layer side still is equipped with a plurality of firm boards, firm board extends to its underground on every side in by the concrete layer.
2. The gas storage well stabilization system according to claim 1, wherein a plurality of hoops are sleeved on the gas storage well body, and a plurality of structural cross bars are arranged on the hoop in the circumferential direction.
3. The gas storage well stabilization system according to claim 2, wherein a structural cross-bar is provided between a plurality of said structural plates, said structural cross-bar connecting a plurality of structural plates.
4. The gas storage well stabilizing system according to claim 3, wherein a sleeve is sleeved on each of the upper and lower parts of the gas storage well body, two structural plates are correspondingly arranged in the concrete layer, and through holes for the sleeves to pass through and connect are respectively arranged on the structural plates in opposite positions.
5. The gas storage well stabilization system according to claim 4, wherein two hoops are sleeved on the gas storage well body, and four structural cross bars are circumferentially arranged at equal intervals on the hoops.
6. The gas storage well stabilizing system according to claim 5, wherein the structural cross bars of the two hoops on the gas storage well body are oppositely arranged, so that the end parts of the structural cross bars of the two hoops are on the same vertical line, four structural vertical bars are correspondingly arranged in the circumferential direction of the gas storage well body, and the four structural vertical bars connect the end parts of the structural cross bars of the two hoops respectively.
7. The gas storage well stabilizing system according to claim 6, wherein the plurality of stabilizing plates comprise a plurality of reinforcement cages irregularly arranged on the side of the concrete layer, and concrete is arranged on the reinforcement cages.
CN201922099170.0U 2019-11-29 2019-11-29 Gas storage well stabilizing system Active CN211526066U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922099170.0U CN211526066U (en) 2019-11-29 2019-11-29 Gas storage well stabilizing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922099170.0U CN211526066U (en) 2019-11-29 2019-11-29 Gas storage well stabilizing system

Publications (1)

Publication Number Publication Date
CN211526066U true CN211526066U (en) 2020-09-18

Family

ID=72444255

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922099170.0U Active CN211526066U (en) 2019-11-29 2019-11-29 Gas storage well stabilizing system

Country Status (1)

Country Link
CN (1) CN211526066U (en)

Similar Documents

Publication Publication Date Title
CN109853527B (en) Precast pile, connection structure of precast pile and construction method of connection structure
CN211526066U (en) Gas storage well stabilizing system
CN105298021A (en) Circular steel tube concrete column and anti-buckling reinforcement and repair method thereof
CN108678791B (en) Novel combined type lock foot stock node device
JP2008025148A (en) Large-sized composite pile composed of steel pipe and soil cement
CN103335172A (en) Oil platform pipeline protection tube capable of meeting different pipe diameters
CN103397650B (en) A kind of large-scale steel cylinder cofferdam structure
JP2005076274A (en) Divided earth retaining frame
CN107083800B (en) Module pool
CN204163077U (en) There is the prestressed concrete pipe pile device of function of prevent erosion
CN212583339U (en) Assembled constructional column for building reinforcement
CN212927320U (en) Foundation pit steel guardrail
CN217711383U (en) Construction structure of oblique steel pipe column and columnar steel reinforcement cage of steel structure conversion layer
CN103322377A (en) Petroleum pipeline joint protection pipe
CN211421599U (en) Quick connection structure of steel core concrete column
CN210950629U (en) Auxiliary positioning support device built by utilizing waste wood
CN218882253U (en) Supporting system for shield well hole template
CN211690323U (en) Concrete pipe pile convenient for pouring steel slag
CN220521315U (en) Prestressed concrete pipe pile
CN210768845U (en) Supporting component for roadway excavation
CN103266856B (en) Rotary drilling rig and follow-up frame thereof
CN203322507U (en) Double-barrelled petroleum platform pipeline protecting tube
CN217782020U (en) Hollow concrete precast tubular pile used as core pile of combined pile
CN217556939U (en) Foundation ditch length secant pile is strutted
CN211006683U (en) Foundation pit supporting structure and foundation pit supporting assembly

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant