CN211524083U - Air conditioner pre-tapping aluminum alloy template assembly - Google Patents

Air conditioner pre-tapping aluminum alloy template assembly Download PDF

Info

Publication number
CN211524083U
CN211524083U CN201922250834.9U CN201922250834U CN211524083U CN 211524083 U CN211524083 U CN 211524083U CN 201922250834 U CN201922250834 U CN 201922250834U CN 211524083 U CN211524083 U CN 211524083U
Authority
CN
China
Prior art keywords
aluminum alloy
alloy template
air conditioner
template
pvc pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922250834.9U
Other languages
Chinese (zh)
Inventor
覃颂
杨浩
陈肖
潘佳帅
冯东海
周彩凤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN201922250834.9U priority Critical patent/CN211524083U/en
Application granted granted Critical
Publication of CN211524083U publication Critical patent/CN211524083U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Other Air-Conditioning Systems (AREA)

Abstract

The utility model discloses an air conditioner trompil aluminum alloy template subassembly in advance, left aluminum alloy template and right aluminum alloy template including bilateral symmetry setting, set up the preformed hole of symmetry on left side aluminum alloy template and the right aluminum alloy template, it has the aluminum alloy circle to lead to alternate in the preformed hole, and the both ends that the aluminum alloy circle leads to are fixed in the preformed hole, and it is fixed to make the aluminum alloy circle lead to can be relative left aluminum alloy template and right aluminum alloy template. The outside cover of aluminum alloy circle expert is equipped with the PVC pipe, and the PVC pipe is for keeping somewhere the subassembly in the preformed hole of wall, and the aluminum alloy circle expert can fix a position the PVC pipe, prevents the dislocation of PVC pipe. The two ends of the PVC pipe are inserted into the reserved holes or are connected between the inner wall of the left aluminum alloy template and the inner wall of the right aluminum alloy template in a jacking mode. The utility model provides a problem of reserving the hole such as air conditioner, not only can carry out reliable location to the air conditioner trompil in advance, can avoid leaking the thick liquid scheduling problem moreover, make the air conditioner reserve the hole shaping good.

Description

Air conditioner pre-tapping aluminum alloy template assembly
Technical Field
The utility model relates to an aluminum alloy template technical field, especially an air conditioner trompil aluminum alloy template subassembly in advance.
Background
Because the existing aluminum alloy template has convenient construction, high efficiency, good stability, high bearing capacity and high efficiency of field management; the system avoids the phenomena of slurry leakage, mold expansion and the like caused by untight abutted seams of similar wood molds, has good concrete surface effect after mold removal, and can realize plastering-free. At present, 75mm PVC water pipes are bound at approximate positions of pre-perforated holes of a shear wall air conditioner for construction, and the PVC water pipes are directly bound on reinforcing steel bars in the construction method, so that the PVC water pipes are vertically deviated due to instability of the reinforcing steel bars. In addition, when the concrete is poured and pounded in the later period, the original binding position can also be displaced, even deviated.
SUMMERY OF THE UTILITY MODEL
Not enough to among the above-mentioned background art, the utility model provides an air conditioner trompil aluminum alloy template subassembly in advance has solved and has used the PVC water pipe to lead to the technical problem of off normal easily as the construction of shear force wall air conditioner trompil in advance among the prior art.
The technical scheme of the utility model is realized like this: the utility model provides an air conditioner trompil aluminum alloy template subassembly, includes left aluminum alloy template and the right aluminum alloy template that bilateral symmetry set up, set up the preformed hole of symmetry on left side aluminum alloy template and the right aluminum alloy template, the interlude has the aluminum alloy circle to lead to in the preformed hole, and the both ends that the aluminum alloy circle leads to are fixed in the preformed hole, make the aluminum alloy circle lead to can be fixed relative left aluminum alloy template and right aluminum alloy template. The outside cover of aluminum alloy circle expert is equipped with the PVC pipe, and the PVC pipe is for keeping somewhere the subassembly in the preformed hole of wall, and the aluminum alloy circle expert can fix a position the PVC pipe, prevents the dislocation of PVC pipe. The two ends of the PVC pipe are inserted into the reserved holes or are connected between the inner wall of the left aluminum alloy template and the inner wall of the right aluminum alloy template in a jacking mode.
Further, both ends of PVC pipe all are provided with the rubber gasket, and the rubber gasket can enough prevent to leak thick liquid, can effectively prevent again that the mortar from getting into between PVC pipe and the aluminum alloy circle expert, is convenient for pour and extracts the aluminum alloy circle expert after accomplishing.
Furthermore, two end parts of the aluminum alloy circular tube are provided with first pin holes, the left aluminum alloy template and the right aluminum alloy template are respectively provided with a second pin hole corresponding to the first pin holes, and fixing pins are matched with the first pin holes and the second pin holes.
Furthermore, the rubber gasket is positioned in the reserved hole, so that the sealing is ensured to be sufficient and reliable.
The utility model provides a problem of reserving the hole such as air conditioner, not only can carry out reliable location to the air conditioner trompil in advance, can avoid leaking the thick liquid scheduling problem moreover, make the air conditioner reserve the hole shaping good. Additionally, the utility model discloses can repetitious usage, present, the utility model discloses a use widely has improved efficiency of construction and economic benefits.
Drawings
In order to illustrate the embodiments of the present invention more clearly, the drawings that are needed in the description of the embodiments will be briefly described below, and it is obvious that the drawings in the description below are only some embodiments of the present invention, and that other drawings can be obtained by those skilled in the art without inventive work.
Fig. 1 is a schematic sectional view of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without any creative effort belong to the protection scope of the present invention.
The utility model provides an air conditioner trompil aluminum alloy template subassembly, as shown in figure 1, including left aluminum alloy template 1 and the right aluminum alloy template 2 that bilateral symmetry set up, set up the preformed hole 3 of symmetry on left side aluminum alloy template 1 and the right aluminum alloy template 2, the preformed hole alternates there is aluminum alloy circular through 4, and the both ends that the aluminum alloy circular through 4 are fixed in preformed hole 3, make aluminum alloy circular through 4 can be fixed with right aluminum alloy template 2 relative left aluminum alloy template. The aluminium alloy circle leads to 4 outside covers and is equipped with PVC pipe 5, and PVC pipe 5 is for keeping somewhere the subassembly in the preformed hole in the wall, and the aluminium alloy circle leads to 4 can fix a position PVC pipe 5, prevents PVC pipe 5 dislocation. Two ends of the PVC pipe 5 are inserted into the preformed hole 3 or are propped between the inner wall of the left aluminum alloy template 1 and the inner wall of the right aluminum alloy template 2.
Further, both ends of PVC pipe 5 all are provided with rubber gasket 6, and rubber gasket 6 can enough prevent to leak thick liquid, can effectively prevent again that the mortar from getting into between PVC pipe 5 and the aluminum alloy circle leads to 4, is convenient for pour and extracts the aluminum alloy circle and leads to 4 after accomplishing.
Further, the rubber gasket 6 is positioned in the preformed hole 3, so that the sealing is ensured to be sufficient and reliable.
Further, two end portions of the aluminum alloy circular tube 4 are provided with first pin holes 7, the left aluminum alloy template 1 and the right aluminum alloy template 2 are respectively provided with second pin holes corresponding to the first pin holes 7, and fixing pins 9 are arranged in cooperation with the first pin holes 7 and the second pin holes.
The present invention is not exhaustive and is well known to those skilled in the art.
The above description is only a preferred embodiment of the present invention, and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (4)

1. The utility model provides an air conditioner trompil aluminum alloy template subassembly in advance, includes left aluminum alloy template (1) and right aluminum alloy template (2) that bilateral symmetry set up, its characterized in that: set up the preformed hole (3) of symmetry on left side aluminum alloy template (1) and right aluminum alloy template (2), the preformed hole alternates there is aluminum alloy circle to lead to (4), and aluminum alloy circle is led to (4) outside cover and is equipped with PVC pipe (5), the both ends of PVC pipe (5) are pegged graft in preformed hole (3) or top joint is between the inner wall of left aluminum alloy template (1) and the inner wall of right aluminum alloy template (2).
2. The air conditioner pre-tapping aluminum alloy form assembly of claim 1, wherein: and rubber gaskets (6) are arranged at the two end parts of the PVC pipe (5).
3. The air conditioner pre-tapping aluminum alloy form assembly of claim 2, wherein: the aluminum alloy round tube is characterized in that first pin holes (7) are formed in two end portions of the aluminum alloy round tube (4), second pin holes corresponding to the first pin holes (7) are formed in the left aluminum alloy template (1) and the right aluminum alloy template (2), and fixing pins (9) are matched with the first pin holes (7) and the second pin holes.
4. The air conditioner pre-tapping aluminum alloy form assembly of claim 2 or 3, wherein: the rubber gasket (6) is positioned in the preformed hole (3).
CN201922250834.9U 2019-12-16 2019-12-16 Air conditioner pre-tapping aluminum alloy template assembly Active CN211524083U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922250834.9U CN211524083U (en) 2019-12-16 2019-12-16 Air conditioner pre-tapping aluminum alloy template assembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922250834.9U CN211524083U (en) 2019-12-16 2019-12-16 Air conditioner pre-tapping aluminum alloy template assembly

Publications (1)

Publication Number Publication Date
CN211524083U true CN211524083U (en) 2020-09-18

Family

ID=72445609

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922250834.9U Active CN211524083U (en) 2019-12-16 2019-12-16 Air conditioner pre-tapping aluminum alloy template assembly

Country Status (1)

Country Link
CN (1) CN211524083U (en)

Similar Documents

Publication Publication Date Title
CN108661671B (en) Vacuum auxiliary pouring method for tunnel vault secondary lining concrete
CN211524083U (en) Air conditioner pre-tapping aluminum alloy template assembly
CN109025899B (en) Well sealing device
CN213063608U (en) Connecting water-stopping structure between pipe joints of transverse bearing pipe curtain
CN216948636U (en) Mortar band-plastering mould for pipeline joint
CN215053224U (en) Basement waterproof structure
CN213979273U (en) Two-in-one basement side wall and bottom plate joint waterproof structure
CN215483149U (en) Waterproof structure of side wall and tunnel in subway main structure
CN110259488B (en) Rear embedded shield tunnel elastic sealing gasket, sealing structure and construction method
CN212908935U (en) Cable trench assembly unit and assembly body
CN213329486U (en) Stagnant water steel sheet for wallboard
CN214064186U (en) Novel QE cold expanding type pipe fitting
CN211948464U (en) Underground continuous wall and foundation slab's pre-buried steel sheet connection structure
CN212533962U (en) Canal lining device that hydraulic engineering used
CN211775777U (en) A waterproof embedded structure for exhaust passage
CN209977507U (en) Aluminum pipe connection sealing structure
CN216865175U (en) Composite structure of waist rail and side wall of main structure
CN209760271U (en) Precipitation well head shaping protection plugging device
CN218148448U (en) Fast assembly cofferdam that oil gas field used
CN212377463U (en) Connecting structure of wall-through embedded sleeve and water stop steel plate
CN217462167U (en) Water plugging structure for tunnel portal of shield segment
JPH027994Y2 (en)
CN210263130U (en) Prefabricated piping lane
CN109281692A (en) Built-in type section of jurisdiction gasket and its built-in process
CN215721326U (en) Water stop structure is reserved to effectual aluminium mould construction bathroom of antiseep

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant