CN211446608U CN201921738974.4U CN201921738974U CN211446608U CN 211446608 U CN211446608 U CN 211446608U CN 201921738974 U CN201921738974 U CN 201921738974U CN 211446608 U CN211446608 U CN 211446608U
Authority
CN
China
Prior art keywords
fixed connection
support
hydraulic stem
bridge construction
lifter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921738974.4U
Other languages
Chinese (zh)
Inventor
曾万英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Yingtan Construction Engineering Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201921738974.4U priority Critical patent/CN211446608U/en
Application granted granted Critical
Publication of CN211446608U publication Critical patent/CN211446608U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a bridge construction technical field discloses an equipment frame for bridge construction, including work platform, support hinged-support, loop bar, hydraulic stem one, connecting rod, locating part, screw, supporting leg and base, work platform includes block net, diaphragm, hydraulic stem two, lifter one, lifter two, backup pad, couple, montant, nut and safety net, the bottom and a hydraulic stem fixed connection of loop bar inner chamber, hydraulic stem one and supporting leg fixed connection, the supporting leg passes through the inner chamber swing joint of hydraulic stem one and loop bar, base and setting element fixed connection, two the connecting rod passes through the screw of locating part and the inner wall fixed connection of locating part. The utility model discloses a hydraulic stem one lets work platform's lift, and the fine setting of two pairs of diaphragms of hydraulic stem, has reached the effect of the better construction of constructor, supports the safety net through the couple on the montant, has reached the effect to constructor protection.

Description

Equipment rack for bridge construction
Technical Field
The utility model relates to a bridge construction technical field specifically is an equipment rack for bridge construction.
Background
The highway bridge engineering refers to the whole work of planning, designing, constructing, maintaining and the like of structures crossing water areas, valleys and all traffic channels on highways, the highway bridge engineering comprises main bridge engineering and auxiliary engineering facilities in the bridge location, the auxiliary engineering facilities comprise approach approaches and bridge approaches for connecting bridge heads of structures for regulating and controlling water flow, such as revetments and diversion dikes and the like for keeping stable riverways at the bridge locations, handrails for preventing wheels from colliding on bridge floors, sidewalk handrails for ensuring the safety of pedestrians, marks on bridges, under-bridge navigation marks, bridge floor lighting equipment and the like, and the equipment frame refers to a device frame on which personnel can stand to work at the bridge joints in the bridge construction.
The existing equipment frame does not take anti-falling measures for workers, only safety belts and safety helmets are arranged for the workers, and meanwhile, when the bottom of a bridge is maintained and constructed, the height of the existing equipment frame sometimes cannot reach the ideal height, which depends on the height of the workers or the application of tools.
SUMMERY OF THE UTILITY MODEL
The utility model provides an equipment rack for bridge construction, this an equipment rack for bridge construction has solved the safe problem of constructor high altitude construction portion.
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: an equipment frame for bridge construction comprises a working platform, a supporting hinged support, a sleeve rod, a first hydraulic rod, a connecting rod, a limiting part, a screw, a supporting leg and a base, wherein the working platform comprises a blocking net, a transverse plate, a second hydraulic rod, a first lifting rod, a second lifting rod, a supporting plate, a hook, a vertical rod, a threaded column, a nut and a safety net;
the locating part is equipped with the thread groove, thread groove threaded connection on screw and the locating part, two the surface swing joint of one end through hinged-support and loop bar of connecting rod, two the other end of connecting rod passes through the inner wall fixed connection of screw and locating part on the locating part.
Preferably, the bottom of block net and the fixed connection all around of diaphragm upper surface, the lower surface of diaphragm and the top fixed connection of hydraulic stem two, the top fixed connection of fixed plate and backup pad is passed through to the bottom of hydraulic stem two, the lower surface swing joint of hinged-support and diaphragm is passed through at the top of lifter one, the top fixed connection of hinged-support and fixed plate is passed through to the bottom of lifter one, the lower surface swing joint of hinged-support and diaphragm is passed through to the bottom of lifter two, the top fixed connection of hinged-support and fixed plate is passed through to the bottom of lifter two, lifter one is through the lantern ring and two swing joints of lifter.
Preferably, the top of montant is through the one end swing joint of hinged-support and couple, the couple cup joints with the safety net through the ring, the upper surface swing joint of hinged-support and backup pad is passed through to the bottom of montant, the top of screw thread post is close to the surface fixed connection of bottom with the montant, the thread groove has been seted up at the both ends of backup pad, the thread groove threaded connection that the surface that the screw thread post is close to the bottom and backup pad was seted up, the bottom threaded connection of nut and screw thread post, the bottom of backup pad and the top fixed connection who supports the hinged-support.
Preferably, the positioning piece is made of steel and is conical.
Preferably, the number of the hooks and the number of the vertical rods are four.
Preferably, the safety net is made of nylon and is square, and the side length of the safety net is five meters.
Borrow by above-mentioned technical scheme, the utility model provides an equipment rack for bridge construction. The method at least has the following beneficial effects:
(1) this an equipment rack for bridge construction lets work platform's lift through hydraulic stem one, and the fine setting of two pairs of diaphragms of hydraulic stem, has reached the effect of constructor's better construction.
(2) This an equipment rack for bridge construction supports the safety net through the couple on the montant, has reached the effect to the constructor protection.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this application:
fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic structural view of the working platform of the present invention 1;
FIG. 3 is a schematic structural view of the present invention;
in the figure: 1 working platform, 2 supporting hinged supports, 3 loop bars, 4 hydraulic rods I, 5 connecting rods, 6 limiting parts, 7 screws, 8 supporting legs, 9 bases, 10 positioning parts, 101 blocking nets, 102 transverse plates, 103 hydraulic rods II, 104 lifting rods I, 105 lifting rods II, 106 supporting plates, 107 hooks, 108 vertical rods, 109 threaded columns, 110 nuts and 111 safety nets.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-3, the present invention provides a technical solution: an equipment frame for bridge construction comprises a working platform 1, a supporting hinged support 2, a loop bar 3, a first hydraulic rod 4, a connecting rod 5, a limiting piece 6, a screw 7, a supporting leg 8 and a base 9, wherein the working platform 1 comprises a blocking net 101, a transverse plate 102, a second hydraulic rod 103, a first lifting rod 104, a second lifting rod 105, a supporting plate 106, a hook 107, a vertical rod 108, a nut 110 threaded column 109 and a safety net 111, the safety net 111 is made of nylon, the safety net 111 is square, the side length of the safety net 111 is five meters, the top of the vertical rod 108 is movably connected with one end of the hook 107 through the hinged support, the safety net 111 is supported through the hook 107 on the vertical rod 108, the protection effect on constructors is achieved, the number of the hooks 107 and the vertical rods 108 is four, the hook 107 is sleeved with the safety net 111 through a circular ring, the bottom of the vertical rod 108 is movably connected with the upper surface of the supporting plate 106 through the, the top of the threaded column 109 is fixedly connected with the outer surface of the vertical rod 108 close to the bottom, thread grooves are formed at two ends of the supporting plate 106, the outer surface of the threaded column 109 close to the bottom is in threaded connection with the thread grooves formed in the supporting plate 106, the nut 110 is in threaded connection with the bottom of the threaded column 109, the bottom of the supporting plate 106 is fixedly connected with the top of the supporting hinged support 2, the bottom of the barrier net 101 is fixedly connected with the periphery of the upper surface of the transverse plate 102, the lower surface of the transverse plate 102 is fixedly connected with the top of the hydraulic rod II 103, the bottom of the hydraulic rod II 103 is fixedly connected with the top of the supporting plate 106 through the fixing plate, the top of the lifting rod I104 is movably connected with the lower surface of the transverse plate 102 through the hinged support, the bottom of the lifting rod II 105 is fixedly connected with the top of the fixing plate through the hinged support, the bottom of the lifting rod II 105 is fixedly connected with, a lifting rod 104 is movably connected with a lifting rod II 105 through a lantern ring, the top of the sleeve rod 3 is fixedly connected with a ball on the support hinged support 2, the bottom of an inner cavity of the sleeve rod 3 is fixedly connected with the bottom of a hydraulic rod I4, the top of the hydraulic rod I4 is fixedly connected with the top of the support leg 8, the support leg 8 is movably connected with the inner cavity of the sleeve rod 3 through the hydraulic rod I4, the working platform is lifted through the hydraulic rod I4, the fine adjustment of the transverse plate 102 is carried out through a hydraulic rod II 103, the better construction effect of construction personnel is achieved, the bottom of the support leg 8 is fixedly connected with the top of the base 9, the bottom of the base 9 is fixedly connected with the top of the positioning piece 10, the positioning piece 10 is made of steel, the shape of the positioning piece 10 is conical, the conical shape can better insert soil, and the better fixing effect.
The locating part 6 is provided with a thread groove, the screw 7 is in threaded connection with the thread groove on the locating part 6, one end of each of the two connecting rods 5 is movably connected with the outer surface of the sleeve rod 3 through a hinged support, and the other end of each of the two connecting rods 5 is fixedly connected with the inner wall of the locating part 6 through the screw 7 on the locating part 6.
When using, separately insert soil through the setting element 10 of base 9 bottom through supporting hinged-support 2 to supporting leg 8 on the loop bar 3 and fix it, fix after well through hydraulic stem 4 lifting work platform, pull up montant 108 simultaneously and fix it with montant 108 through the nut 110 on the screw post 109, it is fixed to the safety net installation through couple 107, connecting two connecting rods 5 through setting element 10, when constructor constructs, finely tune two 103 hydraulic stems and let it reach corresponding height again.
It is right above the utility model provides an equipment rack for bridge construction has carried out detailed introduction. The utility model discloses it is right to have used specific individual example the utility model discloses a principle and implementation have been elucidated, and the explanation of above embodiment is only used for helping understanding the utility model discloses a method and core thought thereof. It should be noted that, for those skilled in the art, without departing from the principle of the present invention, the present invention can be further modified and modified, and such modifications and modifications also fall within the protection scope of the appended claims.

Claims (6)

1. The utility model provides an equipment frame for bridge construction, includes work platform (1), supports hinged-support (2), loop bar (3), hydraulic stem (4), connecting rod (5), locating part (6), screw (7), supporting leg (8) and base (9), its characterized in that: the working platform (1) comprises a blocking net (101), a transverse plate (102), a hydraulic rod II (103), a lifting rod I (104), a lifting rod II (105), a supporting plate (106), a hook (107), a vertical rod (108), a nut (110), a threaded column (109) and a safety net (111), the top of the loop bar (3) is fixedly connected with a ball on the supporting hinged support (2), the bottom of the inner cavity of the loop bar (3) is fixedly connected with the bottom of the hydraulic rod I (4), the top of the hydraulic rod I (4) is fixedly connected with the top of the supporting leg (8), the supporting leg (8) is movably connected with the inner cavity of the loop bar (3) through the hydraulic rod I (4), the bottom of the supporting leg (8) is fixedly connected with the top of the base (9), and the bottom of the base (9) is fixedly connected with the top of the positioning piece (10);
the locating part (6) is provided with a thread groove, the screw (7) is in threaded connection with the thread groove on the locating part (6), one end of each connecting rod (5) is movably connected with the outer surface of the sleeve rod (3) through a hinged support, and the other end of each connecting rod (5) is fixedly connected with the inner wall of the locating part (6) through the screw (7) on the locating part (6).
2. The equipment rack for bridge construction according to claim 1, wherein: the bottom of barrier net (101) and the fixed connection all around of diaphragm (102) upper surface, the lower surface of diaphragm (102) and the top fixed connection of second hydraulic stem (103), the top fixed connection of fixed plate and backup pad (106) is passed through to the bottom of second hydraulic stem (103), the lower surface swing joint of hinge support and diaphragm (102) is passed through at the top of lifter I (104), the top fixed connection of hinge support and fixed plate is passed through to the bottom of lifter I (104), the lower surface swing joint of hinge support and diaphragm (102) is passed through to the bottom of lifter II (105), the top fixed connection of hinge support and fixed plate is passed through to the bottom of lifter II (105), lifter I (104) are through lantern ring and lifter II (105) swing joint.
3. The equipment rack for bridge construction according to claim 2, wherein: the top of montant (108) is through the one end swing joint of hinged-support and couple (107), couple (107) cup joint through ring and safety net, the upper surface swing joint of hinged-support and backup pad (106) is passed through to the bottom of montant (108), the top of screw thread post (109) is connected near the surface fixed connection of bottom with montant (108), the thread groove has been seted up at the both ends of backup pad (106), the thread groove threaded connection that the surface that screw thread post (109) are close to the bottom was seted up with backup pad (106), nut (110) and the bottom threaded connection of screw thread post (109), the bottom of backup pad (106) and the top fixed connection who supports hinged-support (2).
4. The equipment rack for bridge construction according to claim 1, wherein: the positioning piece (10) is made of steel, and the positioning piece (10) is conical.
5. The equipment rack for bridge construction according to claim 1, wherein: the number of the hooks (107) and the number of the vertical rods (108) are four.
6. The equipment rack for bridge construction according to claim 1, wherein: the safety net (111) is made of nylon, the safety net (111) is square, and the side length of the safety net (111) is five meters.
CN201921738974.4U 2019-10-17 2019-10-17 Equipment rack for bridge construction Active CN211446608U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921738974.4U CN211446608U (en) 2019-10-17 2019-10-17 Equipment rack for bridge construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921738974.4U CN211446608U (en) 2019-10-17 2019-10-17 Equipment rack for bridge construction

Publications (1)

Publication Number Publication Date
CN211446608U true CN211446608U (en) 2020-09-08

Family

ID=72305951

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921738974.4U Active CN211446608U (en) 2019-10-17 2019-10-17 Equipment rack for bridge construction

Country Status (1)

Country Link
CN (1) CN211446608U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113322817A (en) * 2021-05-25 2021-08-31 豫新华通路桥集团有限公司 Bridge construction supporting equipment in field of bridge engineering

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113322817A (en) * 2021-05-25 2021-08-31 豫新华通路桥集团有限公司 Bridge construction supporting equipment in field of bridge engineering

Similar Documents

Publication Publication Date Title
CN110722318A (en) Precise adjustable steel truss assembling jig frame and assembling method
CN211446608U (en) Equipment rack for bridge construction
CN208718393U (en) A kind of building overlapping plate bracing frame
CN212384891U (en) Accurate adjustable steel truss assembles bed-jig
KR101612031B1 (en) deck road
CN113802880A (en) Combined supporting structure for mounting large-span steel beam
CN215255126U (en) Safety protective guard is used in road bridge construction
CN210369827U (en) Scaffold for building external wall construction
CN211776478U (en) Special guardrail of construction
CN211639872U (en) Multi-specification PC component placing frame
CN208415880U (en) One kind being used for the adjustable scaffold of house decoration
CN209836771U (en) Highway is salvageed with simple and easy bridge of being convenient for equipment
CN109469308A (en) The structure of major diameter group storehouse support platform
CN213477796U (en) Prefabricated factory of assembled type for bridge construction
CN207079615U (en) A kind of roller-coaster built-in fitting support system
CN214575505U (en) Scaffold reinforcing apparatus for building engineering
CN218091902U (en) Support connection structure for civil engineering
CN211421771U (en) Scaffold frame that construction is convenient for assemble with having protective structure
CN218375713U (en) Metal guardrail net
CN217268710U (en) Building construction is with having building scaffold of anti-falling
CN221796741U (en) Steel anchor beam lifting appliance
CN214364801U (en) Portable operation platform for building of formula of encorbelmenting
CN213234201U (en) Building engineering safety construction platform
CN219993048U (en) Scaffold frame
CN206016232U (en) A kind of construction coherent-wall scaffolding cantilever arrangement

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221128

Address after: 232000 shop S120, building 7, sunshine Europe city, Zijin Road, Shouchun Town, Shou county, Huainan City, Anhui Province

Patentee after: Anhui Yingtan Construction Engineering Co.,Ltd.

Address before: 362000 No. 791, Songshan village, sukeng Town, Yongchun County, Quanzhou City, Fujian Province

Patentee before: Chen Mingji