CN211395701U - Pipeline channel of easy construction - Google Patents

Pipeline channel of easy construction Download PDF

Info

Publication number
CN211395701U
CN211395701U CN201921859167.8U CN201921859167U CN211395701U CN 211395701 U CN211395701 U CN 211395701U CN 201921859167 U CN201921859167 U CN 201921859167U CN 211395701 U CN211395701 U CN 211395701U
Authority
CN
China
Prior art keywords
channel
pipeline channel
pipeline
ground
roof
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921859167.8U
Other languages
Chinese (zh)
Inventor
刘涛
白志强
郑云红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN201921859167.8U priority Critical patent/CN211395701U/en
Application granted granted Critical
Publication of CN211395701U publication Critical patent/CN211395701U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model relates to a pipeline channel of easy construction, including the pipeline channel bed course that is located the gallery bottom of excavation, the cross-section is the pipeline channel of square, and this pipeline channel cross-section both sides are solid formation with the bottom surface, and the pipeline channel roof of top surface is buried pipeline channel roof reinforcing bar in advance, and the thickness of channel roof plate is less than channel side board, pipeline channel roof upper surface covers there is ground concrete. By the scheme, the roof of the channel can be increased (1), the construction requirement is met, the utilization rate of the field is increased, and the situation that the channel cover plate cannot be installed and the field cannot be used is avoided; (2) uneven settlement between the ground and a pipeline channel can be eliminated, a vertical construction joint is changed into a horizontal construction joint, and the overall impression requirement of the ground is not influenced when the channel sinks; (3) the method is particularly important for places with narrow places and high place utilization rate; (4) the ground and the trench are constructed in two steps, so that the appearance quality requirement of the ground surface layer of the whole field is ensured.

Description

Pipeline channel of easy construction
Technical Field
The utility model belongs to the technical field of the engineering construction technique and specifically relates to an easily constructed ground pipeline channel.
Background
In recent years, municipal pipeline transformation is realized by considering daily maintenance and unified management, pipe galleries, comprehensive pipe ditches and the like are widely applied, the pipe ditches can effectively solve the problems of difficult daily maintenance, difficult pipeline buried laying and arrangement and the like, the structure is simple, the problems of 'vertical and horizontal eight faults' and 'spider networks' in the air caused by maintenance, expansion and the like of various pipelines in the urban development process are effectively solved, the urban pipeline transformation is economic in general, the urban pipeline transformation trend becomes the modern construction trend of urban infrastructure, and the urban pipeline transformation method plays a positive promoting role in improving the urban overall image and creating the urban harmonious ecological environment.
Traditional trench adopts reinforced concrete structure, prefabricated apron, the requirement for quality of apron and channel is higher during indoor use, often the shaping back trench is not in the same direction as straight, the general illness such as apron deviation is more, consider simultaneously that peripheral ground and trench foundation treatment are different to cause different subsides, seriously influence holistic impression quality, for solving this problem, pipeline channel roof divides two steps to accomplish to realize the combination of ground and trench, reduce the influence that inhomogeneous subsides caused, reduce occuping in place, improve the construction speed, the following technical scheme is proposed in particular.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing an easy pipeline channel of being under construction to this uneven settlement of solving ground and channel improves the place utilization ratio, optimizes technology, guarantees the shaping back appearance quality, and the scheme specifically is:
an easy-to-construct pipeline channel is characterized in that: comprises that
The pipeline channel cushion layer is positioned at the bottom of the excavated tunnel, the section of the pipeline channel cushion layer is a square pipeline channel, two sides and the bottom of the section of the pipeline channel are formed in a solid mode, pipeline channel top plates on the top surface are pre-embedded with pipeline channel top plate steel bars, the thickness of each channel top plate is smaller than that of each channel side plate, and the upper surface of each pipeline channel top plate is covered with ground concrete.
Further, pipeline channel roof negative ribs are buried in the ground concrete at positions corresponding to the pipeline channels.
Further, the pipeline channel is poured by concrete.
Further, earth is backfilled in the pipeline channel.
Further, the side walls and the bottom wall of the pipeline channel have a thickness of 100 mm.
The utility model has the advantages that: by the technical scheme, the roof of the channel can be increased (1), the construction requirement is met, the utilization rate of the field is increased, and the situation that the channel cover plate cannot be installed and the field cannot be used is avoided; (2) uneven settlement between the ground and a pipeline channel can be eliminated, a vertical construction joint is changed into a horizontal construction joint, and the overall impression requirement of the ground is not influenced when the channel sinks; (3) the method is particularly important for places with narrow places and high place utilization rate; (4) the ground and the trench are constructed in two steps, so that the appearance quality requirement of the ground surface layer of the whole field is ensured.
Drawings
Fig. 1 is a cross-sectional view of the present invention.
Detailed Description
The present invention will be further described with reference to the following examples.
As shown in figure 1, the pipeline channel easy to construct is characterized in that a pipeline channel cushion layer 1 at the bottom of an excavated tunnel plays a role in preventing the whole engineering component from settling and providing a positioning reference, a pipeline channel 2 with a square cross section is further arranged, compared with a circular channel, the square channel is beneficial to field operation, two sides and the bottom of the cross section of the pipeline channel are formed in a solid mode, a factory precast slab can be adopted, concrete can be poured in situ, pipeline channel top plates 4 are embedded in a pipeline channel top plate pre-3 on the top surface, support is provided for the upper surface of the channel, the thickness of the channel top plate is smaller than that of a channel side plate, and the upper surface of the pipeline channel top plate 3 is covered with ground concrete 6.
Example (b):
a ready-to-construct pipeline channel comprising:
the pipeline channel cushion layer 1 is located at the bottom of the excavated tunnel, the section of the pipeline channel cushion layer is a square pipeline channel 2, two sides and the bottom of the section of the pipeline channel are formed in a solid mode, pipeline channel top plates on the top surface are embedded with pipeline channel top plate reinforcing steel bars 4 in advance 3, the thickness of the channel top plates is smaller than that of channel side plates, and the upper surface of each pipeline channel top plate 3 is covered with ground concrete 6.
Further, the ground concrete 6 is embedded with a pipeline channel top plate negative rib at a position corresponding to the pipeline channel 2.
Further, the pipeline channel 2 is poured with concrete.
Further, the pipeline trench 2 is backfilled with earth.
Further, the side walls and the bottom wall of the pipeline channel have a thickness of 100 mm.
The utility model discloses a work progress is:
1. and (5) carrying out slope excavation according to the design size, and pouring cushion concrete.
2. And (3) binding channel steel bars on site, installing templates, not prefabricating cover plates, and installing top plate steel bar templates with the thickness of 100mm in the channels.
3. And pouring concrete on the bottom plate, the wallboard and the top plate of the channel, maintaining and backfilling earthwork in the channel.
4. Binding of steel bars on the ground surface layer on the upper portion of the channel, installation of a template, increasing of steel bar negative bars in the range of a top plate of the channel, and pouring of concrete with the same diameter and ground steel bars.
While one embodiment of the present invention has been described in detail, the description is only a preferred embodiment of the present invention, and should not be considered as limiting the scope of the present invention. All the equivalent changes and improvements made according to the application scope of the present invention should still fall within the patent coverage of the present invention.

Claims (5)

1. An easy-to-construct pipeline channel is characterized in that: comprises that
The pipeline channel cushion layer is positioned at the bottom of the excavated tunnel, the section of the pipeline channel cushion layer is a square pipeline channel, two sides and the bottom of the section of the pipeline channel are formed in a solid mode, pipeline channel top plates on the top surface are pre-embedded with pipeline channel top plate steel bars, the thickness of each channel top plate is smaller than that of each channel side plate, and the upper surface of each pipeline channel top plate is covered with ground concrete.
2. An easily constructed pipeline channel as claimed in claim 1, wherein: and the ground concrete is embedded with a pipeline channel top plate negative rib at a position corresponding to the pipeline channel.
3. An easily constructed pipeline channel as claimed in claim 1, wherein: the pipeline channels are cast by concrete.
4. An easily constructed pipeline channel as claimed in claim 1, wherein: backfill earthwork is arranged in the pipeline channel.
5. An easily constructed pipeline channel as claimed in claim 1, wherein: the side and bottom walls of the pipeline channel are 100mm thick.
CN201921859167.8U 2019-10-31 2019-10-31 Pipeline channel of easy construction Active CN211395701U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921859167.8U CN211395701U (en) 2019-10-31 2019-10-31 Pipeline channel of easy construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921859167.8U CN211395701U (en) 2019-10-31 2019-10-31 Pipeline channel of easy construction

Publications (1)

Publication Number Publication Date
CN211395701U true CN211395701U (en) 2020-09-01

Family

ID=72208077

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921859167.8U Active CN211395701U (en) 2019-10-31 2019-10-31 Pipeline channel of easy construction

Country Status (1)

Country Link
CN (1) CN211395701U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110886299A (en) * 2019-10-31 2020-03-17 中冶天工集团有限公司 Pipeline channel easy to construct and top plate pouring method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110886299A (en) * 2019-10-31 2020-03-17 中冶天工集团有限公司 Pipeline channel easy to construct and top plate pouring method thereof

Similar Documents

Publication Publication Date Title
CN102758451B (en) Concrete cable channel construction process
CN104805866A (en) Prefabricated comprehensive pipe gallery and construction method
CN103981898A (en) Integral open-excavation node top-down underground engineering construction method
CN103806470B (en) Mounting method produced by steel concrete manhole
US11566390B2 (en) Construction method of reclaiming land from the sea based on basement utilization
CN211395701U (en) Pipeline channel of easy construction
CN104790435A (en) Post-subsidence pouring belt advancing waterstop impermeable concrete structure and construction technology thereof
CN107268675A (en) The laying method and structure of a kind of many storehouse underground pipe galleries of combined type
CN207268009U (en) A kind of underground pipe gallery drainage system based on existing blowdown canal
WO2024074079A1 (en) Prefabricated assembled reinforced concrete retaining wall and construction method therefor
CN113136876A (en) Construction method of pipe trench
CN110117959B (en) Construction method for foundation pit support near river
CN112761158A (en) Green construction method for integral outer wall (three-in-one) of reverse construction underground engineering steel concrete key pin occlusive row pile
CN103015457B (en) Method for building rural brick buried sewage treatment facility
CN110886299A (en) Pipeline channel easy to construct and top plate pouring method thereof
CN110056071A (en) A kind of municipal administration storm sewer assembling module and construction method
CN108755758A (en) The construction method of full prefabrication and assembly construction superposed type empty stomach wallboard underground pipe gallery
CN113186977B (en) Reverse-order construction method for underground comprehensive pipe gallery
CN109137984A (en) Assembled integral mixes prefabricated pipe gallery
CN212000674U (en) Novel reverse construction method assembly type non-pressure culvert
CN210122735U (en) Underground structure anti-floating system based on outward-protruding wing foot plate
CN112854415A (en) Combined landscape prefabricated drainage ditch system based on BIM technology and construction process thereof
CN102392459A (en) Construction method for straight manhole
CN214090251U (en) Modular drainage inspection shaft
CN110374141A (en) The construction method of inspection shaft is perfused after a kind of precast module type

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant