CN211285814U - Deep well pump house control platform structure - Google Patents

Deep well pump house control platform structure Download PDF

Info

Publication number
CN211285814U
CN211285814U CN201922137032.7U CN201922137032U CN211285814U CN 211285814 U CN211285814 U CN 211285814U CN 201922137032 U CN201922137032 U CN 201922137032U CN 211285814 U CN211285814 U CN 211285814U
Authority
CN
China
Prior art keywords
deep well
well pump
control platform
pump house
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922137032.7U
Other languages
Chinese (zh)
Inventor
莫如军
侯东奇
张顺利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201922137032.7U priority Critical patent/CN211285814U/en
Application granted granted Critical
Publication of CN211285814U publication Critical patent/CN211285814U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a deep well pump house control platform structure, which belongs to the field of hydropower station plant structures and provides a deep well pump house control platform structure capable of improving the space utilization rate of a deep well pump house, comprising a deep well pump house, wherein a control platform is arranged on one side in the deep well pump house and comprises a support column, a cross beam and a floor slab, the lower end of the support column is arranged on the ground of the pump house, the upper end of the support column is lapped with the cross beam, the floor slab is positioned on the cross beam, and a stair is arranged between the floor slab layer of the control platform and the ground of the pump house; and a reserved hole of electromechanical equipment is arranged on a floor slab of the control platform. By building the control platform structure of the utility model in the deep well pump room, the upper space of the deep well pump room is fully utilized, and the engineering investment is saved; meanwhile, corresponding equipment can be arranged on the control platform, so that the equipment is prevented from being arranged in a region outside the deep well pump room, the centralized arrangement of the equipment is realized, and the operation is more convenient.

Description

Deep well pump house control platform structure
Technical Field
The utility model relates to a power station factory building structure field especially relates to a platform structure is controlled to deep well pump house.
Background
Various devices such as a leakage submersible sewage pump control cabinet, a leakage drainage control cabinet, an overhaul power box, a submersible sewage pump and the like are generally required to be arranged in a deep well pump room of a water conservancy and hydropower engineering factory building, and the various devices are generally horizontally placed on the ground in the pump room, so that the occupied plane area is large; sometimes, when equipment cannot be placed in the pump room, other horizontal space outside the pump room needs to be occupied. However, the actual height of the pump room is often high, and the space at the upper part is often not fully utilized; and when the corresponding equipment is placed outside the pump room, the personnel operating the equipment on site is inconvenient.
SUMMERY OF THE UTILITY MODEL
The utility model provides a technical problem provide a can improve deep well pump house space utilization's deep well pump house and control platform structure.
The utility model provides a technical scheme that its technical problem adopted is: the deep well pump house control platform structure comprises a deep well pump house, wherein a control platform is arranged on one side in the deep well pump house, the control platform comprises support columns, cross beams and a floor slab, the lower ends of the support columns are installed on the ground of the pump house, the upper ends of the support columns are lapped with the cross beams, the floor slab is located on the cross beams, and a stair is arranged between the floor slab of the control platform and the ground of the pump house; and a reserved hole of electromechanical equipment is arranged on a floor slab of the control platform.
Further, the method comprises the following steps: the height of the floor slab from the ground of the pump room is 3 m.
Further, the method comprises the following steps: the control platform is of a reinforced concrete structure or a steel structure.
Further, the method comprises the following steps: one side above a floor slab of the control platform is an equipment placing area, and the other side is reserved with a man-passing channel with the width of 1.2 m; the electromechanical device preformed hole is positioned on one side of the device placing area.
Further, the method comprises the following steps: the side wall of the deep well pump room is provided with a main upright post, and a support column of the control platform at one side of the side wall close to the deep well pump room is the main upright post.
Further, the method comprises the following steps: the edge of the floor slab of the control platform is provided with a guardrail.
The utility model has the advantages that: by building the control platform structure of the utility model in the deep well pump room, the upper space of the deep well pump room is fully utilized, and the engineering investment is saved; meanwhile, corresponding equipment can be arranged on the control platform, so that the equipment is prevented from being arranged in a region outside the deep well pump room, the centralized arrangement of the equipment is realized, and the operation is more convenient.
Drawings
Fig. 1 is a schematic plan view of a deep well pump room control platform structure according to the present invention;
FIG. 2 is an enlarged partial schematic view of the location indicated by A-A in FIG. 1;
FIG. 3 is a schematic view of the position indicated by B-B in FIG. 1;
labeled as: control platform 1, support column 2, crossbeam 3, floor 4, pump house ground 5, stair 6, electromechanical device preformed hole 7, equipment place district 8, passerby passageway 9, guardrail 10, main column.
Detailed Description
The present invention will be further described with reference to the accompanying drawings and the following detailed description.
As shown in fig. 1 to 3, the deep well pump room control platform structure of the present invention comprises a deep well pump room, wherein a control platform 1 is arranged on one side in the deep well pump room, the control platform 1 comprises a support column 2, a beam 3 and a floor slab 4, the lower end of the support column 2 is installed on the ground 5 of the pump room, the upper end of the support column 2 is lapped on the beam 3, the floor slab 4 is located on the beam 3, and a stair 6 is arranged between the floor slab 4 of the control platform 1 and the ground 5 of the pump room; on the floor 4 of the control platform 1 there is arranged a electromechanical equipment prepared hole 7.
In the utility model, the structure of the corresponding control platform 1 is built in the deep well pump room, so that the upper space of the deep well pump room is fully utilized, and the engineering investment is saved; meanwhile, corresponding equipment can be arranged on the control platform 1, so that the equipment is prevented from being arranged in a region outside a deep well pump room, the centralized arrangement of the equipment is realized, and the operation is more convenient; without loss of generality, electromechanical equipment prepared holes 7 are arranged on the floor 4 of the control platform 1, namely, corresponding equipment is convenient to install.
The control platform 1 is constructed by main structures such as support columns 2, cross beams 3 and floor slabs 4, and can be specifically referred to as shown in the attached drawings. In order to ensure that floor 4 has certain height to form corresponding interlayer space above and below floor 4, the utility model discloses in preferably set up floor 4 is 3m apart from the height of pump house ground 5.
In addition, the control platform 1 in the utility model can be a reinforced concrete structure or a steel structure; the method can be reasonably selected according to the convenience of construction.
The utility model discloses a floor 4 top of control platform 1 can form one deck usage space, and then can be used for installing and placing corresponding equipment; as shown in the attached drawing 1, an equipment placing area 8 is arranged on one side above the floor slab 4, namely, the equipment placing area is used for installing corresponding equipment, and a passenger passage 9 with the width of 1.2m is reserved on the other side, so that the passenger passage is convenient to pass; of course, without loss of generality, the electromechanical device pre-prepared hole 7 should be provided at one side of the device placement area 8 to facilitate installation of the corresponding device.
In addition, in consideration of the fact that in the actual construction process, the main upright post 11 is usually arranged on the side wall of the deep well pump house, and the control platform 1 of the utility model is arranged near one side in the deep well pump house, therefore, in the construction process, part of the main upright post 11 can be used as the support post 2 of the control platform 1, i.e. the left part of the main upright post 11 of the deep well pump house is used as the support post 2 in the structure shown in the attached drawing 1; therefore, the construction work amount can be further reduced, and the project investment is saved.
In addition, in order to improve the safety above the floor 4, referring to fig. 1, the utility model is further provided with a guardrail 10 at the edge of the floor 4 of the operation platform 1; a certain safety protection effect is achieved by the guardrail 10. More specifically, the height of the guard rail 10 may be set to 1m or more.

Claims (6)

1. Platform structure is controlled to deep well pump house, including deep well pump house, its characterized in that: arranging a control platform (1) on one side in the deep well pump room, wherein the control platform (1) comprises support columns (2), cross beams (3) and floor slabs (4), the lower ends of the support columns (2) are installed on the pump room ground (5), the upper ends of the support columns (2) are in lap joint with the cross beams (3), the floor slabs (4) are located on the cross beams (3), and stairs (6) are arranged between the floor slabs (4) of the control platform (1) and the pump room ground (5); electromechanical equipment preformed holes (7) are arranged on a floor (4) of the control platform (1).
2. The deep well pump house operation platform structure of claim 1, wherein: the height of the floor (4) from the pump room ground (5) is 3 m.
3. The deep well pump house operation platform structure of claim 1, wherein: the control platform (1) is of a reinforced concrete structure or a steel structure.
4. The deep well pump house operation platform structure of claim 1, wherein: one side above a floor slab (4) of the control platform (1) is an equipment placing area (8), and the other side is reserved with a man-passing channel (9) with the width of 1.2 m; the electromechanical equipment preformed hole (7) is positioned on one side of the equipment placing area (8).
5. The deep well pump house operation platform structure of claim 1, wherein: the side wall of the deep well pump room is provided with a main upright post (11), and a support column (2) on one side of the side wall close to the deep well pump room of the control platform (1) is the main upright post (11).
6. The deep well pump house manipulation platform structure according to any one of claims 1 to 5, wherein: a guardrail (10) is arranged at the edge of the floor (4) of the control platform (1).
CN201922137032.7U 2019-12-03 2019-12-03 Deep well pump house control platform structure Active CN211285814U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922137032.7U CN211285814U (en) 2019-12-03 2019-12-03 Deep well pump house control platform structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922137032.7U CN211285814U (en) 2019-12-03 2019-12-03 Deep well pump house control platform structure

Publications (1)

Publication Number Publication Date
CN211285814U true CN211285814U (en) 2020-08-18

Family

ID=72015270

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922137032.7U Active CN211285814U (en) 2019-12-03 2019-12-03 Deep well pump house control platform structure

Country Status (1)

Country Link
CN (1) CN211285814U (en)

Similar Documents

Publication Publication Date Title
US10190309B2 (en) Slab construction system and method for constructing multi-story buildings using pre-manufactured structures
CN110924509A (en) Turn-back type ultra-deep inspection well
CN108049666A (en) A kind of echelon installation method of super plane multilayer steel truss electronic workshop steel construction
CN211285814U (en) Deep well pump house control platform structure
CN216043765U (en) Plateau railway tunnel assists gallery assembled wind channel formula ventilation structure
CN105625732A (en) Supporting-free construction method of ultrahigh overhung steel-structure truss
CN105089024B (en) Underground power house outlet arrangement and structure
CN205476655U (en) Satisfy installation of extra -high voltage GIS device context with totally closed removal factory building track
CN203924605U (en) Be applicable to the indoor built on stilts floor structure of transformer station's flood control transformation
CN203947557U (en) Enclosure wall discharge structure
CN109138484B (en) Construction method for connecting jacking layer-added concrete-filled steel tubular column with foundation
CN203320543U (en) Basic structure of construction elevator
CN112761245A (en) Assembled reinforced concrete building main body structure and installation construction method thereof
KR102259648B1 (en) Fabricated structure for hydropower generation
CN214363621U (en) Cross section working well for assembled cable channel
CN214949909U (en) Lithium bromide absorption heat pump waste heat recovery factory building
CN215634657U (en) Supporting type vibration isolation platform for concrete cornice edge folding
CN216551985U (en) Detachable assembly type fire fighting pipe ditch
CN216276694U (en) Integrated elevator installation structure
CN211341982U (en) Local reversed beam structure of top plate of underground garage
CN212613277U (en) Installation foundation of GIS equipment
CN212336166U (en) Prefabricated type antidetonation waterproof compound stand alone type pump house that soaks on ground
CN113445741B (en) Half-floor tower suspended ceiling construction method
CN214941502U (en) Backfill-free prefabricated slab with overhead structure
CN212614001U (en) Mechanical garage with high space utilization rate

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant