CN211285684U - Invisible equipment foundation - Google Patents

Invisible equipment foundation Download PDF

Info

Publication number
CN211285684U
CN211285684U CN201921857511.XU CN201921857511U CN211285684U CN 211285684 U CN211285684 U CN 211285684U CN 201921857511 U CN201921857511 U CN 201921857511U CN 211285684 U CN211285684 U CN 211285684U
Authority
CN
China
Prior art keywords
terrace
equipment foundation
equipment
foundation
stake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921857511.XU
Other languages
Chinese (zh)
Inventor
李龙超
郭颖
王伟泽
李娟�
季忠原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co ltd Of China Construction Sixth Engineering Bureau
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd, China Construction Sixth Installation Engineering Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201921857511.XU priority Critical patent/CN211285684U/en
Application granted granted Critical
Publication of CN211285684U publication Critical patent/CN211285684U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses an invisible equipment foundation adopts reinforced concrete structure, is equipped with pre-buried steel sheet, and this equipment foundation covers on the terrace stake, with terrace integrated into one piece, top elevation and terrace parallel and level, thickness are thicker than the terrace, and the reinforcing bar anchor that covers the terrace stake is gone into equipment foundation, equipment foundation joins in marriage double-deck bidirectional reinforcement, equipment foundation's double-deck bidirectional reinforcement stretches into in peripheral adjacent terrace stake of equipment foundation and the terrace handing-over concrete, equipment foundation's concrete label is higher than the concrete label of terrace. The utility model discloses utilize the terrace stake and form whole permanent structure with the terrace, when satisfying the ground bearing capacity, can consolidate the reinforcement terrace structure, can avoid demolising afterwards and cause adverse effect to the terrace. The equipment has sufficient basic operation surface, is beneficial to construction, does not influence the construction period, and is beneficial to construction cost control. The drawknot steel ring is arranged on the basis of the equipment, can be used for temporary drawknot fixation of the equipment, and is convenient for ensuring the drawknot strength.

Description

Invisible equipment foundation
Technical Field
The utility model relates to an equipment foundation, especially an invisible equipment foundation.
Background
With the continuous development of construction technology, the grid structure is rapidly developed and widely applied in nearly thirty or four years due to the characteristics of large rigidity, good integrity, good earthquake resistance, light dead weight, steel saving, good adaptability and the like. The traditional net rack mounting methods at present comprise common construction methods such as a high-altitude assembling method, a lifting method, an integral hoisting method and a jacking method. The high-altitude assembly method needs to consume a large amount of frame materials to set up an operation platform, and has higher material lease and labor cost. Although the integral hoisting in-place method has the characteristics of simple and convenient construction, short construction period, easy guarantee of engineering quality and the like, the overhead cost of a crane is too high, the crane walking road needs to be treated, the construction cost is very high, the key is limited by the site, and the construction requirement is difficult to meet; although hydraulic pressure whole lifting is not restricted by the place, but has higher requirement as the reliable hoisting fulcrum to original structure, and the structural steel column can not satisfy the bearing capacity requirement. The jacking method integrates the advantages, the net rack is assembled on the ground, safety and time saving are realized, the assembling quality is convenient to guarantee, and the installation of the jacking frame body is not limited by the field and the surrounding environment, so that the jacking frame is generally applied. However, how to construct a jacking foundation with a corresponding number on the terrace according to a plurality of set jacking point positions is a problem that is always discussed by the industry.
Disclosure of Invention
The utility model discloses a solve the technical problem who exists among the known art and provide an invisible equipment foundation, this equipment foundation can not cause adverse effect to the terrace, and does benefit to construction cost control.
The utility model discloses a solve the technical scheme that technical problem that exists among the well-known technique took and be: the utility model provides an invisible equipment foundation, adopts reinforced concrete structure, is equipped with pre-buried steel sheet, and this equipment foundation covers on the terrace stake, with terrace integrated into one piece, top elevation and terrace parallel and level, thickness are thicker than the terrace, and the reinforcing bar anchor that covers the terrace stake is gone into equipment foundation, equipment foundation joins in marriage double-deck bidirectional reinforcement, equipment foundation's double-deck bidirectional reinforcement stretches into in peripheral neighbouring terrace stake of equipment foundation and the terrace handing-over concrete, equipment foundation's concrete reference numeral is higher than the concrete reference numeral of terrace.
The area of this equipment foundation covers 2 ~ 6 terrace piles.
The thickness of the equipment foundation is 300-500 mm.
The equipment foundation is provided with a drawknot steel ring, and the drawknot steel ring is welded on the steel bar covering the terrace pile.
The utility model has the advantages and positive effects that: utilize terrace stake and form whole permanent structure with the terrace, when satisfying the ground bearing capacity, can consolidate the reinforcement terrace structure, can avoid demolising afterwards and cause adverse effect to the terrace. The equipment has sufficient basic operation surface, is beneficial to construction, does not influence the construction period, and is beneficial to construction cost control. The drawknot steel ring is arranged on the basis of the equipment, can be used for temporary drawknot fixation of the equipment and is convenient to ensure the drawknot strength; after the temporary drawknot is fixed and used, the drawknot steel ring does not need to be dismantled and can be directly poured in the structural layer without influencing subsequent construction.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a side sectional view of fig. 1.
In the figure: 1. a terrace; 2. reinforcing steel bars; 3. concrete; 4. drawing the steel ring; 5. pre-burying a steel plate; 6. and covering the terrace pile.
Detailed Description
For further understanding of the contents, features and effects of the present invention, the following embodiments are exemplified and will be described in detail with reference to the accompanying drawings:
please refer to fig. 1 and fig. 2, an invisible equipment foundation, which adopts a reinforced concrete structure and is provided with an embedded steel plate 5, the equipment foundation covers on a terrace pile, is integrally formed with the terrace 1, has a top elevation flush with the terrace 1, has a thickness thicker than the terrace 1, and a steel bar covering the terrace pile 6 is anchored into the equipment foundation, the equipment foundation is provided with a double-layer bidirectional steel bar 2, the double-layer bidirectional steel bar 2 of the equipment foundation extends into the peripheral adjacent terrace pile and the terrace jointing concrete, and the grade of the concrete 3 of the equipment foundation is higher than that of the terrace 1.
In this embodiment, the area of recommending this equipment foundation covers 2 ~ 6 terrace piles, but is not limited to this, can confirm as required. The thickness of the equipment foundation is recommended to be 300-500 mm. The size of the pre-buried steel plate 5 is 200X 10 mm.
In this embodiment, be equipped with drawknot steel loop 4 on this equipment basis, drawknot steel loop 4 welds on the reinforcing bar that covers terrace pile 6. The drawknot steel ring 4 can be used for fixing the drawknot of equipment, so that the drawknot strength is convenient to ensure.
Although the preferred embodiments of the present invention have been described with reference to the accompanying drawings, the present invention is not limited to the above-mentioned embodiments, which are only illustrative and not restrictive, and those skilled in the art can make many forms without departing from the spirit and scope of the present invention, which is within the scope of the present invention.

Claims (4)

1. The utility model provides an invisible equipment foundation, adopts reinforced concrete structure, is equipped with pre-buried steel sheet, and its characterized in that, this equipment foundation cover on the terrace stake, with terrace integrated into one piece, top elevation and terrace parallel and level, thickness are thicker than the terrace, and the reinforcing bar anchor that covers the terrace stake is gone into equipment foundation, equipment foundation joins in marriage double-deck bidirectional reinforcement, equipment foundation's double-deck bidirectional reinforcement stretches into in equipment foundation peripheral neighbouring terrace stake and the terrace handing-over concrete, equipment foundation's concrete label is higher than the concrete label of terrace.
2. The invisible equipment foundation of claim 1, wherein the area of the equipment foundation covers 2-6 terrace piles.
3. The invisible apparatus foundation of claim 1 or 2, wherein the thickness of the apparatus foundation is 300-500 mm.
4. The invisible foundation of claim 1, wherein a steel tie ring is provided on the foundation, and the steel tie ring is welded to the steel reinforcement covering the ground level pile.
CN201921857511.XU 2019-10-31 2019-10-31 Invisible equipment foundation Active CN211285684U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921857511.XU CN211285684U (en) 2019-10-31 2019-10-31 Invisible equipment foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921857511.XU CN211285684U (en) 2019-10-31 2019-10-31 Invisible equipment foundation

Publications (1)

Publication Number Publication Date
CN211285684U true CN211285684U (en) 2020-08-18

Family

ID=72035532

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921857511.XU Active CN211285684U (en) 2019-10-31 2019-10-31 Invisible equipment foundation

Country Status (1)

Country Link
CN (1) CN211285684U (en)

Similar Documents

Publication Publication Date Title
CN105113389B (en) Assembled type bridge pier column member with steel-concrete composite structure
CN104294753B (en) A kind of hollow pier stud syndeton of bridge prefabrication and construction
CN201534978U (en) Steel platform foundation of tower crane
CN108035376B (en) Anti-deformation rectification foundation applicable to goaf site wind turbine generator and construction method thereof
CN106245670B (en) Exposed steel column base construction method
CN102031756A (en) Support assembly and construction method of cast-in-place box girder
CN106759434B (en) A kind of groined type precast concrete king-post basis and its construction method
CN108442239A (en) A kind of full assembled light abutment and its construction method
CN109811782A (en) A kind of soft soil foundation reinforcing method and its ruggedized construction
CN208701729U (en) A kind of offshore wind farm High-Rise Pile Cap Foundation using prefabricated cushion cap
CN201770942U (en) Support for soft soil foundation cast-in-place concrete continuous beam bridge
CN207513051U (en) Precast stair bench and the connection fixed structure of terraced beam
CN113005926A (en) Construction method of mountain area abrupt slope pier reinforcing device
CN106958259B (en) A kind of concrete towers column foundation and its construction method
CN101418574B (en) Construction method for reinforcing grade beam
CN204780979U (en) Install steel -pipe pile basis of anti horizontal force of iron tower fast
CN201942994U (en) Bridge bearing pad
CN116856932B (en) Large-diameter prestress assembly vertical shaft structure containing glass fiber rib part and construction method
CN105821962A (en) Assembled integrated connection structure for prefabricated prestressed reinforced concrete beam and frame columns
CN203475289U (en) Pile type continuous rigid frame bridge
CN103510458B (en) Pile type continuous rigid frame bridge and construction method thereof
CN103233537A (en) Heavy-load superimposed overhead terrace and construction method
CN211285684U (en) Invisible equipment foundation
CN110206020B (en) Prefabricated snowflake type concrete steel sheet pile and construction method thereof
CN111197319A (en) Multidirectional prestress prefabricated assembled beam slab foundation of wind power generation tower

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee after: China Construction Sixth Engineering Bureau Northwest Construction Co.,Ltd.

Patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Address before: No. 72 Hangzhou Road, Tianjin Binhai New Area, 300451

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING BUREAU INSTALLATION ENGINEERING Co.,Ltd.

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

CP03 Change of name, title or address
CP01 Change in the name or title of a patent holder

Address after: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee after: The First Construction Co.,Ltd. of China Construction Sixth Engineering Bureau

Patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Address before: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee before: China Construction Sixth Engineering Bureau Northwest Construction Co.,Ltd.

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

CP01 Change in the name or title of a patent holder