CN211256694U - Pier column hoop device for bridge bent cap construction - Google Patents

Pier column hoop device for bridge bent cap construction Download PDF

Info

Publication number
CN211256694U
CN211256694U CN201921901941.7U CN201921901941U CN211256694U CN 211256694 U CN211256694 U CN 211256694U CN 201921901941 U CN201921901941 U CN 201921901941U CN 211256694 U CN211256694 U CN 211256694U
Authority
CN
China
Prior art keywords
semicircle board
fixedly connected
lateral wall
bolt
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921901941.7U
Other languages
Chinese (zh)
Inventor
孟笛
陈丽燕
陈涛
曾孝荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huzhou Traffic Engineering Construction Group Co ltd
Original Assignee
Huzhou Traffic Engineering Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huzhou Traffic Engineering Construction Group Co ltd filed Critical Huzhou Traffic Engineering Construction Group Co ltd
Priority to CN201921901941.7U priority Critical patent/CN211256694U/en
Application granted granted Critical
Publication of CN211256694U publication Critical patent/CN211256694U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a pier stud staple bolt device of bridge bent cap construction, the unable problem that is suitable for all pier studs of pier stud staple bolt device of having solved current bridge bent cap construction, the scheme as follows now is proposed, its right side semicircle board, waterproofing membrane, electric lift and splint, top fixedly connected with right fixed plate about the right side semicircle board lateral wall, through bolt fixed connection between right fixed plate and the left fixed plate, the bolt lateral wall link up and has connect the nut soon, the right side link up in the middle of the bolt lateral wall has the dog, fixedly connected with left semicircle board between the upper and lower left fixed plate, left semicircle board and right semicircle board lateral wall are fixed to bond has waterproofing membrane, left semicircle board and right semicircle board inside wall are fixed to be smeared with the anticorrosion coating. The utility model discloses owing to set up the pawl on rubber pad for the device has increased its friction effect when pressing from both sides tight pier stud, and waterproofing membrane and anticorrosive coating's setting makes the rate of corrosion on device surface slow down, has increased its life.

Description

Pier column hoop device for bridge bent cap construction
Technical Field
The utility model relates to a bridge bent cap technical field especially relates to a pier stud staple bolt device of bridge bent cap construction.
Background
With the continuous development of society and the improvement of living standard of people, the development of automobiles in China is faster and faster, the construction of bridges is more and more, and the construction of the bent cap during the construction of the bridge and one of the important links of the bent cap are required to be continuously researched, so that the anchor ear is arranged on the pier stud at present, and the method for constructing the bent cap is gradually used by people.
The existing patent (publication number: N202298479U) is a pier column hoop device for bridge capping beam construction, which comprises two pairs of end plate sets and a plurality of standard plates; the two end plate groups are connected end to end through the standard plates to wrap the pier stud of the bridge. As a preferred scheme of the utility model, every including two end plates to end plate group, these two boards pass through bolt fixed connection. As a preferred scheme of the present invention, each end plate group is fixedly connected by a bolt, a plurality of steel pipes are arranged on both sides of each end plate group after the fixed connection, and a plurality of steel pipes are also arranged on both sides of the standard plate; and the steel pipes of the end plates are inserted with the steel pipes of the standard plates through bolts, and the end plates are connected with the standard plates end to end.
In implementing the present invention, the inventor finds that at least the following problems exist in the prior art and are not solved: 1. when the existing pier column hoop device for bridge capping beam construction is used, the use range of the device is reduced because the pier columns with all diameters cannot be clamped; 2. the friction between the existing hoop device and the pier stud is small when the existing hoop device is used.
SUMMERY OF THE UTILITY MODEL
The utility model provides a pair of pier stud staple bolt device of bridge bent cap construction has solved the unable problem that is suitable for all pier studs of pier stud staple bolt device of current bridge bent cap construction.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
a pier column hoop device for bridge capping beam construction comprises a right semicircular plate, a waterproof coiled material, an electric lifter and a clamping plate;
the upper and lower top ends of the outer side wall of the right semicircular plate are fixedly connected with a right fixing plate, the right fixing plate is fixedly connected with the left fixing plate through a bolt, the outer side wall of the bolt is in through connection with a nut in a rotating mode, and the middle of the outer side wall of the bolt is in through connection with a stop block in a right-inclined mode;
fixedly connected with left semicircle board between the upper and lower left fixed plate, left semicircle board and the fixed waterproofing membrane that bonds of right semicircle board lateral wall, left semicircle board and the fixed anticorrosive coating of smearing on right semicircle board inside wall, go up and fixedly connected with electric lift down on the left side in the middle of left semicircle board and the right semicircle board inside wall, electric lift outside wall fixedly connected with splint, the splint lateral wall bonds there is the rubber pad, the fixed pawl that is provided with of rubber pad lateral wall, go up fixedly connected with receiver on the right side in the middle of the right semicircle board lateral wall.
Preferably, the middle of the stop block is provided with a through hole in a penetrating way.
Preferably, the bolt and nut are made of stainless steel.
Preferably, the middle of the inner side wall of the right semicircular plate is fixedly connected with a storage battery in a downward mode.
Preferably, the receiver is in signal connection with the remote controller, and the electric elevator and the receiver are electrically connected with the storage battery.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses a set up electric lift in left semicircle board and right semicircle board to and the setting of splint, make the device when using, at first the staff fixes left fixed plate and right fixed plate through the screw bolt and nut effect, and then fix left semicircle board and right semicircle board at the pier stud lateral wall, the staff sends the instruction to the receiver through the remote controller, the receiver controls electric lift after receiving the instruction, thereby through extending, carry out zonulae occludens with the pier stud lateral wall with the rubber pad on the splint, make the device press from both sides tightly the pier stud of different diameters size, realize using the pier stud of different diameters size, thereby enlarged the application range of device, increased the practicality of device;
2. the utility model discloses owing to set up the pawl on rubber pad for the device has increased its friction effect when pressing from both sides tight pier stud, and waterproofing membrane and anticorrosive coating's setting makes the rate of corrosion on device surface slow down, has increased its life.
Drawings
Fig. 1 is a schematic top view of a pier stud hoop device for bridge capping beam construction according to the present invention;
fig. 2 is a detailed diagram of a rubber pad of the pier stud hoop device for bridge capping beam construction provided by the utility model;
fig. 3 is the utility model provides a pier stud staple bolt device's of bridge bent cap construction circuit diagram.
In the figure: 1. a right semicircular plate; 2. waterproof coiled materials; 3. an anti-corrosion coating; 4. an electric hoist; 5. a splint; 6. a rubber pad; 7. a left fixing plate; 8. a right fixing plate; 9. a bolt; 10. a nut; 11. a stopper; 12. a receiver; 13. a storage battery; 14. a left semicircular plate; 15. and (6) chamfering.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
In the description of the present invention, it is to be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
In the description of the present invention, it should be noted that, unless explicitly stated or limited otherwise, the terms "mounted," "connected" and "disposed" are to be interpreted broadly, and may be, for example, fixedly connected, disposed, detachably connected, disposed, or integrally connected and disposed; the utility model discloses in provide only supply the reference with the model of electrical apparatus. For those skilled in the art, different types of electrical appliances with the same function can be replaced according to actual use conditions, and for those skilled in the art, the specific meaning of the above terms in the present invention can be understood in specific situations.
Referring to fig. 1-3, a pier stud hoop device for bridge capping beam construction comprises a right semi-circular plate 1, a waterproof coiled material 2, an electric elevator 4 and a clamping plate 5;
the upper and lower top ends of the outer side wall of the right semicircular plate 1 are fixedly connected with a right fixing plate 8, the right fixing plate 8 is fixedly connected with the left fixing plate 7 through a bolt 9, the outer side wall of the bolt 9 is in through connection with a nut 10 in a rotating mode, and the middle of the outer side wall of the bolt 9 is in through connection with a stop block 11 in a right-inclined mode;
fixedly connected with left semicircle board 14 between the upper and lower left fixed plate 7, left semicircle board 14 and the fixed waterproofing membrane 2 that bonds of 1 lateral wall of right semicircle board, left semicircle board 14 and the fixed anticorrosive coating 3 that has paintd of 1 inside wall of right semicircle board, go up and fixedly connected with electric lift 4 down on the left side in the middle of left semicircle board 14 and the 1 inside wall of right semicircle board, 4 lateral walls fixedly connected with splint 5 of electric lift, splint 5 lateral wall bonds and has rubber pad 6, 6 lateral walls of rubber pad are fixed and are provided with pawl 15, go up fixedly connected with receiver 12 on the right side in the middle of 1 lateral wall of right semicircle board.
In the embodiment, as shown in fig. 1, fig. 2 and fig. 3, by arranging the electric elevator 4 and the clamping plate 5 in the left semicircular plate 14 and the right semicircular plate 1, when the device is used, firstly, a worker fixes the left fixing plate 7 and the right fixing plate 8 by the bolt 9 and the nut 10, and further fixes the left semicircular plate 14 and the right semicircular plate 1 on the outer side wall of the pier stud, the worker sends an instruction to the receiver 12 through the remote controller, the receiver 12 controls the electric elevator 4 after receiving the instruction, so that the rubber pad 6 on the clamping plate 5 is tightly connected with the outer side wall of the pier stud by extension, the device can clamp the pier studs with different diameters, the pier studs with different diameters can be used, the use range of the device is expanded, the practicability of the device is increased, and because the inverted teeth 15 are arranged on the rubber pad 6, make the device when pressing from both sides tight pier stud, increased its friction effect, waterproofing membrane 2 and anti-corrosion coating 3's setting for the corrosion rate on device surface slows down, has increased its life.
Wherein, the middle of the stop block 11 is provided with a through hole in a penetrating way.
Wherein, the bolt 9 and the nut 10 are made of stainless steel.
Wherein, the middle of the inner side wall of the right semi-circular plate 1 is fixedly connected with a storage battery 13 downwards.
Wherein, the receiver 12 is connected with the remote controller by signals, and the electric elevator 4 and the receiver 12 are electrically connected with the storage battery 13.
The utility model discloses electric lift 4's model is 310, and the model of receiver 12 is 2.4G two-way remote control.
The utility model discloses during the use: at first the staff fixes left fixed plate 7 and right fixed plate 8 through bolt 9 and nut 10 effect, and then fix left semicircle board 14 and right semicircle board 1 at the pier stud lateral wall, the staff sends the instruction to receiver 12 through the remote controller, receiver 12 controls electric lift 4 after receiving the instruction, thereby through the extension, carry out zonulae occludens with rubber pad 6 on the splint 5 and pier stud lateral wall, realize the clamping action, set up pawl 15 on rubber pad 6, make the device when pressing from both sides the pier stud, its friction effect has been increased, waterproofing membrane 2 and anticorrosive coating 3's setting, make the corrosion rate on device surface slow down, the service life thereof is prolonged.
Above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the design of the present invention, equivalent replacement or change should be covered within the protection scope of the present invention.

Claims (5)

1. A pier column hoop device for bridge capping beam construction is characterized by comprising a right semicircular plate (1), a waterproof coiled material (2), an electric elevator (4) and a clamping plate (5);
the upper and lower top ends of the outer side wall of the right semicircular plate (1) are fixedly connected with a right fixing plate (8), the right fixing plate (8) and the left fixing plate (7) are fixedly connected through a bolt (9), the outer side wall of the bolt (9) is connected with a nut (10) in a penetrating manner, and the middle of the outer side wall of the bolt (9) is connected with a stop block (11) in a penetrating manner to the right;
fixedly connected with left semicircle board (14) between upper and lower left fixed plate (7), left semicircle board (14) and right semicircle board (1) lateral wall fixed bonding have waterproofing membrane (2), left semicircle board (14) and right semicircle board (1) inside wall fixed coating have anticorrosive coating (3), on the upper side and fixedly connected with electric lift (4) on the lower side in the middle of left semicircle board (14) and right semicircle board (1) inside wall, electric lift (4) lateral wall fixedly connected with splint (5), splint (5) lateral wall bonding has rubber pad (6), rubber pad (6) lateral wall fixed is provided with pawl (15), on the upper side fixedly connected with receiver (12) in the middle of right semicircle board (1) lateral wall.
2. The pier column hoop device for bridge capping beam construction according to claim 1, wherein a through hole is formed through the middle of the stopper (11).
3. The pier locking device for bridge capping beam construction according to claim 1, wherein the bolt (9) and the nut (10) are made of stainless steel.
4. The pier column hoop device for bridge capping beam construction according to claim 1, wherein a storage battery (13) is fixedly connected to the middle of the inner side wall of the right semi-circular plate (1) in a downward direction.
5. The pier locking device for bridge capping beam construction according to claim 1, wherein the receiver (12) is in signal connection with a remote controller, and the electric elevator (4) and the receiver (12) are electrically connected with the storage battery (13).
CN201921901941.7U 2019-11-06 2019-11-06 Pier column hoop device for bridge bent cap construction Expired - Fee Related CN211256694U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921901941.7U CN211256694U (en) 2019-11-06 2019-11-06 Pier column hoop device for bridge bent cap construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921901941.7U CN211256694U (en) 2019-11-06 2019-11-06 Pier column hoop device for bridge bent cap construction

Publications (1)

Publication Number Publication Date
CN211256694U true CN211256694U (en) 2020-08-14

Family

ID=71988096

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921901941.7U Expired - Fee Related CN211256694U (en) 2019-11-06 2019-11-06 Pier column hoop device for bridge bent cap construction

Country Status (1)

Country Link
CN (1) CN211256694U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113846572A (en) * 2021-11-10 2021-12-28 中铁二十四局集团安徽工程有限公司 Holding system for bridge capping beam construction and construction method
CN114606863A (en) * 2022-03-11 2022-06-10 中铁二十四局集团有限公司 Integrative elevating gear of bent cap template

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113846572A (en) * 2021-11-10 2021-12-28 中铁二十四局集团安徽工程有限公司 Holding system for bridge capping beam construction and construction method
CN114606863A (en) * 2022-03-11 2022-06-10 中铁二十四局集团有限公司 Integrative elevating gear of bent cap template
CN114606863B (en) * 2022-03-11 2023-10-03 中铁二十四局集团有限公司 Integrated lifting device for bent cap template

Similar Documents

Publication Publication Date Title
CN211256694U (en) Pier column hoop device for bridge bent cap construction
CN205123185U (en) Non -maintaining insulator wire fixation clamp
CN204144871U (en) A kind of slidingtype electric equipment gold utensil
CN208039272U (en) A kind of anchor rod device that can monitor prestressd anchor cable in real time
CN101934985A (en) Windproof stay rope device
CN209601929U (en) A kind of suspender for wind power flange and tower welding group pair
CN210957064U (en) Transmission line temporary grounding clamp
CN209868519U (en) Driving maintenance auxiliary device
CN211266344U (en) Electrical cable fixing frame
CN210622339U (en) Vertical through anchor cable multi-cycle tensioning aid
CN103094721A (en) Hook-type fast access joint for emergency supply vehicle
CN206640202U (en) A kind of job platform of collapsible single conductor of closely transmitting electricity
CN210466935U (en) Power distribution network standardized transformer station teaching work instrument
CN203224514U (en) Current transformer polarity test wire hanging rod
CN202259718U (en) Movable-type grounding pile
CN220766282U (en) Precast shear wallboard lifting device
CN207144529U (en) A kind of horizontal life line system of fall arrest for being applied to electromechanical installation specialty
CN212315370U (en) Combined type attached pull rod for tower crane
CN221081203U (en) Solar photovoltaic bracket clamp
CN211859535U (en) Electric power fitting for erecting high-altitude line
CN218231531U (en) Lifting hook for tower crane
CN108678525A (en) A kind of Environment-friendlyanticorrosive anticorrosive concrete shaft tower
CN210326766U (en) Tower crane main cable fixing device
CN211981386U (en) Communication line protection device and wire arranging equipment using same
CN211679764U (en) Reinforcing bar device of buckling for construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200814