CN211201268U CN201921435803.4U CN201921435803U CN211201268U CN 211201268 U CN211201268 U CN 211201268U CN 201921435803 U CN201921435803 U CN 201921435803U CN 211201268 U CN211201268 U CN 211201268U
Authority
CN
China
Prior art keywords
ceiling
cross rod
support post
enclosure
disassembly body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921435803.4U
Other languages
Chinese (zh)
Inventor
张乐源
郭玉桥
汪周敏
范帅朋
崔喆林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN201921435803.4U priority Critical patent/CN211201268U/en
Application granted granted Critical
Publication of CN211201268U publication Critical patent/CN211201268U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Tents Or Canopies (AREA)

Abstract

The utility model discloses an assembled detachable construction site uses electrical equipment protection canopy, include support post, enclosure component, be located the ceiling protection component at support post top, support post through first disassembly body with the connection can be dismantled to the enclosure component, support post top bottom can be dismantled through second disassembly body and ground and be connected, the support post top through third disassembly body with the connection can be dismantled to the ceiling protection component, the utility model discloses the setting of a plurality of disassembly body makes support post, enclosure component and ceiling protection component independently dismantle, simple structure, and the material is easily purchased, simple to operate, convenient to operate, and convenient to detach easily has enough to meet the need, has improved and has faced the utilization ratio of building the facility, increases and faces the construction price/performance ratio, and the setting of ceiling protection component slope is convenient for the drainage.

Description

Assembled detachable construction site power consumption facility protection canopy
Technical Field
The utility model relates to a construction field, concretely relates to assembled detachable construction site uses electric installation protection canopy.
Background
With the continuous development of the building field, the requirement on the working efficiency of a building unit is higher and higher, and the safety still needs to be the central importance of a construction site while the construction progress is accelerated. The electricity consumption of a construction site is a large risk factor, various temporary electricity facilities are exposed outdoors in the construction site, and necessary protection measures must be implemented in place. At present, construction enterprises pay great attention to on-site electricity utilization protection, safety measures are more and more comprehensive, and related materials and cost are gradually increased. A protection canopy for electronic box generally all adopts the welding and makes the fixed structure of whole protection canopy and can not dismantle and remove, and after the protection canopy used, the material of protection canopy can not reuse cyclic utilization and turnover, and the wasting of resources has increased construction cost.
Therefore, the assembled detachable construction site electric facility protective shed which can be recycled and is convenient to turnover is provided, and is a problem worthy of research.
Disclosure of Invention
The utility model aims at providing a simple structure dismantles and has enough to meet need convenient assembled detachable construction site power consumption facility protection canopy.
The purpose of the utility model is realized like this:
the utility model provides an assembled detachable construction site uses electrical equipment protection canopy, includes support post, enclosure member, is located the ceiling protective member at support post top, support post through first disassembly body with enclosure member can dismantle the connection, support post top bottom can be dismantled through second disassembly body and ground and be connected, support post top through third disassembly body with ceiling protective member can dismantle the connection, ceiling protective member's the slope is 10~ 15.
The support post sets up four, is located four angles of rectangle respectively, second disassembly body include with support post top welded second steel sheet with make the second steel sheet is with the expansion bolts that ground is fixed.
The enclosure component comprises a first cross rod and a second cross rod, wherein the first cross rod is located above the supporting stand column, the second cross rod is located below the first cross rod, a plurality of enclosure vertical rods are arranged between the first cross rod and the second cross rod and are in the vertical direction, the number of the first cross rod and the number of the second cross rod are four, and the two ends of the first cross rod and the two ends of the second cross rod are connected with the supporting stand column through first dismounting mechanisms.
First disassembly body is including being located the first steel sheet at first horizontal pole and second horizontal pole both ends, being located third steel sheet on the support post side, first steel sheet with the third steel sheet passes through bolt fixed connection.
The ceiling protective component comprises ceiling cross rods positioned at the tops of the supporting columns, supporting frames positioned above the ceiling cross rods and protective layers positioned above the supporting frames, the number of the ceiling cross rods is four, and two ends of each ceiling cross rod are connected with the supporting columns through second disassembling mechanisms.
The second dismounting mechanism comprises sleeves located at the bottoms of two ends of the ceiling cross bar, and the sleeves are located above the supporting upright posts and inserted into the supporting upright posts.
The front side of the canopy guard member is higher than the rear side of the canopy guard member.
The door is arranged on the enclosure component and connected with the enclosure upright stanchion through a hinge, and the door and the enclosure upright stanchion are provided with door locks.
The utility model has the advantages that: the utility model discloses a plurality of disassembly body's setting makes support post, enclosure component and ceiling protective member independently dismantle, simple structure, and the material is easily purchased, simple to operate, and convenient to detach easily has enough to meet the need, has improved and has faced the utilization ratio of building the facility, increases and faces the construction price/performance ratio, and the drainage of being convenient for is applied to the setting of ceiling protective member slope.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a right side view of FIG. 1;
FIG. 3 is a top view of FIG. 1;
FIG. 4 is an enlarged view of the part A;
FIG. 5 is a right side view of FIG. 4;
FIG. 6 is an enlarged view of the part B;
FIG. 7 is a top view of FIG. 6;
FIG. 8 is an enlarged view of the structure of the part C;
in the figure: the novel ceiling structure comprises a first cross rod 1, a ceiling cross rod 2, a second cross rod 3, a supporting upright post 4, an enclosure upright rod 5, a hinge 6, a door lock 7, a supporting frame 8, a protective layer 9, a first steel plate 10, a bolt 11, a second steel plate 12, an expansion bolt 13, a sleeve 14 and a third steel plate 15.
Detailed Description
The present invention will be further explained with reference to the accompanying drawings.
As shown in fig. 1, 2, 6 and 7, an assembled and detachable electric facility protection shed for a construction site comprises support columns 4, enclosure components and ceiling protection components positioned at the tops of the support columns 4, wherein four support columns 4 are arranged and are respectively positioned at four corners of a rectangle, the support columns 4 adopt galvanized square pipes of 40mmx40mmx2.5mm, the lengths of two support columns 4 at the rear side are 2000mm, the lengths of two support columns 4 at the front side are greater than 2000mm, the support columns 4 are detachably connected with the enclosure components through first dismounting mechanisms, the bottoms of the support columns 4 are detachably connected with the ground through second dismounting mechanisms, each second dismounting mechanism comprises a second steel plate 12 welded with the tops of the support columns 4 and expansion bolts 13 for fixing the second steel plate 12 with the ground, the side length of the second steel plate 12 is 200mmx200mm, and the steel plate has a thickness of 6mm, the expansion bolt 13 is an M12 expansion bolt.
As shown in fig. 1, 4 and 5, the enclosure member includes a first cross bar 1 located above the support column 4 and a second cross bar 3 located below the first cross bar 1, a plurality of enclosure vertical rods 5 located in the vertical direction are arranged between the first cross bar 1 and the second cross bar 3, two ends of the enclosure vertical rods 5 are welded to the first cross bar 1 and the second cross bar 3, the first cross bar 1 and the second cross bar 3 are made of 40mmx40mmx1.5mm galvanized square steel, the enclosure vertical rods 5 are made of 30mmx30mmx1.2mm galvanized square steel, the lengths of the first cross bar 1 on the front side and the rear side are 2700mm, the lengths of the second cross bar 3 on the front side and the rear side are 2700mm, the lengths of the first cross bar 1 on the left side and the right side are 1600mm, the first cross bar 1 and the second cross bar 3 are provided with four, the four first cross bars 1 form a rectangle, and the four second cross bars 3 form a rectangle, first horizontal pole 1 with the both ends of second horizontal pole 3 all through first disassembly body with support post 4 is connected, first disassembly body is including being located the first steel sheet 10 at first horizontal pole 1 and 3 both ends of second horizontal pole, being located third steel sheet 15 on the support post 4 side, first steel sheet 10 with third steel sheet 15 passes through bolt 11 fixed connection, and the length of a side of first steel sheet 10 and second steel sheet 15 is 150mmx150mm, and thickness is 6mm, and bolt 11 adopts M10 bolt, and the equipment of enclosing member and support post 4 is accomplished in the setting of first disassembly body, makes first horizontal pole 1, second horizontal pole 3 dismantle convenient with support post 4, easily the turnover, has improved the utilization ratio that faces the construction and has executed.
As shown in fig. 2, 3 and 8, the top of the support upright 4 is detachably connected with the ceiling protective member through a third dismounting mechanism, the slope of the ceiling protective member is 10-15 °, the front side of the ceiling protective member is higher than the rear side of the ceiling protective member, rainwater flows out from the rear end of the ceiling protective member, the ceiling protective member comprises ceiling crossbars 2 positioned at the top of the support upright 4, support frames 8 positioned above the ceiling crossbars 2 and protective layers 9 positioned above the support frames 8, the support frames 8 are built by 90x40mm square timbers, the distance between adjacent square timbers is 150mm, the length of the square timbers is 1750mm, the four ceiling crossbars 2 are provided, the ceiling crossbars 2 are made of 40 mmxmmx 1.5mm galvanized square steel, the protective layers 9 are made of 3mm thick PC strength plates, the square timbers, the ceiling crossbars 2 and the PC strength plates are connected through rivets, the both ends of ceiling horizontal pole 2 pass through second disassembly body with support post 4 is connected, second disassembly body is including being located the sleeve pipe 14 of 2 both ends bottoms of ceiling horizontal pole, sleeve pipe 14 is located support post 4's top just inserts in support post 4, accomplish the equipment of ceiling horizontal pole 2 and substructure, sleeve pipe 14's length is 25cm, and the area of sleeve pipe 14 cross-section is less than support post 4's sectional area, and sleeve pipe 14 inserts in support post 4 promptly, is convenient for dismantle and have enough to meet the need ceiling horizontal pole 2 and support post 4.
The door is arranged on the enclosure component and connected with the enclosure upright stanchion 5 through the hinge 6, and the door lock 7 are arranged on the enclosure upright stanchion 5, so that the phenomenon of electric shock caused by mistake when a person enters the protection shed is avoided.
The utility model discloses a plurality of disassembly body's setting makes support post, enclosure component and ceiling protective member independently dismantle, simple structure, and the material is easily purchased, simple to operate, and convenient to detach easily has enough to meet the need, has improved and has faced the utilization ratio of building the facility, increases and faces the construction price/performance ratio, and the drainage of being convenient for is applied to the setting of ceiling protective member slope.

Claims (8)

1. The utility model provides an assembled detachable construction site uses electrical facilities protection canopy, includes support post, enclosure member, is located the ceiling protective member at support post top, its characterized in that: the support column through first disassembly body with enclosure component can dismantle the connection, the support column bottom can dismantle through second disassembly body and ground and be connected, the support column top through third disassembly body with ceiling protective member can dismantle the connection, ceiling protective member's slope is 10~ 15.
2. The assembled detachable protective shed for electric facilities on construction sites as claimed in claim 1, wherein: the support post sets up four, is located four angles of rectangle respectively, second disassembly body include with support post top welded second steel sheet with make the second steel sheet is with the expansion bolts that ground is fixed.
3. The assembled detachable protective shed for electric facilities on construction sites as claimed in claim 2, wherein: the enclosure component comprises a first cross rod and a second cross rod, wherein the first cross rod is located above the supporting stand column, the second cross rod is located below the first cross rod, a plurality of enclosure vertical rods are arranged between the first cross rod and the second cross rod and are in the vertical direction, the number of the first cross rod and the number of the second cross rod are four, and the two ends of the first cross rod and the two ends of the second cross rod are connected with the supporting stand column through first dismounting mechanisms.
4. The assembled detachable protective shed for electric facilities on construction sites as claimed in claim 3, wherein: first disassembly body is including being located the first steel sheet at first horizontal pole and second horizontal pole both ends, being located third steel sheet on the support post side, first steel sheet with the third steel sheet passes through bolt fixed connection.
5. The assembled detachable protective shed for electric facilities on construction sites as claimed in claim 1, wherein: the ceiling protective component comprises ceiling cross rods positioned at the tops of the supporting columns, supporting frames positioned above the ceiling cross rods and protective layers positioned above the supporting frames, the number of the ceiling cross rods is four, and two ends of each ceiling cross rod are connected with the supporting columns through second disassembling mechanisms.
6. The assembled detachable protective shed for electric facilities on construction sites as claimed in claim 5, wherein: the second dismounting mechanism comprises sleeves located at the bottoms of two ends of the ceiling cross bar, and the sleeves are located above the supporting upright posts and inserted into the supporting upright posts.
7. The assembled detachable protective shed for electric facilities on construction sites as claimed in claim 6, wherein: the front side of the canopy guard member is higher than the rear side of the canopy guard member.
8. The assembled detachable protective shed for electric facilities on construction sites as claimed in claim 2, wherein: the door is arranged on the enclosure component and connected with the enclosure upright stanchion through a hinge, and the door and the enclosure upright stanchion are provided with door locks.
CN201921435803.4U 2019-08-31 2019-08-31 Assembled detachable construction site power consumption facility protection canopy Expired - Fee Related CN211201268U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921435803.4U CN211201268U (en) 2019-08-31 2019-08-31 Assembled detachable construction site power consumption facility protection canopy

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921435803.4U CN211201268U (en) 2019-08-31 2019-08-31 Assembled detachable construction site power consumption facility protection canopy

Publications (1)

Publication Number Publication Date
CN211201268U true CN211201268U (en) 2020-08-07

Family

ID=71853282

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921435803.4U Expired - Fee Related CN211201268U (en) 2019-08-31 2019-08-31 Assembled detachable construction site power consumption facility protection canopy

Country Status (1)

Country Link
CN (1) CN211201268U (en)

Similar Documents

Publication Publication Date Title
CN109235861B (en) Be applied to small high-rise building's assembled scaffold frame
CN202370253U (en) Assembly type single-row vertical rod machining shed for building construction site
CN201786036U (en) Temporary protective barrier for building construction
CN209976088U (en) Assembled protection canopy
CN211201268U (en) Assembled detachable construction site power consumption facility protection canopy
CN202157581U (en) Foundation-pit limb shaping protection device
CN212478675U (en) Convenient ann tears assembled steel construction reinforcing bar processing protection canopy open
CN204040556U (en) A telescopic graduation two electronic box protection canopy
CN111519949B (en) Convenient assembly steel construction reinforcing bar processing protection canopy of tearing open
CN202577162U (en) Combined-type steel pipe bracket
CN214615669U (en) Be suitable for special plain type reinforcing bar protection canopy of processing pile foundation steel reinforcement cage
CN205558325U (en) Multi -functional quick installation and recovery protection canopy
CN202031323U (en) Multifunctional reinforcing plate of reinforced concrete early-disassembled beam template system
CN217508096U (en) Easily install electric power circuit modularization crossing structure
CN217486056U (en) Power line modularization crossing structure
CN206053414U (en) Distribution Board for Construction Site protection canopy
CN211666427U (en) Assembled face limit protective apparatus
CN219451415U (en) Portable steel structure welding operation platform
CN217461640U (en) Assembled steel bar machining workshop structure
CN221481482U (en) Stiff steel column protection structure for steel platform
CN213039059U (en) Personnel warning device for building safety protection
CN216157321U (en) Make things convenient for scalable protection railing of dismouting interlude formula
CN220978730U (en) Lantern frame device for upright post construction
CN220580041U (en) Open caisson formwork platform
CN214939283U (en) Pier shaft template safety protection operation platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200807

CF01 Termination of patent right due to non-payment of annual fee