CN211201099U - Cantilever device for building engineering construction - Google Patents

Cantilever device for building engineering construction Download PDF

Info

Publication number
CN211201099U
CN211201099U CN201921490867.4U CN201921490867U CN211201099U CN 211201099 U CN211201099 U CN 211201099U CN 201921490867 U CN201921490867 U CN 201921490867U CN 211201099 U CN211201099 U CN 211201099U
Authority
CN
China
Prior art keywords
base
fixed
construction
building engineering
universal wheel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921490867.4U
Other languages
Chinese (zh)
Inventor
邱穆彬
万鹏翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201921490867.4U priority Critical patent/CN211201099U/en
Application granted granted Critical
Publication of CN211201099U publication Critical patent/CN211201099U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a scaffold device is used in building engineering construction, including the base, the equal fixed mounting in four corners of the bottom of base has the universal wheel, and the universal wheel is the locking universal wheel, and the fixed column is installed to one side on base top, and the base has the packing ring with the junction fixed mounting of fixed column, stock and base fixed connection that the fixed column was equipped with through its avris, and one side and the wall body of base are laminated mutually. A outrigger device for building engineering construction, block pole and block piece through being equipped with are convenient to fix the spliced pole when reciprocating, extend the transverse length of spliced pole through the extension rod that is equipped with and the fixed block is convenient, avoided because the construction that the distance does not lead to the fact is inconvenient, conveniently remove the outrigger device through the universal wheel that is equipped with, be convenient for fix between outrigger device and the wall body through the connecting rod and the sleeve that are equipped with, security performance when having improved the construction.

Description

Cantilever device for building engineering construction
Technical Field
The utility model relates to a construction field, in particular to outrigger device for building engineering construction.
Background
The scaffold is often needed to be used in the process of constructing buildings, but the existing scaffold is difficult to move when in use, and meanwhile, the longitudinal height and the transverse length of the scaffold can not be adjusted.
Therefore, the cantilever device for the construction of the building engineering is provided.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a scaffold device is used in building engineering construction can effectively solve the problem in the background art.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a scaffold device for building engineering construction, includes the base, the equal fixed mounting in four corners of the bottom of base has the universal wheel, just the universal wheel is the locking universal wheel, the fixed column is installed to one side on base top, the base has the packing ring with the junction fixed mounting of fixed column, stock and base fixed connection that the fixed column was equipped with through its avris, one side and the wall body of base are laminated mutually, the top cover of fixed column is established and is installed the spliced pole.
Preferably, the bottom end of the inside of the base is fixedly provided with a damping spring, and the joint of the base and the wall body is fixedly provided with an anti-collision layer.
Preferably, the one end of spliced pole is through two fixed block fixedly connected with extension rod, two the both sides of the inside of fixed block are all fixed and are equipped with concave screw thread, and two the bolt through connection that the fixed block was equipped with.
Preferably, one side of the middle part of the fixed column is fixedly provided with a clamping block, the bottom of one side of the connecting column is hinged with the clamping block, and the bottom end of the clamping rod is matched with the size of the clamping block.
Preferably, the extension ladder is installed to the opposite side on base top, just the bottom of extension ladder and the top looks block of base, another avris of spliced pole is fixed mounting respectively has the non slipping spur, the extension ladder top respectively with two the position of non slipping spur is corresponding, just the surface mounting of spliced pole has and twines the safety chain of extension ladder one side.
Preferably, the top fixed mounting of wall body has the connecting rod, the inside fixed sleeve that is provided with of connecting rod, the other end of spliced pole passes the sleeve and alternates with the connecting rod to be connected.
Compared with the prior art, the utility model discloses following beneficial effect has:
1. the connecting column can be fixed when moving up and down through the clamping rod and the clamping block, when the scaffold is required to be used, the connecting column is firstly sleeved on the surface of the fixing column, the height of the scaffold is determined according to the height of construction, when the connecting column is moved to a proper position, one end of the connecting column corresponds to the position of the sleeve in the connecting rod, the clamping rod is rotated, the bottom end of the clamping rod and the clamping block at the corresponding position are mutually clamped, then the scaffold device is moved through the universal wheel, and the other end of the connecting column is clamped with the connecting rod;
2. the connecting column is provided with the extension rod and the fixing block, so that the transverse length of the connecting column can be extended, the construction inconvenience caused by insufficient distance is avoided, when the length of the connecting column needs to be extended, the extension rod is clamped and connected with one end of the connecting column, the two connecting blocks are respectively arranged at the top end and the bottom end of the joint, and the two connecting blocks are in threaded connection with the inside of the fixing block through the arranged bolts;
3. through the universal wheel that is equipped with, the convenience is removed the outrigger device, the universal wheel can be fixed at any time for the locking universal wheel simultaneously, the safety of workman when being under construction on the outrigger has been guaranteed, be convenient for fix between outrigger device and the wall body through connecting rod and the sleeve that is equipped with, the security performance when having improved the construction, through the damping spring who is equipped with, wearing and tearing and the collision between outrigger device and external wall body when the part is connected between packing ring and the anticollision layer have all been avoided, the life of outrigger device has been improved, the workman is difficult to the problem of climbing the operation to the outrigger device when having avoided the construction through the non slipping spur that is equipped with and extension ladder, the non slipping spur has played anti-skidding effect.
Drawings
Fig. 1 is a schematic view of the overall structure of a scaffold device for building engineering construction of the present invention;
FIG. 2 is a schematic view of the internal structure of the cantilever device for construction of building engineering of the present invention;
FIG. 3 is a schematic structural view of a connecting rod of the scaffold device for construction of building engineering of the present invention;
fig. 4 is a schematic structural view of a fixing block of the cantilever device for construction of the utility model;
fig. 5 is the utility model relates to a structural schematic of the connecting rod of outrigger device for the construction of building engineering.
In the figure: 1. a base; 2. a universal wheel; 3. fixing a column; 4. connecting columns; 5. an extension ladder; 6. an extension rod; 7. a fixed block; 8. a clamping rod; 9. a clamping block; 10. a gasket; 11. an anchor rod; 12. a damping spring; 13. an anti-collision layer; 14. a wall body; 15. anti-skid blocks; 16. a connecting rod; 17. a sleeve; 18. a bolt; 19. a female thread.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
Example 1
As shown in fig. 1-5, a scaffold device for building engineering construction, including base 1, the equal fixed mounting in four corners of base 1's bottom has universal wheel 2, and universal wheel 2 is the locking universal wheel, fixed column 3 is installed to one side on base 1 top, base 1 and fixed column 3's junction fixed mounting has packing ring 10, stock 11 and base 1 fixed connection that fixed column 3 was equipped with through its avris, one side of base 1 is laminated with wall body 14 mutually, the top cover of fixed column 3 is established and is installed spliced pole 4.
One side at the middle part of the fixed column 3 is fixedly provided with a clamping block 9, the bottom at one side of the connecting column 4 is hinged with the clamping block 9, and the bottom end of the clamping rod 8 is matched with the size of the clamping block 9.
The top end of the wall body 14 is fixedly provided with a connecting rod 16, a sleeve 17 is fixedly arranged inside the connecting rod 16, and the other end of the connecting column 4 penetrates through the sleeve 17 to be connected with the connecting rod 16 in a penetrating manner.
By adopting the technical scheme: through the block pole 8 that is equipped with and block 9 convenient fix spliced pole 4 when reciprocating, when needs use the outrigger, at first establish spliced pole 4 cover with fixed column 3 surface, highly confirm the height of outrigger according to the construction, when removing spliced pole 4 suitable position, correspond spliced pole 4's one end and sleeve 17 position in the connecting rod 16 each other, rotate block pole 8, make the bottom of card and pole with block 9 of corresponding position between each other block and, rethread universal wheel 2 removes the outrigger device, can with the other end and the connecting rod 16 looks block of spliced pole 4.
Example 2
As shown in fig. 1-5, a scaffold device for building engineering construction, including base 1, the equal fixed mounting in four corners of base 1's bottom has universal wheel 2, and universal wheel 2 is the locking universal wheel, fixed column 3 is installed to one side on base 1 top, base 1 and fixed column 3's junction fixed mounting has packing ring 10, stock 11 and base 1 fixed connection that fixed column 3 was equipped with through its avris, one side of base 1 is laminated with wall body 14 mutually, the top cover of fixed column 3 is established and is installed spliced pole 4.
The one end of spliced pole 4 is through two fixed block 7 fixedly connected with extension rod 6, and the both sides of the inside of two fixed blocks 7 are all fixed to be equipped with concave screw thread 19, and two fixed blocks 7 are through connection through the bolt 18 that is equipped with.
By adopting the technical scheme: extension rod 6 and fixed block 7 through being equipped with are convenient to extend the horizontal length of spliced pole 4, have avoided because the distance is inconvenient for the construction that causes inadequately, when needs extend spliced pole 4's length, carry out the block with extension rod 6 and spliced pole 4's one end and be connected, install respectively in the top and the bottom of junction with two connecting blocks again, through the bolt 18 that sets up and fixed block 7 inside carry out threaded connection can.
Example 3
As shown in fig. 1-5, a scaffold device for building engineering construction, including base 1, the equal fixed mounting in four corners of base 1's bottom has universal wheel 2, and universal wheel 2 is the locking universal wheel, fixed column 3 is installed to one side on base 1 top, base 1 and fixed column 3's junction fixed mounting has packing ring 10, stock 11 and base 1 fixed connection that fixed column 3 was equipped with through its avris, one side of base 1 is laminated with wall body 14 mutually, the top cover of fixed column 3 is established and is installed spliced pole 4.
The bottom end of the inside of the base 1 is fixedly provided with a damping spring 12, and the joint of the base 1 and the wall 14 is fixedly provided with an anti-collision layer 13.
Extension ladder 5 is installed to the opposite side on base 1 top, and extension ladder 5's bottom and base 1's top looks block, and another avris of spliced pole 4 fixed mounting has non slipping spur 15 respectively, and extension ladder 5 top is corresponding with two non slipping spur 15's position respectively, and the surface mounting of spliced pole 4 has and twines the safety chain of extension ladder 5 one side.
By adopting the technical scheme: the scaffold device is convenient to move through the universal wheel 2, meanwhile, the universal wheel 2 can be fixed at any time for the locking universal wheel 2, the safety of workers during construction on the scaffold is guaranteed, the scaffold device and the wall body 14 are convenient to fix through the connecting rod 16 and the sleeve 17 which are arranged, the safety performance during construction is improved, the damping spring 12 is arranged, the gasket 10 and the anti-collision layer 13 avoid abrasion during connection between parts and collision between the scaffold device and the external wall body 14, the service life of the scaffold device is prolonged, the problem that the workers are difficult to climb the scaffold device during construction is avoided through the anti-skid block 15 and the telescopic ladder 5, and the anti-skid block 15 plays a role in skid resistance.
It should be noted that the utility model relates to a scaffold device for building engineering construction, when using, when needing to use the scaffold, firstly, the connecting post 4 is sleeved on the surface of the fixed column 3, the height of the scaffold is determined according to the height of construction, when the connecting post 4 is moved to a proper position, one end of the connecting post 4 is corresponding to the sleeve 17 in the connecting rod 16, the clamping rod 8 is rotated to mutually clamp the bottom end of the clamping rod and the clamping block 9 at the corresponding position, then the scaffold device is moved by the universal wheel 2, the other end of the connecting post 4 is clamped with the connecting rod 16, when needing to extend the length of the connecting post 4, the extending rod 6 is clamped with one end of the connecting post 4, then two connecting blocks are respectively arranged at the top end and the bottom end of the junction, and are connected with the inside of the fixed block 7 by the screw thread through the bolt 18, the wearing and tearing and the collision between outrigger device and external wall 14 when having avoided being connected between part and the part through damping spring 12, packing ring 10 and anticollision layer 13 that are equipped with have improved the life of outrigger device, have avoided the problem that the workman is difficult to the operation of climbing of outrigger device when the construction through the non slipping spur 15 that is equipped with and extension ladder 5, and non slipping spur 15 has played anti-skidding effect.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (6)

1. The utility model provides a scaffold device for building engineering construction, includes base (1), its characterized in that: the equal fixed mounting in four corners of the bottom of base (1) has universal wheel (2), just universal wheel (2) are the locking universal wheel, fixed column (3) are installed to one side on base (1) top, base (1) and the junction fixed mounting of fixed column (3) have packing ring (10), stock (11) and base (1) fixed connection that fixed column (3) were equipped with through its avris, one side and wall body (14) of base (1) are laminated mutually, the top cover of fixed column (3) is established and is installed spliced pole (4).
2. The outrigger device for construction of building engineering according to claim 1, wherein: the shock-absorbing floor is characterized in that a shock-absorbing spring (12) is fixedly mounted at the bottom end of the interior of the base (1), and an anti-collision layer (13) is fixedly mounted at the joint of the base (1) and a wall body (14).
3. The outrigger device for construction of building engineering according to claim 1, wherein: the one end of spliced pole (4) is through two fixed block (7) fixedly connected with extension rod (6), two the both sides of the inside of fixed block (7) are all fixed and are equipped with concave screw thread (19), and two bolt (18) through connection that fixed block (7) were equipped with.
4. The outrigger device for construction of building engineering according to claim 1, wherein: one side in the middle of the fixed column (3) is fixedly provided with a clamping block (9), the bottom of one side of the connected column (4) is hinged with the clamping block (9), and the bottom end of the clamping rod (8) is matched with the size of the clamping block (9).
5. The outrigger device for construction of building engineering according to claim 1, wherein: extension ladder (5) are installed to the opposite side on base (1) top, just the bottom of extension ladder (5) and the top looks block of base (1), another avris of spliced pole (4) is fixed mounting respectively has non slipping spur (15), extension ladder (5) top respectively with two the position of non slipping spur (15) is corresponding, just the surface mounting of spliced pole (4) has the safety chain with winding extension ladder (5) one side.
6. The outrigger device for construction of building engineering according to claim 1, wherein: the top fixed mounting of wall body (14) has connecting rod (16), the inside fixed sleeve (17) that is provided with of connecting rod (16), the other end of spliced pole (4) passes sleeve (17) and alternates with connecting rod (16) and is connected.
CN201921490867.4U 2019-09-09 2019-09-09 Cantilever device for building engineering construction Active CN211201099U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921490867.4U CN211201099U (en) 2019-09-09 2019-09-09 Cantilever device for building engineering construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921490867.4U CN211201099U (en) 2019-09-09 2019-09-09 Cantilever device for building engineering construction

Publications (1)

Publication Number Publication Date
CN211201099U true CN211201099U (en) 2020-08-07

Family

ID=71852657

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921490867.4U Active CN211201099U (en) 2019-09-09 2019-09-09 Cantilever device for building engineering construction

Country Status (1)

Country Link
CN (1) CN211201099U (en)

Similar Documents

Publication Publication Date Title
CN211201099U (en) Cantilever device for building engineering construction
KR20150116742A (en) An apparatus for mounting safety guard
CN209259618U (en) A kind of power construction device
CN211472309U (en) Anti-collision traffic guardrail capable of being rapidly disassembled
CN204992407U (en) A cable fixing device for oil well head fishing operation
CN204676756U (en) The fastener of top board furred ceiling
CN209760752U (en) Scaffold for building engineering
CN209891235U (en) Integral pre-buried structure of steel structure column lower margin bolt
CN207974041U (en) A kind of construction site safety alarm device
CN214738303U (en) Hole cleaning tool for underground cut-off wall construction
CN210577467U (en) Cable protector for tower crane
CN213585118U (en) Cable head butt joint reinforcing apparatus for electrical engineering
CN205713060U (en) Scaffold is stood plate
CN204089035U (en) A kind of transmission line pole tower ascent aid
JPH1118226A (en) Expansion rod device and method for expanding/ contacting expansion body of the same
CN214329827U (en) Hanging basket for constructional engineering
CN216381182U (en) Rod climbing anti-skidding ladder stand in rainy days
CN219316344U (en) Engineering site safety construction frame
CN203742185U (en) Hanging bar mounting operating rod
CN203080897U (en) Steel pipe scaffold connecting tube
CN217996511U (en) Unhooking prevention device for travelling crane
CN214942686U (en) Protection device for ready-package building construction
CN217480780U (en) Novel scaffold bolt fastener type wall connecting piece
CN218562080U (en) Bridge overhauls frame
CN216641541U (en) Outer frame regularization steel stair of going up people

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant