CN211189683U - Nitromethane tail gas absorbs processing apparatus - Google Patents

Nitromethane tail gas absorbs processing apparatus Download PDF

Info

Publication number
CN211189683U
CN211189683U CN202020464617.XU CN202020464617U CN211189683U CN 211189683 U CN211189683 U CN 211189683U CN 202020464617 U CN202020464617 U CN 202020464617U CN 211189683 U CN211189683 U CN 211189683U
Authority
CN
China
Prior art keywords
rotating rod
box body
tail gas
nitromethane
fixed mounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020464617.XU
Other languages
Chinese (zh)
Inventor
张军
张世东
耿复虎
张汉生
杨建军
吕海龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhanhua Binbo Chemical Co ltd
Original Assignee
Zhanhua Binbo Chemical Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhanhua Binbo Chemical Co ltd filed Critical Zhanhua Binbo Chemical Co ltd
Priority to CN202020464617.XU priority Critical patent/CN211189683U/en
Application granted granted Critical
Publication of CN211189683U publication Critical patent/CN211189683U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Gas Separation By Absorption (AREA)

Abstract

The utility model discloses a nitromethane tail gas absorbs processing apparatus, including the box, box one side fixed mounting intake pipe, box opposite side fixed mounting outlet duct, outlet duct and intake pipe all communicate with each other with the box is inside, fixed mounting condenser between intake pipe and the box, fixed mounting fan between outlet duct and the box, two vertical baffles of the inside fixed mounting of box, the inside three cavity that is of box, the bottom surface fixed mounting of three cavity has the first standpipe of control valve. The utility model discloses to tail gas absorption efficiency height, easy operation, long service life, can be in time effectual absorb nitromethane tail gas, purified operational environment, stopped tail gas to staff's harm, practice thrift simultaneously and mix the liquid.

Description

Nitromethane tail gas absorbs processing apparatus
Technical Field
The utility model relates to a chemical industry equipment technical field specifically is a nitromethane tail gas absorbs processing apparatus.
Background
Nitromethane is an important basic organic chemical raw material, has good market prospect at home and abroad, a nitration synthesis process route of a sodium nitrite and dimethyl sulfate replacement method is adopted at home at present, sodium nitrite and dimethyl sulfate are added into a reaction kettle in the production process, a reaction product is distilled, condensed, layered and rectified to prepare a product, the synthesis process is intermittent, the sodium nitrite with low price is properly excessive, the yield of the nitromethane is only about 55 percent, a large amount of tail gas of nitromethane isomer methyl nitrite, nitric oxide and the like is generated due to parallel competition reaction and side reaction in production, and environmental pollution can be caused if the tail gas cannot be well absorbed and treated.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a nitromethane tail gas absorbs processing apparatus to it is not enough to solve prior art.
To achieve the above object, the present invention provides a liquid discharge pipe having a liquid discharge pipe with a valve and communicating with the inside of a corresponding rotating rod, a vertical branch pipe fixedly installed inside the chamber, a branch pipe corresponding to the liquid inlet pipe and communicating with the inside of the liquid inlet pipe, a bypass pipe fixedly installed inside the chamber, a motor cartridge having a motor cartridge, a motor cartridge, a motor cartridge, a motor cartridge, a motor cartridge, a motor.
The nitromethane tail gas absorption treatment device comprises an air outlet pipe, wherein a guide frame is fixedly arranged in the air outlet pipe, a plurality of inclined plates are fixedly arranged in the guide frame, the inclined surfaces of the inclined plates face the nearest guide plate, and drying layers are arranged on two sides of each inclined plate.
According to the nitromethane tail gas absorption treatment device, the first vertical pipes with the control valves are fixedly mounted on the bottom surfaces of the three cavities, the control valves are electromagnetic valves, the controller and the timer are fixedly mounted on the bottom surface of the box body, and the timer and the control valves are electrically connected with the controller.
According to the nitromethane tail gas absorption treatment device, the filter layer is fixedly arranged in the air inlet pipe.
According to the nitromethane tail gas absorption treatment device, the cooler is fixedly installed at the end part of the gas outlet pipe.
The utility model has the advantages that: the utility model discloses to tail gas absorption efficiency height, easy operation, long service life, can be in time effectual absorb nitromethane tail gas, purified operational environment, stopped tail gas to staff's harm, practice thrift simultaneously and mix the liquid.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required to be used in the description of the embodiments are briefly introduced below, and it is obvious that the drawings in the following description are some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without inventive labor.
Fig. 1 is a schematic view of the overall structure of the present invention; fig. 2 is an enlarged view of the view from the direction a of fig. 1.
Reference numerals: 1-box body, 2-air inlet pipe, 3-air outlet pipe, 4-condenser, 5-blower, 6-clapboard, 7-cavity, 8-first vertical pipe, 9-box body, 10-circulating pump, 11-liquid outlet pipe, 12-branch pipe, 13-air vent, 14-box body, 15-vertical plate, 16-second vertical pipe, 17-liquid inlet pipe, 18-through hole, 19-rotating rod, 20-stirring rod, 21-belt wheel, 22-belt, 23-motor, 24-bracket, 9.1-first box body, 9.2-second box body, 9.3-third box body, 14.1-first box body, 14.2-second box body and 14.3-third box body.
Detailed Description
As shown in fig. 1 to 2, the nitromethane tail gas absorption treatment device specifically disclosed in the embodiment includes a box body 1, an inlet pipe 2 is fixedly installed on one side of the box body 1, an outlet pipe 3 is fixedly installed on the other side of the box body 1, both the outlet pipe 3 and the inlet pipe 2 are communicated with the inside of the box body 1, a condenser 4 is fixedly installed between the inlet pipe 2 and the box body 1, a fan 5 is fixedly installed between the outlet pipe 3 and the box body 1, two vertical partition plates 6 are fixedly installed inside the box body 1, three cavities 7 are formed inside the box body 1, a first vertical pipe 8 with a control valve is fixedly installed on the bottom surface of the three cavities 7, a box body 9 is fixedly installed at the lower end of the first vertical pipe 8, four first vertical pipes 8 are fixedly installed on the bottom surface of the box body 1, box bodies 9 are fixedly installed on the lower parts of the box body 1, both the box body 1 and the box body 9 are communicated with the corresponding to a rotating rod 14, the rotating rod 7 is arranged from the rotating rod 7, a rotating rod 7.7, a rotating rod 7 is arranged to the rotating rod 7, a rotating rod 7 is arranged to rotate, a rotating rod 7 is arranged to rotate, a rotating rod 7 is arranged to rotate a rotating rod 7, a rotating rod 7 is arranged to rotate, a rotating rod 7 is arranged to rotate a rotating rod 7, a rotating rod 7 is arranged to rotate a rotating rod 7, a rotating rod 7 is arranged to rotate a rotating rod 7, a rotating rod is arranged to rotate a rotating rod 7, a rotating rod 7 is arranged to rotate a rotating rod 7, a rotating rod 7 is arranged to rotate a rotating rod 7, a rotating rod 7 is arranged to rotate a rotating rod 7, a rotating rod is arranged to rotate a rotating rod 7, a rotating rod is arranged to rotate a rotating rod 7, a rotating rod is arranged to rotate a rotating rod 7, a rotating rod.
Specifically, this embodiment 3 inside fixed mounting water conservancy diversion frames of outlet duct, a plurality of swash plates of fixed mounting in the water conservancy diversion frame, the inclined plane direction of swash plate is towards nearest guide plate, the swash plate both sides set up the drying layer. When gaseous 3 outflow through the outlet duct, can remove the tide to gaseous through the drying layer, when the drying layer need be changed, can continue to use after handling with the dismantlement of water conservancy diversion frame.
Specifically, this embodiment the bottom surface fixed mounting of three cavity 7 have a first standpipe 8 of control valve, the control valve is the solenoid valve, the bottom surface fixed mounting controller and the timer of box 1, timer and control valve all with controller electric connection. When the device is used, the time is set through the timer, the controller is transmitted with the signal after the time is up, and the controller can control the electromagnetic valve to work, so that the intelligent operation can be realized.
Further, the filter layer is fixedly installed inside the air inlet pipe 2. When using this device, can prevent through the filter layer that the impurity in the tail gas from entering into in the box 1 to can be convenient for absorb the processing to tail gas.
Furthermore, the end of the outlet pipe 3 of the present embodiment is fixedly installed with a cooler. When the device is used, the gas can be cooled again through the cooler, so that the gas can be conveniently discharged.
The embodiments of the present invention have been described with reference to the accompanying drawings, but these descriptions should not be construed as limiting the scope of the present invention, and the technical contents not described in detail in the present invention are known in the art.

Claims (5)

1. The nitromethane tail gas absorption treatment device is characterized by comprising a box body (1), an air inlet pipe (2) is fixedly installed on one side of the box body (1), an air outlet pipe (3) is fixedly installed on the other side of the box body (1), the air outlet pipe (3) and the air inlet pipe (2) are communicated with the inside of the box body (1), a condenser (4) is fixedly installed between the air inlet pipe (2) and the box body (1), a fan (5) is fixedly installed between the air outlet pipe (3) and the box body (1), two vertical partition plates (6) are fixedly installed inside the box body (1), three cavities (7) are formed inside the box body (1), a first vertical pipe (8) with a control valve is fixedly installed on the bottom surface of the three cavities (7), a rotating rod (9) is fixedly installed on the bottom surface of the box body (1), four first vertical pipes (8) are fixedly installed on the bottom surface of the box body (1), the rotating rod (1) is fixedly installed on the rotating rod (9), the rotating rod (1) and the box body (9) are communicated with the inside a first vertical pipe (14), the rotating rod (7), the rotating rod (14), the rotating rod (7) is installed on the rotating rod (7), the rotating rod (9) is installed on the rotating rod (7), the rotating rod (9) and the rotating rod (7), three rotating rod (9), the rotating rod (9), three rotating rod (2), three rotating rod (14) is installed on the rotating rod (2), the rotating rod (7), three rotating rod (2), three rotating rod (7) is installed on the rotating rod (7), three rotating rod (2) and the rotating rod (2), three rotating rod (7), three rotating rod (2) are installed on the rotating rod (2) and the rotating rod (2), three rotating rod (2) and the rotating rod (7), three rotating rod (2) are installed on the rotating rod (2) and the rotating rod (2), three rotating rod (2) are installed on the rotating rod (2), three rotating rod (2) are installed on the rotating rod (7), three rotating rod (2) are installed on the rotating rod (2) and the rotating rod (2), three rotating rod (2) are installed on the rotating rod (14) from the rotating rod (2), three rotating rod (14) from the rotating rod (2), three rotating rod (14) from the rotating rod (14) are installed from the rotating rod (2), three rotating rod (14).
2. The nitromethane tail gas absorption treatment device according to claim 1, characterized in that: the inside fixed mounting water conservancy diversion frame of outlet duct (3), fixed mounting several swash plates in the water conservancy diversion frame, the inclined plane direction of swash plate is towards nearest guide plate, the swash plate both sides set up the drying layer.
3. The nitromethane tail gas absorption treatment device according to claim 1, characterized in that: the bottom surface fixed mounting of three cavity (7) have first standpipe (8) of control valve, the control valve is the solenoid valve, the bottom surface fixed mounting controller and the timer of box (1), timer and control valve all with controller electric connection.
4. The nitromethane tail gas absorption treatment device according to claim 1, characterized in that: the filter layer is fixedly arranged in the air inlet pipe (2).
5. The nitromethane tail gas absorption treatment device according to claim 1, characterized in that: and a cooler is fixedly arranged at the end part of the air outlet pipe (3).
CN202020464617.XU 2020-04-02 2020-04-02 Nitromethane tail gas absorbs processing apparatus Expired - Fee Related CN211189683U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020464617.XU CN211189683U (en) 2020-04-02 2020-04-02 Nitromethane tail gas absorbs processing apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020464617.XU CN211189683U (en) 2020-04-02 2020-04-02 Nitromethane tail gas absorbs processing apparatus

Publications (1)

Publication Number Publication Date
CN211189683U true CN211189683U (en) 2020-08-07

Family

ID=71882620

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020464617.XU Expired - Fee Related CN211189683U (en) 2020-04-02 2020-04-02 Nitromethane tail gas absorbs processing apparatus

Country Status (1)

Country Link
CN (1) CN211189683U (en)

Similar Documents

Publication Publication Date Title
CN208553653U (en) A kind of Horizental showering tower for pickling exhaust-gas treatment
CN217773770U (en) Energy-efficient tail gas washing tower
CN211189683U (en) Nitromethane tail gas absorbs processing apparatus
CN206881453U (en) One kind mixing organic waste-gas purification and energy processing system
CN208642288U (en) A kind of production of chloroacetic acid exhaust purifier
CN215261286U (en) Cooler and regeneration cooling system for adsorbing methanol tail gas
CN214276565U (en) Cooling tower for efficient treatment of industrial sewage
CN212396098U (en) Filter device with cooling system
CN210410163U (en) Waste gas desulfurization denitration is with spraying purifier
CN212680540U (en) Acid mist collecting device for storage battery processing
CN212283551U (en) Integrated form VOC exhaust gas purification device
CN220003524U (en) Hydrochloric acid tail gas absorption treatment device
CN220531170U (en) Tail gas recovery and purification treatment device of pivaloyl chloride production line
CN205154637U (en) Vacuum pump water inlet section water installation
CN220489810U (en) Chemical equipment heat transfer recycling equipment
CN218901273U (en) High-efficient processing apparatus of garbage incinerator tail gas thermal cycle
CN212262710U (en) Chemical industry is exhaust treatment device for reation kettle
CN214661157U (en) Hydraulic pump convenient to clean oil tank
CN220125831U (en) Elevator part spraying exhaust treatment device
CN209493324U (en) A kind of embrane method ammonia nitrogen waste water prepares ammonium hydroxide system
CN219376685U (en) Waste gas purification device for coal chemical industry
CN218944691U (en) Exhaust treatment device for ethylene carbonate
CN209596905U (en) A kind of exhaust gas washing tower being readily transported
CN213171836U (en) Novel water treatment equipment
CN214159135U (en) Vertical acid-base waste gas washing treatment device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A nitromethane tail gas absorption and treatment device

Effective date of registration: 20200914

Granted publication date: 20200807

Pledgee: Bank of China Binzhou branch

Pledgor: Zhanhua Binbo Chemical Co.,Ltd.

Registration number: Y2020980006016

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200807