CN211173100U - From area detachable hangs mould finished product and wears floor sleeve pipe - Google Patents

From area detachable hangs mould finished product and wears floor sleeve pipe Download PDF

Info

Publication number
CN211173100U
CN211173100U CN201921491524.XU CN201921491524U CN211173100U CN 211173100 U CN211173100 U CN 211173100U CN 201921491524 U CN201921491524 U CN 201921491524U CN 211173100 U CN211173100 U CN 211173100U
Authority
CN
China
Prior art keywords
hanging
sleeve
die
mould
suspension
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921491524.XU
Other languages
Chinese (zh)
Inventor
罗聪
骆金洁
齐凯
单景利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201921491524.XU priority Critical patent/CN211173100U/en
Application granted granted Critical
Publication of CN211173100U publication Critical patent/CN211173100U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model relates to a finished product floor-penetrating sleeve with a detachable hanging die, which comprises a hanging rod, a sleeve, a hanging die and a hanging wire; the hanging mould comprises a hanging mould flat plate main body and a hanging mould vertical part which are connected in a welding mode; the hanging die flat plate main body and the hanging die vertical part are welded to form an integral body with an inverted T-shaped structure; the sleeve can be embedded into a reserved hole of the floor slab, the outer wall of the sleeve is tightly attached to the inner wall of the reserved hole, and the diameter of the vertical part of the suspended mould is smaller than that of the sleeve; the bottom end of the suspension wire is fixedly connected with the top end of the vertical part of the suspension mould through welding, and the top end of the suspension wire is bolted with the suspension rod; the finished product of the suspended mould of the utility model is easy to construct and low in cost, and the suspended mould and the hanging rod are connected by the suspending wire, so that the position of the sleeve can be finely adjusted conveniently in the period, and the reliable installation of the sleeve is ensured; after concrete is poured and solidified, the hoisting wires are taken down, the hoisting die can be detached conveniently, the casing hoisting die part can be used in a circulating mode in the casing with the same pipe diameter, the time and labor are saved in installation, and the quality of the hoisting die is good.

Description

From area detachable hangs mould finished product and wears floor sleeve pipe
Technical Field
The utility model relates to a construction technical field especially relates to a from taking dismountable hanging formwork finished product to wear floor sleeve pipe.
Background
The building construction refers to production activities in the engineering construction implementation stage, is the construction process of various buildings, and can also be said to be the process of changing various lines on the design drawing into a real object in a designated place, and comprises foundation engineering construction, main structure construction, roofing engineering construction, decoration engineering construction and the like; in the building construction, vertical pipe installation is owing to ensure the perpendicular installation of pipeline, often reserves the entrance to a cave on the floor, and after pipeline and sleeve pipe installation are accomplished, reserve the entrance to a cave and carry out the secondary and hang the mould grout, and it is time-consuming to take a lot of work, and hangs the mould quality not good.
SUMMERY OF THE UTILITY MODEL
The utility model aims to overcome prior art's the time and labor consuming, and hang the not good defect of mould quality, provide a from taking detachable to hang the mould finished product and wearing floor sleeve pipe, have with low costs, application scope extensively, the construction is convenient and guarantee to hang the advantage of mould quality.
The technical scheme for realizing the purpose is as follows:
the utility model provides a finished product floor-penetrating sleeve with a detachable hanging die, which comprises a hanging rod, a sleeve, a hanging die and a hanging wire; the hanging mould comprises a hanging mould flat plate main body and a hanging mould vertical part which are connected in a welding mode; the hanging die flat plate main body and the hanging die vertical part are welded to form an integral body with an inverted T-shaped structure; the sleeve can be embedded into a reserved hole of a floor slab, the outer wall of the sleeve is tightly attached to the inner wall of the reserved hole, the diameter of the hanging die flat plate main body is larger than that of the reserved hole, and the diameter of the vertical part of the hanging die is smaller than that of the sleeve; the bottom end of the suspension wire is fixedly connected with the top end of the vertical part of the suspension mould through welding, and the top end of the suspension wire is bolted with the suspension rod.
Preferably, four suspension wires are arranged and distributed in a diagonal manner; the two hanging rods are arranged and distributed in parallel. In order to facilitate the installation of the hanging mould to be firmer.
Preferably, the main body of the hanging mould flat plate of the hanging mould is of a disc-shaped structure, and the vertical part of the hanging mould is of a solid cylinder structure. In order to facilitate the hanging mould to match with the reserved hole of the floor slab.
Preferably, the diameter of the vertical part of the hanging die is less than 4cm of the diameter of the sleeve. The mould is hung in order to facilitate later stage dismantlement.
Preferably, the hanging rod is of a rectangular structure and is linear, two ends of the hanging rod are respectively provided with a bending part which is bent downwards, and the bending part is of an S-shaped structure. In order to facilitate the later taking down of the suspension wire, the suspension wire is more firm when being connected with the suspension rod and the suspension mould.
The utility model has the advantages that: the finished product of the suspended mould of the utility model is easy to construct and low in cost, and the suspended mould and the hanging rod are connected by the suspending wire, so that the position of the sleeve can be finely adjusted conveniently in the period, and the reliable installation of the sleeve is ensured; after concrete is poured and solidified, the hoisting wires are taken down, the hoisting die can be detached conveniently, the casing hoisting die part can be used in a circulating mode in the casing with the same pipe diameter, the time and labor are saved in installation, and the quality of the hoisting die is good.
Drawings
FIG. 1 is a schematic cross-sectional view of the device for overhung high-altitude construction around a limb of the present invention;
FIG. 2 is a schematic structural view of the device for overhung high-altitude construction work outside the adjacent edge of the present invention;
description of reference numerals:
1. a hanging rod is hung; 2. a sleeve; 3. lifting the mold; 4. and (5) hoisting the wires.
Detailed Description
The invention will be further explained with reference to the drawings and the specific embodiments.
Referring to fig. 1-2, the utility model provides a self-contained detachable hanging die finished product floor-penetrating casing pipe, which comprises a hanging rod 1, a casing pipe 2, a hanging die 3 and a hanging wire 4; the hanging die 3 comprises a hanging die flat plate main body and a hanging die vertical part which are connected in a welding mode, and the hanging die flat plate main body is a steel plate with the thickness of 2 mm; the hanging die flat plate main body and the hanging die vertical part are welded to form an integral body with an inverted T-shaped structure; the sleeve 2 is designed according to the depth and the diameter of a reserved hole of a floor slab, the sleeve 2 can be embedded into the reserved hole of the floor slab, the outer wall of the sleeve 2 is tightly attached to the inner wall of the reserved hole, the diameter of the hanging die flat plate main body is larger than that of the reserved hole, the diameter of the vertical part of the hanging die is smaller than that of the sleeve 2, the vertical part of the hanging die can be ensured to penetrate into the sleeve 2, the hanging die 3 is lifted through the hanging wires 4 in the later period, and the sleeve 2 is supported through the hanging die flat plate main body; the bottom of hang wire 4 links to each other through welded fastening with the vertical portion top of hanging mould, the top with play peg 1 bolt, each one person cooperation installation of lower floor in the time of the construction needs, the personnel of lower floor install, upper personnel are responsible for fixing finished product sleeve pipe 2 on the floor through play peg 1, sleeve pipe 2 is when vertical running through reservation entrance to a cave, can finely tune, treat that the sleeve pipe 2 installation finishes the back and reserve entrance to a cave and sleeve pipe 2 center alignment after fixed, hang wire 4 top is tied on play peg 1, fixed back concreting after finishing, loose behind the concrete setting hang wire 1 and hang wire 4 after demolish hang mould 3 can.
Further, as shown in fig. 2, four suspension wires 4 are provided, and the four suspension wires 4 are distributed diagonally; the two hanging rods 1 are arranged and distributed in parallel, the hanging die 3 is hung by the hanging wires 4, the stability of the hanging die 3 can be guaranteed, and the sleeve 2 is stably supported so as to be convenient for later-stage concrete pouring.
Further, as shown in fig. 2, the hanging die flat main body of the hanging die 3 is of a disc-shaped structure, the vertical portion of the hanging die is of a solid cylinder structure, the hanging die flat main body is of a steel plate, the vertical portion of the hanging die is fixed at the center of the vertical portion of the hanging die in a welding manner, when the hanging die is installed, the vertical portion of the hanging die penetrates into the sleeve 2, the hanging die flat main body supports the sleeve 2, and the hanging die flat main body is tightly attached to the bottom surface of the floor slab.
Further, according to the illustration in fig. 1, the diameter of the vertical part of the hanging die is smaller than 4cm of the diameter of the casing 2, that is, after the hanging die 3 is installed, 2cm gaps are respectively formed between the two sides of the vertical part of the hanging die and the inner wall of the casing 2, so that the hanging die 3 can be removed through the gaps.
Further, as shown in fig. 1 and fig. 2, the hanging rod 1 is of a rectangular structure and is linear, two ends of the hanging rod 1 are respectively provided with a bending part which is bent downwards, the bending part is of an S-shaped structure, and the bending part which is bent downwards ensures that a certain gap exists between the hanging rod 1 and the floor surface after installation and use, so that the top end of the suspension wire 4 is conveniently fastened on the hanging rod 1, and the hanging rod 1 and the suspension wire 4 are conveniently taken down at a later stage, so that the suspension die 3 is convenient to disassemble; the S-shaped structure of the bending part has an elastic effect, and after the suspension wire 4 is fastened, the firmness of the installation of the suspension mould 3 and the sleeve 2 can be ensured, thereby being beneficial to pouring concrete to complete the installation of the sleeve 2.
The utility model discloses a theory of operation is: as mentioned above, during construction, one person is required to install the upper layer and the lower layer of the floor slab in a matching way, the person in the lower layer is responsible for welding and fixing the bottom end of the suspension wire 4 and the vertical part of the suspension mould 3, penetrating the sleeve 2 through the reserved hole of the floor slab from bottom to top and embedding the vertical part of the suspension mould 3 into the sleeve 2, the person in the upper layer is responsible for fixing the finished sleeve 2 on the floor slab through the suspension rod 1, in addition, when the person in the lower layer penetrates the sleeve 2 through the reserved hole of the floor slab, the positions of the sleeve 2 and the reserved hole are aligned, then upper-layer personnel fasten the top end of the suspension wire 4 on the suspension rod 1 to ensure the reliable matching among the suspension rod 1, the floor slab, the sleeve 2 and the suspension mould flat plate main body, as shown in the attached figure 1, a lifting hanging rod 1 and a lifting mould flat plate main body form clamping fit to clamp a floor slab, and a casing 2 at the inner side is stabilized by using a lifting wire 4 and the lifting mould flat plate main body;
after the fixation is finished, concrete grouting is directly performed, after the concrete is solidified, the top end of the suspension wire 4 is separated from the suspension rod 1, a screwdriver can be selected to extend into a gap between the two sides of the vertical part of the suspension mold and the inner wall of the sleeve 2 to abut against the flat plate main body of the suspension mold, and the suspension mold 3 can be detached by tapping the top end of the screwdriver.
The present invention has been described in detail with reference to the embodiments shown in the drawings, and those skilled in the art can make various modifications to the present invention based on the above description. Therefore, certain details of the embodiments should not be construed as limitations of the invention, which are intended to be covered by the following claims.

Claims (5)

1. A finished product floor-penetrating sleeve with a detachable hanging die is characterized by comprising a hanging rod, a sleeve, a hanging die and a hanging wire; the hanging mould comprises a hanging mould flat plate main body and a hanging mould vertical part which are connected in a welding mode; the hanging die flat plate main body and the hanging die vertical part are welded to form an integral body with an inverted T-shaped structure; the sleeve can be embedded into a reserved hole of a floor slab, the outer wall of the sleeve is tightly attached to the inner wall of the reserved hole, the diameter of the hanging die flat plate main body is larger than that of the reserved hole, and the diameter of the vertical part of the hanging die is smaller than that of the sleeve; the bottom end of the suspension wire is fixedly connected with the top end of the vertical part of the suspension mould through welding, and the top end of the suspension wire is bolted with the suspension rod.
2. The finished through-floor sleeve with the detachable hoisting die as claimed in claim 1, wherein four hoisting wires are provided, and the four hoisting wires are distributed diagonally; the two hanging rods are arranged and distributed in parallel.
3. The removable drop die finished through-floor sleeve of claim 1, wherein the drop die platform body of the drop die is a disc-shaped structure and the drop die vertical portion is a solid cylindrical structure.
4. The removable drop die finished through-floor sleeve of claim 1, wherein the drop die vertical portion diameter is less than 4cm of the sleeve diameter.
5. The removable finished product floor slab penetrating sleeve with hanging die as claimed in claim 1, wherein the hanging rod is rectangular and linear, and the hanging rod has two ends with downward bent parts, and the bent parts are S-shaped.
CN201921491524.XU 2019-09-09 2019-09-09 From area detachable hangs mould finished product and wears floor sleeve pipe Active CN211173100U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921491524.XU CN211173100U (en) 2019-09-09 2019-09-09 From area detachable hangs mould finished product and wears floor sleeve pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921491524.XU CN211173100U (en) 2019-09-09 2019-09-09 From area detachable hangs mould finished product and wears floor sleeve pipe

Publications (1)

Publication Number Publication Date
CN211173100U true CN211173100U (en) 2020-08-04

Family

ID=71805842

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921491524.XU Active CN211173100U (en) 2019-09-09 2019-09-09 From area detachable hangs mould finished product and wears floor sleeve pipe

Country Status (1)

Country Link
CN (1) CN211173100U (en)

Similar Documents

Publication Publication Date Title
CN104947719B (en) The rear pouring tape construction method of formwork erecting structure is hung in basement roof post-cast strip
CN105133755B (en) A kind of construction method and shear wall structure of reinforcement welding rack composite shear wall
CN107605177A (en) The construction method of efficient precast floor slab and its independent support frame
CN204609154U (en) The hollow stair system of a kind of prefabricated assembling type reinforced concrete
CN104947846B (en) A kind of prefabricated integral frame light filling lining and preparation method thereof
CN108222066A (en) A kind of combined steel formwork support system and its construction method
CN105672664A (en) Integral heat insulation wallboard building system
CN102733608B (en) Construction method for spray head layer of granulation tower
CN205976167U (en) Based on cast -in -place floor structures of detachable positioning control spare
CN206769199U (en) After wear formula post stretching vertical prestressing cast-in-place concrete rod structure
CN109732773B (en) Mounting node and mounting method of support hinged concrete prefabricated part
CN206769200U (en) First wear formula post stretching vertical prestressing cast-in-place concrete rod structure
CN211173100U (en) From area detachable hangs mould finished product and wears floor sleeve pipe
CN213173317U (en) Be used for T roof beam wet seam construction equipment of encorbelmenting
CN204690801U (en) Formwork erecting structure is hung in basement roof ater-casting
CN205804745U (en) A kind of precast concrete shear wall component
CN107100322A (en) Post stretching vertical prestressing cast-in-place concrete rod structure and construction method
CN208363461U (en) A kind of segmented steel reinforced concrete assembling stair
CN208363460U (en) The steel reinforced concrete assembling stair of section are poured after a kind of setting
CN106284978A (en) A kind of movement joint both sides shear wall synchronous construction technique and canalization template
CN207582763U (en) Two-way close spelling laminated floor slab connecting joint structure with groove type embedded part
CN216819253U (en) Be used for disposable pre-buried crane span structure transition festival piece
CN106013568B (en) Based on detachable positioning controller cast-in-situ floorslab structure and construction method
CN214614095U (en) Suspension type concrete strutting arrangement
CN205677156U (en) Hang mould special utility supporting steel bar

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant