CN211169242U - Cable pay-off is used in electric power construction - Google Patents

Cable pay-off is used in electric power construction Download PDF

Info

Publication number
CN211169242U
CN211169242U CN201922335789.7U CN201922335789U CN211169242U CN 211169242 U CN211169242 U CN 211169242U CN 201922335789 U CN201922335789 U CN 201922335789U CN 211169242 U CN211169242 U CN 211169242U
Authority
CN
China
Prior art keywords
fixed mounting
cable
base
power construction
cable drum
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922335789.7U
Other languages
Chinese (zh)
Inventor
武国文
梁静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201922335789.7U priority Critical patent/CN211169242U/en
Application granted granted Critical
Publication of CN211169242U publication Critical patent/CN211169242U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a cable pay-off for electric power construction belongs to electric power engineering technical field. The utility model provides a cable pay-off for electric power construction, includes the base, the bottom fixed mounting of base has the universal wheel, one side of base up end is provided with the depressed part, positioning groove has been seted up to the up end of base. According to the cable pay-off device for power construction, the cable drum can be effectively positioned through the arranged positioning groove, so that the cable drum is prevented from moving, and dangerous conditions are reduced; can carry out effectual chucking through fixed disk and activity dish and fix cable drum, and can fix the cable drum of different length and diameter size, when the installation, need not the manual work and mention cable drum, can make fixed disk and activity dish descend through left telescopic link and right telescopic link, make the circular in same straight line of centre of a circle and cable drum that fixed disk and activity dish descend for cable drum's installation is lighter, and the practicality is high.

Description

Cable pay-off is used in electric power construction
Technical Field
The utility model relates to an electric power engineering technical field specifically is a cable pay-off for electric power construction.
Background
Electric power engineering, i.e. engineering related to the production, transmission and distribution of electric energy, also includes engineering of applying electricity as power and energy in various fields in a broad sense, the development of national economy is seriously hindered by insufficient electricity, and the experience of countries in the world shows that the development speed of electricity production is higher than that of other departments so as to promote the coordinated development of national economy, so the electric power industry is also called "forerunner" of national economy.
Traditional cable pay-off is at the in-process fixed to cable drum, and cable drum can not by effectual location, leads to cable drum to have the possibility of removing, has certain danger, and present cable drum is very hard in the installation, and the degree of difficulty is great, has reduced cable pay-off's practicality.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a cable pay-off for electric power construction to propose traditional cable pay-off in solving above-mentioned background art at the in-process fixed to the cable drum, the cable drum can not be by effectual location, leads to the cable drum to have the possibility of removing, has certain danger, and present cable drum is very hard in the installation, and the degree of difficulty is great, has reduced the problem of cable pay-off's practicality.
In order to achieve the above object, the utility model provides a following technical scheme:
the utility model provides a cable pay-off for electric power construction, includes the base, the bottom fixed mounting of base has the universal wheel, one side of base up end is provided with the depressed part, positioning groove has been seted up to the up end of base, positioning groove is undercut's arc structure, left telescopic link and right telescopic link are installed to the left and right sides symmetry of base up end, the upper end fixed mounting of left side telescopic link has the left branch fagging, the upper end fixed mounting of right telescopic link has the right branch fagging.
Preferably, the outside fixed mounting of left branch fagging has driving motor, the upper end of left branch fagging is installed a left side through the bearing and is linked the axle, the one end fixed mounting that links the axle on a left side has a left fixed plate, the other end that links the axle on a left side and driving motor's output shaft fixed connection, the outside of left fixed plate has the fixed disk through bolt fixed mounting, the outside fixed mounting of fixed disk has left card post.
Preferably, the upper end of right branch fagging is installed the right side through the bearing and is linked the axle, the right side links the inner fixed mounting right side fixed plate of axle, there is the activity dish in the outside of right side fixed plate through bolt fixed mounting, the outside fixed mounting of activity dish has right card post.
Preferably, the equal fixed mounting in the outside of left branch fagging and right branch fagging has the mounting panel, install the pivot through the bearing between the mounting panel, outside fixed mounting in the middle of the pivot has the leading wheel.
Preferably, the activity groove has been seted up to the avris of base, the inside fixed mounting in both sides has the fixture block about the activity groove, the inboard in activity groove is provided with the movable block, the draw-in groove has been seted up to the left and right sides of movable block, the fixture block is inboard at the draw-in groove, the up end fixed mounting of depressed part has the cylinder, the expansion end and the movable block fixed connection of cylinder, right side telescopic link fixed mounting is at the up end of movable block.
Compared with the prior art, the beneficial effects of the utility model are that:
1. this cable pay-off for power construction can carry out effectual location work to cable drum through the positioning groove who sets up, is at the in-process to cable drum installation, prevents that cable drum from removing, reduces the emergence of the dangerous condition.
2. This cable pay-off for electric power construction can carry out effectual chucking through fixed disk and activity dish to cable drum and fix, and can fix the cable drum of different length and diameter size, when the installation, need not the manual work and mention cable drum, can make fixed disk and activity dish descend through left telescopic link and right telescopic link, the centre of a circle that makes fixed disk and activity dish descend is in same straight line with cable drum's circular for cable drum's installation is lighter, and the practicality is high.
The part which is not involved in the device is the same as the prior art or can be realized by the prior art, the cable pay-off device for electric power construction can effectively position a cable drum through the arranged positioning groove, so that the cable drum is prevented from moving, and the occurrence of dangerous conditions is reduced; can carry out effectual chucking through fixed disk and activity dish and fix cable drum, and can fix the cable drum of different length and diameter size, during the installation, need not the manual work and mention cable drum, can make fixed disk and activity dish descend through left telescopic link and right telescopic link, make the centre of a circle that fixed disk and activity dish descend and cable drum's circular the collinear that is in for cable drum's installation is lighter.
Drawings
Fig. 1 is a schematic view of a three-dimensional structure of a cable releasing device for electric power construction provided by the present invention;
fig. 2 is a schematic side view of the cable releasing device for electric power construction according to the present invention;
fig. 3 is a schematic view of the installation structure of the left support plate and the right support plate of the cable pay-off device for electric power construction provided by the utility model;
fig. 4 is the utility model provides a cable pay-off device base structure sketch map for electric power construction.
In the figure: 1. a base; 2. a universal wheel; 3. a recessed portion; 4. a positioning groove; 5. a left telescoping rod; 6. a right telescopic rod; 7. a left support plate; 8. a right support plate; 9. a drive motor; 10. a left connecting shaft; 11. a left fixing plate; 12. fixing the disc; 13. a left clamp post; 14. a right connecting shaft; 15. a right fixing plate; 16. a movable tray; 17. a right clamping column; 18. mounting a plate; 19. a rotating shaft; 20. a guide wheel; 21. a movable groove; 22. a clamping block; 23. a movable block; 24. a card slot; 25. and a cylinder.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
In the description of the present invention, it is to be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: a cable pay-off device for electric power construction comprises a base 1, universal wheels 2, a concave part 3, a positioning groove 4, a left telescopic rod 5, a right telescopic rod 6, a left supporting plate 7, a right supporting plate 8, a driving motor 9, a left connecting shaft 10, a left fixing plate 11 and a fixing plate 12, left side card post 13, right side even axle 14, right side fixed plate 15, movable disc 16, right side card post 17, mounting panel 18, pivot 19, leading wheel 20, movable groove 21, fixture block 22, movable block 23, draw-in groove 24 and cylinder 25, base 1's bottom fixed mounting has universal wheel 2, one side of base 1 up end is provided with depressed part 3, positioning groove 4 has been seted up to base 1's up end, positioning groove 4 is the arc structure of undercut, left telescopic link 5 and right telescopic link 6 are installed to the left and right sides symmetry of base 1 up end, the upper end fixed mounting of left telescopic link 5 has left support plate 7, the upper end fixed mounting of right telescopic link 6 has right support plate 8.
The outside fixed mounting of left branch fagging 7 has driving motor 9, left axle 10 is even installed through the bearing in the upper end of left branch fagging 7, the one end fixed mounting of left axle 10 has left fixed plate 11 even, the other end of left axle 10 even and driving motor 9's output shaft fixed connection, there is fixed disk 12 in the outside of left fixed plate 11 through bolt fixed mounting, the outside fixed mounting of fixed disk 12 has left calorie of post 13, through the fixed orifices block with the cable spool both sides on left calorie of post 13 and right calorie of post 17, fix the cable spool, it is rotatory to drive left axle 10 even through driving motor 9 that sets up, it is rotatory to drive fixed disk 12, thereby carry out unwrapping wire work.
The upper end of the right supporting plate 8 is provided with a right connecting shaft 14 through a bearing, the inner end of the right connecting shaft 14 is fixedly provided with a right fixing plate 15, the outer side of the right fixing plate 15 is provided with a movable disc 16 through a bolt, the outer side of the movable disc 16 is fixedly provided with a right clamping column 17, and the fixed disc 12 rotates and simultaneously drives the movable disc 16 to move so as to reduce the occurrence of dangerous conditions.
The outer sides of the left support plate 7 and the right support plate 8 are fixedly provided with mounting plates 18, a rotating shaft 19 is mounted between the mounting plates 18 through a bearing, a guide wheel 20 is fixedly mounted on the outer side of the middle of the rotating shaft 19, and the cable is guided through the guide wheel 20.
The side of the base 1 is provided with a movable groove 21, the insides of the left side and the right side of the movable groove 21 are fixedly provided with a fixture block 22, the inner side of the movable groove 21 is provided with a movable block 23, the left side and the right side of the movable block 23 are provided with a clamping groove 24, the fixture block 22 is clamped at the inner side of the clamping groove 24, the upper end surface of the concave part 3 is fixedly provided with an air cylinder 25, the movable end of the air cylinder 25 is fixedly connected with the movable block 23, a right telescopic rod 6 is fixedly arranged at the upper end surface of the movable block 23, when the cable coil is installed, the cable coil is placed at a positioning groove 4 and is prevented from moving through the positioning groove 4, then, the left telescopic rod 5 and the right telescopic rod 6 are lowered to the lowest, the left telescopic rod 5 and the right telescopic rod 6 adopt electric telescopic rods, then the cable coil is moved, so that the left clamping column 13 is clamped at, the movable disc 16 is driven to move, so that the right clamping column 17 is clamped to the inner side of the fixing hole at the other side of the cable coil, and the cable coil is tightly clamped between the fixed disc 12 and the movable disc 16 to fix the cable coil.
The working principle is as follows: firstly, when the cable coil is installed, the cable coil is placed at a positioning groove 4, the cable coil is prevented from moving through the positioning groove 4, then, a left telescopic rod 5 and a right telescopic rod 6 are lowered to the lowest, the left telescopic rod 5 and the right telescopic rod 6 adopt electric telescopic rods, then the cable coil is moved, a left clamping column 13 is clamped to the inner side of a fixed hole at one side of the cable coil, then an air cylinder 25 is started, the air cylinder 25 drives a movable block 23 to move towards the left telescopic rod 5, a movable disc 16 is driven to move, a right clamping column 17 is clamped to the inner side of the fixed hole at the other side of the cable coil, the cable coil is tightly clamped between the fixed disc 12 and the movable disc 16, the cable coil is fixed, then the left telescopic rod 5 and the right telescopic rod 6 extend upwards, the cable coil is lifted, a cable on the cable coil is pulled out and passes through a guide wheel 20, then restart driving motor 9, driving motor 9 drives left connecting shaft 10 rotatory, it is rotatory to drive fixed disk 12, thereby carry out the unwrapping wire work, whole can carry out effectual location work to the cable drum, in-process to the cable drum installation, prevent the cable drum removal, reduce the emergence of dangerous condition, can carry out effectual fixed to the cable drum simultaneously, and can fix the cable drum of different length and diameter size, when the installation, need not the manual work and mention the cable drum, can make fixed disk 12 and activity dish 16 descend through left telescopic link 5 and right telescopic link 6, the centre of a circle that makes fixed disk 12 and activity dish 16 descend is in same straight line with the circular of cable drum, make the installation of cable drum lighter, and convenient to use.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (5)

1. The utility model provides a cable pay-off for power construction, includes base (1), its characterized in that: the bottom fixed mounting of base (1) has universal wheel (2), one side of base (1) up end is provided with depressed part (3), positioning groove (4) have been seted up to the up end of base (1), positioning groove (4) are undercut's arc structure, left telescopic link (5) and right telescopic link (6) are installed to the left and right sides symmetry of base (1) up end, the upper end fixed mounting of left side telescopic link (5) has left support plate (7), the upper end fixed mounting of right telescopic link (6) has right support plate (8).
2. The cable pay-off device for power construction as claimed in claim 1, wherein: the utility model discloses a bearing of left support plate, including left support plate (7), the outside fixed mounting of left support plate (7) has driving motor (9), the upper end of left support plate (7) is installed a left side through the bearing and is linked axle (10), the one end fixed mounting that links axle (10) on a left side has left fixed plate (11), the other end that links axle (10) on a left side and the output shaft fixed connection of driving motor (9), there is fixed disk (12) in the outside of left side fixed plate (11) through bolt fixed mounting, the outside fixed mounting of fixed disk (12) has left calorie of post (13).
3. The cable pay-off device for power construction as claimed in claim 1, wherein: the upper end of right branch fagging (8) is installed the right side through the bearing and is linked axle (14), the right side links inner fixed mounting right side fixed plate (15) of axle (14), there is movable dish (16) in the outside of right side fixed plate (15) through bolt fixed mounting, the outside fixed mounting of movable dish (16) has right card post (17).
4. The cable pay-off device for power construction as claimed in claim 1, wherein: the equal fixed mounting in the outside of left branch fagging (7) and right branch fagging (8) has mounting panel (18), install pivot (19) through the bearing between mounting panel (18), outside fixed mounting in the middle of pivot (19) has leading wheel (20).
5. The cable pay-off device for power construction as claimed in claim 1, wherein: activity groove (21) have been seted up to the avris of base (1), the inside fixed mounting in activity groove (21) left and right sides has fixture block (22), the inboard in activity groove (21) is provided with movable block (23), draw-in groove (24) have been seted up to the left and right sides of movable block (23), fixture block (22) block is inboard at draw-in groove (24), the up end fixed mounting of depressed part (3) has cylinder (25), the expansion end and the movable block (23) fixed connection of cylinder (25), right side telescopic link (6) fixed mounting is at the up end of movable block (23).
CN201922335789.7U 2019-12-24 2019-12-24 Cable pay-off is used in electric power construction Expired - Fee Related CN211169242U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922335789.7U CN211169242U (en) 2019-12-24 2019-12-24 Cable pay-off is used in electric power construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922335789.7U CN211169242U (en) 2019-12-24 2019-12-24 Cable pay-off is used in electric power construction

Publications (1)

Publication Number Publication Date
CN211169242U true CN211169242U (en) 2020-08-04

Family

ID=71821983

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922335789.7U Expired - Fee Related CN211169242U (en) 2019-12-24 2019-12-24 Cable pay-off is used in electric power construction

Country Status (1)

Country Link
CN (1) CN211169242U (en)

Similar Documents

Publication Publication Date Title
CN216883524U (en) Supplementary automobile wheel hub processing mounting fixture
CN211169242U (en) Cable pay-off is used in electric power construction
CN220260866U (en) A equipment frock for large-scale clamp of commercial car
CN214021502U (en) Paint spraying mechanism for metal iron tower support
CN211889897U (en) Engine cover plate machining clamp
CN204906130U (en) Motor punching device
CN115157176A (en) Auxiliary disassembling and assembling tool and method for base bearing of wind driven generator
CN210677223U (en) Production clamp for locking mandrel
CN211840765U (en) Automobile side wall welding clamp
CN202414973U (en) Lifting tool for dismounting and mounting machine tool spindle
CN219971410U (en) Cable laying turntable
CN220679860U (en) Steel structure welding jig
CN215934671U (en) Magnetic suspension motor assembly operation platform
CN217768653U (en) Battery package module scaffold weldment assembly anchor clamps
CN215204299U (en) Auxiliary tool for assembling automobile tire
CN220148993U (en) Lifting truck carrying environment modeling analysis system
CN213294480U (en) Hoisting mechanism for chuck production
CN220178119U (en) New energy automobile structure die casting die carrier
CN219860177U (en) Stator hoisting clamping tool
CN220178469U (en) Gantry welding with protective structure
CN220283139U (en) Winding device for elevator steel wire rope processing
CN214351133U (en) Battery package upset special fixture
CN219521825U (en) Clamp positioning structure
CN216141131U (en) Indoor wallboard installation hoisting accessory for service
CN218311747U (en) Steel fixing clamp for section steel forming machine

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200804

Termination date: 20201224