CN211136148U - Pipeline erection welding steel frame for building construction - Google Patents
Pipeline erection welding steel frame for building construction Download PDFInfo
- Publication number
- CN211136148U CN211136148U CN201922386724.5U CN201922386724U CN211136148U CN 211136148 U CN211136148 U CN 211136148U CN 201922386724 U CN201922386724 U CN 201922386724U CN 211136148 U CN211136148 U CN 211136148U
- Authority
- CN
- China
- Prior art keywords
- fixedly connected
- steel frame
- welding steel
- threaded rod
- lateral wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a pipeline erects welding steel frame for construction, including the underframe, two symmetries of lateral wall fixedly connected with set up the riser on the underframe, two fixedly connected with base between the riser, the inside cavity of having seted up of base, riser one side lateral wall fixedly connected with motor, and the output of motor run through to inside and fixedly connected with lifting unit of cavity, and the lifting unit upper end runs through to base outside and fixedly connected with backup pad, and the lateral wall fixedly connected with arc seat on the backup pad, and the lateral wall is equipped with the centre gripping subassembly on the arc seat. This pipeline erection welding steel frame for construction, through setting up lifting unit and motor, the starter motor drives the threaded rod and rotates, and the threaded rod drives thread piece horizontal migration, drives the thread piece like this and drives the dwang and rotate, then promotes the lifter plate and shifts up, drives the backup pad through the montant and shifts up, has realized the altitude mixture control of pipeline like this, convenient to use.
Description
Technical Field
The utility model relates to a pipeline erects technical field, specifically is a pipeline erects welding steel frame for construction.
Background
The building engineering is an engineering entity for planning, surveying, designing, constructing and completing various technical works such as building construction and accessory structure facilities for new construction, reconstruction or extension, and installation engineering of lines, pipelines and equipment matched with the engineering entity, the building pipelines are used as guide channels of various fluids, and are widely applied to daily production and life, and the sealing reliability of the pipelines is directly related to the safety of production and life.
Need erect it in the use of pipeline, erect and adopt the welding steel frame usually, but current welding steel frame is not convenient for height-adjusting in the in-process of using, and the fixed of pipeline is convenient inadequately.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides a pipeline erects welding steel frame for construction has solved the problem that proposes in the above-mentioned background art.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the utility model provides a pipeline erects welding steel frame for construction, includes the underframe, two symmetries of lateral wall fixedly connected with set up the riser on the underframe, two fixedly connected with base between the riser, the inside cavity of having seted up of base, riser one side lateral wall fixedly connected with motor, and the output of motor run through to inside and the fixedly connected with lifting unit of cavity, and the lifting unit upper end runs through to base outside and fixedly connected with backup pad, and lateral wall fixedly connected with arc seat on the backup pad, and the lateral wall is equipped with the centre gripping subassembly on the arc seat.
Optionally, the clamping assembly comprises a cylinder fixedly connected to the upper side wall of the arc-shaped seat, an output end of the cylinder is fixedly connected with a telescopic rod, and the other end of the telescopic rod is fixedly connected with a clamping plate.
Optionally, lifting unit includes fixed connection at the threaded rod of motor output, and the threaded rod other end rotates and inserts and establish at the cavity inner wall, the screw thread has cup jointed the thread piece on the threaded rod, and rotates on the threaded rod and be connected with the dwang, and the dwang upper end rotates and is connected with the lifter plate, and lifter plate sliding connection is at the cavity inner wall, the montant that two symmetries of side wall fixedly connected with set up on the lifter plate, and the montant upper end runs through to base outside and backup pad fixed connection.
Optionally, the bottom frame is provided with four corners of the lower side wall with rollers, and the rollers are fixedly connected with the bottom frame through bolts.
Optionally, a horizontally arranged limiting rod is fixedly connected between the inner walls of the cavities, and the limiting rod penetrates through the thread block.
Optionally, a semicircular groove is formed in the side wall of the arc-shaped seat, the clamping plate is arc-shaped, and the semicircular groove is matched with the clamping plate.
(III) advantageous effects
The utility model provides a pipeline erects welding steel frame for construction possesses following beneficial effect:
1. this pipeline erection welding steel frame for construction, through setting up lifting unit and motor, the starter motor drives the threaded rod and rotates, and the threaded rod drives thread piece horizontal migration, drives the thread piece like this and drives the dwang and rotate, then promotes the lifter plate and shifts up, drives the backup pad through the montant and shifts up, has realized the altitude mixture control of pipeline like this, convenient to use.
2. This pipeline erection welding steel frame for construction through setting up the centre gripping subassembly, starts the cylinder, drives the telescopic link extension, makes the grip block fix the pipeline like this, has realized the centre gripping work of pipeline like this, and the work is erect to the safety of being convenient for.
Drawings
FIG. 1 is a left side three-dimensional structure view of a pipeline erection welding steel frame for building construction according to the present invention;
FIG. 2 is a right side three-dimensional structure view of a pipeline erection welding steel frame for building construction provided by the utility model;
FIG. 3 is a front structural view of a welded steel frame for erecting pipelines for building construction according to the present invention;
fig. 4 is a structural view of fig. 1 at a.
In the figure: 1. a bottom frame; 2. a vertical plate; 3. a base; 4. an arc-shaped seat; 5. a support plate; 6. a roller; 7. an electric motor; 8. a lifting assembly; 81. a thread block; 82. a threaded rod; 83. rotating the rod; 84. a lifting plate; 85. a vertical rod; 9. a clamping assembly; 91. a cylinder; 92. a telescopic rod; 93. and (4) clamping the plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1 to 4, the present invention provides a technical solution: a pipeline erection welding steel frame for building construction comprises a bottom frame 1, wherein the side wall of the bottom frame 1 is fixedly connected with two symmetrically arranged vertical plates 2, a base 3 is fixedly connected between the two vertical plates 2, a cavity is formed in the base 3, the side wall of one side of each vertical plate 2 is fixedly connected with a motor 7, the output end of the motor 7 penetrates into the cavity and is fixedly connected with a lifting assembly 8, the lifting assembly 8 comprises a threaded rod 82 fixedly connected with the output end of the motor 7, the other end of the threaded rod 82 is rotatably inserted into the inner wall of the cavity, a threaded block 81 is sleeved on the threaded rod 82 in a threaded manner, a rotating rod 83 is rotatably connected onto the threaded rod 82, the upper end of the rotating rod 83 is rotatably connected with a lifting plate 84, the lifting plate 84 is slidably connected onto the inner wall of the cavity, two symmetrically arranged vertical rods 85 are fixedly connected onto the upper side wall of, underframe 1 downside wall four corners department all installs gyro wheel 6, and adopt bolt fixed connection between gyro wheel 6 and the underframe 1, it is convenient for remove to set up gyro wheel 6, fixed connection has the gag lever post that the level set up between the cavity inner wall, and the gag lever post runs through screw thread piece 81 and sets up, starter motor 7, motor 7 drives threaded rod 82 and rotates, and threaded rod 82 drives screw thread piece 81 horizontal migration, it drives dwang 83 to drive screw thread piece 81 like this and rotates, then promote lifting plate 84 and shift up, it shifts up to drive backup pad 5 through montant 85, the altitude mixture control of pipeline has been realized like this, and is convenient to use.
And 8 upper ends of lifting unit run through to 3 outsides of base and fixedly connected with backup pad 5, and lateral wall fixedly connected with arc seat 4 on backup pad 5, the semicircular groove has been seted up to the lateral wall on arc seat 4, the shape of grip block 93 is the arc form, and semicircular groove and grip block 93 match each other, and lateral wall is equipped with centre gripping subassembly 9 on arc seat 4, centre gripping subassembly 9 includes the cylinder 91 of fixed connection lateral wall on arc seat 4, and the output fixedly connected with telescopic link 92 of cylinder 91, and telescopic link 92 other end fixedly connected with grip block 93, start cylinder 91, drive the extension of telescopic link 92, make grip block 93 fix the pipeline like this, the centre gripping work of pipeline has been realized like this, the safe work of setting up of being convenient for.
The electrical components presented in the document are all electrically connected with an external master controller and 220V mains, and the master controller can be a conventional known device controlled by a computer or the like.
To sum up, this pipeline erection welding steel frame for construction, place the pipeline in the semicircular groove inside of arc seat 4, then start cylinder 91, drive the extension of telescopic link 92, make grip block 93 fix the pipeline like this, the centre gripping work of pipeline has been realized like this, the work of erectting of being convenient for safely, starter motor 7, motor 7 drives threaded rod 82 and rotates, and threaded rod 82 drives threaded block 81 horizontal migration, it drives dwang 83 and rotates like this to drive threaded block 81, then promote lifting plate 84 and shift up, it moves up to drive backup pad 5 through montant 85, the altitude mixture control of pipeline has been realized like this, and convenient use.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.
Claims (6)
1. The utility model provides a pipeline erection welding steel frame for construction, includes underframe (1), its characterized in that: underframe (1) two symmetries of lateral wall fixedly connected with set up riser (2), two fixedly connected with base (3) between riser (2), the cavity has been seted up to base (3) inside, riser (2) one side lateral wall fixedly connected with motor (7), and the output of motor (7) runs through to inside and fixedly connected with lifting unit (8) of cavity, and lifting unit (8) upper end runs through to base (3) outside and fixedly connected with backup pad (5), and backup pad (5) side wall fixedly connected with arc seat (4), and the lateral wall is equipped with centre gripping subassembly (9) on arc seat (4).
2. The pipe erection welding steel frame for building construction according to claim 1, characterized in that: the clamping assembly (9) comprises a cylinder (91) fixedly connected to the upper side wall of the arc-shaped seat (4), an output end of the cylinder (91) is fixedly connected with an expansion rod (92), and the other end of the expansion rod (92) is fixedly connected with a clamping plate (93).
3. The pipe erection welding steel frame for building construction according to claim 1, characterized in that: lifting unit (8) include threaded rod (82) of fixed connection at motor (7) output, and threaded rod (82) other end rotates and inserts and establish the cavity inner wall, threaded rod (82) are gone up the screw thread and have been cup jointed screw thread piece (81), and rotate on threaded rod (82) and be connected with dwang (83), and dwang (83) upper end rotation is connected with lifter plate (84), and lifter plate (84) sliding connection is at the cavity inner wall, montant (85) that two symmetries of side wall fixedly connected with set up on lifter plate (84), and montant (85) upper end runs through to base (3) outside and backup pad (5) fixed connection.
4. The pipe erection welding steel frame for building construction according to claim 1, characterized in that: bottom frame (1) side wall four corners department all installs gyro wheel (6), and adopts bolt fixed connection between gyro wheel (6) and bottom frame (1).
5. The pipe erection welding steel frame for building construction according to claim 1, characterized in that: and a horizontally arranged limiting rod is fixedly connected between the inner walls of the cavities and penetrates through the thread block (81).
6. The pipe erection welding steel frame for building construction according to claim 2, characterized in that: the side wall has seted up the semicircle groove on arc seat (4), the shape of grip block (93) is the arc form, and semicircle groove and grip block (93) match each other.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201922386724.5U CN211136148U (en) | 2019-12-26 | 2019-12-26 | Pipeline erection welding steel frame for building construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201922386724.5U CN211136148U (en) | 2019-12-26 | 2019-12-26 | Pipeline erection welding steel frame for building construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211136148U true CN211136148U (en) | 2020-07-31 |
Family
ID=71745042
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201922386724.5U Expired - Fee Related CN211136148U (en) | 2019-12-26 | 2019-12-26 | Pipeline erection welding steel frame for building construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211136148U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112356447A (en) * | 2020-10-20 | 2021-02-12 | 安徽瑞丰管业有限公司 | PVC pipeline welding device and using method thereof |
-
2019
- 2019-12-26 CN CN201922386724.5U patent/CN211136148U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112356447A (en) * | 2020-10-20 | 2021-02-12 | 安徽瑞丰管业有限公司 | PVC pipeline welding device and using method thereof |
CN112356447B (en) * | 2020-10-20 | 2022-07-19 | 安徽瑞丰管业有限公司 | PVC pipeline welding device and using method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210050396U (en) | PCCP pipeline fixing device for hydraulic engineering construction | |
CN211136148U (en) | Pipeline erection welding steel frame for building construction | |
CN209742378U (en) | Multipurpose clamping and fixing device for building construction | |
CN211010166U (en) | Pipeline installation locating support for water conservancy and hydropower | |
CN214834923U (en) | Wall body erection equipment for assembly type structure | |
CN211473446U (en) | Steel construction assembled wallboard node | |
CN210032652U (en) | Concrete pouring operation rack for building floor slab | |
CN218149760U (en) | Building engineering frame post template is consolidated and sealing device | |
CN214697877U (en) | Geotechnical engineering construction supporting device | |
CN214305596U (en) | Detachable support for construction | |
CN211741326U (en) | Speed measuring device for direct current motor | |
CN209907953U (en) | House concrete placement platform convenient to control | |
CN210342734U (en) | Support column for prefabricated building | |
CN211078401U (en) | Lifting device for construction | |
CN111017829A (en) | Operating platform for installing support frame of external climbing tower crane | |
CN218083511U (en) | Cutting device for construction site water and electricity construction | |
CN220565705U (en) | Support knot of post-cast strip template | |
CN214326912U (en) | Auxiliary hoisting device for steel structure construction | |
CN216081434U (en) | Concrete inclinometer for constructional engineering | |
CN213616574U (en) | Fire engineering water system installation auxiliary device | |
CN112744727B (en) | Detachable tower crane steel structure platform | |
CN216690294U (en) | Multifunctional lifting platform for house building construction | |
CN216446466U (en) | Lifting type construction platform for house building engineering | |
CN215443241U (en) | Building reinforcing apparatus suitable for wall body is restoreed | |
CN211393720U (en) | Jacking device based on architectural decoration engineering design |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200731 Termination date: 20201226 |