CN211113013U - Cement temporary storage tank for highway construction site - Google Patents

Cement temporary storage tank for highway construction site Download PDF

Info

Publication number
CN211113013U
CN211113013U CN201921961132.5U CN201921961132U CN211113013U CN 211113013 U CN211113013 U CN 211113013U CN 201921961132 U CN201921961132 U CN 201921961132U CN 211113013 U CN211113013 U CN 211113013U
Authority
CN
China
Prior art keywords
wall
tank
raceway
water
construction site
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921961132.5U
Other languages
Chinese (zh)
Inventor
张秀平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201921961132.5U priority Critical patent/CN211113013U/en
Application granted granted Critical
Publication of CN211113013U publication Critical patent/CN211113013U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a cement jar of keeping in for highway construction site, including automobile body and base, the top of automobile body is connected with the landing leg, the top welding of base has the support, the top both sides welding of support has a jar body, the inner chamber of the jar body is equipped with the water tank, the water tank is equipped with the delivery port, the delivery port intercommunication has first raceway, one side of first raceway communicates in the end of intaking of suction pump, the play water end intercommunication of suction pump has the second raceway, the outer wall of second raceway has cup jointed three-way head, the second raceway communicates in the second sprinkler head, three-way head intercommunication has the third raceway, the third raceway communicates in first sprinkler head. The utility model discloses the setting of water tank, suction pump and sprinkler head has washd the remaining material of jar internal chamber, has reduced the erosion of remaining material to the jar body, and with the collocation of automobile body and the use of the wheel of the jar body, has improved the maneuverability that uses at the highway job site.

Description

Cement temporary storage tank for highway construction site
Technical Field
The utility model relates to a cement jar technical field specifically is a cement jar of keeping in for highway construction scene.
Background
The cement tank is also called as a cement bin or a mud conveying bin, is generally used in bulk cement storage of a concrete mixing plant, is suitable for storing various bulk building materials such as cement, fly ash and the like, a material level system is arranged on the bin body, the position and the quantity of the materials can be displayed, and the hole breaking device can relieve firmness caused by long-term material deposition. The mud conveying bin and the spiral conveying pump are matched for use, so that materials can be conveyed to various positions, and the bin body is convenient to install, safe and reliable and is an ideal bulk storage tank for various mixing stations.
The existing cement tank is too large in size and cannot be moved, so that the cement tank is not convenient to use on a highway construction site, after the cement tank is used for a long time, the accumulated dust in the cement tank erodes the interior of the cement tank, and the service life of the cement tank is shortened.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a cement jar of keeping in for highway construction scene to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a cement temporary storage tank for highway construction site, includes automobile body and base, the top of automobile body is connected with the landing leg, the top of landing leg welds with the bottom of base, the top welding of base has the support, the welding of the top left and right sides of support has a jar body, the bottom left side of the inner chamber of the jar body is equipped with the water tank, the outer wall top left side of water tank is equipped with the water filling port, the bottom right side screwed connection of the inner chamber of the jar body has the suction pump, the power input end of suction pump is equipped with power plug, power plug's output and the input electric connection of suction pump, the top both sides screwed connection of the inner chamber of the jar body has first sprinkler head and second sprinkler head, the bottom on the outer wall right side of water tank is equipped with the delivery port, the delivery port intercommunication has first raceway, one side of first raceway communicates, the water outlet end of the water suction pump is communicated with a second water delivery pipe, a tee joint is sleeved on the outer wall of the second water delivery pipe, one side of the second water delivery pipe is communicated with the second spraying head, the tee joint is communicated with a third water delivery pipe, and one side of the third water delivery pipe is communicated with the first spraying head.
As further preferable in the present technical solution: the right side welding of the outer wall of the jar body has the ladder, the top left side of the jar body is equipped with first feed inlet, the top of the jar body is equipped with first dust shaker in one side that is close to first feed inlet, the top of the jar body is located the right side of first dust shaker and is equipped with the relief valve, the air inlet of relief valve is linked together with the top of the jar body, the top of the jar body is located the right side of relief valve and is equipped with the second dust shaker, the right side welding of second dust shaker has the second feed inlet.
As further preferable in the present technical solution: the utility model discloses a high-pressure gas stove, including jar body, outer wall bottom of jar body is connected with the hopper, the bottom of hopper is connected with the discharge gate, the outer wall right side top welding of first feed inlet has first broken ware that encircles, the air jet of first broken ware is linked together with first feed inlet, the outer wall left side top welding of second feed inlet has the broken ware that encircles of second, the air jet of the broken ware that encircles of second is linked together with the second feed inlet, the left side welding at hopper outer wall top has the broken ware that encircles of third, the air jet of the broken ware that encircles of third is linked together with the hopper, the right side welding at hopper outer wall top has the broken ware that encircles of fourth, the air jet of the broken ware that encircles of fourth is linked.
As further preferable in the present technical solution: the left side of water filling port runs through in the outer wall of the jar body, the outer wall bottom left side of water tank is equipped with the outlet, the left side in the outlet runs through in the outer wall of the jar body.
As further preferable in the present technical solution: the surface of the water pump is sleeved with a water pump cover, the bottom of the water pump cover is riveted with the bottom of the inner cavity of the tank body, and the power plug penetrates through the outer wall of the tank body.
As further preferable in the present technical solution: a first hook ring and a second hook ring are welded on two sides of the top of the tank body.
As further preferable in the present technical solution: the left side of the front side of the tank body is provided with a level gauge.
As further preferable in the present technical solution: the right side of the front side of the tank body is provided with a material visible window.
As further preferable in the present technical solution: the bottom of the base is provided with wheels.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses a combination of the jar body and automobile body, make its convenience more and swift, hook and loop cooperation loop wheel machine uses unloads, wheel through the base, jar body freely removes, the spirit level of the jar body, can adjust the equilibrium of the jar body, prevent that the automobile body from turning on one's side, the material visual window of jar body front side another department, be convenient for master the condition of material, the dust shaker of jar body top setting in time adsorbs the suspended particles in the jar body, reduce the pollution to the surrounding environment, the relief valve at jar body top, carry out the pressure release when exceeding the standard to the internal pressure of jar, its security performance has been increased, the water tank of jar body inner chamber installation, suction pump and sprinkler head, wash jar body inner chamber, the erosion of remaining cement to the jar body has been reduced, the life of the jar body has been increased.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural view of the temporary cement storage tank of the present invention in cooperation with a truck body;
fig. 3 is a schematic structural view of a first dust remover according to the present invention.
In the figure: 1. a vehicle body; 2. a base; 3. a support; 4. a tank body; 5. a wheel; 6. a support leg; 7. a first shackle; 8. a first feed port; 9. a first dust remover; 10. a safety valve; 11. a second feed port; 12. a second hook ring; 13. a level gauge; 14. a material visible window; 15. a third arch breaker; 16. a fourth arch breaker; 17. a first arch breaker; 18. a second arch breaker; 19. a ladder; 20. a hopper; 21. a discharge port; 22. a second dust remover; 31. a water tank; 32. a water pump; 33. a water injection port; 34. a water outlet; 35. a water outlet; 37. a power plug; 38. a first water delivery pipe; 39. a second water delivery pipe; 40. a third water delivery pipe; 41. a tee joint; 42. a first sprinkler head; 43. a second spray head; 44. and (4) a water pump cover.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Examples
Referring to fig. 1-3, the present invention provides a technical solution: a cement temporary storage tank for a highway construction site comprises a vehicle body 1 and a base 2, wherein the top of the vehicle body 1 is connected with supporting legs 6, the tops of the supporting legs 6 are welded with the bottom of the base 2, a support 3 is welded on the top of the base 2, tank bodies 4 are welded on the left side and the right side of the top of the support 3, a water tank 31 is arranged on the left side of the bottom of an inner cavity of each tank body 4, a water filling port 33 is arranged on the left side of the top of the outer wall of each water tank 31, a water suction pump 32 is connected to the right side of the bottom of the inner cavity of each tank body 4 through screws, a power supply input end of each water suction pump 32 is provided with a power supply plug 37, the output end of each power supply plug 37 is electrically connected with the input end of the water suction pump 32, a first sprinkler head 42 and a second sprinkler head 43 are connected to the two sides of the top, the water outlet end of the water pump 32 is communicated with a second water pipe 39, the outer wall of the second water pipe 39 is sleeved with a three-way head 41, one side of the second water pipe 39 is communicated with a second sprinkler 43, the three-way head 41 is communicated with a third water pipe 40, and one side of the third water pipe 40 is communicated with a first sprinkler 42.
In this embodiment, specifically: ladder 19 has been welded on the right side of the outer wall of the jar body 4, the top left side of the jar body 4 is equipped with first feed inlet 8, the top of the jar body 4 is equipped with first dust shaker 9 in the one side that is close to first feed inlet 8, the right side that the top of the jar body 4 is located first dust shaker 9 is equipped with relief valve 10, the air inlet of relief valve 10 is linked together with the top of the jar body 4, the right side that the top of the jar body 4 is located relief valve 10 is equipped with second dust shaker 22, the right side welding of second dust shaker 22 has second feed inlet 11, ladder 19 is convenient for personnel's reinforced or maintenance machine, relief valve 10 is.
In this embodiment, specifically: the bottom of the outer wall of the tank body 4 is connected with a hopper 20, the bottom of the hopper 20 is connected with a discharge hole 21, a first arch breaking device 17 is welded at the top of the right side of the outer wall of the first feed port 8, an air jet of the first arch breaking device 17 is communicated with the first feed port 8, a second arch breaking device 18 is welded at the top of the left side of the outer wall of the second feed port 11, an air jet of the second arch breaking device 18 is communicated with the second feed port 11, a third arch breaking device 15 is welded at the left side of the top of the outer wall of the hopper 20, an air jet of the third arch breaking device 15 is communicated with the hopper 20, a fourth arch breaking device 16 is welded at the right side of the top of the outer wall of the hopper 20, an air jet of the fourth arch breaking device 16 is communicated with the hopper 20, the first arch breaking device 17, the second arch breaking device 18, the third arch breaking device 15 and the fourth arch.
In this embodiment, specifically: the left side of the water filling port 33 penetrates through the outer wall of the tank body 4, the left side of the bottom of the outer wall of the water tank 31 is provided with a water outlet 34, the left side of the water outlet 34 penetrates through the outer wall of the tank body 4, and the water filling port 33 and the water outlet 34 facilitate water filling and water draining of the water tank 31.
In this embodiment, specifically: the surface of the water pump 32 is sleeved with a water pump cover 44, the bottom of the water pump cover 44 is riveted with the bottom of the inner cavity of the tank body 4, the power plug 37 penetrates through the outer wall of the tank body 4, the power plug 37 is connected with an external power supply and used for electrifying the water pump 32 to work, and the water pump cover 44 is used for protecting the water pump 32 from being corroded by cement.
In this embodiment, specifically: the first shackle 7 and the second shackle 12 are welded to the two sides of the top of the tank body 4, and the shackles are convenient for the crane to suspend and move.
In this embodiment, specifically: the level meter 13 is arranged on the left side of the front side of the tank body 4, and the level meter 13 is beneficial to measuring the balance degree of the tank body 4, so that the vehicle body 1 is not easy to turn over due to the unbalance of the tank body 4.
In this embodiment, specifically: the right side of the front side of the tank body 4 is provided with a material visible window 14, and the material visible window 14 enables an operator to master the internal material condition.
In this embodiment, specifically: the landing leg 6 of the bottom left and right sides of base 2 is adjustable, and the bottom of base 2 is equipped with wheel 5, through the height of adjusting landing leg 6, makes wheel 5 drive the removal of jar body 4.
The working principle or the structural principle is that when in use, cement is poured in from the first feed port 8 and the second feed port 11 respectively, the first arch breaking device 17 at the first feed port 8 and the second arch breaking device 18 at the second feed port 11 are opened to blow and break, the first dust remover 9 and the second dust remover 22 are opened to adsorb suspended particles in the tank body and reduce the pollution to the environment, the balance of the tank body 4 is adjusted through the level meter 13 to avoid the side turning of the vehicle body, the material visual window 14 is convenient for grasping the condition of cement materials, the safety valve 10 at the top of the tank body 4 is used for relieving the pressure in the tank body 4 when the pressure in the tank body 4 exceeds the standard, the first shackle 7 and the second shackle 12 at the left side and the right side of the top of the tank body 4 are hooked and hung by a crane for unloading, the tank body 4 can move freely through the wheels 5, the water tank 31, the water suction pump 32, the first sprinkler head 42 and the second sprinkler head 43 are used for cleaning the materials remained, the corrosion of the residual materials to the tank body 4 is reduced.
The model of the water pump 32 is ZB400A600A800A, the model of the first dust remover 9 is CQTF, the model of the second dust remover 22 is CQTF, the model of the safety valve 10 is RXAF-P6/1.0, the model of the first arch breaking device 17 is AH30, the model of the second arch breaking device 18 is AH30, the model of the third arch breaking device 15 is AH30, and the model of the fourth arch breaking device 16 is AH 30.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (9)

1. The utility model provides a highway is cement jar of keeping in job site, includes automobile body (1) and base (2), its characterized in that: the top of automobile body (1) is connected with landing leg (6), the top of landing leg (6) welds with the bottom of base (2), the top welding of base (2) has support (3), the welding of the top left and right sides of support (3) has jar body (4), the bottom left side of the inner chamber of the jar body (4) is equipped with water tank (31), the outer wall top left side of water tank (31) is equipped with water filling port (33), the bottom right side screwed connection of the inner chamber of the jar body (4) has suction pump (32), the power input end of suction pump (32) is equipped with power plug (37), the output of power plug (37) and the input electric connection of suction pump (32), the top both sides screwed connection of the inner chamber of the jar body (4) has first sprinkler head (42) and second sprinkler head (43), the bottom on the outer wall right side of water tank (31) is equipped with delivery port (35), delivery port (35) intercommunication has first raceway (38), one side of first raceway (38) communicates in the end of intaking of suction pump (32), the play water end intercommunication of suction pump (32) has second raceway (39), the outer wall of second raceway (39) has cup jointed tee joint head (41), one side of second raceway (39) communicates in second sprinkler head (43), tee joint head (41) intercommunication has third raceway (40), one side of third raceway (40) communicates in first sprinkler head (42).
2. The cement temporary storage tank for the road construction site as claimed in claim 1, wherein: ladder (19) are welded on the right side of the outer wall of the tank body (4), the top left side of the tank body (4) is equipped with first feed inlet (8), one side that the top of the tank body (4) is close to first feed inlet (8) is equipped with first dust shaker (9), the right side that the top of the tank body (4) is located first dust shaker (9) is equipped with relief valve (10), the air inlet of relief valve (10) is linked together with the top of the tank body (4), the right side that the top of the tank body (4) is located relief valve (10) is equipped with second dust shaker (22), the right side welding of second dust shaker (22) has second feed inlet (11).
3. The cement temporary storage tank for the road construction site as claimed in claim 2, wherein: the utility model discloses a broken structure of feed hopper, including the jar body (4), the outer wall bottom of the body is connected with hopper (20), the bottom of hopper (20) is connected with discharge gate (21), the welding of outer wall right side top of first feed inlet (8) has first broken ware (17) of encircleing, the air jet of first broken ware (17) is linked together with first feed inlet (8), the welding of outer wall left side top of second feed inlet (11) has broken ware (18) of second, the air jet of broken ware (18) of second is linked together with second feed inlet (11), the welding of the left side at hopper (20) outer wall top has broken ware (15) of third, the air jet of broken ware (15) of third is linked together with hopper (20), the welding of the right side at hopper (20) outer wall top has broken ware (16) of fourth, the air jet of broken ware (16) is linked together with hopper (20).
4. The cement temporary storage tank for the road construction site as claimed in claim 1, wherein: the left side of water filling port (33) runs through in the outer wall of the jar body (4), the outer wall bottom left side of water tank (31) is equipped with outlet (34), the left side of outlet (34) runs through in the outer wall of the jar body (4).
5. The cement temporary storage tank for the road construction site as claimed in claim 1, wherein: the surface of the water suction pump (32) is sleeved with a water pump cover (44), the bottom of the water pump cover (44) is riveted with the bottom of an inner cavity of the tank body (4), and the power plug (37) penetrates through the outer wall of the tank body (4).
6. The cement temporary storage tank for the road construction site as claimed in claim 1, wherein: and a first hook ring (7) and a second hook ring (12) are welded on two sides of the top of the tank body (4).
7. The cement temporary storage tank for the road construction site as claimed in claim 1, wherein: the left side of the front side of the tank body (4) is provided with a level meter (13).
8. The cement temporary storage tank for the road construction site as claimed in claim 1, wherein: the right side of the front side of the tank body (4) is provided with a material visible window (14).
9. The cement temporary storage tank for the road construction site as claimed in claim 1, wherein: the bottom of the base (2) is provided with wheels (5).
CN201921961132.5U 2019-11-14 2019-11-14 Cement temporary storage tank for highway construction site Expired - Fee Related CN211113013U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921961132.5U CN211113013U (en) 2019-11-14 2019-11-14 Cement temporary storage tank for highway construction site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921961132.5U CN211113013U (en) 2019-11-14 2019-11-14 Cement temporary storage tank for highway construction site

Publications (1)

Publication Number Publication Date
CN211113013U true CN211113013U (en) 2020-07-28

Family

ID=71717535

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921961132.5U Expired - Fee Related CN211113013U (en) 2019-11-14 2019-11-14 Cement temporary storage tank for highway construction site

Country Status (1)

Country Link
CN (1) CN211113013U (en)

Similar Documents

Publication Publication Date Title
CN204297682U (en) A kind of oil-filed fracturing propping agent positive pneumatic transport sledge
CN211113013U (en) Cement temporary storage tank for highway construction site
CN211274029U (en) Electrostatic adsorption dust suppression system
CN212371961U (en) Simple sand blasting and rust removing device
EP2776300A1 (en) Sand dispenser for preventing train wheels from skidding
CN215518236U (en) Rubble spreader is used in road surface restoration
CN206129451U (en) A air cleaner that is used for high dust work equipment of breathing in and vehicle
CN213386867U (en) Powder storage system and mixing plant
CN211358210U (en) Wisdom is dust device for building site
CN205299081U (en) Recovery system of gas gathering station unloading natural gas
CN210473425U (en) But rotatory automatic spray dust suppression device of quick assembly disassembly
CN203540684U (en) Movable sealed collector for pebble coal
CN112777338A (en) Spraying dust suppression device for funnel, control method of spraying dust suppression device and funnel
CN110039654A (en) A kind of novel self-leveling cement stirring and pneumatic conveying all-in-one machine
CN211140367U (en) Silo and main part dust collector
CN219602735U (en) Sand and stone material storage box
CN204767984U (en) A low pressure pulse discharge apparatus for dust collecting equipment
CN206512788U (en) A kind of non-tower water feeder
CN203924726U (en) The pump spray apparatus of cement premixing mortar construction
CN220370705U (en) Hopper convenient for spraying water and falling dust for pure electric dump truck
CN214437558U (en) Green civilization building construction dust fall equipment
CN208199227U (en) A kind of pesticide adaptor
CN212387358U (en) Funnel is with spraying dust suppression device and funnel
CN213890555U (en) Make things convenient for stirring station cement storehouse body of unloading
CN2688358Y (en) Effective coal dust collector with self block eliminator

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200728

Termination date: 20211114