CN211085205U - Level for engineering survey - Google Patents

Level for engineering survey Download PDF

Info

Publication number
CN211085205U
CN211085205U CN201921918978.0U CN201921918978U CN211085205U CN 211085205 U CN211085205 U CN 211085205U CN 201921918978 U CN201921918978 U CN 201921918978U CN 211085205 U CN211085205 U CN 211085205U
Authority
CN
China
Prior art keywords
level
arc
mounting disc
plates
surveyor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921918978.0U
Other languages
Chinese (zh)
Inventor
邹伟雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Benchu Information Technology Co ltd
Original Assignee
Yunnan Benchu Information Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Benchu Information Technology Co ltd filed Critical Yunnan Benchu Information Technology Co ltd
Priority to CN201921918978.0U priority Critical patent/CN211085205U/en
Application granted granted Critical
Publication of CN211085205U publication Critical patent/CN211085205U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The utility model provides a surveyor's level for engineering survey. Level for engineering survey includes: the leveling instrument comprises a triangular support, a mounting disc and a leveling instrument body, wherein the triangular support is rotatably mounted at the bottom of the mounting disc, and the leveling instrument body is fixedly mounted at the top of the mounting disc; the annular groove is formed in the outer side of the mounting disc; two arc structures, two the arc structure is located the mounting disc circles outward, the arc structure includes arc and arc piece, arc piece fixed mounting in the inboard of arc, the arc piece with annular groove looks adaptation. The utility model provides a surveyor's level for engineering survey is through setting up the fender water canopy, can avoid the water droplet of roof to fall on the surveyor's level in the tunnel, has certain guard action to the surveyor's level, simultaneously, through setting up the light, can throw light on in the tunnel that light is darker, has made things convenient for the operation of surveyor's level.

Description

Level for engineering survey
Technical Field
The utility model relates to a measuring instrument technical field especially relates to a surveyor's level for engineering survey.
Background
The level is an instrument for establishing a horizontal sight line to measure the height difference between two points on the ground. The principle is to measure the height difference between ground points according to the leveling principle. The main components are hopeful to be a telescope, a tube level (or compensator), a vertical shaft, a base and a foot screw, and are divided into a micro-inclination level, an automatic leveling level, a laser level and a digital level (also called an electronic level) according to the structure.
In the engineering of some tunnel tunnelling, need measure the tunnel through the surveyor's level sometimes, the water content in some tunnels is great, and the in-process of digging has more water to fall from the roof lowly, uses in such tunnel when traditional surveyor's level, must have water to fall on the level, can cause the damage to the surveyor's level like this.
Therefore, it is necessary to provide a level for engineering measurement to solve the above technical problems.
SUMMERY OF THE UTILITY MODEL
The utility model provides a technical problem provide a can protect the spirit level and provide the engineering level for measurement of illumination function.
In order to solve the technical problem, the utility model provides a level for engineering survey, include: the leveling instrument comprises a triangular support, a mounting disc and a leveling instrument body, wherein the triangular support is rotatably mounted at the bottom of the mounting disc, and the leveling instrument body is fixedly mounted at the top of the mounting disc; the annular groove is formed in the outer side of the mounting disc; the two arc structures are arranged on the outer ring of the mounting plate and comprise arc plates and arc blocks, the arc blocks are fixedly arranged on the inner sides of the arc plates and are matched with the annular grooves, and the arc plates are arranged on the outer sides of the mounting plate; and the water blocking shed is arranged right above the level gauge body.
Preferably, the arc-shaped plate and the arc-shaped block are both of semicircular structures, and the circle centers are the same circle center.
Preferably, two the fixed plates are symmetrically installed at the two ends of the arc-shaped plate, and four threaded through holes are formed in the fixed plates.
Preferably, two screw rods are installed on the four fixing plates in a threaded mode, and handles are installed at one ends of the two screw rods in a fixed mode.
Preferably, two equal fixed mounting in top of arc has the bracing piece, and two bracing pieces are the symmetric distribution.
Preferably, the two support rods are rotatably connected with the bottom of the water blocking shed.
Preferably, the bottom of the water blocking shed is provided with an illuminating lamp and a battery.
Compared with the prior art, the utility model provides a surveyor's level for engineering survey has following beneficial effect:
the utility model provides an engineering survey is with surveyor's level, through setting up the fender water canopy, the water droplet that can avoid roof in the tunnel falls on the surveyor's level, has certain guard action to the surveyor's level, simultaneously, through setting up the light, can throw light on in the tunnel that light is darker, has made things convenient for the operation of surveyor's level.
Drawings
Fig. 1 is a schematic view of a front view structure of a level for engineering measurement provided by the present invention;
fig. 2 is a schematic front sectional view of the leveling instrument for engineering measurement according to the present invention;
FIG. 3 is an enlarged view of portion A of FIG. 2;
fig. 4 is a schematic structural view of the level mounting plate for engineering measurement provided by the present invention;
fig. 5 is a schematic view of a top cross-sectional structure of the leveling instrument for engineering measurement provided by the present invention.
Reference numbers in the figures: 1. a triangular support, 2, a mounting disc, 3, a level body, 4, an annular groove, 5, an arc block, 6, an arc plate, 7, a fixing plate, 8, a screw rod, 9, a handle, 10, a support rod, 11, a water blocking shed, 12, a lighting lamp, 13 and a battery.
Detailed Description
The present invention will be further described with reference to the accompanying drawings and embodiments.
Referring to fig. 1-5, in an embodiment of the present invention, a level for engineering survey includes: the leveling instrument comprises a triangular support 1, a mounting disc 2 and a leveling instrument body 3, wherein the triangular support 1 is rotatably mounted at the bottom of the mounting disc 2, and the leveling instrument body 3 is fixedly mounted at the top of the mounting disc 2; the annular groove 4 is formed in the outer side of the mounting disc 2; the two arc structures are arranged on the outer ring of the mounting plate 2 and comprise arc plates 6 and arc blocks 5, the arc blocks 5 are fixedly arranged on the inner sides of the arc plates 6, the arc blocks 5 are matched with the annular grooves 4, and the arc plates 6 are arranged on the outer sides of the mounting plate 2; and the water blocking shed 11 is arranged right above the level gauge body 3.
The arc-shaped plate 6 and the arc-shaped block 5 are both of semicircular structures, and the circle centers are the same.
Two fixed plates 7 are symmetrically arranged at two ends of the arc-shaped plate 6, and threaded through holes are formed in the fixed plates 7.
Four two lead screws 8 are installed on the fixed plate 7 in a threaded mode, and handles 9 are fixedly installed at one ends of the two lead screws 8.
Two equal fixed mounting in top of arc 6 has the bracing piece 10, and two bracing pieces 10 are the symmetric distribution.
The two support rods 10 are rotatably connected with the bottom of the water blocking shed 11.
The bottom of the water blocking shed 11 is provided with an illuminating lamp 12 and a battery 13.
The utility model provides a surveyor's level for engineering survey's theory of operation as follows:
when measuring in tunnels with large water content, the device is firstly arranged on the mounting disc 2, so that the water blocking shed 11 can block the water falling from the top plate of the tunnel, the water is prevented from directly dropping on the level body 3 to damage the level body 3, because the light in the tunnel is darker, the illumination can be carried out through the illuminating lamp 12 at the moment so as to be convenient for operating the level body 3, when the device needs to be dismantled, the handle 9 is rotated to rotate the screw rod 8, thereby leading the screw rod 8 to move out of the corresponding fixed plate 7, leading the two arc-shaped plates 6 to move, then leading the two arc-shaped plates 6 to move towards opposite directions, leading the arc-shaped plates 6 to move to drive the arc-shaped block 5 to move, thereby make the arc piece 5 shift out the ring channel 4, what the arc 6 removed also can drive the bracing piece 10 to rotate simultaneously, two bracing pieces 10 play the effect of supporting to manger plate canopy 11, can demolish this device finally.
Compared with the prior art, the utility model provides a surveyor's level for engineering survey has following beneficial effect:
through setting up the fender water canopy, the water droplet that can avoid roof in the tunnel falls on the surveyor's level, has certain guard action to the surveyor's level, simultaneously, through setting up the light, can throw light on in the tunnel that light is darker, has made things convenient for the operation of surveyor's level.
The above only is the embodiment of the present invention, not limiting the scope of the present invention, all the equivalent structures or equivalent processes of the present invention are used in the specification and the attached drawings, or directly or indirectly applied to other related technical fields, and the same principle is included in the protection scope of the present invention.

Claims (7)

1. A level for engineering surveying, comprising:
the leveling instrument comprises a triangular support, a mounting disc and a leveling instrument body, wherein the triangular support is rotatably mounted at the bottom of the mounting disc, and the leveling instrument body is fixedly mounted at the top of the mounting disc;
the annular groove is formed in the outer side of the mounting disc;
the two arc structures are arranged on the outer ring of the mounting plate and comprise arc plates and arc blocks, the arc blocks are fixedly arranged on the inner sides of the arc plates and are matched with the annular grooves, and the arc plates are arranged on the outer sides of the mounting plate;
and the water blocking shed is arranged right above the level gauge body.
2. The level for engineering surveying of claim 1, wherein the arc plate and the arc block are both semi-circular structures and have a same center of circle.
3. The level gauge for engineering measurement according to claim 1, wherein two ends of each of the two arc-shaped plates are symmetrically provided with a fixing plate, and four fixing plates are provided with threaded through holes.
4. The level for engineering surveying of claim 3, wherein two lead screws are threadedly mounted on the four fixing plates, and a handle is fixedly mounted on one end of each of the two lead screws.
5. The level for engineering surveying of claim 1, wherein support rods are fixedly mounted on top of both of the curved plates, and the two support rods are symmetrically distributed.
6. The level for engineering surveying of claim 5 wherein both of said support rods are pivotally connected to the bottom of said water dam.
7. The level for engineering surveying of claim 1, wherein an illumination lamp and a battery are installed at a bottom of the water blocking shed.
CN201921918978.0U 2019-11-08 2019-11-08 Level for engineering survey Active CN211085205U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921918978.0U CN211085205U (en) 2019-11-08 2019-11-08 Level for engineering survey

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921918978.0U CN211085205U (en) 2019-11-08 2019-11-08 Level for engineering survey

Publications (1)

Publication Number Publication Date
CN211085205U true CN211085205U (en) 2020-07-24

Family

ID=71628820

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921918978.0U Active CN211085205U (en) 2019-11-08 2019-11-08 Level for engineering survey

Country Status (1)

Country Link
CN (1) CN211085205U (en)

Similar Documents

Publication Publication Date Title
CN110332436B (en) Engineering mapping device convenient to remove
CN205718949U (en) A kind of civil engineering measurement apparatus
CN209166412U (en) A kind of inclination of transmission line tower measuring instrument
CN105444733A (en) Measuring scale and measuring method for automatically-centralized level gauge
CN211085205U (en) Level for engineering survey
CN115930844A (en) Land area surveying instrument for land reclamation
US11854429B2 (en) Portable simulated flood discharge culvert for surveying and mapping
CN208269883U (en) A kind of civil engineering measuring device
CN201217936Y (en) Signal generating structure of plastering machine aligning apparatus
CN207408589U (en) A kind of adjustable laser rangefinder
CN212131848U (en) Bridge detects with convenient height-adjusting's check out test set frame
CN215003548U (en) Level with night illumination function and leveling function
CN216448887U (en) Simple remote plumb bob device for perpendicularity test
CN206362332U (en) A kind of ancient building shelter bridge construction portable transit
CN108286426B (en) Horizontal inclined hole inclinometry platform
CN213902378U (en) Civil engineering is measured with fixed point sighting rod
CN204718561U (en) Portable electric pole gradient measurement instrument
CN210831214U (en) Tripod for mapping engineering
CN210154603U (en) Special measuring device of highway engineering
CN209741625U (en) Road and bridge construction measuring device
CN209557978U (en) A kind of surveying instrument supporting frame convenient for leveling
CN215572894U (en) Prism flattening device for deep groove measurement
CN211399077U (en) Portable tripod for engineering survey
CN112414385A (en) Measuring apparatu for civil engineering
CN208619990U (en) A kind of tripod of Surveying Engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant