CN211080305U - Utility tunnel - Google Patents

Utility tunnel Download PDF

Info

Publication number
CN211080305U
CN211080305U CN201921899766.2U CN201921899766U CN211080305U CN 211080305 U CN211080305 U CN 211080305U CN 201921899766 U CN201921899766 U CN 201921899766U CN 211080305 U CN211080305 U CN 211080305U
Authority
CN
China
Prior art keywords
cabin
gas
pipeline
box body
water supply
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921899766.2U
Other languages
Chinese (zh)
Inventor
林建仁
赵明
伍根伙
王义廷
李仰根
刘文龙
谢芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Meiyi Tongji Housing Industry Co ltd
Original Assignee
Fujian Meiyi Tongji Housing Industry Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Meiyi Tongji Housing Industry Co ltd filed Critical Fujian Meiyi Tongji Housing Industry Co ltd
Priority to CN201921899766.2U priority Critical patent/CN211080305U/en
Application granted granted Critical
Publication of CN211080305U publication Critical patent/CN211080305U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a comprehensive pipe rack, which comprises a pipe rack main body, wherein an independent sewage discharging cabin, a gas cabin, an electric power cabin, a communication cabin and a water supply cabin are arranged in the pipe rack main body, the sewage discharging cabin is positioned on the right side of the inside of the pipe rack main body, the upper end of the side wall of the sewage discharging cabin is provided with a vent, the gas cabin and the water supply cabin are arranged below the inside of the pipe rack main body side by side at intervals, the gas cabin is in a sealing arrangement, a gas leakage inductor is arranged in the gas cabin, the inner wall of the gas cabin is provided with an anticorrosive layer and a fireproof layer, a box body for placing cables is arranged in the electric power cabin, the front end and the rear end of the box body are in an open shape, the periphery of the box body is in a closed shape, a switch door is arranged on the box body, a bracket for placing communication lines is arranged in the communication cabin, partition plates are arranged on the bracket at even intervals, and all function, can avoid mutual interference, facilitate the operation and have high safety.

Description

Utility tunnel
Technical Field
The utility model relates to a utility tunnel.
Background
The pipe gallery is a comprehensive underground structure integrating power cables, telecommunications, water supply, rain sewage, gas and the like. Present utility tunnel most all concentrates on an under-deck with multiple pipeline or cable, can receive the influence of other pipeline or cable when leading to the staff operation, and the operation is laid to inconvenient, lacks safety monitoring equipment to the gas pipeline cabin moreover, and the cable also directly exposes externally, lacks the protection, and the time has been received the erosion easily for a long time, and laying of communication line also is together piling up of general, and the circuit is more mixed and disorderly.
SUMMERY OF THE UTILITY MODEL
For solving the technical problem, the utility model aims at providing an all function cabins all independently set up, can avoid mutual interference, make things convenient for the operation, the high utility tunnel of security.
The utility model provides a pair of utility tunnel, its characterized in that: the pipeline corridor comprises a pipeline corridor main body, wherein an independent pollution discharge cabin, a gas cabin, an electric power cabin, a communication cabin and a water supply cabin are arranged in the pipeline corridor main body, the pollution discharge cabin is positioned on the right side inside the pipeline corridor main body, a vent hole is formed in the upper end of the side wall of the pollution discharge cabin, the gas cabin and the water supply cabin are arranged below the inside of the pipeline corridor main body side by side at a left-right interval, the gas cabin is arranged in a sealing manner, a gas leakage inductor is installed in the gas cabin, an anticorrosive layer and a fireproof layer are arranged on the inner wall of the gas cabin, the electric power cabin and the communication cabin are arranged above the inside of the pipeline corridor main body side by side at a left-right interval, and the electric power cabin and the communication cabin and the gas cabin and the water supply cabin form an upper-lower layer arrangement and; the electric power cabin is provided with a box body for placing cables, the front end and the rear end of the box body are open, the periphery of the box body is closed, the box body is provided with a switch door, a bracket for placing communication lines is arranged in the communication cabin, and partition plates are arranged on the bracket at uniform intervals.
Furthermore, a sewage pipeline buttress is arranged in the middle of the bottom of the sewage discharging cabin, and a sewage pipeline pipe support is arranged on the sewage pipeline buttress.
Further, a gas pipeline buttress is arranged in the middle of the bottom of the gas cabin, and a gas pipeline pipe support is arranged on the gas pipeline buttress.
Furthermore, a water supply pipeline buttress is arranged in the middle of the bottom of the water supply cabin, and a water supply pipeline pipe support is arranged on the water supply pipeline buttress.
Further, the box body is arranged on the inner wall of the left side of the electric power cabin at an upper-lower uniform interval, and the switch door is located on the right side of the box body.
Further, the bracket is arranged on the inner wall of the right side of the communication cabin at an upper-lower uniform interval, and the partition plate is arranged at a left-right uniform interval.
Furthermore, illuminating lamps are arranged in the middle of the tops of the electric power cabin and the communication cabin.
Furthermore, a handle is arranged on the switch door.
Borrow by above-mentioned scheme, the utility model discloses at least, have following advantage: this utility tunnel passes through the inside blowdown cabin of piping lane main part, the gas cabin, the electric power cabin, communication cabin and water supply tank all set up independently, it is corresponding more to have during messenger's staff's operation, avoid mutual interference, make things convenient for the operation, can real-time supervision through the gas leakage inductor in the gas cabin, in case there is gas leakage can in time discover, the security has been improved, box body through in the electric power cabin can be with cable enclosure, it is outside to avoid the cable directly to expose, avoid the cable to receive the erosion, the life of extension cable, division board through on the bracket in the communication cabin can carry out the communication line regularly, neat laying, avoid the communication line intertwine.
The above description is only an overview of the technical solution of the present invention, and in order to make the technical means of the present invention clearer and can be implemented according to the content of the description, the following detailed description is made with reference to the preferred embodiments of the present invention and accompanying drawings.
Drawings
Figure 1 is the utility model discloses utility tunnel's structural schematic.
Detailed Description
The following detailed description of the embodiments of the present invention is provided with reference to the accompanying drawings and examples. The following examples are intended to illustrate the invention, but are not intended to limit the scope of the invention.
Example (b): a utility tunnel comprises a main body 1 of the pipe rack, wherein an independent sewage discharging cabin 2, a gas cabin 3, an electric power cabin 4, a communication cabin 5 and a water feeding cabin 6 are arranged in the main body of the pipe rack, the sewage discharging cabin is positioned on the right side of the inside of the main body of the pipe rack, a vent 7 is arranged at the upper end of the side wall of the sewage discharging cabin, the gas cabin and the water feeding cabin are arranged below the inside of the main body of the pipe rack side by side at left and right intervals, the gas cabin is arranged in a sealing manner, a gas leakage inductor 8 is arranged in the gas cabin, an anticorrosive layer and a fireproof layer are arranged on the inner wall of the gas cabin, the electric power cabin and the communication cabin are arranged above the inside of the main body side by side at left and right intervals, and the electric power cabin and the communication cabin and the gas cabin and the water feeding cabin form upper and lower layers and are; be equipped with the box body 9 that the power cable was placed in the electric power cabin, the box body front and back end is open form, be the closed form around the box body, be equipped with switch door 10 on the box body, be equipped with the bracket 11 that supplies communication line to place in the communication cabin, even interval is equipped with division board 12 on the bracket.
A sewage pipeline buttress 13 is arranged in the middle of the bottom of the sewage discharging cabin, and a sewage pipeline pipe bracket 14 is arranged on the sewage pipeline buttress.
And a gas pipeline buttress 15 is arranged in the middle of the bottom of the gas cabin, and a gas pipeline pipe support 16 is arranged on the gas pipeline buttress.
A water supply pipeline buttress 17 is arranged in the middle of the bottom of the water supply cabin, and a water supply pipeline pipe bracket 18 is arranged on the water supply pipeline buttress.
The box body is arranged on the inner wall of the left side of the electric power cabin at an upper-lower uniform interval, and the switch door is positioned on the right side of the box body.
The bracket is arranged on the inner wall of the right side of the communication cabin at an upper and lower uniform interval, and the partition plate is arranged at a left and right uniform interval.
And illuminating lamps 19 are arranged in the middle of the tops of the electric power cabin and the communication cabin.
The switch door is provided with a handle 20.
This utility tunnel passes through the inside blowdown cabin of piping lane main part, the gas cabin, the electric power cabin, communication cabin and water supply tank all set up independently, it is corresponding more to have during messenger's staff's operation, avoid mutual interference, make things convenient for the operation, can real-time supervision through the gas leakage inductor in the gas cabin, in case there is gas leakage can in time discover, the security has been improved, box body through in the electric power cabin can be with cable enclosure, it is outside to avoid the cable directly to expose, avoid the cable to receive the erosion, the life of extension cable, division board through on the bracket in the communication cabin can carry out the communication line regularly, neat laying, avoid the communication line intertwine.
The above description is only a preferred embodiment of the present invention, and is not intended to limit the present invention, and it should be noted that, for those skilled in the art, a plurality of modifications and variations can be made without departing from the technical principle of the present invention, and these modifications and variations should also be regarded as the protection scope of the present invention.

Claims (8)

1. The utility model provides a utility tunnel which characterized in that: the pipeline corridor comprises a pipeline corridor main body, wherein an independent pollution discharge cabin, a gas cabin, an electric power cabin, a communication cabin and a water supply cabin are arranged in the pipeline corridor main body, the pollution discharge cabin is positioned on the right side inside the pipeline corridor main body, a vent hole is formed in the upper end of the side wall of the pollution discharge cabin, the gas cabin and the water supply cabin are arranged below the inside of the pipeline corridor main body side by side at a left-right interval, the gas cabin is arranged in a sealing manner, a gas leakage inductor is installed in the gas cabin, an anticorrosive layer and a fireproof layer are arranged on the inner wall of the gas cabin, the electric power cabin and the communication cabin are arranged above the inside of the pipeline corridor main body side by side at a left-right interval, and the electric power cabin and the communication cabin and the gas cabin and the water supply cabin form an upper-lower layer arrangement and; the electric power cabin is provided with a box body for placing cables, the front end and the rear end of the box body are open, the periphery of the box body is closed, the box body is provided with a switch door, a bracket for placing communication lines is arranged in the communication cabin, and partition plates are arranged on the bracket at uniform intervals.
2. A utility tunnel according to claim 1, characterized in that: and a sewage pipeline buttress is arranged in the middle of the bottom of the sewage discharging cabin, and a sewage pipeline pipe bracket is arranged on the sewage pipeline buttress.
3. A utility tunnel according to claim 2, characterized in that: the middle of the bottom of the gas cabin is provided with a gas pipeline buttress, and a gas pipeline pipe support is arranged on the gas pipeline buttress.
4. A utility tunnel according to claim 3, characterized in that: the middle of the bottom of the water supply cabin is provided with a water supply pipeline buttress, and a water supply pipeline pipe support is arranged on the water supply pipeline buttress.
5. A utility tunnel according to claim 4, characterized in that: the box body is arranged on the inner wall of the left side of the electric power cabin at an upper-lower uniform interval, and the switch door is positioned on the right side of the box body.
6. A utility tunnel according to claim 5, characterized in that: the bracket is arranged on the inner wall of the right side of the communication cabin at an upper and lower uniform interval, and the partition plate is arranged at a left and right uniform interval.
7. A utility tunnel according to claim 6, characterized in that: and illuminating lamps are arranged in the middle of the tops of the electric power cabin and the communication cabin.
8. A utility tunnel according to claim 7, characterized in that: and a handle is arranged on the switch door.
CN201921899766.2U 2019-11-06 2019-11-06 Utility tunnel Active CN211080305U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921899766.2U CN211080305U (en) 2019-11-06 2019-11-06 Utility tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921899766.2U CN211080305U (en) 2019-11-06 2019-11-06 Utility tunnel

Publications (1)

Publication Number Publication Date
CN211080305U true CN211080305U (en) 2020-07-24

Family

ID=71643453

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921899766.2U Active CN211080305U (en) 2019-11-06 2019-11-06 Utility tunnel

Country Status (1)

Country Link
CN (1) CN211080305U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111894035A (en) * 2020-09-09 2020-11-06 李绍凤 Assembled rectangle utility tunnel of underground construction and piping lane prefab

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111894035A (en) * 2020-09-09 2020-11-06 李绍凤 Assembled rectangle utility tunnel of underground construction and piping lane prefab

Similar Documents

Publication Publication Date Title
CN211080305U (en) Utility tunnel
CN106098993A (en) A kind of battery case
CN201533132U (en) Electric/optical cable trough and die for preparing same
CN212129225U (en) Underground pipe gallery
CN206301735U (en) A kind of gas relay rain cover
CN204793792U (en) Bury case becomes casing waterproofly
CN211368781U (en) Utility tunnel
CN205127215U (en) High altitude power equipment extinguishing device
CN211266372U (en) Cable laying equipment
CN114379707A (en) Low-flash-point fuel ship
CN207504491U (en) A kind of strong and weak electricity is layered isolated cable testing bridge
CN211295837U (en) Shore power box with multiple functional partitions inside
CN107069363A (en) A kind of SF6The quick switching device of insulative distributing
CN106544680A (en) A kind of erosion protection system for essential service water system of nuclear power station pipeline
CN209798823U (en) Detachable comprehensive pipe gallery prevents hot wall structure
CN207283086U (en) A kind of track traffic computer room comprehensive wiring mechanism
CN205811443U (en) A kind of control box of dual control board
CN110984355A (en) Cable work well with intelligent drainage function
CN104979791B (en) Cable shaft
CN206640248U (en) A kind of wire or cable terminal box
CN206163549U (en) Battery box
CN210468688U (en) High-voltage power supply device
CN109217156B (en) Offshore booster station
CN219671429U (en) Electric power communication inspection well
CN218392004U (en) Oil collecting pit overflow risk detection device for converter station/transformer substation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant