Info

Publication number
CN211025607U
CN211025607U CN201921980670.9U CN201921980670U CN211025607U CN 211025607 U CN211025607 U CN 211025607U CN 201921980670 U CN201921980670 U CN 201921980670U CN 211025607 U CN211025607 U CN 211025607U
Authority
CN
China
Prior art keywords
fixedly connected
pipe
atomizing
water
water storage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921980670.9U
Other languages
Chinese (zh)
Inventor
姚红亮
陈天生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Zhongqiang Construction Engineering Co ltd
Original Assignee
Shaoguan Xidian Information Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaoguan Xidian Information Technology Co ltd filed Critical Shaoguan Xidian Information Technology Co ltd
Priority to CN201921980670.9U priority Critical patent/CN211025607U/en
Application granted granted Critical
Publication of CN211025607U publication Critical patent/CN211025607U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Special Spraying Apparatus (AREA)

Abstract

The utility model discloses a construction dust device, including removing shallow, atomizing spray tube, water storage bucket, a supply-air section of thick bamboo, remove shallow front end fixedly connected with pipe support, fixedly connected with atomizing spray tube on the pipe support, the last atomizer that evenly arranges of atomizing spray tube, the upper end fixed surface of removing the shallow is connected with the water storage bucket, water storage bucket lower extreme fixedly connected with atomizing pump, the removal shallow surface difference fixedly connected with support column of atomizing pump both sides, support column top fixedly connected with backup pad, backup pad top hinged joint has a supply-air section of thick bamboo, supply-air section of thick bamboo front end fixedly connected with gathers the wind fill, gather the exit fixedly connected with annular fog pipe of wind fill, the multiunit atomising head has evenly arranged on the annular fog pipe. The utility model has the advantages of simple structure, dust fall wide range, convenient to use are nimble and have the effect of pressing down the dirt, its mainly used construction site the dust fall, press down the dirt.

Description

Building construction dust device
Technical Field
The utility model relates to a construction equipment technical field, specific building construction dust device that says so.
Background
Often can accompany a large amount of dusts in the work progress in present building construction place, the dust volume in the air has seriously influenced constructor's healthy, consequently the dust fall in construction place all has always been the key in the construction management work, difficult problem, current dust device often is bulky, because the hindrance of material and equipment in the construction place, often not nimble enough during the use, can't pass in and out complicated construction place at will, and among the prior art, dust device often singly relies on atomizer to spray water smoke in to the air, consequently the dust fall scope is smaller.
SUMMERY OF THE UTILITY MODEL
To the above-mentioned weak point that exists among the prior art, the utility model aims at providing a simple structure, dust fall wide range, convenient to use are nimble and have the construction dust device of dust suppression effect.
The utility model discloses a realize that the technical scheme that above-mentioned purpose adopted is: a building construction dust fall device comprises a movable trolley, an atomizing spray pipe, a water storage barrel and an air supply barrel, wherein a pipe support is fixedly connected to the front end of the movable trolley, the upper end of the pipe support is inclined towards the front end of the movable trolley, the atomizing spray pipe is fixedly connected to the upper end of the pipe support, a plurality of groups of atomizing spray heads are uniformly arranged and mounted on the pipe wall of the front side of the atomizing spray pipe, the upper side edges of two ends of the atomizing spray pipe are connected with atomizing branch pipes through hinge pieces, a plurality of groups of atomizing spray heads are uniformly arranged and mounted on the pipe wall of the front side of the atomizing branch pipes, connecting pipes are respectively and fixedly connected to the pipe walls of two ends of the atomizing spray pipe, and the; the upper end surface of the movable cart is fixedly connected with a water storage barrel, the lower end of the water storage barrel is fixedly connected with a water delivery pipe, the other end of the water delivery pipe is fixedly connected with a water inlet outlet of an atomizing pump, the atomizing pump is fixedly connected with the surface of the movable cart between the water storage barrel and the pipe support, the surfaces of the movable carts on two sides of the atomizing pump are respectively and fixedly connected with supporting columns, the top ends of the supporting columns are fixedly connected with supporting plates, the top surfaces of the supporting plates are fixedly connected with U-shaped supports, air supply cylinders are hinged between the U-shaped supports, air supply fans are fixedly connected with the rear ends of the air supply cylinders, air gathering hoppers are fixedly connected with the front ends of the air supply cylinders, annular fog pipes are fixedly connected with the outlets of the air gathering hoppers, multiple groups of atomizing heads are uniformly distributed on the; the delivery port fixedly connected with outlet pipe of atomizing pump, the outlet pipe end is fixedly connected with a water pipe and No. two water pipes respectively, the terminal fixed connection of a water pipe is in atomizing spray tube middle part, the terminal fixed connection of No. two water pipes is in on the annular fog pipe.
Further, the surface of the lower end of the movable trolley is fixedly connected with an axle, and two ends of the axle are rotatably connected with movable wheels.
Furthermore, a pushing handle is fixedly connected to the rear end of the movable trolley.
Furthermore, the bottom of the air supply fan is fixedly connected with an adjusting rope, the other end of the adjusting rope is tied on a fixing rod, and two ends of the fixing rod are respectively and fixedly connected to the supporting columns.
Furthermore, raceway one end sets up inside water storage bucket and fixedly connected with filter equipment, inside fixed mounting of water storage bucket has level sensor.
Furthermore, the water delivery pipe, the first branch water pipe and the second branch water pipe are fixedly connected with electromagnetic valves, and the connecting pipe is fixedly connected with a manual valve.
Further, a controller is fixedly connected to the outer wall of one side of the water storage barrel, and the controller is respectively connected with the atomizing pump, the air supply fan, the liquid level sensor and the electromagnetic valve through data lines.
The utility model has the advantages that: this device simple structure, can remove the most place of construction place with it during the use, use more nimble, can increase atomizing gas's transport distance through the air supply section of thick bamboo that is provided with and increased the regional scope of dust fall, the atomizing spray tube that is provided with simultaneously can carry out the dust suppression to the bottom surface in construction place and handle, further reduces the dust flying upward in construction place.
Drawings
FIG. 1 is a schematic perspective view of the present invention;
FIG. 2 is a schematic side view of the cross-sectional structure of the present invention;
FIG. 3 is a schematic diagram illustrating a detailed structure of a part A1 in FIG. 2;
fig. 4 is a schematic view of the connection structure of the middle air supply barrel of the present invention.
In the figure: the atomizing device comprises a movable cart 1, an atomizing spray pipe 2, a water storage barrel 3, an air supply barrel 4, a pipe support 5, an atomizing spray head 6, an atomizing branch pipe 7, a connecting pipe 8, a water delivery pipe 9, a support column 10, a support plate 11, a U-shaped support 12, an air supply fan 13, an air collecting hopper 14, an annular atomizing pipe 15, an atomizing spray head 16, a water outlet pipe 17, a water pipe 18I, a water delivery pipe 19 II, a movable wheel 20, a push handle 21, an adjusting rope 22, a fixing rod 23, an electromagnetic valve 24 and an atomizing pump 25.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, a building construction dust-settling device comprises a movable cart 1, an atomizing spray pipe 2, a water storage bucket 3 and an air supply barrel 4, wherein the front end of the movable cart 1 is fixedly connected with a pipe support 5, the upper end of the pipe support 5 is obliquely arranged towards the front end of the movable cart 1, the upper end of the pipe support 5 is fixedly connected with the atomizing spray pipe 2, a plurality of groups of atomizing spray heads 6 are uniformly arranged and mounted on the pipe wall at the front side of the atomizing spray pipe 2, the upper side edges at two ends of the atomizing spray pipe 2 are connected with an atomizing branch pipe 7 through hinges, a plurality of groups of atomizing spray heads 6 are uniformly arranged and mounted on the pipe wall at the front side of the atomizing branch pipe 7, connecting pipes 8 are respectively and fixedly connected to the pipe walls at two ends of the; the surface of the upper end of the mobile cart 1 is fixedly connected with a water storage barrel 3, the lower end of the water storage barrel 3 is fixedly connected with a water delivery pipe 9, the other end of the water delivery pipe 9 is fixedly connected with a water inlet of an atomizing pump 25, the atomizing pump 25 is fixedly connected with the surface of the mobile cart 1 between the water storage barrel 3 and a pipe support 5, the surfaces of the mobile carts 1 on two sides of the atomizing pump 25 are respectively and fixedly connected with supporting columns 10, the top ends of the supporting columns 10 are fixedly connected with supporting plates 11, the top end surface of each supporting plate 11 is fixedly connected with a U-shaped support 12, an air supply barrel 4 is hinged between the U-shaped supports 12, the rear end of the air supply barrel 4 is fixedly connected with an air supply fan 13, the front end of the air supply barrel 4 is fixedly connected with an air gathering hopper 14, an annular fog pipe 15 is fixedly connected with the; the delivery port fixedly connected with outlet pipe 17 of atomizing pump 25, outlet pipe 17 end fixedly connected with No. one water pipe 18 and No. two water pipes 19 respectively, No. one the end fixed connection of water pipe 18 is in atomizing spray tube 2 middle part, No. two the end fixed connection of water pipe 19 is on annular fog pipe 15.
In the utility model, the lower end surface of the mobile cart 1 is fixedly connected with an axle, and the two ends of the axle are rotatably connected with mobile wheels 20 for the displacement movement of the mobile cart 1;
the rear end of the movable trolley 1 is fixedly connected with a push handle 21 for pushing and pulling the movable trolley 1;
the bottom of the air supply fan 13 is fixedly connected with an adjusting rope 22, the other end of the adjusting rope 22 is tied on a fixing rod 23, two ends of the fixing rod 23 are respectively and fixedly connected to the supporting columns 10, and the inclination angle of the air supply cylinder 4 is changed by adjusting the length of the adjusting rope 22;
one end of the water delivery pipe 9 is arranged in the water storage barrel 3 and is fixedly connected with a filtering device to prevent the atomizing spray head 6 and the atomizing spray head 16 from being blocked, and a liquid level sensor is fixedly arranged in the water storage barrel 3 and is used for detecting the liquid level change in the water storage barrel 3 in real time;
the water delivery pipe 9, the first branch water pipe 18 and the second branch water pipe 19 are all fixedly connected with electromagnetic valves 24, and the connecting pipe 8 is fixedly connected with a manual valve for controlling the circulation of the pipelines;
the outer wall of one side of the water storage barrel 3 is fixedly connected with a controller, and the controller is respectively connected with the atomizing pump 25, the air supply fan 13, the liquid level sensor and the electromagnetic valve 24 through data lines and used for the use and operation of the device.
The utility model discloses a theory of operation is: when the air supply device is used, the movable trolley 1 is pushed and pulled to a specified position through the push handle 21, the front end of the movable trolley 1 faces a dust area, the adjusting rope 22 is pulled, the air supply cylinder 4 rotates around a hinge joint, the spraying angle is adjusted, the adjusting rope 22 is fixed on the fixing rod 23, the electromagnetic valves 24 on the water delivery pipe 9 and the second branch water pipe 19 are opened, the atomizing pump 25 and the air supply fan 13 are started, the atomizing pump 25 delivers water into the annular fog pipe 15, atomized air is sprayed out through the atomizing head 16 on the annular fog pipe 15, meanwhile, the air supply fan 13 delivers air into the air supply cylinder 4 and blows out from one end of the air collection hopper 14, and the atomized air is taken out along the air in the blowing process, so that the effect of eliminating dust in the air is achieved;
the utility model discloses can also press down dirt to the road surface and handle, specifically do: open solenoid valve 24 on raceway 9 and a water pipe 18, then start atomizing pump 25, and the pulling removes shallow 1 and moves on the road surface, atomizing pump 25 carries water to in atomizing spray tube 2, atomize water and spray on the road surface through atomizer 6 on atomizing spray tube 2, thereby reach the effect that the road surface pressed down dirt, according to the width on road surface, can also expand atomizing branch pipe 7 at atomizing spray tube 2 both ends to both sides reversal, open the manual valve on connecting pipe 8 simultaneously, thereby can increase the area that presses down dirt to the road surface.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (7)

1. The utility model provides a construction dust device, includes removal shallow (1), atomizing spray tube (2), water storage bucket (3), air supply cylinder (4), its characterized in that: the front end of the movable trolley (1) is fixedly connected with a pipe support (5), the upper end of the pipe support (5) is inclined towards the front end of the movable trolley (1), the upper end of the pipe support (5) is fixedly connected with an atomizing spray pipe (2), a plurality of groups of atomizing spray heads (6) are uniformly arranged and installed on the pipe wall of the front side of the atomizing spray pipe (2), the upper side edges of the two ends of the atomizing spray pipe (2) are connected with atomizing branch pipes (7) through hinge pieces, a plurality of groups of atomizing spray heads (6) are uniformly arranged and installed on the pipe wall of the front side of the atomizing branch pipes (7), the pipe walls of the two ends of the atomizing spray pipe (2) are respectively and fixedly connected with connecting pipes (8), and the other ends of the connecting pipes (8) are fixedly; the water storage barrel (3) is fixedly connected to the upper end surface of the movable cart (1), the water delivery pipe (9) is fixedly connected to the lower end of the water storage barrel (3), the other end of the water delivery pipe (9) is fixedly connected to the water inlet outlet of the atomizing pump (25), the atomizing pump (25) is fixedly connected to the surface of the movable cart (1) between the water storage barrel (3) and the pipe support (5), the supporting columns (10) are respectively and fixedly connected to the surfaces of the movable cart (1) on the two sides of the atomizing pump (25), the supporting plate (11) is fixedly connected to the top ends of the supporting columns (10), the U-shaped support (12) is fixedly connected to the top end surface of the supporting plate (11), the air supply barrel (4) is hinged between the U-shaped supports (12), the air supply fan (13) is fixedly connected to the rear end of the air supply barrel (4), and the air collection hopper, an outlet of the air gathering hopper (14) is fixedly connected with an annular fog pipe (15), a plurality of groups of atomizing heads (16) are uniformly arranged on the annular fog pipe (15), and the atomizing heads (16) are obliquely arranged towards the center of the annular fog pipe (15); delivery port fixedly connected with outlet pipe (17) of atomizing pump (25), outlet pipe (17) end difference fixedly connected with No. one water pipe (18) and No. two water pipes (19), the terminal fixed connection of a water pipe (18) be in atomizing spray tube (2) middle part, the terminal fixed connection of No. two water pipes (19) be in on annular fog pipe (15).
2. The building construction dust device of claim 1, characterized in that: the lower end surface of the movable trolley (1) is fixedly connected with an axle, and two ends of the axle are rotatably connected with movable wheels (20).
3. The building construction dust device of claim 1, characterized in that: the rear end of the movable cart (1) is fixedly connected with a push handle (21).
4. The building construction dust device of claim 1, characterized in that: the bottom of the air supply fan (13) is fixedly connected with an adjusting rope (22), the other end of the adjusting rope (22) is tied on a fixing rod (23), and two ends of the fixing rod (23) are fixedly connected to the supporting columns (10) respectively.
5. The building construction dust device of claim 1, characterized in that: one end of the water delivery pipe (9) is arranged inside the water storage barrel (3), the filtering device is fixedly connected with the inside of the water storage barrel (3), and the liquid level sensor is fixedly arranged inside the water storage barrel (3).
6. The building construction dust device of claim 1, characterized in that: the water delivery pipe (9), the first water branch pipe (18) and the second water branch pipe (19) are fixedly connected with electromagnetic valves (24), and the connecting pipe (8) is fixedly connected with a manual valve.
7. The building construction dust device of claim 1, characterized in that: the water storage tank is characterized in that a controller is fixedly connected to the outer wall of one side of the water storage tank (3), and the controller is respectively connected with the atomizing pump (25), the air supply fan (13), the liquid level sensor and the electromagnetic valve (24) through data lines.
CN201921980670.9U 2019-11-17 2019-11-17 Building construction dust device Expired - Fee Related CN211025607U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921980670.9U CN211025607U (en) 2019-11-17 2019-11-17 Building construction dust device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921980670.9U CN211025607U (en) 2019-11-17 2019-11-17 Building construction dust device

Publications (1)

Publication Number Publication Date
CN211025607U true CN211025607U (en) 2020-07-17

Family

ID=71568788

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921980670.9U Expired - Fee Related CN211025607U (en) 2019-11-17 2019-11-17 Building construction dust device

Country Status (1)

Country Link
CN (1) CN211025607U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113842736A (en) * 2021-11-16 2021-12-28 泰利建设集团有限公司 Dust settling method for green building construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113842736A (en) * 2021-11-16 2021-12-28 泰利建设集团有限公司 Dust settling method for green building construction

Similar Documents

Publication Publication Date Title
WO2018049588A1 (en) Arm type watering cart for gardens
CN107469537A (en) It is a kind of to build special cleaner
CN211025607U (en) Building construction dust device
CN108867499B (en) Dust fall watering lorry is used in municipal construction
CN208660681U (en) A kind of building site slag-soil truck Dust Improvement device
CN210699320U (en) Dust collecting equipment for building construction site is built in room
CN110359399A (en) A kind of construction site device for reducing dust
CN211513961U (en) Dustproof sprinkler that uses of construction
CN107881963A (en) A kind of construction site dust arrester
CN206668312U (en) Tunnel dust arrester
CN210977569U (en) Open-cast mining dust collecting equipment
CN210613200U (en) Watering dust collector for building engineering
CN114016458A (en) Portable dust device that highway engineering construction used
CN213492699U (en) Building construction dust collector
CN210482161U (en) Building construction ground dust collecting equipment
CN109260865A (en) A kind of construction device for reducing dust
CN219149640U (en) Indoor automatic dust removal sprinkler of green building
CN212309173U (en) Building engineering construction dust collector
CN215692877U (en) Subway construction dust collector
CN219149648U (en) Spray dust collector convenient to move
CN213433663U (en) Construction raise dust administers device
CN212701074U (en) Dust collector for coal mining
CN214416739U (en) High-flow water mist injection device for tracked vehicle
CN216856147U (en) Dust device is used in municipal works construction
CN213574726U (en) Fan for coal mine with filtering function

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210611

Address after: 242000 No.14, building D, Zhenxing East Street, Wuxing Township, Xuanzhou District, Xuancheng City, Anhui Province

Patentee after: Anhui Zhongqiang Construction Engineering Co.,Ltd.

Address before: 512000 f1011, 1st floor, R & D office building, guanshao innovation and innovation equipment center, Huake City, 42 Baiwang Road, Wujiang District, Shaoguan City, Guangdong Province

Patentee before: Shaoguan Xidian Information Technology Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200717

Termination date: 20211117