CN210973976U - Coal mine water conveying device - Google Patents
Coal mine water conveying device Download PDFInfo
- Publication number
- CN210973976U CN210973976U CN201921511083.5U CN201921511083U CN210973976U CN 210973976 U CN210973976 U CN 210973976U CN 201921511083 U CN201921511083 U CN 201921511083U CN 210973976 U CN210973976 U CN 210973976U
- Authority
- CN
- China
- Prior art keywords
- purifying cylinder
- water
- coal mine
- drainage
- water filtering
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Water Treatment By Sorption (AREA)
Abstract
The utility model discloses a colliery water conveyor, including first drainage purifying cylinder and second drainage purifying cylinder, install the circulating pipe between first drainage purifying cylinder and the second drainage purifying cylinder, install the flange board on the top of circulating pipe between first drainage purifying cylinder and the second drainage purifying cylinder, the water pump is installed to the one end of inlet tube, the drain pipe is installed to one side of second drainage purifying cylinder, the inboard at braced frame is installed to first drainage purifying cylinder and second drainage purifying cylinder, the supporting leg is installed to braced frame's below, the support base is installed to the one end of supporting leg. The utility model discloses install first drainage purifying cylinder and second drainage purifying cylinder, and connect through the circulating pipe between first drainage purifying cylinder and the second drainage purifying cylinder, can carry out purification treatment to the coal mine water through first drainage purifying cylinder and the circulation filtration of mutually supporting of second drainage purifying cylinder.
Description
Technical Field
The utility model relates to a colliery water conveyor field specifically is a colliery water conveyor.
Background
The coal mine water conveying device is used for conveying coal mine water, the coal mine water is waste water generated in the coal mine collecting process, acid water containing free sulfuric acid is contained in a coal mine, the acid water of the coal mine has a corrosion effect on rails, drain pipes and various metal equipment, generally adopted measures are to neutralize the water by using quick lime, and ceramic, stainless steel, acid-resistant bronze or plastic drainage equipment and the like are used, the coal mine is an area where people mine coal resources in a coal-rich mining area and is generally divided into a mineworker coal mine and an opencast coal mine, when a coal layer is far away from the ground surface, a roadway is generally dug underground, the coal mine is a mineworker coal mine, when the coal layer is close to the ground surface, a surface soil layer is generally selected to be directly stripped to dig the coal, the opencast coal mine is an opencast coal mine, most of China belongs to the mineworker coal mine, the coal mine comprises the ground and related large areas, coal mines are reasonable spaces excavated by humans when excavating geological formations rich in coal and generally include roadways, wells, and mining surfaces, among others.
The coal mine water conveying device at the present stage has various defects, such as poor treatment effect, inconvenient use, complex structure, inconvenient installation and disassembly and unstable fixation.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a colliery water conveyor to the treatment effect who solves among the prior art is poor, uses inconveniently, and the structure is complicated, and the installation is dismantled inconveniently, and fixed unstable problem inadequately.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a coal mine water conveyor, includes first drainage purifying cylinder and second drainage purifying cylinder, install the circulating pipe between first drainage purifying cylinder and the second drainage purifying cylinder, the flange board is all installed on the top of installing the circulating pipe between first drainage purifying cylinder and the second drainage purifying cylinder, the inlet tube is installed at the top of flange board, the shunt tubes is installed to one side of inlet tube, the water pump is installed to the one end of inlet tube, the drain pipe is installed to one side of second drainage purifying cylinder, the inboard at braced frame is installed to first drainage purifying cylinder and second drainage purifying cylinder, the supporting leg is installed to braced frame's below, the support base is installed to the one end of supporting leg.
Preferably, a return pipe is installed on one side of the drain pipe, and a control valve is installed on the return pipe.
Preferably, a connecting seat is installed between the supporting bases and is connected with the supporting bases in a welding mode.
Preferably, the shunt tube is arranged between the water inlet tube and the second water filtering and purifying cylinder.
Preferably, the first water filtration and purification cylinder and the second water filtration and purification cylinder are internally provided with activated carbon adsorption rods.
Preferably, the connecting seats are provided with two, and the two connecting seats are correspondingly installed at the bottoms of the first water filtering and purifying cylinder and the second water filtering and purifying cylinder respectively.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses install first drainage purifying cylinder and second drainage purifying cylinder, and connect through the circulating pipe between first drainage purifying cylinder and the second drainage purifying cylinder, through first drainage purifying cylinder and second drainage purifying cylinder mutually support circulation filtration can carry out purification treatment to the colliery water, and first drainage purifying cylinder and second drainage purifying cylinder all install on braced frame, install the supporting leg in braced frame's below, install the support base in the one end of supporting leg, make it more stable to first drainage purifying cylinder and second drainage purifying cylinder, and the device sets up comparatively simply, conveniently carry and transport.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a top view of the present invention.
Fig. 3 is a top view of the support frame of the present invention.
In the figure: 1. a water pump; 2. a water inlet pipe; 3. a flange plate; 4. a first water filtration purification cartridge; 5. An activated carbon adsorption rod; 6. a circulation pipe; 7. a shunt tube; 8. a second water filtration purification cylinder; 9. a drain pipe; 10. a support frame; 11. supporting legs; 12. a connecting seat; 13. a support base; 14. A control valve; 15. a return pipe.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1 to 3, in the embodiment of the present invention, a coal mine water conveying device comprises a first water filtering and purifying cylinder 4 and a second water filtering and purifying cylinder 8, a circulating pipe 6 is installed between the first water filtering and purifying cylinder 4 and the second water filtering and purifying cylinder 8, the circulating pipe 6 enables coal mine water to circulate between the first water filtering and purifying cylinder 4 and the second water filtering and purifying cylinder 8, a flange plate 3 is installed on the top end of the circulating pipe 6 installed between the first water filtering and purifying cylinder 4 and the second water filtering and purifying cylinder 8, a water inlet pipe 2 is installed on the top of the flange plate 3, the water inlet pipe 2 and a shunt pipe 7 are used for respectively conveying coal mine water into the first water filtering and purifying cylinder 4 and the second water filtering and purifying cylinder 8, a shunt pipe 7 is installed on one side of the water inlet pipe 2, the shunt pipe 7 is installed between the water inlet pipe 2 and the second water filtering and purifying cylinder 8, an activated carbon adsorption rod 5 is installed inside the first, activated carbon adsorption stick 5 is used for adsorbing and filtering the impurity in the coal mine water, water pump 1 is installed to the one end of inlet tube 2, water pump 1 is used for the suction coal mine water, drain pipe 9 is installed to one side of second drainage purifying cylinder 8, back flow 15 is installed to one side of drain pipe 9, back flow 15 can flow back to repeated filtration in the second drainage purifying cylinder 8, install control valve 14 on the back flow 15, the inboard at braced frame 10 is installed to first drainage purifying cylinder 4 and second drainage purifying cylinder 8, braced frame 10 is used for supporting first drainage purifying cylinder 4 and second drainage purifying cylinder 8, braced frame 10's below is installed supporting leg 11, supporting base 13 is installed to the one end of supporting leg 11, install connecting seat 12 between the supporting base 13, and connecting seat 12 and supporting base 13 welded connection, connecting seat 12 is provided with two altogether, two connecting seats 12 correspond safe drainage purifying cylinder 4 and second drainage purifying cylinder 8's bottom respectively with first drainage purifying cylinder 4 and second drainage purifying cylinder 8 and strain water and filter And (6) assembling.
The utility model discloses a theory of operation is: this equipment is when using, carry the coal mine water to first drainage purification section of thick bamboo 4 in by inlet tube 2 through 1 effect of water pump, shunt simultaneously through shunt tubes 7 in to second drainage purification section of thick bamboo 8, activated carbon adsorption stick 5 in through first drainage purification section of thick bamboo 4 and the second drainage purification section of thick bamboo 8 carries out purification treatment to the waste residue in the coal mine water, and the coal mine water after will filtering purification through drain pipe 9 is discharged, and open control valve 14 can control part coal mine water and flow back to second drainage purification section of thick bamboo 8 in, carry out repeated filtration.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Claims (6)
1. A coal mine water conveying device comprises a first water filtering and purifying cylinder (4) and a second water filtering and purifying cylinder (8), and is characterized in that a circulating pipe (6) is installed between the first water filtering and purifying cylinder (4) and the second water filtering and purifying cylinder (8), a flange plate (3) is installed at the top end of the circulating pipe (6) installed between the first water filtering and purifying cylinder (4) and the second water filtering and purifying cylinder (8), a water inlet pipe (2) is installed at the top of the flange plate (3), a flow dividing pipe (7) is installed at one side of the water inlet pipe (2), a water pump (1) is installed at one end of the water inlet pipe (2), a water outlet pipe (9) is installed at one side of the second water filtering and purifying cylinder (8), the first water filtering and purifying cylinder (4) and the second water filtering and purifying cylinder (8) are installed at the inner side of a supporting frame (10), and supporting legs (11) are installed below the supporting, and a support base (13) is installed at one end of the support leg (11).
2. A coal mine water delivery apparatus as claimed in claim 1, wherein: a return pipe (15) is installed on one side of the drain pipe (9), and a control valve (14) is installed on the return pipe (15).
3. A coal mine water delivery apparatus as claimed in claim 1, wherein: and connecting seats (12) are arranged between the supporting bases (13), and the connecting seats (12) are connected with the supporting bases (13) in a welding manner.
4. A coal mine water delivery apparatus as claimed in claim 1, wherein: the shunt pipe (7) is arranged between the water inlet pipe (2) and the second water filtering and purifying cylinder (8).
5. A coal mine water delivery apparatus as claimed in claim 1, wherein: and the first water filtering and purifying cylinder (4) and the second water filtering and purifying cylinder (8) are internally provided with activated carbon adsorption rods (5).
6. A coal mine water delivery apparatus as claimed in claim 3, wherein: the connecting seats (12) are provided with two connecting seats, and the two connecting seats (12) are correspondingly installed at the bottoms of the first water filtering and purifying cylinder (4) and the second water filtering and purifying cylinder (8) respectively.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921511083.5U CN210973976U (en) | 2019-09-11 | 2019-09-11 | Coal mine water conveying device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921511083.5U CN210973976U (en) | 2019-09-11 | 2019-09-11 | Coal mine water conveying device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210973976U true CN210973976U (en) | 2020-07-10 |
Family
ID=71457623
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921511083.5U Expired - Fee Related CN210973976U (en) | 2019-09-11 | 2019-09-11 | Coal mine water conveying device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210973976U (en) |
-
2019
- 2019-09-11 CN CN201921511083.5U patent/CN210973976U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108314106B (en) | DNAPL (deoxyribonucleic acid-styrene-acrylonitrile copolymer) polluted underground water in-situ remediation method | |
CN110451685A (en) | Combined restoration system and method for removing organic pollution in underground water in mine | |
CN103979676B (en) | Polluted-water is administered and is repaired with suspension lifting formula aeration and biological membrane filtration system and construction process thereof | |
CN210973976U (en) | Coal mine water conveying device | |
CN203715402U (en) | Integrated water purifier | |
CN210766987U (en) | Green plant watering and water storage system for mine environment restoration | |
CN210012715U (en) | Vortex solidification groundwater repair system | |
CN208965621U (en) | A kind of dredging device for water conservancy projects | |
CN102886356B (en) | Pre-decontamination channel of nuclear biochemical pollution decontamination trailer | |
CN206355686U (en) | A kind of superpower purifier | |
CN210105905U (en) | Coal mine safety ventilation dust collector | |
CN209143884U (en) | A kind of groundwater extraction prosthetic device | |
CN113461080A (en) | System and method for purifying water resources by utilizing collapse column under coal mine in karst mining area | |
CN213314091U (en) | Air filtering device for coal mining | |
CN214936523U (en) | Coal mine underground purified water collecting and recycling system | |
CN213513209U (en) | Natural gas production pipeline hydrops recovery unit | |
CN214035779U (en) | Water pumping device with anti-blocking function for coal mining | |
CN208039442U (en) | Roof rainwater collection treatment for reuse equipment with phosphorus removal functional | |
CN210917525U (en) | Water conservancy construction sediment removal device | |
CN213112860U (en) | Oil field sewage treatment tank | |
CN113431066B (en) | Super pressure-suction combined vacuum dewatering system for deep foundation pit and construction method thereof | |
CN110513056A (en) | Operation field environmental protection cofferdam | |
CN215798865U (en) | Sewage purification device for coal mine processing | |
CN219064985U (en) | River course waste water sampling equipment for waste water detection | |
CN218862954U (en) | Filtering anti-blocking device of adjustable submersible pump |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200710 Termination date: 20210911 |