CN210947401U CN201921865745.9U CN201921865745U CN210947401U CN 210947401 U CN210947401 U CN 210947401U CN 201921865745 U CN201921865745 U CN 201921865745U CN 210947401 U CN210947401 U CN 210947401U
Authority
CN
China
Prior art keywords
water supply
joint
prefabricated wall
supply pipeline
wall body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921865745.9U
Other languages
Chinese (zh)
Inventor
韩上海
陈建
李皓
李慕然
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Shanshui Huitong Technology Development Co ltd
Original Assignee
Hangzhou Shanshui Huitong Technology Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Shanshui Huitong Technology Development Co ltd filed Critical Hangzhou Shanshui Huitong Technology Development Co ltd
Priority to CN201921865745.9U priority Critical patent/CN210947401U/en
Application granted granted Critical
Publication of CN210947401U publication Critical patent/CN210947401U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Domestic Plumbing Installations (AREA)

Abstract

The utility model discloses an assembled water supply pipeline structure of a prefabricated wall body, which comprises a wall body frame, a plurality of filling bodies and a water supply device; the plurality of filling bodies are arranged in the accommodating groove at intervals; the water supply device comprises a water supply distributor and a water supply pipeline assembly which is connected with the water supply distributor and bridged on the plurality of filling bodies, and the water supply pipeline assembly is provided with a plurality of joint structures; still including setting up on wall body frame and supporting the locating component who presses a plurality of joint designs and water supply pipe assembly, locating component and a plurality of joint design difference fixed connection adopt this technical scheme, play the installation positioning action to the pre-buried pipe joint in prefabricated wall body through locating component, prevent to cause aversion, adverse effect such as subsidence to pipeline and joint design when pre-buried pouring concrete, guarantee that the mounted position is accurate, structural stability is good, makes the construction operation become swiftly convenient, not only safe and reliable but also can reduce cost.

Description

Prefabricated wall's assembled water supply pipe structure
Technical Field
The utility model relates to a building technical field, concretely relates to prefabricated wall's assembled water supply line structure.
Background
In the traditional wall structure building construction, a reinforced concrete frame system or a steel structure frame system is usually built by concrete, and pipelines and exterior decorative surfaces are laid after the building is finished, so that the process is complicated. With the development of building industrialization, the existing building adopts a module building, a reinforced concrete plate type member for building assembly, referred to as a prefabricated wallboard for short, is usually processed and manufactured in a prefabrication factory or a construction site, each prefabricated wallboard is transported to a construction site and connected through a fixing piece to complete the construction of a wall body structure, the installation process is simple, and the assembly efficiency is high.
After the template of the prefabricated wall board is constructed, various pipelines are usually laid on the prefabricated wall board corresponding to positions of a shower room, a washbasin, a closestool, a dish washing tank, a washing machine and the like according to building design requirements, and finally when the prefabricated wall board is poured, the pipelines are directly poured and fixed on the prefabricated wall board in a concrete pouring mode, so that the pipelines and the prefabricated wall body are connected into a whole, and the prefabricated wall board is only required to be lifted to a preset building position for installation. However, in actual production manufacturing the following often occur: when the concrete is poured on the prefabricated wall plate for construction, adverse effects such as displacement, settlement and even damage are easily caused to the joint part of the pipeline, so that a user in the later period needs to make a hole again and open a groove for adjustment, the wall plate structure is damaged, potential safety hazards are caused, and the cost is increased.
SUMMERY OF THE UTILITY MODEL
Therefore, the to-be-solved technical problem of the utility model lies in overcoming prefabricated wallboard among the prior art and easily causing harmful effects such as aversion, subsidence to pipe joint when the construction concretes to the later stage user still needs to make a hole again and opens in a wretched state and adjusts, has both destroyed the wallboard structure, the problem of incremental cost again.
In order to solve the technical problem, the utility model provides an assembled water supply pipe structure of prefabricated wall body, include: the wall body frame is enclosed to form an accommodating groove, and a bottom plate is covered at the bottom of the accommodating groove in a sealing manner;
the plurality of filling bodies are arranged in the accommodating groove at intervals;
the water supply device comprises a water supply distributor arranged on the filling body and a water supply pipeline assembly connected with the water supply distributor and bridged on the filling bodies, wherein the water supply pipeline assembly is provided with a plurality of joint structures used for connecting water using equipment;
and the positioning assembly is arranged on the wall body frame and abuts against the plurality of joint structures and the water supply pipeline assembly, and the positioning assembly is fixedly connected with the plurality of joint structures respectively.
As a preferred scheme, the positioning assembly comprises a plurality of angle steel parts which are arranged on side frames at two sides of the wall frame corresponding to the joint structure fixing frame, and the angle steel parts are sequentially connected into an integral structure.
As an optimized scheme, the joint structure is bent towards the direction of the top of the containing groove is convex, a notch through which the joint structure part can pass is formed on the angle steel part, and a fixing structure for keeping the angle steel part and the joint structure fixedly connected is arranged between the joint structures.
As a preferred scheme, fixed knot constructs including setting up a plurality of installation bosss on the joint design lateral wall are established with the cover fixed steel sheet on the joint design, and pass fixed steel sheet's through-hole is fixed in screw spare on the installation boss.
As a preferred scheme, fixed knot constructs still including setting up angle steel part bottom and with the installation face of fixed steel sheet laminating, and correspond the shaping and be in the installation face with connecting hole on the fixed steel sheet, and pass the connecting hole pair the fixed plate with the fastening components of fastening power is applyed to the installation face, the notch setting is in it is flat.
As a preferable scheme, the wall frame is a square structure formed by four channel steels.
As a preferable scheme, the plurality of filling bodies are arranged in the accommodating groove in a rectangular array, and a plurality of reinforcing steel bar grooves which are intersected in the transverse direction and the vertical direction are formed.
As a preferable scheme, a plurality of rib columns and rib beams composed of steel bars are arranged in the plurality of steel bar grooves, and the rib columns, the rib beams and the filling bodies are covered by filling a cast concrete structure in the accommodating grooves.
Preferably, the filling body is made of a lightweight building material.
As a preferred scheme, be equipped with a plurality of connection ports on the water distributor, water supply pipe assembly is including connecting a plurality of connection ports's many water pipes, the water pipe is kept away from connection ports's one end is equipped with joint design.
Compared with the prior art, the technical scheme of the utility model have following advantage:
1. the utility model provides an assembled water supply pipeline structure of prefabricated wall body, according to the requirement of various water equipment in the building design, the water supply pipeline component that connects out from the water distributor should correspond and extend to water equipment position, so that the follow-up joint design and water equipment realize accurate and reliable connection, joint design and water supply pipeline component are pressed on a plurality of filling bodies through the positioning component, the filling bodies can play the installation supporting role, and the positioning component is fixedly connected with the joint design, the advantage of the design lies in that the positioning component limits the installation position of the joint design, plays the installation positioning role to the pipeline joint pre-buried in the prefabricated wall body, prevents the pipeline and the joint design thereof from causing adverse effects such as displacement, settlement and the like when the concrete is pre-buried and poured, also can avoid reducing the displacement or even the disjointing of the water supply pipeline component, the accurate correspondence of the position between the joint design after the embedding and the water consumption equipment is ensured, the structure stability of the prefabricated wall body is good, the construction operation is enabled to be rapid and convenient, and the prefabricated wall body is safe and reliable and can reduce the cost.
2. The utility model provides an assembled water supply pipe structure of prefabricated wall body, locating component establishes a plurality of angle steel parts on the side bearer of wall frame both sides by the mount and constitutes, be a body structural connection according to a plurality of angle steel parts, as long as aim at the joint design of predetermineeing the position fix to wall frame on can, simplify the installation procedure, simple to operate is swift, thereby can lean on a plurality of joint designs to push down, and correspond fixed connection respectively through a plurality of angle steel parts and a plurality of joint designs, all can play the location installation effect to a plurality of joint designs, guarantee the installation stability of joint design when concreting, be favorable to improving the efficiency of construction.
3. The utility model provides an assembled water supply line structure of prefabricated wall body, when installation angle steel part and joint design, earlier reliably fix fixed steel sheet on the joint design through the screw spare, be connected with the help of the installation face cooperation of fixed steel sheet and angle steel part, then pass the installation face through fastening components and realize fastening connection with fixed steel sheet angle steel part behind the connecting hole of fixed steel sheet, use as the connecting piece between angle steel part and the joint design according to fixed steel sheet, the large and atress stability of installation area, construction operation is comparatively convenient, thereby realize the fixed mounting of angle steel part and joint design, guarantee the mounted position reliable and stable of joint design.
4. The utility model provides an assembled water supply pipe structure of prefabricated wall body, the obturator is made by light building material, has reliable structural strength after becoming an organic whole with concrete pouring, and structural stability is good, alleviates the weight of prefabricated wall body greatly, not only environmental protection but also greatly reduced cost.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the embodiments or the technical solutions in the prior art will be briefly described below.
FIG. 1 is a schematic structural view of an assembled water supply pipeline structure of a prefabricated wall body according to the present invention;
FIG. 2 is a schematic cross-sectional view of the prefabricated wall shown in FIG. 1;
fig. 3 is a schematic view of an installation structure of the angle steel member and the joint structure of the present invention;
fig. 4 is a schematic view of the installation plane of the multi-surface prefabricated wall body of the utility model;
fig. 5 is a schematic diagram of the distribution of water pipes in the prefabricated wall body according to the present invention;
description of reference numerals: 1-wall frame, 11-accommodating groove, 12-reinforcing groove, 13-channel steel, 2-bottom plate, 3-filling body, 4-water distributor, 41-connecting port, 5-water supply pipeline component, 51-water pipe, 6-joint structure, 61-mounting boss, 62-fixing steel plate, 63-screw piece, 7-positioning component, 71-angle steel component, 711-mounting plate surface and 8-fastening component.
Detailed Description
The technical solution of the present invention will be described clearly and completely with reference to the accompanying drawings, and obviously, the described embodiments are some, but not all embodiments of the present invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "first", "second" and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Example 1
The present embodiment provides an assembled water supply pipe structure of prefabricated wall body as shown in fig. 1 to 5, including: a wall body frame 1 with a containing groove 11 is enclosed, a bottom plate 2 is sealed at the bottom of the containing groove 11, and the bottom plate is detachable;
a plurality of filling bodies 3 arranged in the accommodating groove 11 at intervals;
the water supply device comprises a water supply distributor 4 arranged on the filling body 3 and a water supply pipeline assembly 5 connected with the water supply distributor 4 and bridged on a plurality of filling bodies, wherein the water supply pipeline assembly 5 is provided with a plurality of joint structures 6 used for connecting water using equipment;
and the positioning component 7 is detachably arranged on the wall body frame 1 and abuts against the plurality of joint structures 6 and the water supply pipeline component, and the positioning component 7 is fixedly connected with the plurality of joint structures 6 respectively.
The above embodiment is a core technical solution of this embodiment, according to requirements of various water-consuming apparatuses in a building design, the water supply pipe assembly 5 connected from the water supply distributor 4 is to correspondingly extend to positions of the water-consuming apparatuses, such as positions of a water heater, a washbasin, a toilet, a dish washing tank, a washing machine, etc., so as to facilitate accurate and reliable connection between the joint structure 6 and the water-consuming apparatuses, the joint structure 6 and the water supply pipe assembly are pressed against a plurality of filling bodies 3 through the positioning assembly 7, the filling bodies can play a role in mounting and supporting, and the positioning assembly 7 is fixedly connected with the joint structure 6, so that the positioning assembly 7 defines a mounting position of the joint structure 6, and plays a role in mounting and positioning the joint structure pre-embedded in a prefabricated wall body, thereby preventing displacement of the pipe and the joint structure thereof caused by pouring concrete, The adverse effects such as settlement can also be avoided reducing the aversion to the water supply pipe assembly and even disjointing, guarantee that the joint design 6 after pre-burying corresponds with the position accuracy between the water equipment, the structural stability of this kind of prefabricated wall body is good, makes the construction operation become swift convenient, not only safe and reliable but also can reduce construction cost.
The specific arrangement of the positioning assembly is described in detail below with reference to fig. 1-3:
positioning assembly 7 is including corresponding a plurality of the 6 mounts of joint design are established a plurality of angle steel parts 71 on the side frame of wall frame 1 both sides, these angle steel parts adopt the bolt mode to fix on wall frame 1, according to a plurality of angle steel parts 71 links up an organic whole structure mutually in proper order, during the installation, as long as aim at the joint design of predetermineeing the position fix to wall frame 1 is last can, thereby it is a plurality of joint design 6 and water supply pipeline subassembly and water distributor can lean on to push down, simplify the installation procedure, and simple to operate is swift to correspond fixed connection respectively through a plurality of angle steel parts 71 and a plurality of joint design 6, can all play the location installation effect to a plurality of joint designs 6, guarantee joint design 6's installation stability when concreting is favorable to improving the efficiency of construction.
In this embodiment, as shown in fig. 1, wall frame 1 is enclosed into square structure by four channel-section steels 13, storage tank 11 corresponds to square groove structure, and four channel-section steels 13 are in concrete pouring is accomplished to prefabricated wall body and is solidified the back removable unloading, and the pouring height of concrete is the roughly parallel and level with the storage tank, joint design 6 one end court storage tank 11 top direction is protruding, the shaping has the confession on the angle steel part 71 the fluting (not shown in the figure) that joint design 6 part passed can make joint design 6 one end after the pouring expose prefabricated wall body surface like this, and it exposes highly not higher than 2cm, makes things convenient for like this to be connected and wall decoration with the water equipment.
In order to ensure that the mounting position of the joint structure 6 is accurate, a fixing structure for holding the angle iron member 71 and the joint structure 6 in fixed connection is provided between the angle iron member 71 and the joint structure 6. As a preferred embodiment, the fixing structure includes a plurality of mounting bosses 61 disposed on the side wall of the joint structure 6, and a fixing steel plate 62 sleeved on the joint structure 6, and a screw member 63 passing through the through hole of the fixing steel plate 62 and fixed on the mounting boss 61, the mounting boss is correspondingly provided with a threaded hole, the fixing steel plate and the joint structure are reliably fixed together by the screw member, further, the fixing structure further includes a mounting plate 711 disposed at the bottom of the angle iron component 71 and attached to the fixing steel plate 62, and a connecting hole correspondingly formed in the mounting plate 711 and the fixing steel plate 62, and a fastening assembly 8 passing through the connecting hole to apply fastening force to the fixing steel plate 62 and the mounting plate 711, the fastening assembly 8 is a bolt assembly, the notch is disposed on the mounting plate 711, the fixing steel plate 62 is also correspondingly provided with an opening through which a part of the joint component can pass, and according to the structure, when the angle steel component 71 and the joint structure 6 are installed, the fixing steel plate 62 can be fixed to the joint structure 6 through a screw, the fixing steel plate is connected with the installation plate surface of the angle steel component in a matched mode, then the angle steel component 71 and the fixing steel plate 62 are fastened and connected after passing through the connecting hole of the installation plate surface 711 and the fixing steel plate 62 through the fastening assembly 8, according to the fact that the fixing steel plate 62 is used as a connecting piece between the angle steel component 71 and the joint structure 6, the installation area is increased, stress is stable, construction operation is convenient, accordingly, fixed installation of the angle steel component and the joint structure is achieved, and stable and reliable installation positions of the joint structure 6.
In this embodiment, referring to fig. 1, a plurality of the filling bodies 3 are arranged in the accommodating groove 11 in a rectangular array, and a plurality of reinforcing steel bar grooves 12 intersecting in a horizontal direction and a vertical direction are formed, a plurality of ribbed columns and ribbed beams composed of reinforcing steel bars are arranged in the plurality of reinforcing steel bar grooves 12, and the accommodating groove 11 is filled with a poured concrete structure to cover the ribbed columns, the ribbed beams and the filling bodies, so that a reinforced concrete structure can be formed in the prefabricated wall, and the usage amount of concrete is effectively reduced while ensuring sufficient load bearing capacity of the prefabricated wall.
Preferably, the filling body 3 is made of a light building material, has reliable structural strength after being poured with concrete into a whole, has good structural stability, greatly reduces the weight of the prefabricated wall body, is environment-friendly and can greatly reduce the cost. The light building material can be selected from common light composite materials on the market, and has various styles, for example, the composite material is mainly made of foamed polyphenyl particles or gypsum materials or alkali-resistant glass fibers and other base materials, and other equivalent embodiments are not described in detail.
The manner in which the feed water distributor and feed water pipe assembly are arranged is described in detail below with reference to FIGS. 3-5:
tap water pipe systems in building design use water distributors to centrally manage and distribute tap water pipes, the water supply distributor 4 is provided with a plurality of connecting ports 41, the water supply pipe assembly 5 comprises a plurality of water pipes 51 connected with the plurality of connecting ports 41, that is, after the tap water pipe is connected to the water distributor from the water meter, all the water pipes 51 are branched from the water distributor, so as to extend to each water using area of a kitchen, a toilet, a balcony, etc., the end of the water pipe 51 far away from the connection port 41 is provided with the joint structure 6, and is connected with water using equipment through the joint structure, the position of the water utilization equipment in the building design is designed, and the prefabricated wall body is lifted to a preset installation position for use, so that a kitchen or a toilet and the like can be conveniently assembled, and the assembly is convenient and rapid. In order to better understand the installation and use of the water supply device in the prefabricated wall, a bathroom composed of a plurality of prefabricated walls will be exemplified below with reference to fig. 4-5, a represents a prefabricated wall, a shower room 01, a washbasin 02, a toilet 03, a water heater, etc. arranged in the bathroom are all connected with the water pipe 51, the positions of a plurality of joint structures arranged in the prefabricated wall are different according to the installation position of water-consuming equipment, or the joint structures are arranged high or low, the installation height of the joint structures is set according to relevant building design standards, as can be seen from fig. 5, a plurality of the water pipes 51 comprise a water inlet pipeline 511 connected with a tap water pipe and a toilet pipeline 512 connected with the toilet, a bathroom pipeline 513 connected with the bathroom, a cold water pipeline 514 connected with the water heater and a water circulation pipeline 515, and a faucet pipeline 516 connected with the washbasin, the pipelines are connected together in the water supply distributor 4 and finally connected to corresponding water utilization equipment through joint structures, so that the use requirements of various water utilization equipment can be well met, the design is reasonable, and the matching and installation are reliable. The specific arrangement of the water pipes can be selected by those skilled in the art according to the above description, and other equivalent manners are not described in detail herein.
It should be understood that the above examples are only for clarity of illustration and are not intended to limit the embodiments. Other variations and modifications will be apparent to persons skilled in the art in light of the above description. And are neither required nor exhaustive of all embodiments. And obvious variations or modifications can be made without departing from the scope of the invention.

Claims (10)

1. The utility model provides an assembled water supply pipe structure of prefabricated wall body which characterized in that includes:
the wall body frame (1) is enclosed to form a containing groove (11), and a bottom plate (2) is sealed at the bottom of the containing groove (11);
the filling bodies (3) are arranged in the accommodating groove (11) at intervals;
the water supply device comprises a water supply distributor (4) arranged on the filling body (3) and a water supply pipeline assembly (5) connected with the water supply distributor (4) and bridged on a plurality of filling bodies, wherein the water supply pipeline assembly is provided with a plurality of joint structures (6) used for connecting water using equipment;
the positioning assembly (7) is arranged on the wall body frame (1) and abuts against the plurality of joint structures (6) and the water supply pipeline assembly, and the positioning assembly (7) is fixedly connected with the plurality of joint structures (6) respectively.
2. The prefabricated wall assembled water supply pipeline structure of claim 1, wherein: the positioning assembly (7) comprises a plurality of angle steel parts (71) which correspond to a plurality of fixed frames of the joint structures (6) and are arranged on side frames on two sides of the wall body frame (1), and the angle steel parts (71) are sequentially connected into an integral structure.
3. The prefabricated wall assembled water supply pipeline structure of claim 2, wherein: joint design (6) one end dorsad obturator one side is protruding, the shaping has the confession on angle steel part (71) the grooving that joint design (6) part passed, and with be provided with between joint design (6) and keep angle steel part (71) with joint design (6) fixed connection's fixed knot constructs.
4. The prefabricated wall assembled water supply pipeline structure of claim 3, wherein: fixed knot constructs including setting up a plurality of installation base (61) on joint design (6) lateral wall, establish with the cover fixed steel sheet (62) on joint design (6), and pass the through-hole of fixed steel sheet (62) is fixed in screw spare (63) on installation base (61).
5. The prefabricated wall assembled water supply pipeline structure of claim 4, wherein: the fixed knot constructs still including setting up angle steel part (71) bottom and with installation face (711) of fixed steel sheet laminating, and correspond the shaping and be in installation face (711) with connecting hole on the fixed steel sheet (62), and pass the connecting hole pair fixed steel sheet (62) with fastening components (8) of fastening power are applyed to installation face (711), the fluting set up in installation face (711).
6. The prefabricated wall assembled water supply pipeline structure of claim 1, wherein: the wall frame (1) is in a square structure formed by four channel steels (13).
7. The prefabricated wall assembled water supply pipeline structure according to any one of claims 1 to 6, wherein: the plurality of filling bodies (3) are arranged in the accommodating groove (11) in a rectangular array, and a plurality of reinforcing steel bar grooves (12) which are intersected in the transverse direction and the vertical direction are formed.
8. The prefabricated wall assembled water supply pipeline structure of claim 7, wherein: and a plurality of rib columns and rib beams which are composed of steel bars are arranged in the plurality of steel bar grooves (12), and the accommodating grooves (11) are filled with a poured concrete structure to cover the rib columns, the rib beams and the filling bodies.
9. The prefabricated wall assembled water supply pipeline structure of claim 8, wherein: the filling body (3) is made of a lightweight building material.
10. The prefabricated wall assembled water supply pipeline structure of claim 1, wherein: be equipped with a plurality of connection port (41) on feedwater distributor (4), it is a plurality of including connecting to feed water pipe assembly (5) many water pipes (51) of connection port (41), water pipe (51) are kept away from the one end of connection port (41) is equipped with joint design (6).
CN201921865745.9U 2019-10-31 2019-10-31 Prefabricated wall's assembled water supply pipe structure Active CN210947401U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921865745.9U CN210947401U (en) 2019-10-31 2019-10-31 Prefabricated wall's assembled water supply pipe structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921865745.9U CN210947401U (en) 2019-10-31 2019-10-31 Prefabricated wall's assembled water supply pipe structure

Publications (1)

Publication Number Publication Date
CN210947401U true CN210947401U (en) 2020-07-07

Family

ID=71391678

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921865745.9U Active CN210947401U (en) 2019-10-31 2019-10-31 Prefabricated wall's assembled water supply pipe structure

Country Status (1)

Country Link
CN (1) CN210947401U (en)

Similar Documents

Publication Publication Date Title
CN201635388U (en) Unilateral supporting formwork system for cast-in-place concrete arc outer wall
CN102704712B (en) Integrated bathroom made of composite material and assembly method of integrated bathroom
CN212001800U (en) Connecting assembly and connecting structure of external wall panel
CN210947401U (en) Prefabricated wall's assembled water supply pipe structure
CN202324501U (en) Full clamping piece connecting member for mounting low carbon board on building outer brim
CN201128967Y (en) Cavity component with groove
CN207934066U (en) One kind exempting from vertical support overlapping piping lane device
CN209227594U (en) A kind of aluminum wood gang form applied to pipe gallery construction
CN207646855U (en) Prefabricated assembled light steel wallboard and prefabricated house building
CN211114816U (en) Anti-bank antiseep mould
CN215650754U (en) Waterproof chassis of whole bathroom
CN213683039U (en) Practice thrift ligneous assembled floor structure
CN213682833U (en) Precast concrete wallboard
CN209353689U (en) Modular system is hung for the area Jiang Ban that constructs
CN212248809U (en) Prefabricated formula side fascia of assembly type structure
CN112127590A (en) Practice thrift ligneous assembled floor structure
CN114809273B (en) Passive prefabricated steel structure building house and construction method thereof
CN114319774B (en) Assembled integrated quick-mounting ground and mounting method thereof
CN210061555U (en) Precast beam pedestal for precast building precast beam
CN214615016U (en) Prefabricated wall's assembled water supply pipe structure
CN215484309U (en) Steel construction assembly structure of modularization stone material finish wall
CN215367836U (en) Prefabricated stand board and building foundation connection structure
CN216921168U (en) Assembled integrated into one piece fast-assembling ground
CN211974441U (en) Reinforced structure of existing building floor
CN218643736U (en) Peripheral dado of steel construction

Legal Events