CN210887596U - Cement beam curing room - Google Patents

Cement beam curing room Download PDF

Info

Publication number
CN210887596U
CN210887596U CN201921421358.6U CN201921421358U CN210887596U CN 210887596 U CN210887596 U CN 210887596U CN 201921421358 U CN201921421358 U CN 201921421358U CN 210887596 U CN210887596 U CN 210887596U
Authority
CN
China
Prior art keywords
house
cement
ground
curing room
house body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921421358.6U
Other languages
Chinese (zh)
Inventor
刘福祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201921421358.6U priority Critical patent/CN210887596U/en
Application granted granted Critical
Publication of CN210887596U publication Critical patent/CN210887596U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model provides a cement roof beam curing room which relates to cement roof beam makes technical field, characterized by: comprises a maintenance system and a plurality of house bodies; the house comprises a plurality of houses, a plurality of guide posts and a plurality of springs, wherein the houses are sequentially communicated along the length direction of the houses, four corner ends of the bottom of each house are fixedly connected with the ground through a damping device, each damping device comprises a sliding block, a guide post and a spring, the bottom end of each guide post is correspondingly and fixedly connected with the ground, a sliding block is sleeved on a column body of each guide post, the top and the bottom of each column body of each guide post, which correspond to the sliding block, are provided with the springs, the top end of each guide post is provided with a compression nut for compressing the springs, and one; the outer sides of the two ends of the house body are respectively sleeved with a stopping cable which is correspondingly matched with the appearance of the house body, and the two ends of the stopping cable are correspondingly and fixedly connected with the ground through dampers; the utility model discloses effectively solved traditional curing room disposable cost height, the problem of resource-wasting.

Description

Cement beam curing room
Technical Field
The utility model belongs to the technical field of the cement roof beam manufacturing technology and specifically relates to a cement roof beam curing room is related to.
Background
As is known, the standard railway cement beam of China is 50 meters long, × meters wide, 2.7 meters wide, × meters high and 1.7 meters high, the production process flow is to adopt the steel mould to make on the spot, the cement beam is cured for 24 hours according to the temperature route from 15 ℃ -40 ℃ -60 ℃ after solidifying, can reach the strength, hardness requirement of the cement bridge, most of the traditional curing methods are connected and built into the frame by the steel tube on the spot, then the curing shed is formed by the shed cloth, the coal boiler burns steam, hot water for curing, after the country forbids using the coal boiler, the electric boiler is used for curing and burns steam, hot water for curing, the electric boiler not only has large investment once, but also has potential safety hazard, one cement beam is used for curing the space area of 450 square, 1 and 2 tons of electric boilers must be used for heating and curing, and 1 and 2 tons of electric boilers need to be equipped with a transformer, special lines, and the electricity is also charged for increasing capacity, the cost is expensive, the production is unfavorable, and the curing shed built by the steel tube has poor heat preservation effect, and;
chinese patent (publication number: CN 208126235U) discloses an automatic temperature control device and a curing shed; the device comprises a controller, a humidifier, a heater, a temperature sensor and a humidity sensor, wherein the humidifier is connected with the controller, the heater is connected with the controller, and the temperature sensor is connected with the controller and used for detecting a temperature signal of a box girder and feeding the temperature signal back to the controller; although the temperature monitoring degree of automation is high, and temperature control is accurate, this patent cost is higher, and later maintenance operation is complicated.
Disclosure of Invention
In order to overcome the not enough in the background art, the utility model discloses a cement roof beam curing room.
In order to achieve the purpose, the utility model adopts the following technical scheme:
a cement beam curing room comprises a curing system and a plurality of room bodies; the house comprises a plurality of houses, a plurality of guide posts and a plurality of springs, wherein the houses are sequentially communicated along the length direction of the houses, four corner ends of the bottom of each house are fixedly connected with the ground through a damping device, each damping device comprises a sliding block, a guide post and a spring, the bottom end of each guide post is correspondingly and fixedly connected with the ground, a sliding block is sleeved on a column body of each guide post, the top and the bottom of each column body of each guide post, which correspond to the sliding block, are provided with the springs, the top end of each guide post is provided with a compression nut for compressing the springs, and one; the outer sides of two ends of the house body are respectively sleeved with a stopping cable which is correspondingly matched with the appearance of the house body, two ends of each stopping cable are correspondingly and fixedly connected with the ground through dampers, and each edge of the house body, which corresponds to each stopping cable, is provided with a pulley for supporting the stopping cable; the maintenance system comprises a spraying device arranged inside the house body and a steam generating device arranged outside the house body; the spraying device comprises a plurality of arc pipes which are arranged in an array along the length direction of the house body, the opening width of each arc pipe is larger than the width of the cement beam body, a plurality of spray heads used for spraying steam to the surface of the cement beam body are arranged on the inner arc surfaces of the arc pipes at intervals, and the arc pipes are correspondingly connected with the top in the house body through a connecting frame; steam generator contains the gas heater and provides the water softener of soft water for the gas heater, the steam output of gas heater corresponds the intercommunication with every curved pipe respectively through the pipeline, and the curved pipe switch-on has the cooling water pipe that is used for temperature regulation.
Preferably, an air bag with the same length as the ground beam is arranged between the bottom surface of the ground beam and the ground.
Preferably, the connecting frame is correspondingly connected with the top in the house body through a vertically arranged telescopic device.
Preferably, the telescopic device is a cylinder or an electric telescopic cylinder.
Preferably, the bottom in the house body is provided with a water collecting tank for collecting the excessive water.
Preferably, the bottom in the house body is provided with a track for transporting the cement beam body.
Preferably, the outer ends of the two outermost rooms are provided with doors for the cement beam body to pass through.
Preferably, the house body is provided with a transparent window.
Preferably, the top and the lateral wall in the house body are provided with a plurality of temperature sensors for detecting the temperature of the cement beam body.
Preferably, the side wall plate and the top plate of the house body are both provided with heat-insulating interlayers.
Due to the adoption of the technical scheme, the utility model discloses following beneficial effect has:
the utility model discloses a cement beam curing room, simple structure, easy assembly, low production cost, the whole room body skeleton is formed by the bolt connection of the structural steel, the assembly, splicing, disassembly and transfer are very convenient, and can be repeatedly used, the use cost is effectively reduced, the use cost can be matched with a damping device through a stopping cable, the room body has good wind resistance, and the damage of the room body caused by severe weather such as strong wind during field operation is avoided; the bottom in the house body is provided with a water collecting tank for collecting excessive water, namely the excessive water sprayed by the spraying device and the excessive water which is not absorbed by the cement beam body can be collected through the water collecting tank, so that the collected water can be recycled after being purified, the purpose of avoiding water resource waste is achieved, and meanwhile, a certain amount of hot water can be contained in the water collecting tank to achieve the purpose of heating the bottom of the cement beam body; the roof portion and the lateral wall are equipped with a plurality of temperature sensor that are used for detecting cement roof beam body temperature in the room body, can be through the temperature sensor real-time detection cement roof beam body's temperature promptly to be in 15 ℃ -40 ℃ -60 ℃ of temperature process flow according to making the cement roof beam body maintain the cement roof beam body in proper order.
Drawings
FIG. 1 is a schematic view of the structure of a house body;
FIG. 2 is a diagram illustrating the usage of the present invention;
fig. 3 is a schematic structural view of the shock absorbing device.
In the figure: 1. a house body; 2. a slider; 3. a guide post; 4. a spring; 5. a compression nut; 6. a ground beam; 7. an air bag; 8. a stopper cable; 9. a damper; 10. an arc tube; 11. a cement beam body; 12. a spray head; 13. a connecting frame; 14. a steam generating device; 15. A pulley; 16. a door; 17. a transparent window; 18. a telescoping device; 19. a track.
Detailed Description
The invention will be explained in more detail by the following examples, which disclose the invention and are intended to protect all technical improvements within the scope of the invention.
With reference to the attached drawings 1-3, a cement beam curing house comprises a curing system and a plurality of house bodies 1; the house comprises a plurality of house bodies 1, wherein the house bodies 1 are sequentially communicated along the length direction of the house bodies 1, four corner ends of the bottom of each house body 1 are fixedly connected with the ground through a damping device, each damping device comprises a sliding block 2, a guide pillar 3 and a spring 4, the bottom end of each guide pillar 3 is correspondingly and fixedly connected with the ground, a column body of each guide pillar 3 is sleeved with the corresponding sliding block 2, the top and the bottom of each column body of each guide pillar 3, which correspond to the corresponding sliding block 2, are respectively provided with the spring 4, the top end of each guide pillar 3 is provided with a compression nut 5 for compressing the spring 4, and one side of each sliding block 2; according to the requirement, the air bag 7 with the same length as the ground beam 6 is arranged between the bottom surface of the ground beam 6 and the ground, namely the air bag 7 can be inflated and expanded when in use, so that the gap between the ground beam 6 and the ground is sealed through the air bag 7, on one hand, the air bag 7 can play a role in stably supporting the ground beam 6, the uneven stress of the ground beam 6 caused by uneven ground is avoided, on the other hand, the air bag 7 can play a good sealing role, and the moisture-proof effect is achieved; the outer sides of two ends of the house body 1 are respectively sleeved with a stopping rope 8 which is correspondingly matched with the appearance of the house body 1, two ends of each stopping rope 8 are correspondingly and fixedly connected with the ground through a damper 9, namely when the house body 1 swings due to strong wind, the dampers 9 can effectively counteract the swinging force and control the swing amplitude of the house body 1 to be minimum, so that the house body 1 is prevented from being damaged by the strong wind, and each edge of the house body 1 corresponding to the stopping rope 8 is provided with a pulley 15 for supporting the stopping rope 8, namely the stopping rope 8 can be matched with a damping device to enable the house body 1 to have good wind resistance, and the house body 1 is prevented from being damaged due to severe weather such as strong wind during field operation; in addition, the bottom in the house body 1 is provided with a track 19 for transporting the cement beam body 11, namely the cement beam body 11 can be transported through the track 19, so that the operation is convenient and fast; doors 16 convenient for the cement beam body 11 to pass through are arranged at the outer ends of the two outermost house bodies 1, namely the doors 16 can be closed to play a role in heat preservation in the process of maintaining the cement beam body 11, and the doors 16 can be opened after maintenance is finished, so that the cement beam body 11 can be transported out conveniently; the house body 1 is provided with a transparent window 17 which can provide sufficient illumination for the house body 1 in the daytime, so that an operator has good sight; the side wall plate and the top plate of the house body 1 are both provided with heat insulation interlayers, so that a good heat insulation effect can be achieved; the whole skeleton of the house body 1 is formed by connecting structural steel through bolts, so that the assembly, splicing, disassembly and transfer are very convenient, the use cost is effectively reduced, and the house can be repeatedly utilized;
the maintenance system comprises a spraying device arranged inside the house body 1 and a steam generating device 14 arranged outside the house body 1; the spraying device comprises a plurality of arc pipes 10 which are arranged in an array mode along the length direction of the house body 1, the opening width of each arc pipe 10 is larger than the width of the cement beam body 11, a plurality of spray heads 12 used for spraying steam to the surface of the cement beam body 11 are arranged on the inner arc surface of each arc pipe 10 at intervals, and each arc pipe 10 is correspondingly connected with the inner top of the house body 1 through a connecting frame 13; according to the requirement, the connecting frame 13 is correspondingly connected with the top in the house body 1 through a vertically arranged expansion device 18, the expansion device 18 is a cylinder or an electric expansion cylinder, namely, the spray device can be lifted upwards through the expansion device 18 in the process of transporting the cement beam body 11, so that the interference influence of the spray device on other equipment for transporting the cement beam body 11 is avoided; the steam generating device 14 comprises a gas heater and a water softening processor for providing soft water for the gas heater, the steam output end of the gas heater is correspondingly communicated with each arc-shaped pipe 10 through a pipeline respectively, the arc-shaped pipes 10 are communicated with a cooling water pipe for adjusting the temperature, namely cooling water can be introduced through the cooling water pipe, and the temperature of the steam water mist sprayed out of the spray head 12 is adjusted and controlled by controlling the flow of the cooling water; in addition, the bottom in the house body 1 is provided with a water collecting tank for collecting the excess water, namely, the excess water sprayed by the spraying device and the excess water which is not absorbed by the cement beam body 11 can be collected by the water collecting tank, so that the collected water can be recycled after being purified, the purpose of avoiding water resource waste is achieved, and meanwhile, a certain amount of hot water can be contained in the water collecting tank to achieve the purpose of heating the bottom of the cement beam body 11; the top and the lateral wall in the room body 1 are provided with a plurality of temperature sensors for detecting the temperature of the cement beam body 11, namely the temperature of the cement beam body 11 can be detected in real time through the temperature sensors, so that the cement beam body 11 can be maintained according to the process flow that the cement beam body 11 is sequentially at the temperature of 15-40-60 ℃.
When the cement beam curing house is implemented, the plurality of house bodies 1 are combined together according to the length of the cement beam body 11 when in use, the total length of the combined house bodies 1 is larger than the length of the cement beam body 11, the door 16 is opened, the spraying device is lifted upwards through the telescopic device 18, the interference influence of the spraying device on other equipment for conveying the cement beam body 11 is avoided, the cement beam body 11 is transferred to the house body 1 through the track 19, the door 16 is closed, the steam generating device 14 can be started to provide high-temperature steam for the spraying device, the arc-shaped pipe 10 of the spraying device is communicated with a cooling water pipe for adjusting the temperature, namely, cooling water can be introduced through the cooling water pipe, the temperature of the steam water mist sprayed out by the spray head 12 can be regulated and controlled by controlling the flow of the cooling water, so as to maintain the cement beam body 11 according to the process flow that the cement beam body 11 is sequentially at the temperature of 15-40-60 ℃.
The part of the utility model not detailed is prior art.

Claims (10)

1. The utility model provides a cement roof beam curing room which characterized by: comprises a maintenance system and a plurality of house bodies (1); the house comprises a plurality of house bodies (1), wherein the house bodies (1) are sequentially communicated along the length direction of the house bodies (1), four corner ends of the bottom of each house body (1) are fixedly connected with the ground through a damping device, each damping device comprises a sliding block (2), a guide pillar (3) and a spring (4), the bottom end of each guide pillar (3) is correspondingly and fixedly connected with the ground, a sliding block (2) is sleeved on a column body of each guide pillar (3), each spring (4) is arranged at the top and the bottom of each guide pillar (3) corresponding to the corresponding sliding block (2), a compression nut (5) for compressing the corresponding spring (4) is arranged at the top end of each guide pillar (3), and one side of each sliding block (2) is correspondingly and fixedly connected with the side wall of a ground; the outer sides of two ends of the house body (1) are respectively sleeved with a stopping cable (8) which is correspondingly matched with the appearance of the house body (1), two ends of each stopping cable (8) are correspondingly and fixedly connected with the ground through dampers (9), and each edge of the house body (1) corresponding to each stopping cable (8) is provided with a pulley (15) for supporting each stopping cable (8); the maintenance system comprises a spraying device arranged inside the house body (1) and a steam generating device (14) arranged outside the house body (1); the spraying device comprises a plurality of arc pipes (10) which are arranged in an array mode along the length direction of the house body (1), the opening width of each arc pipe (10) is larger than the width of the cement beam body (11), a plurality of spray heads (12) used for spraying steam to the surface of the cement beam body (11) are arranged on the inner arc surface of each arc pipe (10) at intervals, and each arc pipe (10) is correspondingly connected with the inner top of the house body (1) through a connecting frame (13); steam generation device (14) contain the gas heater and provide the water softener of soft water for the gas heater, the steam output of gas heater passes through the pipeline and corresponds the intercommunication with every curved pipe (10) respectively, and curved pipe (10) switch-on has the condenser tube that is used for temperature regulation.
2. A cement beam curing room as defined in claim 1, wherein: an air bag (7) with the same length as the ground beam (6) is arranged between the bottom surface of the ground beam (6) and the ground.
3. A cement beam curing room as defined in claim 1, wherein: the connecting frame (13) is correspondingly connected with the inner top of the house body (1) through a vertically arranged telescopic device (18).
4. A cement beam curing room as defined in claim 3, wherein: the telescopic device (18) is a cylinder or an electric telescopic cylinder.
5. A cement beam curing room as defined in claim 1, wherein: the bottom in the house body (1) is provided with a water collecting tank for collecting redundant moisture.
6. A cement beam curing room as defined in claim 1, wherein: the bottom in the house body (1) is provided with a track (19) for transporting the cement beam body (11).
7. A cement beam curing room as defined in claim 1, wherein: the outer ends of the two outermost house bodies (1) are provided with doors (16) which are convenient for the cement beam body (11) to pass through.
8. A cement beam curing room as defined in claim 1, wherein: the house body (1) is provided with a transparent window (17).
9. A cement beam curing room as defined in claim 1, wherein: the roof portion and lateral wall are equipped with a plurality of temperature sensor that are used for detecting cement roof beam body (11) temperature in the room body (1).
10. A cement beam curing room as defined in claim 1, wherein: the side wall plate and the top plate of the house body (1) are both provided with heat preservation interlayers.
CN201921421358.6U 2019-08-29 2019-08-29 Cement beam curing room Active CN210887596U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921421358.6U CN210887596U (en) 2019-08-29 2019-08-29 Cement beam curing room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921421358.6U CN210887596U (en) 2019-08-29 2019-08-29 Cement beam curing room

Publications (1)

Publication Number Publication Date
CN210887596U true CN210887596U (en) 2020-06-30

Family

ID=71331875

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921421358.6U Active CN210887596U (en) 2019-08-29 2019-08-29 Cement beam curing room

Country Status (1)

Country Link
CN (1) CN210887596U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110485569A (en) * 2019-08-29 2019-11-22 刘福祥 A kind of cement beam curing room
CN113334550A (en) * 2021-05-12 2021-09-03 中交一公局集团有限公司 Intelligent automatic spraying maintenance system for precast beam field

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110485569A (en) * 2019-08-29 2019-11-22 刘福祥 A kind of cement beam curing room
CN113334550A (en) * 2021-05-12 2021-09-03 中交一公局集团有限公司 Intelligent automatic spraying maintenance system for precast beam field

Similar Documents

Publication Publication Date Title
CN210887596U (en) Cement beam curing room
CN101922245A (en) Method for constructing environment-friendly container house
CN111802142A (en) Photovoltaic system of agricultural greenhouse
CN209027158U (en) A kind of mobile artificial snow-making vehicle
CN203518669U (en) Cooling tower for glass fiber reinforced plastic structure
CN203174916U (en) Lighting ventilation roof
CN204282845U (en) Buildings in cold roof insulating structure
CN206890383U (en) A kind of intelligent air gridding monitoring device
CN209649068U (en) A kind of prefabricated case beam steam curing canopy
CN103884200B (en) The indirect air cooling light-weight steel cage structure tower of anti-freezing economical can be realized
CN207846810U (en) A kind of novel ceiling applied on steel construction ceiling framework
CN202417227U (en) Integrated corner type heat collection photothermal french window of photothermal building
CN203083163U (en) Manual and automatic system of solar photo-thermal energy-saving balcony
CN206582827U (en) A kind of anti-blocking grey economizer
CN2346214Y (en) Gas temp-control special roasting room for yellow tobacco
CN110485569A (en) A kind of cement beam curing room
CN205369639U (en) Automatic daylight roof of rotation type
CN211572087U (en) Heat-preserving steel structure wall
CN210774598U (en) Vertical extensible comprehensive circulating wind tunnel with track platform
CN209866336U (en) Cathode hanging single-column device of wet electrostatic dust collector
CN208526121U (en) A kind of cover film dust-extraction unit for coal yard
CN206667480U (en) Cellular prefabricated house
CN111021795A (en) Self-adaptation steel construction cooling tower of anti strong typhoon
CN217110563U (en) Fog dispersal module for fog dispersal water-saving cooling tower
CN209129450U (en) Multifuctional solar dries storehouse

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant