CN210859054U - Hoisting operation platform for prefabricated concrete tower barrel section of wind driven generator - Google Patents
Hoisting operation platform for prefabricated concrete tower barrel section of wind driven generator Download PDFInfo
- Publication number
- CN210859054U CN210859054U CN201921436911.3U CN201921436911U CN210859054U CN 210859054 U CN210859054 U CN 210859054U CN 201921436911 U CN201921436911 U CN 201921436911U CN 210859054 U CN210859054 U CN 210859054U
- Authority
- CN
- China
- Prior art keywords
- platform
- stage
- concrete tower
- section
- precast concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/72—Wind turbines with rotation axis in wind direction
Landscapes
- Wind Motors (AREA)
Abstract
The utility model discloses a hoist and mount operation platform of aerogenerator precast concrete tower section of thick bamboo shell of thick bamboo festival. The construction method comprises a multistage operation platform assembled in a modularized mode, wherein single-stage construction platforms or multistage construction platforms are connected and hung in sections of the multistage reducing precast concrete tower barrel with different diameters through hanging strips and pre-buried hanging points on the barrel wall after being mutually assembled through assembling pieces. The utility model relates to a hoist and mount operation platform of aerogenerator precast concrete tower tube shell section can quick assembly disassembly to be fit for the general operation of multistage tower section of thick bamboo tube section.
Description
Technical Field
The utility model relates to a hoist and mount operation platform of aerogenerator precast concrete tower section of thick bamboo shell of thick bamboo festival.
Background
In recent years, wind generating sets tend to be large-sized, and steel towers become bottlenecks in development of the wind power industry due to influences of impeller height, steel performance, steel cost, transportation conditions and the like, and cannot meet further development of the wind power industry. The concrete prefabricated tower cylinder is an optimal solution through the modes of on-site prefabrication, segmental transportation, modular hoisting and the like. In order to facilitate prefabrication and transportation, the height of the prefabricated shell ring is strictly limited, so that the number of the prefabricated shell rings is large, and in the process of hoisting and assembling the shell rings, the shell rings need to be butted at an interface, and a platform for operators to stand is needed. Every shell ring department all installs fixed platform, and difficult dismantlement after the hoist and mount need stay in the shell ring, can waste a large amount of steel like this, in order to solve this problem, need the hoist and mount operation platform that suits with it, must can reach the operation requirement, must be safe, high-efficient quick assembly disassembly, general, be fit for multistage reducing precast concrete tower section of thick bamboo requirement.
SUMMERY OF THE UTILITY MODEL
For solving the technical problem, the utility model provides a hoist and mount operation platform of aerogenerator precast concrete tower tube shell section, this platform can quick assembly disassembly to be fit for the general operation of multistage tower section of thick bamboo tube section.
In order to realize the technical purpose, the utility model adopts the following technical scheme:
a hoisting operation platform for a prefabricated concrete tower cylinder section of a wind driven generator comprises a multi-stage operation platform assembled in a modularized mode, wherein a single-stage construction platform or a multi-stage construction platform is connected and hung in cylinder sections of different diameters of a multi-stage reducing prefabricated concrete tower cylinder through hanging strips and pre-buried hanging points on the cylinder wall after being mutually assembled through assembling pieces.
The modularly assembled multi-stage work platform comprises:
the first-stage central platform can be hoisted in a C-section shell ring with the smallest shell diameter in the multistage reducing precast concrete tower barrel and comprises a central platform main body in a C-shaped structure;
the second-stage segmented platform is assembled with the first-stage central platform and then can be hung in a B-section shell ring of which the shell diameter is larger than that of a C-section shell ring in the multistage reducing precast concrete tower cylinder, and comprises a plurality of second-stage platform units, and the plurality of second-stage platform units are assembled with each other and then are surrounded outside the central platform main body in a C-shaped structure;
and the three-stage segmented platform can be hung in the section A shell ring with the largest shell diameter in the multistage reducing precast concrete tower cylinder after being assembled with the two-stage segmented platform, and comprises a plurality of three-stage platform units, and the inner side of each three-stage platform unit is surrounded and connected outside the two-stage segmented platform through an assembling piece.
The central platform main body of the C-shaped structure is connected with the plurality of secondary platform units through bolts;
and the third-stage platform unit is connected with the second-stage platform unit through bolts.
And a frame structure for mounting the electric hoist and the materials is arranged on the primary central platform.
And bolt connecting holes for installing guardrails are formed in the primary central platform, the secondary segmented platform and the tertiary segmented platform.
Has the advantages that:
the utility model discloses hoist and mount operation platform of aerogenerator precast concrete tower tube shell section comprises one-level central platform, second grade segmentation platform, tertiary segmentation platform, because the platform size is great, for the convenient manufacturing transportation of operation platform, adopts the piecemeal manufacturing, and the mode of field assembly is solved, and wherein second grade and tertiary platform piecemeal manufacturing, field assembly can quick assembly disassembly to be fit for the general operation of multistage tower section of thick bamboo shell section.
Drawings
Fig. 1 is a schematic structural view of the combined three-stage platform of the present invention;
wherein, 1, a first-level central platform; 2. a secondary stage segmentation platform; 3. a three-stage segmented platform;
FIG. 2 is a schematic diagram of a connection structure of a primary central platform and a secondary segmented platform;
FIG. 3 is a schematic structural diagram of a primary central platform;
4, a frame structure; 5. a guardrail; 6. a bolt connecting plate;
FIG. 4 is a top view of FIG. 1;
FIG. 5 is a top view of the secondary segmented platform without the guardrail installed;
wherein, 9, installing bolt connecting holes for guardrails;
FIG. 6 is a perspective view of a single tertiary platform unit when the guardrail is not installed;
FIG. 7 is a schematic view of a work platform through a reducer section;
wherein, 7, A section shell ring; 8. and B section of cylindrical shell section.
Detailed Description
The technical scheme of the hoisting operation platform of the wind driven generator precast concrete tower tube shell section of the present invention is further described in detail with reference to the drawings and the specific embodiments.
A hoisting operation platform for a prefabricated concrete tower cylinder section of a wind driven generator comprises a multi-stage operation platform assembled in a modularized mode, wherein a single-stage construction platform or a multi-stage construction platform is connected and hung in cylinder sections of different diameters of a multi-stage reducing prefabricated concrete tower cylinder through hanging strips and pre-buried hanging points on the cylinder wall after being mutually assembled through assembling pieces.
As shown in fig. 1 to 6, in the embodiment, the modularly assembled multi-stage work platform includes:
the first-stage central platform 1 can be hoisted in a C-section shell ring with the smallest shell diameter in the multistage reducing precast concrete tower barrel and comprises a central platform main body in a C-shaped structure;
the second-stage segmented platform 2 is assembled with the first-stage central platform and then can be hung in a B-stage shell ring with the diameter larger than that of the C-stage shell ring in the multistage reducing precast concrete tower cylinder, and comprises a plurality of second-stage platform units, and the plurality of second-stage platform units are assembled with each other and then are surrounded outside the central platform main body in a C-shaped structure;
and the three-stage segmented platform 3 can be hung in the section A shell ring with the largest shell diameter in the multistage reducing precast concrete tower cylinder after being assembled with the two-stage segmented platform, and comprises a plurality of three-stage platform units, and the inner side of each three-stage platform unit is connected to the outer part of the two-stage segmented platform in a surrounding mode through an assembling piece.
The central platform main body of the C-shaped structure is connected with the plurality of secondary platform units through bolts;
and the third-stage platform unit is connected with the second-stage platform unit through bolts.
As the utility model discloses a technical scheme's a preferred embodiment, be equipped with the frame construction that installation electric block and material were used on the platform of one-level center, in this embodiment, frame construction is the steel frame who sets up in platform center department of one-level center.
As a preferred embodiment of the technical scheme, all be equipped with the bolted connection hole that is used for installing the guardrail usefulness on one-level central platform, second grade segmentation platform and the tertiary segmentation platform.
As shown in fig. 7, the working method of the hoisting operation platform of the wind driven generator precast concrete tower tube shell section is as follows:
when the concrete prefabricated shell ring needs to be lifted, a first-level operation platform to a third-level operation platform are assembled on site, the operation range of the platform is suitable for the section A shell ring with the largest diameter of the tower, after the platform is assembled, the platform is lifted into the section A shell ring by a crane and is connected with the pre-buried lifting points on the upper portion of the cylinder wall of the section A shell ring through the lifting belts, the platform is suspended in the section A shell ring, the crane can start to lift the other section A shell ring, and an operation worker stands on the platform to complete the butt joint work of the section A shell ring. After the field butt joint operation is finished, the platform is lifted to the previous cylinder section by a crane or lifting equipment (a winch, hydraulic equipment and the like) on the platform, and after the platform is in place, the next cylinder section is continuously lifted.
And after the hoisting of the section A shell ring is finished, starting to hoist the transition section between the section A shell ring and the section B shell ring, dismantling the three-stage segmented platform of the operation platform after the hoisting of the section A shell ring is finished, and transporting the platform to the ground. And repeating the steps, dismantling the secondary section platform after the section B is hoisted, reserving the primary central platform, entering the section C for hoisting, and after the section B is hoisted in the place, hoisting the tower barrel by the primary central platform by the crane to finish the hoisting work.
In order to realize the disassembly and assembly of the operation platform, the platform is formed by assembling a plurality of modules, and the modules can be connected through bolts, hinges, sliding chutes, pushing and pulling and the like.
Claims (5)
1. The hoisting operation platform for the prefabricated concrete tower cylinder sections of the wind driven generator is characterized by comprising a multi-stage operation platform assembled in a modularized mode, wherein a single-stage construction platform or a multi-stage construction platform is connected and hung in the cylinder sections of different diameters of the multi-stage diameter-variable prefabricated concrete tower cylinder through hanging strips and pre-buried hanging points on the cylinder wall after being mutually assembled through assembling pieces.
2. The hoisting work platform for the precast concrete tower tube section of the wind turbine as claimed in claim 1, wherein the modularly assembled multistage work platform comprises:
the first-stage central platform can be hoisted in a C-section shell ring with the smallest shell diameter in the multistage reducing precast concrete tower barrel and comprises a central platform main body in a C-shaped structure;
the second-stage segmented platform is assembled with the first-stage central platform and then can be hung in a B-section shell ring of which the shell diameter is larger than that of a C-section shell ring in the multistage reducing precast concrete tower cylinder, and comprises a plurality of second-stage platform units, and the plurality of second-stage platform units are assembled with each other and then are surrounded outside the central platform main body in a C-shaped structure;
and the three-stage segmented platform can be hung in the section A shell ring with the largest shell diameter in the multistage reducing precast concrete tower cylinder after being assembled with the two-stage segmented platform, and comprises a plurality of three-stage platform units, and the inner side of each three-stage platform unit is surrounded and connected outside the two-stage segmented platform through an assembling piece.
3. The hoisting operation platform for the precast concrete tower tube section of the wind driven generator according to claim 2, wherein bolt connection plates for bolt connection are arranged between the central platform body of the C-shaped structure and the plurality of secondary platform units and between the tertiary platform unit and the secondary platform units.
4. The hoisting operation platform for the precast concrete tower tube section of the wind driven generator according to claim 2, wherein a frame structure for mounting an electric hoist and materials is arranged on the primary central platform.
5. The hoisting operation platform for the precast concrete tower tube section of the wind driven generator according to claim 2, wherein bolt connecting holes for installing guardrails are formed in the primary central platform, the secondary segmented platform and the tertiary segmented platform.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921436911.3U CN210859054U (en) | 2019-08-30 | 2019-08-30 | Hoisting operation platform for prefabricated concrete tower barrel section of wind driven generator |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921436911.3U CN210859054U (en) | 2019-08-30 | 2019-08-30 | Hoisting operation platform for prefabricated concrete tower barrel section of wind driven generator |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210859054U true CN210859054U (en) | 2020-06-26 |
Family
ID=71301053
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921436911.3U Active CN210859054U (en) | 2019-08-30 | 2019-08-30 | Hoisting operation platform for prefabricated concrete tower barrel section of wind driven generator |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210859054U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111997432A (en) * | 2020-07-29 | 2020-11-27 | 上海市机电设计研究院有限公司 | Construction platform lifting device and method for precast concrete tower barrel |
CN115783179A (en) * | 2022-11-24 | 2023-03-14 | 广东精铟海洋工程股份有限公司 | Prefabricated modular foundation platform and assembling method thereof |
-
2019
- 2019-08-30 CN CN201921436911.3U patent/CN210859054U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111997432A (en) * | 2020-07-29 | 2020-11-27 | 上海市机电设计研究院有限公司 | Construction platform lifting device and method for precast concrete tower barrel |
CN115783179A (en) * | 2022-11-24 | 2023-03-14 | 广东精铟海洋工程股份有限公司 | Prefabricated modular foundation platform and assembling method thereof |
CN115783179B (en) * | 2022-11-24 | 2023-07-21 | 广东精铟海洋工程股份有限公司 | Prefabricated modularized foundation platform and assembly method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102864936B (en) | Combination lifting construction method for large-scale high hollow building roof of steel structure | |
CN107697818B (en) | Construction method and special construction equipment for wall of prestressed concrete wind power tower | |
CN210859054U (en) | Hoisting operation platform for prefabricated concrete tower barrel section of wind driven generator | |
CN203654702U (en) | Operating platform for construction of reinforced concrete chimney | |
CN107142954B (en) | Steel hanging box lifting system for integral lifting and lifting method thereof | |
CN106988299B (en) | The pay-off method of assembled steel reinforced cage descending frame and steel reinforcement cage | |
CN213015280U (en) | Movable material loading platform | |
CN110409803B (en) | Hoisting method for disassembling central drum ring of hydraulic mold lifting device | |
CN210460016U (en) | Integrated form single power lift material platform | |
CN115818458A (en) | Standard knot assembling and disassembling system and operation method | |
CN112502475B (en) | Supporting bearing capacity conversion device and using method thereof | |
CN213536960U (en) | Arrangement structure of shaft construction hoisting system | |
CN114278113A (en) | Construction method for dismantling reinforced concrete chimney in complex environment | |
CN210973666U (en) | Simple lifting device for upright post construction cylinder of antiaircraft gun billboard | |
CN109306938B (en) | Tower drum of wind generating set, installation method of tower drum and wind generating set | |
CN210597326U (en) | Precast concrete bearing structure that can assemble | |
CN113120741A (en) | 3200T tower section of thick bamboo lifting device | |
CN113336108A (en) | Movable mast tool for dismantling high-altitude tower crane in cooling tower | |
CN201980890U (en) | Herringbone hoisting mast for hoisting under special situation of high altitude | |
CN2033034U (en) | Electric mould-lifting device for face headframe | |
CN212642084U (en) | Construction platform for hoisting of mixed tower | |
CN114046083B (en) | Construction method for building steel inner cylinder chimney | |
CN220134107U (en) | Working platform in concrete tower | |
CN217027968U (en) | Color steel plate construction device for outer wall | |
CN214498490U (en) | A demolish device for adobe room |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |