CN210857607U - Frame structure of building wall - Google Patents
Frame structure of building wall Download PDFInfo
- Publication number
- CN210857607U CN210857607U CN201921667111.2U CN201921667111U CN210857607U CN 210857607 U CN210857607 U CN 210857607U CN 201921667111 U CN201921667111 U CN 201921667111U CN 210857607 U CN210857607 U CN 210857607U
- Authority
- CN
- China
- Prior art keywords
- frame body
- stud
- fixed
- frame
- connecting block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000003780 insertion Methods 0.000 claims description 9
- 230000037431 insertion Effects 0.000 claims description 9
- 238000010276 construction Methods 0.000 claims description 8
- 238000003825 pressing Methods 0.000 claims description 8
- 230000007704 transition Effects 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 3
- 230000008569 process Effects 0.000 abstract description 3
- 210000003205 muscle Anatomy 0.000 description 8
- 229910000831 Steel Inorganic materials 0.000 description 5
- 239000010959 steel Substances 0.000 description 5
- 230000000694 effects Effects 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 238000005728 strengthening Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 239000004567 concrete Substances 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a frame structure of building wall, relating to the technical field of buildings, comprising a first frame body and a second frame body, wherein the first frame body is positioned at one side of the second frame body, a stud is fixed at the middle part of one side of the first frame body, a through hole matched with the stud is arranged at the middle part of the inner part of the second frame body, the outer part of the stud is connected with a connecting ring through screw thread screwing, the connecting ring is rotationally connected with the second frame body through a rotating seat, the stud penetrates the rotating seat and extends to the inner part of the through hole, in the utility model, the space between the first frame body and the second frame body can be rapidly adjusted through the rotating ring and the stud under the action of the rotating seat, so that the whole device can pour building walls with different thicknesses, the practicability of the device is greatly increased, and meanwhile, the through hole can avoid the stud from directly contacting with the second frame body, and then the stability in the second frame body adjusting process can be improved.
Description
Technical Field
The utility model belongs to the technical field of the building, specifically be a building wall's frame construction.
Background
The building is a general name of various buildings and engineering facilities which provide material and technical foundations for human life and production, and modern building construction mainly takes reinforced concrete as a main component.
But present building wall's frame construction still has the defect when using, for example, traditional frame is difficult to adjust different thickness, is difficult to utilize the frame to pour out the building wall of different thickness, causes the frame practicality low, and in addition, the frame is when the inside strengthening rib of fixed wall, owing to be difficult to fix a position the strengthening rib fast and fix, causes the holistic lower problem of efficiency of building of frame.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to solve the problem in the background art, provide a building wall's frame construction to the frame practicality who proposes in solving above-mentioned background art is low, and the problem that efficiency is extremely low of buildding of frame.
The utility model adopts the technical scheme as follows: a frame structure of a building wall comprises a first frame body and a second frame body, wherein the first frame body is positioned on one side of the second frame body, a stud is fixed in the middle of one side of the first frame body, a through hole matched with the stud is formed in the middle of the inside of the second frame body, the outside of the stud is connected with a connecting ring in a screwing mode through threads, the connecting ring is rotatably connected with the second frame body through a rotating seat, the stud penetrates through the rotating seat and extends into the through hole, a fixing plate is fixed on the opposite sides of the outside of the first frame body and the outside of the second frame body, a first connecting block is connected to one side of the fixing plate, a second connecting block is connected to one side of the first connecting block opposite to the fixing plate, a first jack is formed in the inside of the first connecting block, a second jack is formed in the inside of the second connecting block, and a first fixing bolt is connected to the outside of the first connecting block in, one end of the first fixing bolt extends to the inside of the first jack, the outside of the second connecting block is connected with a second fixing bolt through thread screwing, and one end of the second fixing bolt extends to the inside of the second jack.
The top of the second frame body is fixed with an inserting block, and the bottom of the second frame body is provided with a slot matched with the inserting block.
The four corners of the first frame body are fixed with inserting rods, the four corners of the second frame body are fixed with sleeves matched with the inserting rods, and one ends of the inserting rods, relative to the first frame body, extend into the sleeves.
The connecting block is fixed inside the second frame body and outside the through hole, and the cross section of the connecting block is triangular.
And a pressing block is fixed at one end of the first fixing bolt and inside the first insertion hole, and an anti-slip groove is formed in the outer wall of the pressing block.
The outer part of the connecting ring is fixed with a convex block, and the outer wall of the convex block is in arc transition.
To sum up, owing to adopted above-mentioned technical scheme, the beneficial effects of the utility model are that:
1. the utility model discloses in, through swivel becket and double-screw bolt and under the effect of rotating the seat, but the interval between the first framework of quick adjustment and the second framework to make the whole building wall body that can pour formation different thickness of device, greatly increased the practicality of device, double-screw bolt and second framework direct contact can be avoided to the through-hole simultaneously, and then the stability in the second framework adjustment process can be improved.
2. The utility model discloses in, through first jack and the second jack that each other is the vertical direction, can make the device can fix a position horizontal muscle and vertical muscle fast, simultaneously under the effect of first gim peg and second gim peg, can consolidate horizontal muscle and vertical muscle fast, and then can improve the convenient degree when horizontal muscle and vertical muscle are installed to efficiency when hoisting frame builds.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a side view of a second frame body of the present invention;
FIG. 3 is an enlarged view of portion A of FIG. 1;
fig. 4 is a sectional view of a second connecting block of the present invention;
in the figure: the device comprises a rotating seat 1, a through hole 2, a bump 3, a connecting ring 4, a stud 5, a first frame 6, an inserting block 7, an inserting rod 8, a sleeve 9, a second frame 10, a connecting block 11, a slot 12, a second fixing bolt 13, a second connecting block 14, a first insertion hole 15, a first connecting block 16, a fixing plate 17, a first fixing bolt 18, a pressing block 19 and a second insertion hole 20.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the invention.
Referring to fig. 1-4, a frame structure of a building wall, comprising a first frame body 6 and a second frame body 10, wherein the first frame body 6 is located at one side of the second frame body 10, a stud 5 is fixed at the middle of one side of the first frame body 6, a through hole 2 matched with the stud 5 is formed at the middle of the inside of the second frame body 10, a connection ring 4 is connected to the outside of the stud 5 in a screwing manner, the connection ring 4 is rotatably connected with the second frame body 10 through a rotating base 1, the stud 5 penetrates through the rotating base 1 and extends to the inside of the through hole 2, when the connection ring 4 is rotated, the whole second frame body 10 moves along the stud 5 towards the first frame body 6, so as to change the space between the first frame body 6 and the second frame body 10, so that the device can form building walls with different thicknesses, a fixing plate 17 is fixed at the opposite side of the outside of the first frame body 6 and the second frame body 10, a first connecting block 16 is connected to one side of the fixed plate 17, a second connecting block 14 is connected to one side of the first connecting block 16 opposite to the fixed plate 17, a first jack 15 is arranged inside the first connecting block 16, a second jack 20 is arranged inside the second connecting block 14, a first fixing bolt 18 is screwed outside the first connecting block 16 through screw threads, one end of the first fixing bolt 18 extends to the inside of the first jack 15, a second fixing bolt 13 is screwed outside the second connecting block 14 through screw threads, one end of the second fixing bolt 13 extends to the inside of the second jack 20, the directions of the first jack 15 and the second jack 20 are mutually vertical, and then insert first jack 15 and second jack 20 back with the reinforcing bar for building respectively, can make between the reinforcing bar form horizontal muscle and vertical muscle in the wall body fast, later mix earth and water the back that finishes, can greatly strengthen the fastness of wall body.
Furthermore, the top of the second frame body 10 is fixed with the insertion block 7, the bottom of the second frame body 10 is provided with the slot 12 matched with the insertion block 7, and the plurality of devices can be integrally spliced by the aid of the manner that the insertion block 7 and the slot 12 can be plugged, so that the devices can be poured to form a wall body with a larger area.
Furthermore, four corners of the first frame body 6 are fixed with inserting rods 8, four corners of the second frame body 10 are fixed with sleeves 9 matched with the inserting rods 8, one end of each inserting rod 8, relative to the first frame body 6, extends into the sleeves 9, and contact points between the first frame body 6 and the second frame body 10 can be directly increased by means of the inserting rods 8 and the sleeves 9, so that the overall stability of the device can be improved.
Furthermore, a connecting block 11 is fixed inside the second frame 10 and outside the through hole 2, and the cross section of the connecting block 11 is triangular so as to enhance the tensile strength of the second frame 10 itself.
Specifically, one end of the first fixing bolt 18 is fixed with a pressing block 19 inside the first insertion hole 15, an anti-slip groove is formed in the outer wall of the pressing block 19, and after the steel bar is inserted into the first insertion hole 15, the pressing block 19 can further increase the friction force between the first fixing bolt 18 and the steel bar.
Specifically, the bump 3 is fixed outside the connecting ring 4, the outer wall of the bump 3 is in arc transition, and the bump 3 can improve the convenience of the connecting ring 4 in the rotating process.
The working principle, referring to fig. 1-4, when in use, the connecting ring 4 outside the stud 5 can be rotated according to the actual thickness of the wall to be poured, then the second frame 10 can move towards the first frame 6, the inserted rod 8 and the sleeve 9 can further improve the stability between the first frame 6 and the second frame 10 during the movement, when the distance between the first frame 6 and the second frame 10 is close to the thickness of the wall to be poured, the connecting ring 4 can be stopped to rotate, then the steel bars can be respectively inserted into the first jack 15 and the second jack 20, and the steel bars inside the first jack 15 and the second jack 20 can be respectively fixed by the first fixing bolt 18 and the second fixing bolt 13, because the directions of the first jack 15 and the second jack 20 are perpendicular to each other, the inserted steel bars can quickly form a transverse bar and a longitudinal bar in the wall, then concrete can be poured outside the device, so as to form a complete building wall.
The above description is only exemplary of the present invention and should not be taken as limiting the scope of the present invention, as any modifications, equivalents, improvements and the like made within the spirit and principles of the present invention are intended to be included within the scope of the present invention.
Claims (6)
1. A frame structure of building wall, its characterized in that: the connecting device comprises a first frame body (6) and a second frame body (10), wherein the first frame body (6) is positioned on one side of the second frame body (10), a stud (5) is fixed in the middle of one side of the first frame body (6), a through hole (2) matched with the stud (5) is formed in the middle of the inner portion of the second frame body (10), a connecting ring (4) is connected to the outer portion of the stud (5) in a screwing mode through threads, the connecting ring (4) is rotatably connected with the second frame body (10) through a rotating seat (1), the stud (5) penetrates through the rotating seat (1) and extends into the through hole (2), a fixing plate (17) is fixed on one side, opposite to the outer portion of the first frame body (6) and the outer portion of the second frame body (10), a first connecting block (16) is connected to one side of the fixing plate (17), and a second connecting block (14) is connected to one side, opposite to the fixing plate (17), of the, and first jack (15) have been seted up to the inside of first connecting block (16), second jack (20) have been seted up to the inside of second connecting block (14), the outside of first connecting block (16) closes soon through the screw thread and is connected with first gim peg (18), the one end of first gim peg (18) extends to the inside of first jack (15), the outside of second connecting block (14) closes soon through the screw thread and is connected with second gim peg (13), the one end of second gim peg (13) extends to the inside of second jack (20).
2. A frame structure for a construction wall according to claim 1, wherein: the top of the second frame body (10) is fixed with an inserting block (7), and the bottom of the second frame body (10) is provided with a slot (12) matched with the inserting block (7).
3. A frame structure for a construction wall according to claim 1, wherein: inserted bar (8) all are fixed with in four corners of first framework (6), all be fixed with in four corners of second framework (10) with inserted bar (8) assorted sleeve pipe (9), inserted bar (8) extend to the inside of sleeve pipe (9) for the one end of first framework (6).
4. A frame structure for a construction wall according to claim 1, wherein: the inside of second framework (10) just is located the outside of through-hole (2) and is fixed with connecting block (11), the cross-sectional shape of connecting block (11) is triangle-shaped.
5. A frame structure for a construction wall according to claim 1, wherein: one end of the first fixing bolt (18) is fixed with a pressing block (19) inside the first insertion hole (15), and an anti-slip groove is formed in the outer wall of the pressing block (19).
6. A frame structure for a construction wall according to claim 1, wherein: the outer part of the connecting ring (4) is fixed with a convex block (3), and the outer wall of the convex block (3) is in circular arc transition.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921667111.2U CN210857607U (en) | 2019-10-08 | 2019-10-08 | Frame structure of building wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921667111.2U CN210857607U (en) | 2019-10-08 | 2019-10-08 | Frame structure of building wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210857607U true CN210857607U (en) | 2020-06-26 |
Family
ID=71290455
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921667111.2U Expired - Fee Related CN210857607U (en) | 2019-10-08 | 2019-10-08 | Frame structure of building wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210857607U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112093214A (en) * | 2020-09-23 | 2020-12-18 | 厦门煌柳化工科技有限公司 | Assembly type integrated connecting device for construction equipment |
CN114412021A (en) * | 2022-01-24 | 2022-04-29 | 安徽富煌钢构股份有限公司 | Wallboard assembly for assembly type building and assembly method |
-
2019
- 2019-10-08 CN CN201921667111.2U patent/CN210857607U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112093214A (en) * | 2020-09-23 | 2020-12-18 | 厦门煌柳化工科技有限公司 | Assembly type integrated connecting device for construction equipment |
CN112093214B (en) * | 2020-09-23 | 2022-07-12 | 青岛穗禾集成房屋有限公司 | Assembly type integrated connecting device for construction equipment |
CN114412021A (en) * | 2022-01-24 | 2022-04-29 | 安徽富煌钢构股份有限公司 | Wallboard assembly for assembly type building and assembly method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210857607U (en) | Frame structure of building wall | |
CN202248298U (en) | Node of steel reinforced concrete framework | |
CN207727757U (en) | A kind of prefabricated wall column one-part form steel bar connecting structure | |
CN211499678U (en) | Construction fastener formula steel pipe template strutting arrangement | |
CN204456670U (en) | Fabricated construction straight screw sleeve connection joint | |
CN207499196U (en) | A kind of cladding node of assembled architecture outer wall and precast facade | |
CN204609002U (en) | Profile steel concrete column and prestressed girder frame joint | |
CN206233359U (en) | A kind of assembled architecture reinforced concrete member | |
CN205077730U (en) | High strength steel muscle support frame | |
CN210857257U (en) | Connection structure of recycled concrete precast pile and pile foundation pile cap | |
CN210459181U (en) | New and old ground is wall T joint design node even | |
CN209760877U (en) | Building wall reinforcing and supporting structure | |
CN207647029U (en) | A kind of two-way building detached column of putting more energy into | |
CN208346825U (en) | A kind of Z-type foundation pit supporting pile and its connection structure | |
CN209958764U (en) | Connecting and locking device for building template | |
CN208907255U (en) | A kind of brace type metal energy consumption coupling beam built-in fitting of high-bearing capacity | |
CN206034423U (en) | Concrete pile | |
CN221480795U (en) | Anti-floating anchor rod for deep foundation pit construction | |
CN205134309U (en) | Cement mixing method with reducing strength core pile | |
CN210032192U (en) | Use reliable prefabricated steel pipe shear force wall connection structure | |
CN205134736U (en) | Steel pipe concrete transition rod spare | |
CN212358321U (en) | Connecting structure for concrete foundation pile | |
CN213296409U (en) | Precast pile foundation capable of improving soil occlusion capacity | |
CN217581158U (en) | Cast concrete ground steel frame connecting device | |
CN216429106U (en) | Building structure's reinforcement connecting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200626 |
|
CF01 | Termination of patent right due to non-payment of annual fee |